TAY HA NOI 220KV SUBSTATION - The World Bank · Tay Ha Noi 220kV Substation Resettlement Plan...
Transcript of TAY HA NOI 220KV SUBSTATION - The World Bank · Tay Ha Noi 220kV Substation Resettlement Plan...
NATIONAL POWER TRANSMISSION CORPORATION
Northern Power Projects Management Board
-------------------------------
RESETTLEMENT PLAN
(RP)
SUBPROJECT:
TAY HA NOI 220KV SUBSTATION
PREPARED BY
INSTITUTE OF ENERGY
Hanoi, February 2014
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Tay Ha Noi 220kV Substation Resettlement Plan
Institute of Energy - IE 2
TABLE OF CONTENTS
SUMMARY .................................................................................................................................... 9
1. INTRODUCTION.................................................................................................................. 10
1.1. TRANSMISSION EFFICIENCY PROJECT (TEP) ....................................................... 10
1.2. THE TAY HANOI 220KV SUBSTATION SUBPROJECT .......................................... 10
1.3. OBJECTIVE OF THE RESETTLEMENT PLAN .......................................................... 12
2. LEVEL OF IMPACTS OF THE SUBPROJECT ............................................................. 13
2.1. DETERMINATION OF THE SUBPROJECT'S ............................................................. 13
2.1.1. Determination of project impacted area..................................................................... 13
2.1.2. Determination of project affected people .................................................................. 13
2.2. TYPES OF PROJECT IMPACTS .................................................................................... 13
2.2.1. Impacts on cultivation land......................................................................................... 13
2.2.2. Permanently affected crops ........................................................................................ 14
2.2.3. Number and types of affected perennials .................................................................. 14
2.2.4. Affect to house and structures .................................................................................... 14
3. LEGAL FRAMEWORK AND COMPENSATION POLICIES .................................... 15
4. RESETTLEMENT, SUPPORT AND COMPENSATION PLAN .................................. 28
4.1. COMPENSATION ............................................................................................................ 28
4.1.1. Compensation unit price for land .............................................................................. 28
4.1.2. Compensation unit price for perenials ...................................................................... 28
4.1.3. Compensation unit price for food crops and crops .................................................. 29
Table 4.1.3 – Food crops and crops compensation unit price............................................. 29
4.1.4. Compensation unit price for fish yield ..................................................................... 29
4.1.5. Total project compensation cost ............................................................................. 29
4.2. LIVING REHABILITATION SUPORT FOR AFFECTED PEOPLE .......................... 30
Tay Ha Noi 220kV Substation Resettlement Plan
Institute of Energy - IE 3
5. COMMUNITY CONSULTATION AND INFORMATION ANNOUNCEMENT ..... 31
5.1. COMMUNITY CONSULTATION AND PARTICIPATION ....................................... 31
5.2. DISCLOSURE ................................................................................................................... 33
5.3. GRIEVANCE REDRESS ADMINISTRATIVE ............................................................. 33
6. REPORT, SUPERVISION AND EVALUATION............................................................ 35
6.1. INTERNAL SUPERVISION ............................................................................................ 35
6.2. INDEPENDENT MONITORING .................................................................................... 37
6.3. REPORTING CONDITION ............................................................................................. 37
7. IMPLEMENTATION SCHEDULE ................................................................................... 38
8. COSTS ..................................................................................................................................... 42
8.1. COSTS FOR IMPLEMENTATION OF RESETTLEMENT PLAN ............................. 42
8.1.1. Costs for Resettlement Plan establishment and detailed measurement ................... 42
8.1.2. Cost for compensation ................................................................................................ 42
8.1.3. Cost for management .................................................................................................. 42
8.1.4. Cost for supervision .................................................................................................... 43
8.1.5. Contingency ................................................................................................................. 43
8.2. TOTAL COST ESTIMATE OF RESETTLEMENT PLAN .......................................... 43
Tay Ha Noi 220kV Substation Resettlement Plan
Institute of Energy - IE 4
List of tables
Table 1.2 – Project items ........................................................................................................ 12
Table 2.1.2 – Total number of affected people with classification ................................... 13
Table 2.2.1 – Permanently affected cultivating land ......................................................... 14
Table 2.2.2 – Permanently affected crops ............................................................................ 14
Table 2.2.3 – Affected perennials .......................................................................................... 14
Table 4.1.1 – Permanent farmland compensation unit price ........................................... 28
Table 4.1.2 – Perenials compensation unit price ................................................................ 28
Table 4.1.4 – Compensation unit price for fish yield ......................................................... 29
Table 4.1.5a – Compensation cost ......................................................................................... 29
Table 4.1.5b – Summary of Land Acquisition cost: ........................................................... 30
Table 5.1– Summary on residents’ opnion in community consultation meeting .......... 32
Bảng 6.1 – Some fundamental activities of internal supervision and evaluation .......... 35
Bảng 8.2 – Total cost estimate of Resettlement Plan ......................................................... 43
Figure
Figure 7.1 – Organization chart of implementation institution of Resettlement Plan
...................................................................................................Error! Bookmark not defined.
Tay Ha Noi 220kV Substation Resettlement Plan
Institute of Energy - IE 5
GLOSSARY
Census and Inventory If the project needs to change the land use or to acquire land for
project purposes, a Census of people that will be affected and an Inventory of affected assets
will be undertaken based on the technical design of the project. The Census will include key
socioeconomic information of the project affected persons (DPs), such as main occupations,
sources of income, and levels of income in order to be able to determine vulnerable
households as well as to establish baseline data for monitoring livelihood restoration of the
DPs. The Inventory will include a detailed description of all affected lands, trees, structures,
to be acquired permanently or temporarily in order to complete the Project; the names of the
persons entitled to compensation (from the census); and the estimated full replacement costs,
etc.
Compensation (in cash or in kind) for loss of assets and rehabilitation measures to restore
and improve incomes will be determined in consultation with the DPs. Compensation for loss
of assets will be at replacement costs.
Cut-off-date is the date of completion of the inventory of losses during preparation of the
Resettlement Plan (RP). Project affected households and local communities will be informed
of the cut-off date for each project, and that anyone moving into the Project Area after that
date will not be entitled to compensation and assistance under the Project.
Eligibility is the criteria to receive benefits under the resettlement program. This Resettlement
Policy Framework (RPF) will provide general guidance on this but the eligibility criteria will
not be definitively confirmed until the development of the RP.
Productive land refers to the various sub-categories of land that are used for agricultural
purpose (as opposed to land for residential purpose), including agricultural, forestry, garden,
aquaculture and pond land. N.B. Loss of land on which businesses are located is covered
under the „relocation of business‟ section of the entitlement matrix.
Replacement Cost. is the concept used to calculate the compensation amount for an asset and
involves using current market value plus the transaction costs which may include taxes, fees,
transportation, labor, etc. (OP 4.12, footnote 11).
Resettlement. This RPF, in accordance with the World Bank‟s Operational Policy on
Involuntary Resettlement (OP 4.12), covers the involuntary taking of land that results in (i)
relocation or loss of shelter, (ii) loss of assets or access to assets; or (iii) loss of income
sources or means of livelihood, whether or not the affected persons must move to another
location.
Livelihood (income) restoration Livelihoods restoration refers to that compensation for PAPs
who suffers loss of income sources or means of livelihoods to restore their income and living
standards to the pre- displacement levels.
Tay Ha Noi 220kV Substation Resettlement Plan
Institute of Energy - IE 6
Right of Way. For this Policy Framework, Right of Way (ROW) is determined as a safety
corridor along a power line or substation with width, length and height specified in the Decree
106/2005/ND-CP (dated August 17th, 2005 guiding the implementation of a number of articles
under the Electricity Law regarding safety protection of high-voltage power grid) and Decree
81/2009/ND-CP (dated on 12th October 2009, amending or supplementing a number of articles
of the Government‟s Decree No. 106/205/ND-CP).
Vulnerable Groups. Vulnerable groups include those distinct groups of people who might
suffer disproportionately or face the risk of being marginalized by the effects of resettlement,
and specifically include:
a) Poor and very poor household as identified by regulations of Government of Vietnam.
b) Ethnic minority household (Ethnic Minority Planning Framework).
c) Household covered by Decree 67/2007/ND-CP of April 13th, 2007 on support policies
for social protection beneficiaries and Decree 13/2010/ND-CP of February 27th, 2010
amending and supplementing a number of articles of the Government's Decree No.
67/2007/ND-CP.
Tay Ha Noi 220kV Substation Resettlement Plan
Institute of Energy - IE 7
ABBREVIATION
CPC Commune People‟s Committee
TEP Transmission Efficient Project
ECOP Environmental Code of Practice
EIA Environmental Impact Assessment
EMF Electromagnetic Field
EMP Environmental Management Plan
EVN Electricity of Vietnam
GOV Government of Vietnam
HH Household
MOIT Ministry of Industry and Trade
MONRE Ministry of Natural Resources and Environment
MV Medium Voltage
NPT National Power Transmision Corporation
PAH Project Affected Household
PCBs Polychlorinated Biphenyls
NPPMB Northern Power Projects Management Board (under the NPT)
PPC Provincial People‟s Committee
WB World Bank
CSC Construction supervision Consultant
CDD Community Driven Development
DP Displaced Person
DPC District People‟s Committee
ERAV Electricity Regulatory Authority of Vietnam
GFU Grievance facilitation unit
Tay Ha Noi 220kV Substation Resettlement Plan
Institute of Energy - IE 8
IA Implementing Agency
NGO Non-governmental Organization
OP Operation Policy
RP Resettlement Plan
RPF Resettlement Policy Framework
Tay Ha Noi 220kV Substation Resettlement Plan
Institute of Energy - IE 9
SUMMARY
The subproject: “Tay Ha Noi 220kV Substation” is one of the subprojects that will be
implemented in Phase I of the Transmission Efficiency Project (TEP) funded by the World
Bank. The subproject will be implemented in Dong Quang commune of Quoc Oai district, Ha
Noi city. The implementation of the subproject is in line with the national Power
Development Master Plan 7 (PDMP7) to meet the growing electricity demand load and power
system in the West area of Hanoi city.
The subproject might affects to 121 households (454 citizens) of Dong Quang
commune, Quoc Oai district, Ha Noi. The survey conducted by the Institute of Energy reveals
that the proportion of affected land fluctuates from 0.05% to 9,23% of the total land they own.
Specifically:
- Number of DPs with less than 20% of productive land permanently
acquired: 121 HHs (454 persons)
- Number of DPs with crops permanently affected: 121 HHs (454 persons)
- Number of DPs with perennial trees permanently affected: 7 HHs (28
persons)
The Resettlement Plan of the Tay Ha Noi 220kV Substation subproject is prepared on the
basis of the Involuntary Resettlement Policy (OP 4.12) of the World Bank and the
Resettlement Policy Framework that has been approved for the Distribution Efficiency
Project.
The compensation and assistance activities for affected households are expected to start
from 2013. The estimated cost for the implementation of Resettlement Plan is
44.853.000.000 VND (will be updated when the subproject is implemented to ensure the
principle of compensation at replacement cost). Fund for the implementation of RP will be
from counterpart: Vietnam Electricity.
Tay Ha Noi 220kV Substation Resettlement Plan
Institute of Energy - IE 10
1. INTRODUCTION
1.1. TRANSMISSION EFFICIENCY PROJECT (TEP)
1. The National Power Transmission Cooperation (NPT) is developing Efficient
Transmission Project (TEP) with funding from the World Bank (WB). The Project
Development Objective (PDO) for TEP is to support the implementation of an investment
programs to increase capacity of Vietnam‟s electricity transmission grid, improve efficiency
and reliability of electricity services and strengthen the institutional capacity of the National
Power Transmission Corporation. The direct beneficiary of the project would be Vietnam‟s
electricity transmission company NPT. Indirect beneficiaries would include all segments of
population. They would benefit from: (i) Improved reliability, which will reduce unserved
demand and the number and duration of power outages; and (ii) Increased energy efficiency,
which will reduce overall costs and GHG emissions. The project would also bring direct
temporary benefits for skilled and unskilled workers that would be employed for the construction of the project.
2. The proposed project is comprised of the following three components: (i) The
Transmission Infrastructure Component; (ii) The Smart Grid Component; and (iii) The Capacity Building and Institutional Strengthening Component.
(a) The Transmission Infrastructure Component will finance transmission lines and
substations at voltage levels of 220kV and 500kV. The investments will target three areas that
are key to the overall economic development of Vietnam, namely the Greater Hanoi Area, the
Greater Ho Chi Minh City Area and the Mekong Delta. Investments at the 500kV level will
help increase the transport capacity of the main 500kV trunk system while increasing its
reliability. Investments at the 220kV level are aimed at increasing the capacity of the supply
points to the distribution utilities and improve the reliability of the network that serves these
points.
(b) The Smart Grid Component will support modernization of monitoring, control,
and protection equipment in 500kV and 220kV substations to improve the reliability of the
interconnected power system as a whole and of some bulk-supply points in the distribution
network. Today, 60 percent of the faults in substations are a consequence of faulty operations
of monitoring, control, and protection equipment. Aided by monitoring and control gear,
protection equipment: (i) detects - among other things - the locations and intensity of faults
and, based on such information, determines what equipment should be disconnected to protect
the system from damage; and (ii) decides when disconnected equipment should be reconnected to ensure that interruptions in the provision of electricity services are minimized.
(c) The Capacity Building and Institutional Strengthening Component will contribute to
the gradual development of NPT to become an independent transmission company with
revenues from the application of cost-of-service regulation in the transmission sector. The
steps to be supported in this operation include the definition of technical and financial
performance indicators, the introduction of enterprise asset management systems and strategies.
3. Component 1 and Component 2 will be implemented by three management boards of NPT, Component 3 and a part of the component 2 will be implemented by NPT and ERAV.
4. To implement sub-projects components, land acquisition will be required. However, land
acquisition and resettlment aren‟t required in component 2 – Smart Grid Development and
component 3 – capacity improvement and system reinforcement. In this subproject, land acquisition is required only under sub-projects in component 1.
1.2. THE TAY HANOI 220KV SUBSTATION SUBPROJECT
Tay Ha Noi 220kV Substation Resettlement Plan
Institute of Energy - IE 11
Figure 1.1. The subproject's location
Subproject of Tay Ha Noi 220kV substation locates on Yen Noi Village, Dong Quang
Commune, Quoc Oai District, Hanoi (see Appendix1: Project Area). The subproject aims to:
- Meet the load growing demand of Northern Vietnam, especially Hanoi.
- Receive power supply from northwestern hydroelectric plants and support existing
220kV substations in the region, in a long run will become an important 500/220kV
node in the system.
- Create circuit link among regions in the system; enhance operation safety and
stability for national power system.
Tay Ha Noi 220kV Substation Resettlement Plan
Institute of Energy - IE 12
- Reduce power lossess of transmission grid, increasing production efficiency in
general for NPT.
The subproject includes construction and equipment installment of Tay Hanoi 220kV
substation with capacity of 2x250MVA.
Table 1.2 – Project items
Province – District/Commune Capacity (MVA) Area (m2)
Hanoi – Quoc Oai District
1. Dong Quang Commune 2x250
- Tay Ha Noi 220kV Substation 60.093,0
- Substation accessing road 3.188,0
Total 63.281,0
Substation specifications:
- Substation: 220kV/110kV/22kV
+ High voltage level : 220kV
+ Medium voltage level : 110kV
+ Low voltage level : 22kV
- Area for construction of susbstation and substation accessing road: 60.093m2
- Capacity: 2x250MVA
- 220kV side includes following compartments:
+ 2 compartments of transformers 500/220kV-900MVA
+ 2 compartments of transformers 220/110/22kV-250MVA
+ 10 outgoing compartments (2 to Hoa Binh, 2 to Ha Dong, 2 to Chem, 2 to Phuc
Tho và 2 to Hoa Lac.)
+ 1 compartment of loop circuit
+ 1 communicative compartment
- 110kV side includes following compartments:
+ 2 compartments of transformers 220/110/22kV-250MVA
+ 2 compartments of transformers 110/35/22kV-63MVA
+ 10 outgoing compartments (2 to Son Tay, 1 to Ha Dong, 1 to Chem, 2 to An
Khanh and 4 provisional outgoing compartments)
+ 1 compartment of loop circuit
+ 1 communicative compartment
+ 2 compartments for capacitors
1.3. OBJECTIVE OF THE RESETTLEMENT PLAN
The Resettlement Plan is established for the following objectives:
- Involuntary resettlement must be avoided where possible, or be reduce to the lowest
possible extent by selecting appropriate design options.
- Where involuntary resettlement is unavoidable, the resettlement activities must be
prepared and executed with sustainable development programs and sufficiently provided
investment supports, enabling displaced people to benefit from the subproject. The displaced
people will be fully consulted and allowed to participate in preparatory and implementing
activities of Resettlement Plan.
APs must be supported in terms of their capacity to improve their living conditions and
to rehabilitate their living standards higher than or at least equal to that before constructing the
subproject.
Tay Ha Noi 220kV Substation Resettlement Plan
Institute of Energy - IE 13
2. LEVEL OF IMPACTS OF THE SUBPROJECT
2.1. DETERMINATION OF THE SUBPROJECT'S
2.1.1. Determination of project impacted area
The subproject will affect Dong Quang Commune, Quoc Oai District, Tay Ha Noi
capital.
Impacted area of the subproject merely includes:
Construction area of the substation:
Total occupied area of the substation: 60093.0m2; Occupied area of subsstation
accessing road 3188 m2.
Above affected area is farmland, fragmented, owned little by each household, on which
people grow crops and fruit trees besides rice. They have to do extra works other than farming
for living. The impacted area by the project does not significantly affect their living.
2.1.2. Determination of project affected people
According to the survey result, there are 121 households (451 people) affected by the
subproject, in which percentage of households having land acquired is 0.05-9.23%, including:
- Persons with cultivating land partly or fully affected (permanently);
- Persons with perennial and/or seasonal trees partly or fully affected (permanently).
- Vulnerable group affected by the subproject is mainly minor households (15
households).
Synthesized result is presented in following tables (for details see Appendix 8:
Inventory of Project affected peope):
Table 2.1.2 – Total number of affected people with classification
Description Households Persons
Permanent AP
– AP with permanently acquired land under 20% of total
farmland owned (under 10% for poor and vulnerable group) 121 454
– AP with permanently affected crops 121 454
– AP with permanently affected perennials 7 28
Total number of permanent AP 121 454
All affected persons live in Dong Quang Commune, Quoc Oai District.
Note: For more details of AP Entitlement, Compensation Policy, Enforcement Items for
types of impact, see Appendix 3. Benefit Matrix.
2.2. TYPES OF PROJECT IMPACTS
Types of impacts on AP in the subproject include:
- Having cultivation land (farmland) permanently acquired due to construction of the
substation.
- Having permanently affected crops (vegetables crops) and perennials inside the area
expected for construction of substation.
The result is described in the following tables:
2.2.1. Impacts on cultivation land
Permanent impact: The total permanent affected land area is 55687 m2, details are
Tay Ha Noi 220kV Substation Resettlement Plan
Institute of Energy - IE 14
summarized in the table below:
Table 2.2.1 – Permanently affected cultivation land
Unit m2
City/district/commune Farmland Total
Dong Quang Commune/Quoc
Oai/Hanoi 55687 55687
As is mentioned above, the subproject will be located in the agriculture land of Dong Quang
commune, thus, affected land is almost farming land. There will be no house, buidling or residential land in the project area.
Temporary impact: This type is expected to occur during the project construction
with the construction/expansion of the access road to the project area to carry
equipment, wire stringing….
The total temporary affected land area is approximately 2,300 m2.
2.2.2. Permanently affected crops
Part of paddy field is utilized for growing seasonal crops.
Table 2.2.2 – Permanently affected crops
Unit m2
City/district/commune Land for crops Total
Dong Quang Commune/Quoc
Oai/Hanoi 6694 6694
2.2.3. Number and types of affected perennials
Table 2.2.3 – Affected perennials
No.
Inside construction scope of substation
and substation accessing road Basic features
Note Rice
(m2)
Crops
(m2)
Fruilt
trees
(tree)
Bare land,
ponds
(m2)
Ф of
tree
(mm)
Height
(m)
1 55687 6694 35 900 25 5
Longan trees
and litchi trees
scatter
2.2.4. Affect to house and structures
Base on the invesment project report, there is no house or buidling in the subproject's
area. Most of the land used for this subproject is agiculture land.
Tay Ha Noi 220kV Substation Resettlement Plan
Institute of Energy - IE 15
3. LEGAL FRAMEWORK AND COMPENSATION POLICIES
3.1 LEGAL FRAMEWORK
3.1.1 The Government’s policy in Viet Nam:
The Legal Framework of the Government of Vietnam: For public investment projects
using domestic budget, principles and policies on land acquisition, compensation and
resettlement arrangement are stipulated by the Government on the basis of laws, decrees and
decisions by the Government on land acquisition, compensation and resettlement, including
the following:
The Constitution of Vietnam 2013.
The Land Law 2003, no. 13/2003/QH11, issued on November 26, 2003 (to be
replaced by the Land Law 2013 which become effective from July 1st, 2014)
Decree 181/2004/ND-CP issued on October 29th, 2004 guiding the
implementation of the Land Law revised 2003.
Decree No.188/2004/ND-CP issued on November 16th, 2004 providing the
method of land price calculation and the tariff for all types of land;
Decree 197/2004/ND-CP issued on December 3rd, 2004 on compensation,
support and resettlement when land is recovered by the state.
Decree 188/2004/ND-CP issued on November 16th, 2004 on methods to
determine land prices and assorted land price brackets.
Decree 123/2007/ND-CP dated July 27, 2007, on revision and supplementation of
some regulations in decree 188/2004/ND-CP of November 16, 2004 on methods
to determine land prices and assorted land price brackets.
Decree 17/2006/ND-CP dated January 27th, 2006 on revision and
supplementation of some regulations in decrees guiding the implementation of the
Land Law and Decree no. 187/2004/ND-CP on transformation of state companies
into joint-stock companies.
Decree 84/2007/ND-CP dated May 25th 2007 on revision of issuing LURC, land
acquisition, implementation of land use right, procedure for compensation,
resettlement when land acquired by State and grievance redress.
Decree No. 69/2009/ND-CP, effective 1st October 2009; an amendment to
Decree No. 197/2004/ND-CP; supplementary regulations on land use planning,
land prices, land acquisition, compensation, support and resettlement.
Circular No.116/2004/TT-BTC dated 17 December 2004 providing guidance for
the implementation of Decree No.197/2004/ND-CP dated 3 December 2004 on
compensation, assistance and resettlement upon the State recovery of land;
Circular 14/TT-BTNMT dated 1st October 2009 providing detailed regulations on
Tay Ha Noi 220kV Substation Resettlement Plan
Institute of Energy - IE 16
compensation, assistances, relocation and process and procedures for land
acquisition, land hand-over and land lease.
Circular 57/2010/TT-BTC issued on April 16th, 2010 prescribing the estimation,
use and settlement of funds for compensation, support and resettlement upon
recovery by the State.
Circular No.02/2010/TTLT-BTNMT-BTC dated 8 January 2010 issued by the
Ministry of Natural Resource and Environment and Ministry of Finance guiding
the preparation appraisal, and issuance and revision of land prices revision and
the competence of the city/province PC under the National Government control.
Decision No. 1956/2009/QD-TTg, dated November 17 2009, by the Prime
Minister approving the Master Plan on vocational training for rural labors by
2020.
Decision No. 52/2012/QD-TTg, dated November 16 2012, on the support policies
on employment and vocational training to farmers whose agricultural land has
been recovered by the State.
The Electricity Law 2004, no. 28/2004/QH11, ratified on December 3rd, 2004.
Decree 106/2005/ND-CP (and its associated guiding circulars) dated on August
17th, 2005, guiding the implementation of a number of articles under the
Electricity Law regarding safety protection of high-voltage power grid.
Decree 81/2009/ND-CP (and its associated guiding circulars) dated on October
12th, 2009, amending or supplementing a number of articles of the government‟s
decree No. 106/205/ND-CP of August 17th, 2005 which details and guide a
number of articles of the electricity law regarding the safe protection of high-
voltage power grid works.
Circular 03/2010/TT-BCT dated on January 22, 2010 of Ministry of Industry and
Trade, regulating a number of articles under decrees 106/2005/ND-CP and decree
81/2009/ND-CP.
Current regulations on compensation, support and resettlement of local authority
applied in Resettlement Plan of subproject include: (i) Decision No.108/2009/QD-
UBND of Hanoi People Committee. (ii) Decision No.27/2013/QD-UBND dated
July 18th 2013 of Hanoi People Committee about specific regulation on
determination of land price, resettlement house price as basis for compensation,
support and resettlement when the State recovers land in Hanoi. (iii) Notice
No.7038/SCT-BG dated December 31st 2012 of Hanoi Department of Finance on
compensation and support unit price for trees, crops, cattles servicing for land
acquisition in Hanoi in 2013.
3.1.2 Policy of the World Bank
The World Bank‟s OP 4.12 Involuntary Resettlement includes the following
Tay Ha Noi 220kV Substation Resettlement Plan
Institute of Energy - IE 17
principles:
Involuntary resettlement should be avoided where feasible, or minimized,
exploring all viable alternative project designs;
Where it is not feasible to avoid resettlement, resettlement activities should be
conceived and executed as sustainable development programs, providing
sufficient investment resources to enable the persons displaced by the project to
share in project benefits. Project affected persons should be meaningfully
consulted and should have opportunities to participate in planning and
implementing resettlement programs;
Project affected persons should be assisted in their efforts to improve their
livelihoods and standards of living or at least to restore them, in real terms, to pre-
displacement levels or to levels prevailing prior to the beginning of project
implementation, whichever is higher.
Criteria for the validity and compensation:
Who have to relocate or be affected by the project are valid compensation include: (a)
who have a legal right in land or other assets, (b) who is there has been no legal rights in land
or other assets, but has filed application for certificate authority to declare legal use in
accordance with the laws of the State, based on documents such as property tax bill land,
residential status certificate, or upon the residence of allowing local authorities to be in and
use of the land affected by the project, and (c) who have no legal right or without certification
report for the legal right to use land.
Persons of item (a) and (b) compensation for lost land and other assistance. Those
under item (c) relocation assistance, rather than compensation for the land they are and other
assistance, if necessary, to achieve the objectives outlined in this policy, if they have land
within the project area before the closing date specified in the RPs. Those who infringe on the
land after the closing date specified in the RP will not be entitled to any compensation or
resettlement assistance.
Valuation of damages and compensation method used to determine the value of
damage in projects financed by the Bank is based on the replacement cost (as defined in
section B). In this project, the damage includes the loss of land, buildings and other assets.
Replacement cost of land includes the value of land is determined by the market price plus the
cost of getting certificates of land use rights. For houses and other buildings, the value of
which is determined by the market prices of construction materials to build a replacement
house with an area and quality at least as old home before affected. For those works affected
part or entire should compensation value includes the market prices of construction materials
plus the cost of shipping materials, labor costs and contractor fees, registration fees and taxes
transfer.
3.1.3 The necessary differences and exemptions
Comparison between Government of Vietnam and World Bank Approaches: Although
Tay Ha Noi 220kV Substation Resettlement Plan
Institute of Energy - IE 18
the recent legislation on resettlement of Vietnam tends to be more consistent with that of the
World Bank, there still exists some discrepancies required particular attention. The
differences between the Government‟s Laws and Decrees and World Bank Policy with regard
to resettlement and compensation, and how to address these gaps are shown in Table 1.
Table 1 Comparison of Vietnam’s and World Bank’s Policies related to Involuntary
Resettlement
Subjects Bank’s OP 4.12 Government of
Vietnam
Project Measures
Land Property
Policy objectives
DPs should be assisted
in their efforts to
improve their
livelihoods and
standards of living or at
least to restore them, in
real terms, to pre-
displacement levels or
to levels prevailing
prior to the beginning
of project
implementation,
whichever is higher
Resettlement site and
its infrastructure
should have equal or
better development
conditions than the
existing one.
Livelihoods and
income sources will
be restored in real
terms, at least, to
the pre-
displacement levels
or to levels
prevailing prior to
the beginning of
project
implementation,
whichever is
higher.
Support for
affected
households who
have no
recognizable legal
right or claim to
the land they are
occupying
Financial assistance to
all project affected
persons to achieve the
policy objective (to
improve their
livelihoods and
standards of living or at
least to restore them, in
real terms, to pre-
displacement levels or
to levels prevailing
prior to the beginning
of project
implementation,
whichever is higher)
Financial assistance
provided at different
levels depending on
the “legal” status of
affected persons
Financial assistance
of an agreed
amount will be
given to all DPs,
regardless of their
legal status, until
their livelihoods
and standards of
living restore in
real terms, at least,
to pre-displacement
levels.
Compensation for
illegal structures
Compensation at full
cost for all structures
regardless of legal
Provided to cover the
new structure costs.
Depending on the
Compensation at
full replacement
cost will be given
Tay Ha Noi 220kV Substation Resettlement Plan
Institute of Energy - IE 19
Subjects Bank’s OP 4.12 Government of
Vietnam
Project Measures
status of the DP‟s land
and structure.
“illegality status”
attributed , covering
between 80% and 0%
of the total costs
for all structures
affected, regardless
of legal status of
the land and
structure.
Compensation
Methods for
determining
compensation rates
Compensation for lost
land and other assets
should be paid at full
replacement costs,
Compensation for lost
assets is calculated at
price close to
transferring the assets
in local markets or the
cost of newly-built
structures. Provincial
governments are
granted to annually
set up compensation
prices for different
categories of assets
Independent
appraiser identifies
replacement costs
for all types of
assets affected.
Provincial
government will
use this assessment
to establish the
compensation rates
at full replacement.
Compensation for
loss of income
sources or means
of livelihood
Loss of income sources
should be compensated
(whether or not the
affected persons must
move to another
location)
Assistance in respect
of income loss is given
only for registered
businesses. For
affected persons losing
agricultural land,
additional financial
support will be
provided.
All income losses
are to be
compensated and,
where necessary to
achieve the
objectives of the
policy,
development
assistance in
addition to
compensation will
be provided.
Compensation for
indirect impact
caused by land or
structures taking
It is good practice for
the borrower to
undertake a social
assessment and
implement measures to
minimize and mitigate
adverse economic and
social impacts,
Not addressed. Social assessment
has been
undertaken and
measures identified
and being
implemented to
minimize and
mitigate adverse
Tay Ha Noi 220kV Substation Resettlement Plan
Institute of Energy - IE 20
Subjects Bank’s OP 4.12 Government of
Vietnam
Project Measures
particularly upon poor
and vulnerable groups.
impacts,
particularly upon
poor and vulnerable
groups.
As a World Bank member country, the Government of Vietnam has committed that,
should the international agreements signed or acceded to by Vietnam with the World Bank
contain provisions different from those in the present resettlement legal framework in
Vietnam, the provisions of the international agreements with the World Bank shall prevail.
This RPF confirms that in approving this instrument, the Government of Vietnam and the
Province/City People‟s Committee, grant the waivers to the relevant articles in various
Vietnamese laws that contradict or are not consistent with the objectives set forth in this RPF.
The measures taken to address the differences and comply with World Bank involuntary
resettlement policies are addressed under this RPF.
3.2 COMPENSATION POLICY
3.2.1 Genaral Principles
All DPs who have assets within or reside within the area of project land-take before the
cut-off date are entitled to compensation or assistance for their losses. Those who have lost
their income and/or subsistence will be eligible for livelihood rehabilitation assistance, based
on the criteria of eligibility defined by the project and in consultation with the DPs.1 If, by the
end of the project, livelihoods have been shown not to be restored to pre-project levels,
additional measures will be provided.
- The compensation rates will be determined based on the results of independent
land/assets appraisal in a timely and consultative fashion. All fees and taxes on land
and/or house transfers will be waived or otherwise included in a compensation
package for land and structures/houses or businesses. The local authorities will ensure
that DPs choosing relocation on their own obtain, without additional cost, the
necessary property titles and official certificates commensurate with similar packages provided to those who choose to move to the project resettlement sites;
- Land will be compensated “land for land” or in cash according to the DP‟s choice
whenever possible. The choice of land for land must be offered to those losing 20% or
more of their productive land. If land is not available, the borrower must assure itself
that this is indeed the case. Those losing 20% or more of their land will have to be
assisted to restore their livelihood. The same principles apply for the poor and
vulnerable people losing 10% or more of their productive landholding;
- DPs that prefer “land for land” will be provided with land plots with the equivalent
1 Voluntary donation might be allowed for some types of lending projects, e.g., CDD projects, where there are those who may choose to voluntarily contribute affected land for the project construction. A procedure for determining and documenting the voluntary nature of the contribution should be set up and be clearly documented in the RP.
Tay Ha Noi 220kV Substation Resettlement Plan
Institute of Energy - IE 21
productive capacity for lost lands or a combination of land (a standard land plot) in a
new residential area nearby for residential land, and cash adjustment for the difference
between their lost land and the land plots provided. The resettlement area will be
planned properly and implemented in consultation with the DPs. All basic
infrastructures, such as paved roads, sidewalks, drainage, water supply, and electricity and telephone lines, will be provided;
- DPs that prefer “cash for land” will be compensated in cash at the full replacement
cost. These DPs will be assisted in rehabilitating their livelihoods and making their own arrangements for relocation;
- Compensation for all residential, commercial, or other structures will be offered at the
replacement cost, without any depreciation of the structure and without deduction for
salvageable materials. Structures shall be evaluated individually. Any rates set by
category of structure must use the highest value structure in that group (not the lowest);
- The DPs will be provided full assistance (including a transportation allowance) for
transportation of personal belongings and assets, in addition to the compensation at replacement cost of their houses, lands, and other properties;
- Plans for acquisition of land and other assets and provision of rehabilitation measures
will be carried out in consultation with the DPs (with particular attention to vulnerable
DPs), to minimize the disturbance and shorten the resettlement transition period. The
rehabilitation measures will be provided to the DP's prior to the expected start-up date of works in the respective project sites;
- If, by the end of the project, livelihoods have been shown not to be restored to pre-
project levels, additional measures should be considered;
- Financial services (such as loans or credits) will be provided to DPs, if necessary. The
installment amounts and the schedule of payments will be within the repayment capacity of DPs;
- Additional efforts, such as economic rehabilitation assistance, training and other forms
of assistance, should be provided to DPs losing income sources, especially to
vulnerable groups in order to enhance their future prospects toward livelihood restoration and improvement;
- The previous level of community services and resources, encountered prior to
displacement, will be maintained or improved for resettlement areas;
- Contractors can only commence civil works after (i) the governmental competent
agency has satisfactorily completed compensation payments and rehabilitation
assistances in accordance to approved RP for that sub-project; (ii) already-compensated
DPs have cleared the area in a timely manner; and (iii) the area is free from any encumbrances.
Temporary Resettlemen: Relocation of any households more than once should be
avoided, because it leads to DPs being impacted twice or more and will slow down the
livelihood restoration time. If it must happen, these households should be considered for
additional benefits as they have been impacted twice. If the implementing agency has verified
that temporary resettlement is unavoidable for such reasons as the final resettlement is subject
to the temporary resettlement (e.g., construction of the resettlement site will not take place
until the DPs are temporarily relocated) and an implementation plan for the final resettlement
Tay Ha Noi 220kV Substation Resettlement Plan
Institute of Energy - IE 22
is agreed by the DPs and approved by District People‟s Committee (DPC) or Provincial
People‟s Committee (PPC) and the Bank, then an additional assistance package is offered
3.2.2. Policies on compensation, assistance and resettlement applied to the subproject
3.2.1.1. Compensation for Loss of Agricultural Land
1) Legal and Legalized Land Users
If the lost area represents less than 20% of a Household‟s (HH‟s) land holding (or less
than 10% for poor and vulnerable groups), and the remaining area is economically viable,
compensation in cash will be at 100% replacement cost for the lost area.
If the lost area represents 20% or more of the HHs‟ land holding, (or 10% or more for the
poor and vulnerable groups) or the remaining area is economically not viable, then “land for
land” compensation should be considered as the preferred option.
a. If no land is available, then implementing agencies (IAs) must demonstrate this to the
World Bank‟s satisfaction before proceeding.
b. If land is not available, or if the DP prefers cash compensation, then cash
compensation will be provided for the lost area at 100% of land replacement cost, and
the DP will be provided with rehabilitation measures to restore the lost income
sources, such as agricultural extension, job training, credit access, provision of non-agricultural land at a location appropriate for running off-farm business or services.
c. If the DPs wish, and there is land of similar value elsewhere, the project should also
assist these DPs to visit these areas and help with legal transactions should they wish
to acquire them.
d. For agricultural land lying intermixed with residential areas, and garden and pond land
lying adjacent to residential areas, apart from compensation at the price of agricultural
land having the same use purpose, monetary support shall also be provided; with the
prices for such support being equal to between 50% and 70% of the prices of adjacent
residential land; and with the specific support levels being decided by the Provincial People's Committees (PPC) to suit local conditions.
2) Users with temporary or leased rights to use communal/public land (DPs who rent
communal or public land)
Cash compensation at the amount corresponding to the remaining investment put on the
land or corresponding to the remaining value of the land rental contract, if it exists.
For DPs currently using land assigned by State-owned agricultural or forestry farms on a
contractual basis for agricultural, forestry, or aquaculture purposes (excluding land under
special use forests and protected forests), compensation shall be provided for investments
made on the land, but not for the land itself, and these DPs may also receive additional
support according to the following provisions:
a. Additional monetary support shall be provided for DPs that receive land on a
contractual basis and are public employees or workers of State-owned agricultural or
forestry farms, or who are former employees of such farms and who are now receiving
an allowance related to their former employment. The highest level of additional
monetary support shall be equal to the price of land to be compensated, calculated on
the basis of the value of the affected land area which shall, however, not exceed the
local agricultural land assignment limits. The PPC shall decide on the specific support
Tay Ha Noi 220kV Substation Resettlement Plan
Institute of Energy - IE 23
levels to suit the local conditions but the additional monetary support shall not be less than 70% of the compensation value for the land actually acquired.
b. Where DPs receive land on a contractual basis but are other than the individuals
specified at (a) above, they shall only receive compensation for investments made on
the land.
3) Land Users without formal or customary recognized rights to the affected land
Instead of compensation, these DPs will receive rehabilitation assistance up to 100% of
the land value in cash. DPs will be entitled to rehabilitation measures mentioned above to
ensure their living standards are restored.
In case the land is rented through civil contract between individuals, households, or
organizations, then the compensation for crops, trees, or aquaculture products will be paid to
the affected land users and the project client shall assist the renter to find similar land to rent.
In cases when DPs utilize public land (or protected areas), with an obligation to return the
land to the Government when requested, the DPs will not be compensated for the loss of use
of the land. However, these DPs will be compensated for crops, trees, structures and other
assets they own or use, at full replacement cost. Although they cannot reside in such public
safety-hazard areas, if access has not been denied previously through well-documented signs
and such things as fences, the social and baseline assessment should consider if such a
physical impediment (like a newly restricted public safety area) is causing loss of livelihood
due to people no longer being able to get to jobs and other assets associated with their
subsistence as a result of restricted safety zone definition, which may for example add
significant cost to traveling from home to business, schools, etc.
3.2.2.2. Compensation for Loss of Residential Land
1) Losing of residential land without associated structures: Compensation for loss of land
in cash at replacement cost to legal and/or “legalizable” land users. For land users who have
no recognizable land use right, financial assistance of an agreed amount will be provided. The amount will be determined by the respective Provincial People‟s Committee.
2) Loss of residential land with associated structures and the remaining land is sufficient
to rebuild the structure (reorganizing DP): Compensation for loss of land will be made in cash
at (i) full replacement cost for legal and legalizable land users; (ii) Financial assistance of an
agreed amount will be provided to land users who do not have recognizable land use rights. If
DPs have to rebuild their houses, they will be provided with a rental allowance for a period of 3
months while their houses are being rebuilt.
3) Loss of residential land with associated structures and the remaining land is
insufficient to rebuild the structure (relocating DP): other than specific provisions listed
below, in case where relocated DPs belong to vulnerable groups, the project will consider
providing them with additional assistance (in cash and kind) to ensure that they can afford to relocated to a new site.
- For DPs who have legal or legalizable rights to the affected land:
A land plot of equivalent size and quality, in a well-developed resettlement site.
Where land is not available, an apartment will be provided to the DP. The will be done
in consultation with the DP. Full ownership title to the land or apartment will be given at no cost to the DP.
Tay Ha Noi 220kV Substation Resettlement Plan
Institute of Energy - IE 24
Or,
On request of and with full consultation with the DP, cash compensation at full
replacement cost, plus the amount equivalent to the value of the infrastructure
investments calculated as an average for each household in a resettlement site. In this case, the household will be expected to relocate themselves.
In the event that the compensation (or assistance) amount accounts less than the cost of a
land plot in the project‟s resettlement site, DPs will be supported with the difference required
for the acquisition of the land plot. If a land plot in the project resettlement site is not the
chosen DP‟s option, cash assistance will be provided equivalent to difference required to
acquire a chosen land plot.
- DPs who do not have formal or customary rights to the affected land:
Financial assistance of an amount to be determined by provincial People‟s Committee
will be given.
If the DP has no place to move, a land plot or an apartment satisfactory to them will be provided in the resettlement site.
In case the relocated DPs belong to poor or vulnerable groups or households, additional
assistance (in cash and kind) will be provided to ensure that they are able to fully relocate to a new site.
3.2.2.3. Compensation Policy for Loss of Houses/Structures
Houses
Compensation or assistance in cash will be made for all affected private-owned
houses/structures, at 100% of the replacement costs for materials and labor, regardless of
whether or not they have title to the affected land or a construction permit for the affected
structure. The compensation will be sufficient to rebuild the affected house/structure of the
same quality. As per OP 4.12 cash compensation will be at full replacement cost in local
markets. No deductions will be made for depreciation or salvageable materials.
If the house/structure is partially affected, a financial assistance will be provided to
enable DPs to repair the affected house/structures to restore it to the former condition, or
better, at no additional cost to them.
Graves
Compensation for the removal of graves/ tombs will include the cost of excavation,
relocation, reburial and other related costs which are necessary to satisfy customary
requirements. Compensation in cash will be paid to each affected family or to the affected
group as a whole as is determined through a process of consultation with the affected
community. The level of compensation will be decided in consultation with the affected
families/communities. Household and individual graves are considered physical cultural
resources (PCR) and even though the costs associated with their relocation may be covered in
the resettlement plan, the WB OP 4.11 on Physical Cultural Resources should be triggered
and relevant cross references should be made to the Environmental Management Plan or
project implementation manual.
Tenants
Tay Ha Noi 220kV Substation Resettlement Plan
Institute of Energy - IE 25
The tenants of state or organization‟s houses will be: (i) entitled to rent or buy a new
apartment of the area at least equal to their affected one if they/he/she have a demand for; or
(ii) provided an assistance equal 60% of replacement cost of the affected land and houses. The
structure created by the DPs themselves will be compensated at their full replacement costs.
The tenants who are leasing a private house for living purposes will be provided with
transportation allowance for moving assets, as well as will be assisted in identifying alternative
accommodation.
3.2.2.4. Compensation Policy for Loss of Standing Crops and Trees
For annual and perennial standing crops, regardless of the legal status of the land,
compensation will be paid to the affected persons, who cultivate the land, according to the full
market value of the affected crops and/or at replacement cost for affected perennial trees.
Regarding the removable affected trees, the compensation will be equal the transportation cost
plus actual loss. Perennial crops will be compensated for at the calculated value of their life time
productivity.
3.2.2.5. Compensation Policy for Loss of Income and/or Business/Productive Assets
For DPs losing income and/or business/productive assets as a result of land acquisition, the
mechanism for compensating will be:
- The registered non-farm producer/business DPs, who have income-generating and/or
business/productive assets affected, will be given cash business assistance for the loss
of business income, equivalent to 50% of the annual average for the last 3 years net
income. (This amount is equivalent to 100% of monthly net income for 6 months).
- The non-registered business or non-farm producer DPs, whose operations are
recognized by local authority and who have income and/or business/productive assets
affected, will be given assistance in cash for the income losses for three months at the
minimum
- If the business has to be relocated, then, a priority to provide a replacement business
site accessible to customers, or, compensation in cash for the affected area at a
replacement cost, plus transportation allowance to remove movable attached assets. If
there is no land available, then the business/non-farm producer DPs will be entitled for
rehabilitation measures such as job training, credit access to help restore the income sources.
3.2.2.6. Compensation Policy for Temporary Impact during Construction
In the event of temporary impact during construction, DPs are entitled to the following:
- Compensation for all affected assets/investments made on the land, including trees, crops etc., at full replacement cost;
- Cash compensation for land temporarily acquired in the form of rent which is at least
equivalent to the net income that would have been derived from the affected property during the period of disruption;
3.2.2.7. Damages to Private or Public Structures
Damaged property by contractor will be restored by contractors immediately at full
replacement value, after completion of civil works, to its former condition. Under their contract
specifications, the contractors will be required to take extreme care to avoid damaging property
Tay Ha Noi 220kV Substation Resettlement Plan
Institute of Energy - IE 26
during their construction activities. Where damages do occur, the contractor will be required to
pay compensation immediately to affected families, groups, communities, or government
agencies at the same compensation rates that are applied to all other assets affected by the
Project.
Compensation for loss of community assets: In cases where community infrastructure
such as schools, bridges, factories, water sources, roads, sewage systems is damaged, the project
will ensure that these will be restored or repaired at no cost for the community and to the
community‟s satisfaction.
3.2.2.8. Secondary DPs
This applies to those affected by development of individual resettlement or group
resettlement sites. Because all secondary DPs are likely to be affected in similar ways as
primary ones, they will be entitled to compensation and rehabilitation assistance in
accordance with the same respective provisions for all other DPs.
3.2.2.9. Allowances and Rehabilitation Assistance
Besides the compensation for affected assets, DPs will be provided with financial
assistance to cover their expenses during the transition period. The assistance levels will be
adjusted, taking into account inflation factor and price increase to be appropriate to the
payment time. These will be detailed in the RP. They include, but are not limited to:
- Transportation allowance will be given to relocating DPs. The amount will be determined by local authority
- House renting allowance or temporary accommodation will be provided for relocating
DPs during the time when the DPs are waiting for the land plot or apartment to be ready
plus for the period of building the new house.
- Removal Support: Organizations and DPs that are allocated or leased land by the state
or are lawfully using land and have to relocate their productive and/or business
establishments are entitled to financial support for dismantling, relocating and re-
installation of the establishment. Support levels will be determined by actual costs at
the time of removal, based on self-declaration of the organizations and verification by
the agency in charge of compensation. This will then be submitted to the relevant
authorities for approval.
- Subsistence allowance for relocating: All DPs (i) relocating within province shall
receive a cash allowance equal to 30 kg of rice per month in uninterrupted 03 months;
(ii) relocating out of province shall receive a cash allowance equal to 30 kg of rice per
month in uninterrupted 06 months; (iii) who are in a severe socioeconomic difficulty
or who relocating to areas of socioeconomic difficulty shall be receive cash allowance equal to 30 kg of rice per month in uninterrupted 12 months.
- Support for living stabilization: (a) DPs losing 20 - 70% of their agricultural
landholding (or 10 - 70% for the poor and vulnerable groups) will be provided with the
amount equivalent to 30 kg of rice/person/month for 6 months if they do not have to
relocate and 12 months in case of relocation. In some special cases, in extremely
difficult areas, the compensation may be provided for a maximum of 24 months; (b)
DPs losing more than 70% of their agricultural landholding will be assisted for 12
months if they do not have to relocate and 24 months in case of relocation. In some
special cases, in extremely difficult areas, the compensation may be provided upto a
Tay Ha Noi 220kV Substation Resettlement Plan
Institute of Energy - IE 27
maximum of 36 months; (c) Households affected by loss of less than 20% of land,
where the remaining land is rendered unviable for continued use, will be assisted with
the above support plus any additional support as determined, for a period of 12
months. In case of land-for-land compensation, DPs will be assisted with seedlings, agricultural-forestry extension programs, husbandry etc.
- Support for job changing (with several options provided depending on the interest of
the DPs): The support amount is 2-5 times of the agricultural land price for the whole
acquired agricultural area but not exceeding the local land allocation limit at the moment of handing over land.
- Support for training, apprenticeships on vocational training establishments in the
province and exemption from tuition fees for the training courses for those of working
age (not applicable for those who enroll for a vocational training outside the province).
After finishing training courses, they will be given priorities to be recruited in local manufacturers/businesses.
- Support for the poor and vulnerable groups: Additional support will be provided to the
poor and vulnerable groups to ensure they will be able to restore the losses and livelihood at least at pre-project level
- Other rehabilitation measures as agricultural extension services, job training and
creation, credit access, non-farm land allocation for non-farming business/activities,
and/or other measures as appropriate will be given to DPs losing major income sources to ensure their livelihood is restored to the pre-project level.
Relocation bonus: A bonus of maximum 5 million VND will be awarded to DPs who
dismantle their houses and vacate their premises in accordance with the resettlement
schedule.
Tay Ha Noi 220kV Substation Resettlement Plan
Institute of Energy - IE 28
4. RESETTLEMENT, SUPPORT AND COMPENSATION PLAN
4.1. COMPENSATION
Project Notification Date: Project notification date has been fixed as December 14st
2012 during survey and inventory process. Project notification date has been officially
announced by competent local authorities in very first community meetings at wards related
to the project.
Residents who encroach or move into estimated affected area after Project notification
date will have no right for compensation and resettlement. They will be requested to
dismantle structures, cut down trees or harvest their crops to clear land for the project, but
they do not have to pay any penalty. Project notification date and term “no compensation for
encroachers” have been clearly informed in community meetings.
Replacement price: In this subproject, damages only include land, perennials and crops.
Survey result shows that substation of the subproject is constructed in rural areas; most of
them have been used for gardening or rice and crops growing with long-term stability. There
is nearly no land, tree or crop transaction in these areas (mostly transferred to their children
and relatives), and though consultation with local authorities (Yen Noi Village, Dong Quang
Ward, Quoc Oai District, Hanoi), compensation price for land, trees and crops will apply
accordingly to unit price issued by Hanoi People Committee. Compensation unit price has
been widely announced in community consultation meetings and accepted by affected
households.
Decision of Hanoi People Committee on unit price applied in compensation: (i)
Decision No.108/2009/QD-UBND of Hanoi People Committee about regulations on
compensation, support and resettlement when the State recovers land in Hanoi. (ii) Decision
No.27/2013/QD-UBND dated July 18th 2013 of Hanoi People Committee about specific
regulation on determination of land price, resettlement house price as basis for compensation,
support and resettlement when the State recovers land in Hanoi. (iii) Notice No.7038/SCT-BG
dated December 31st 2012 of Hanoi Department of Finance on compensation and support unit
price for trees, crops, cattles servicing for land acquisition in Hanoi in 2013
It is necessary to notice that land unit price applied in this Resettlement Plan is only for
purpose of cost estimation (in period of preparing this Resettlement Plan). At time of
Resettlement Plan implementation (expected in 2014), land unit price will be updated to
ensure that AP will be compensated with replacement price for their losses.
Other impacts arising in the subproject will be applied Resettlement Policy Framework.
4.1.1. Compensation unit price for land
Table 4.1.1 – Permanent farmland compensation unit price
Local name
Price (dong/m2)
Land for rice Land for
seasonal tree
Land for
perennials
Land for
aquaculture
Dong Quang
Commune 135 000 135 000 158 000
135 000
LAND PRICE (Attached to Decision No.51/2012/QD-UBND dated December 28th
2012 of
Hanoi People Committee)
4.1.2. Compensation unit price for perenials
Table 4.1.2 – Perenials compensation unit price
Kinds Unit price (dong/tree)
Tay Ha Noi 220kV Substation Resettlement Plan
Institute of Energy - IE 29
Longan, litchi 800 000
Banana 35 000
COMPENSATION UNIT PRICE OF TREES AND CROPS FOR LAND ACQUISITION IN
HANOI 2013
(Attached to Notice No. 7038/2012/STC-BG dated December 31st 2012 of Hanoi Department
of Finance)
Note: Above Decision classifies numerous unit prices for different tree ages (usually 3-8
kinds according to tree ages), highest compensation price framework of affected perennials is
applied as table above.
4.1.3. Compensation unit price for food crops and crops
Table 4.1.3 – Food crops and crops compensation unit price
Kinds Unit price (dong /m2)
Plain rice 7 000
Corn 5 000
Kohlrabi, cabbage and
kinds of vegetables 8 000
COMPENSATION UNIT PRICE OF TREES AND CROPS FOR LAND ACQUISITION IN
HANOI 2013
(Attached to Notice No. 7038/2012/STC-BG dated December 31st 2012 of Hanoi Department
of Finance)
4.1.4. Compensation unit price for fish yield
Table 4.1.4 – Compensation unit price for fish yield
Unit price (dong /m2)
Fish
Normally fed, yield < 7 tons/ha 10 000
4.1.5. Total project compensation cost
Western Hanoi 220kV substation is located at paddy field in the territory of Yen Noi
Village, Dong Quang Commune, Quoc Oai District, Hanoi. Compensation items are
permanently acquired.
Table 4.1.5a – Compensation cost
No. Compensation
items Unit Quantity Unit (dong) Cost (dong)
1 Permanently
acquired
Land:
- For rice
- For crops
- Ponds
m2
55 687
6 694
900
135 000
135 000
135 000
8,542,935,000
7,517,745,000
903,690,000
121,500,000
Perennials:
- Longan, litchi
Tree
35
800 000
28,000,000
28,000,000
Food crop:
- Plain rice
m2
55 687
7 000
389,809,000
389,809,000
Crops:
- Kohlrabi, cabbage
and kinds of
vegetables
m2
6 694
8 000
53,552,000
53,552,000
Tay Ha Noi 220kV Substation Resettlement Plan
Institute of Energy - IE 30
Total 9,181,357,000
Table 4.1.5b – Summary of Land Acquisition cost:
Unit: dong
No. Items Cost
I Land compensation cost 38,443,207,500
2.1 Farmland 8,542,935,000
2.2 Living stability and training support (section 2.1 x 3,5) 29,900,272,500
II Compensation cost for perennials 28,000,000
III Compensation cost for food crop (plain rice) 389,809,000
IV Compensation cost for crops 53,552,000
TOTAL COST 38,914,568,500
4.2. LIVING REHABILITATION SUPORT FOR AFFECTED PEOPLE
In addition to direct compensation for losses, for people who are severely afected (have
to displace or lose more than 20% of owned land area or over 10% for vulnerable
households), they will alsi receive other supports (subsidies/allowances) in accordance with
Project Policy Framework. However, there is no case of this affected group in the subproject,
subsequently there is no living rehabilitation support activities in this Resettlement Plan.
Tay Ha Noi 220kV Substation Resettlement Plan
Institute of Energy - IE 31
5. COMMUNITY CONSULTATION AND INFORMATION ANNOUNCEMENT
5.1. COMMUNITY CONSULTATION AND PARTICIPATION
5.1.1. PUBLIC CONSULTATION
Public consultants are carried out by sending summary document of the subproject and
organized community meetings. This summary document was described subproject‟s
components, resettlement policy, frequently asked questions of APs, prevented methods for
risk of shock and protect measures for the substation's area, potential impacts and minimized
methods, etc.
Institute of Energy held community meetings at People‟s Committee of Dong Quang
communes on 04th Dec. 2012. Minutes of public consultant meetings and photos are presented
in Annex 5 of the RP.
Participant components who invited to the public consultation meeting consist of
representatives of subproject affected households, local authorities, Fatherland Front
Committee and local mass organizations (Women Union, Farmers Associations, etc.) (Please
see details in Annex 4).
In the consultation meetings, representatives of the subproject owner as the consultant
presented some major issues as follows:
- Introduction of the subproject and implementation schedule.
- Impacts on land, houses, structures, trees; mitigation measures for land acquisition; principles and policy of compensation; the grievance procedure.
- Impacts on air quality, noise, water quality, socio-economic activities and mitigation
measures.
In the community meetings, APs‟ queries on RP related issues such as entitlement,
compensation, etc., will be answered and recorded by representatives of the subproject owner;
and updated in the RP.
5.1.2. SYNTHESIS OF COMMUNITY CONSULTATION
Community consultation is carried out in 02 forms: deliver flyers Things to know about
compensation, land acquisition and power safety policies of the project; and hold community
meetings.
Flyers Things to know about compensation, land acquisition and power safety policies
of Transmission Efficiency Project have been prepared (in forms of question-answer and
images) and are delivered to 100% of affected households and officially published at project
areas (August 2013) – this is the basis for community and AP to participate in different stages
of the construction. This material consists of 2 main parts, specifically: (1) Frequentlt asked
of AP; (2) Images describing electrical accident countermeasures and power grid safety
corridor protection measures. Based on information provided in the flyers, damages and
losses survey result, compensation and support plan, Benefit Matrix and other compensation-
related works, local community and AP will directly and effectively participate into
supervision activities for implementation of the Plan. District Compensation Councils hold
meetings with concerned wards/villages to inform them about the subproject. In addition,
ward leaders also inform related local residents about potential impacts of the project,
especially Benefit Matrix.
Tay Ha Noi 220kV Substation Resettlement Plan
Institute of Energy - IE 32
Community consultation meeting was held at village office Yen Noi Village, Dong
Quang Commune, Quoc Oai District, Hanoi. The Owner and Consultant Unit consulted
residents‟ opinions on Resettlement Plan of subproject “Western Hanoi 220kV Substation”.
Representatives of the Owner and Consultant Unit presented to the public on the following
issues:
- Project Description: power line construction plan, location and importance of
substation and power line, financial resources invested for the project, project
objectives, project items
- Project compensation policy;
- Measures to minimize impacts and losses for residents, etc.
- Public representatives invited to community consultation meeting include:
representatives of affected households, authorities and related agencies, NGOs
(Women Union, Farmers Union, Veterans Union, etc.) and local power agency (For
more details see Apendix 5).
Table 5.1– Summary on residents’ opnion in community consultation meeting
No. Place/Time/Number of people
participating Opinions
– Village Office, Yen Noi Village,
Dong Quang Commune, Quoc
Oai District, Hanoi.
– Time: August 9th
2013
– Participated representatives: 60
persons (represented for
household)
– Request the Owner and Consultant Unit to
provide details of affected land area, announce
compensation unit price for land, trees and
assets affected by the Project;
– Request the Owner to protect environment
and people‟s health and safety during
construction process and later operation.
– It is requested to inform about project
compensation policy;
– Request the Owner and design unit to
carefully survey and have optimal designs and
construction methods in order to minimize
environmental impacts on residents;
– The implementation of the Project is of great
significance for local region and residents, so it
is requested to widely inform local residents
about the Project.
– Transportation of sand, stone and
construction materials will affect environment
and cause losses to residents, construction units
are expected to solve these and compensate;
– The Owner is requested to widely announce
Project compensation policy so affected
residents can approach.
– The Owner is requested to have appropriate
design solution to matter of electromagnetic
field for households near the substation.
Representatives of the Owner and Consultant Unit have provided information
concerning implementation time of the project, project land area, etc., received contributive
opinions and will make consideration on updating the report.
Tay Ha Noi 220kV Substation Resettlement Plan
Institute of Energy - IE 33
- Resettlement Plan. Apart from existing information in the material handed to
representatives, following information has been additionally provided to participants:
- Receive opinions on wide publishment of information on compensation policy for
affected households; Information will be provided at Dong Quang People
Committee, Quoc Oai District – location of the substation. Also, information will
announced by Quoc Oai Electricity Corporation;
- Land occupied by the project will be calculated and adequately compensated by the
Owner;
- During the operation of the substation, ponds and fields around substation rail
operate and cultivate normally;
- Substation design and construction solutions are in compliance with world standard,
ensuring matter of electromagnetic field for households around the substation, etc.
Above opinions and receiving opinions have bee updated in the content of this
Resettlement Plan.
5.2. DISCLOSURE
Per requirement of Bank‟s policy, the Vietnamese version of this draft report was
publically disclosed at project communes, PMBs, and VDIC of the World Bank office in
Hanoi (Jan. 2014). English version was also disclosed in InfoShop of the World Bank in
Washington D.C. Final versions (English and Vietnamese) will also be re-disclosed at project
sites, PMBs, VDIC and InfoShop.
5.3. GRIEVANCE REDRESS ADMINISTRATIVE
APs are entitled to the complaints regarding their interests and responsibilities in the
Project implementation including but not limited to such things entitlements to compensation,
compensation policy, unit prices, land acquisition, resettlement and other entitlements related
to the recovery support programs. Complaints can also concern issues related to construction
safety and nuisances caused by construction. Grievance procedures should be affordable and
accessible procedures for third party settlement of disputes arising from resettlement; such
grievance mechanisms should take into account the availability of judicial recourse and
community and traditional dispute settlement mechanisms. All complaints will be recorded, recognized and processed by the functional units at all levels.
Local mass organizations such as Fatherland Front, Farmers Association, Women‟s
Association etc. are mobilized to participate actively in the process of resolving complaints,
questions. APs can report their complaints (without any administrative and legal charges) to
the responsible units under district and commune/ward people‟s committee. PMB must ensure
having assigned staff in these responsible units to work on the project and maintaining a
throughout reporting system. Following the aforementioned arrangement, the grievance procedure will be:
- Step 1. Any persons who are not satisfied with any contents of the program of
economic recovery and resettlement can report verbally or in writing to their
Ward/Commune People‟s Committee (CPC) who will be responsible for resolving
their complaints within 15 days through inspection, and identification and proposal to
upper authorities.
- Step 2. After the due date, if there is no agreement, conciliation formed between APs
and CPC or no answer from CPC, APs can appeal to the District People‟s Committee (DPC) who will give their decisions within 30 days after receiving the complaints.
- Step 3. If after the due date, there is no agreement, conciliation formed between APs
and DPC or no answer from DPC no agreement/conciliation/answer is made, APs may
Tay Ha Noi 220kV Substation Resettlement Plan
Institute of Energy - IE 34
appeal to the responsible unit of Provincial People‟s Committee (PPC) who will give their decisions within 30 days after receiving the complaints.
- Step 4. If they are not satisfied with the decisions at the provincial level, APs may present their petition to their district administrative court.
AP‟s will be exempted from all administrative and legal fees. Besides that, an escrow
accounts for resettlement payments should be used when grievance is resolving to avoid
excessive delay of the project while ensuring compensation payment after the grievance has
been resolved. All GRC should maintain a system to register queries, suggestions and
grievances of the APs. All queries, suggestions and grievances and their resolution should be
recorded and forwarded to the PMB and its functioning monitored monthly. All the cost of GRM establishing and functioning should be included in the subproject cost.
Tay Ha Noi 220kV Substation Resettlement Plan
Institute of Energy - IE 35
6. REPORT, SUPERVISION AND EVALUATION
The implementation of Resettlement Plan needs to be regularly checked and supervised
by PMU in close cooperation with People Committees of all levels and independent
consultant units. All findings will be recorded in quarterly report and submitted to PMU of
electricity constructions in the North, EVNNPT and World Bank.
6.1. INTERNAL SUPERVISION
NPPMB is responsible for implementing internal supervision for execution of
Resettlement Plan. Internal check and supervision aim to:
- Verify that fundamental information of AP has been done, and costs of lost or
damaged assets, compensations, resettlement and other living rehabilitation rights
have been carried out in accordance with terms of policy framework and this
Resettlement Plan.
- Supervise to ensure the implementation of Resettlement Plan is in compliance with
approved design.
- Determine financial resouces provided for NPPMB timely and sufficiently for
purpose of implementing Resettlement Plan, and confirm these funds are used in
accordance with terms of Resettlement Plan and policy framework.
- Record all complaints and solutions, and ensure complaints are dealt within regulated
time.
Staffs for resettlement and land acquisition compensation of subproject execution unit
are responsible for updating information based on some following activities:
Table 6.1 – Some fundamental activities of internal supervision and evaluation
No. Resettlement Plan activities Perform
Description
Yes No
1 Inform residents and local
authority about the project x
2 Inventory total damages x
3 Survey replacement cost x
4 Establish Resettlement Plan x
5 Approve Resettlement Plan x
- EVNNPT x
- Hanoi People Commitee
- Dong Quang Commune,
Quoc Oai District People
Committees
- World Bank
6 Proclaim Resettlement Plan x
- Project location: Dong
Quang Commune, Quoc Oai
District
x
Tay Ha Noi 220kV Substation Resettlement Plan
Institute of Energy - IE 36
No. Resettlement Plan activities Perform
Description
Yes No
7 Count and measure x
8 Apply compensation price (from
Resettlement Plan) x
9 Build up specific Compensation
Plan x
10 Approve Compensition Plan x
11 Annouce Compensition Plan x
12 Adjust and approve (if any) x
13
Cover compensation (including
updated amount comparing with
Resettlement Plan – for example:
number of AP, cost, affected
degree, etc.)
x
14 Internally supervise x
15 Independently supervise x
16 Report on plan implementation x
17 Collect and solve complaints x
18 Community consultation and
participation x
- Public meeting x
- Provide flyers
19 Cooperate with other agencies
(especially Compensation Council) x
20 Mid-term and end-term evaluation
(joined with the project) x
Tay Ha Noi 220kV Substation Resettlement Plan
Institute of Energy - IE 37
6.2. INDEPENDENT MONITORING
An independent agencies or individual consultants contracting with NPPMB periodically
carry out external monitoring and evaluation of the implementation of RPs. The independent
agencies can be academic or research institutions, non- Governmental Organizations (NGO)
or independent consulting firms, all with qualified and experienced staff and terms of
reference acceptable to the World Bank. Independent monitoring begins about the same time
as implementation activities and continues until the end of project/subproject.
Independent monitoring can be contracted with NPT once for all sub-projects. The scope of
work and other terms of conference will be prepared by NPT which then will be sent to WB
for review.
Independent monitoring Agency will:
Prepare the action plan for the involvement of DPs; check whether the compensation
and other benefits are in line with WB‟s Policy framework or not;
Assess whether the objectives of Policy framework in tern of improving or at least
maintaining income and living standard for the DPs are successfully achieved or not;
Collect the quality indicators of the economic-social impacts of the Sub-project on DPs;
Make recommendations on adjusting the RP‟s implementation plan in individual cases
to achieve the objectives and aims of Policy framework.
6.3. REPORTING CONDITION
Internal monitoring agencies will prepare a quarterly report detailing the progress of
RP implementation; the report should be made available to EVN/NPT, WB, and independent
external monitoring agency. The terms for the independent external monitoring agency will be
detailed in the contract (Independent external monitoring agency and NPPMB).
A Resettlement Plan cannot be considered complete until a completion audit or survey
confirms that all entitlements have been received by beneficiaries and livelihood restoration is
progressing on schedule.
Tay Ha Noi 220kV Substation Resettlement Plan
Institute of Energy - IE 38
7. IMPLEMENTATION SCHEDULE
7.1. IMPLEMENTATION RESPONSIBILITY
Southern Power Project Management Board (NPPMB)
NPPMB, representing NPT, have following responsibilities:
- Prepare RPs in accordance with the RPF. Coordinate with the provincial People‟s
Committees and local authorities to obtain consensus from provincial People‟s Committee for the RPs and submit them to the WB for review and clearance.
- Develop and implement a training program for the provincial and district People‟s
Committee‟s, relevant stakeholders involved in RP implementation and Grievance Redress.
- Where relevant, provide technical support (e.g. consultation mobilization) in
identifying the replacement cost to inform compensation rate during the RP
implementation.
- Secure timely availability of required budget for RP preparation and implementation;
- Conduct internal monitoring of RP implementation as per requirements set out in the project‟s RPF and the RPs.
- Prepare bi-annual progress reports and submit to WB
- Designate staff with solid experience in resettlement and familiar with Bank‟s safeguard policies as a social focal point for PMB.
- Take part in compensation, support and resettlement council at local level and ensure
that the agreed RPs are properly implemented, documented and reported.
- Work closely with competent governmental agencies to address concern, grievances related to resettlement in their managed subprojects.
Provincial People‟s Committees (PPC)
Provincial People‟s Committees have responsibilities as follows:
- To direct, organize, propagate and mobilize all organizations and individuals
concerning compensation, support and resettlement policies and ground clearance
according to the land recovery decisions of competent State bodies;
- To direct the provincial/municipal services, departments, branches and district-level
People's Committees: (i) To draw up resettlement and resettlement area plans in
service of the land recovery; (ii) To draw up compensation, support and resettlement
plans according to their competence;
- To approve or assign the district-level People's Committees to approve compensation, support and resettlement plans;
- To approve land prices; promulgate the property price tables for compensation
calculation; prescribe support levels and supporting measures according to their
competence; resettlement arrangement plans, job change training plans according to their assigned competence;
- To direct the concerned agencies to settle citizens' complaints, denunciations related to compensation, support and resettlement according to their law-prescribed competence;
- To guarantee impartiality and equity when considering and deciding on the
compensation, support and resettlement when land is recovered by the State according
Tay Ha Noi 220kV Substation Resettlement Plan
Institute of Energy - IE 39
to their competence prescribed in this Decree;
- To decide or assign the district-level People's Committees to apply coercion to cases
of deliberately failing to abide by the State's land recovery decisions according to their competence;
- To direct the examination and handling of violations in the compensation, support and
resettlement domain.
District People‟s Committees
The District People‟s Committees have responsibilities as follows:
- To direct, organize, propagate and mobilize all organizations and individuals
concerning compensation, support and resettlement policies and ground clearance according to the land recovery decisions of competent State bodies;
- To direct the compensation, support and resettlement councils of the same level to
draw up, and organize the implementation of, the compensation, support and
resettlement plans; approve the compensation, support and resettlement plans
according to the responsibility assignment by the provincial-level People's
Committees;
- To coordinate with the provincial/municipal services, departments and branches,
organizations and investors in executing investments projects to build and plans to
create resettlement areas in their localities according to the assignment of the
provincial-level People's Committees;
- To settle citizens' complaints, denunciations related to compensation, support and
resettlement according to their assigned competence; issue coercive decisions and
organizing coercion in the cases falling under their competence; coordinate with the
functional agencies in organizing coercion according to the decisions of competent bodies.
Compensation, support and resettlement councils
The compensation, support and resettlement councils shall assist the People's Committees
of the same level in making, and organizing the implementation of, compensation, support
and resettlement arrangement plans; work on the collective principle and decide by majority;
where the numbers of votes for and against are equal, the opinion of the side joined by the council chairman shall be followed. Responsibilities of council members are as follow:
- The council chairman shall direct the council members to make, submit for approval
and organize the implementation of, the compensation, support and resettlement plan;
- The investor shall be responsible for assisting the council chairman in making the
compensation, support and resettlement plan, ensuring sufficient funds for timely payment of compensation, support and resettlement money;
- Representatives of persons who have land recovered shall be responsible for reflecting
the aspirations of persons who have land recovered, persons who must be relocated;
mobilizing persons who have land recovered to move and clear the ground according to schedule;
- Other members shall perform the tasks as assigned and directed by the council
chairman, suitable to their respective branches.
- The compensation, support and resettlement councils shall be responsible for the
accuracy and rationality of inventory statistics, the legality of land and property
Tay Ha Noi 220kV Substation Resettlement Plan
Institute of Energy - IE 40
eligible or ineligible for compensation, supports in the compensation, support and resettlement
Center for Land Fund Development
The Center for Land Fund Development has main responsibilities related to resettlement as follows:
- To assume the prime responsibility for, or coordinate the with the compensation and
ground clearance council in, organizing compensation and ground clearance;
- To work and coordinate closely with project‟s stakeholders to update and implement RP as per project‟s RPF.
- To provide compensation and ground clearance services;
- To develop resettlement areas;
- To build infrastructure on land funds assigned to it for management in order to organize auction;
- To provide information on land prices and land funds to organizations and individuals
upon request;
- To assist the District People‟s Committee and Provincial People‟s Committee in disseminating information related to Resettlement Plan.
- To assist the District People‟s Committee in handling complaints at district level.
- To perform other tasks under decisions of the provincial-level People's Committee.
Commune People's Committees
The Commune People's Committees shall have the responsibilities:
- To organize propaganda on the land recovery purposes, compensation, support and resettlement polices of the projects;
- To coordinate with the compensation, support and resettlement councils in certifying
land and property of persons who have land recovered;
- To join in, and create conditions for, the payment of compensation and support money
to, and arrange resettlement for, persons who have land recovered, and create conditions for the ground clearance.
Displaced persons (DPs)
DPs are ready with their necessary RP related papers i.e. LURC, ownership of other
assets.
DPs are responsible for carefully checking on their lost assets and respective entitlements and clear land in a timely manner once DPs receive full entitlements.
Independent Monitoring
An independent agency is responsible to supervise and evaluate implementation of RP for
the subproject. This agency will submit monitoring reports periodically during
implementation of RP and suggest solving measures for all identified issues to SPPMB and WB.
7.2. IMPLEMENTATION SCHEDULE
Project Management Unit and Compensation Council:
Tay Ha Noi 220kV Substation Resettlement Plan
Institute of Energy - IE 41
1. Establish Compensation Council: District Compensation Council has been
established.
2. Implement public announcement 06. 2014
3. Implement detailed measurement and asset inventory 07. 2014
4. Implement compensation payment 09. 2014
Affected people:
1. Declare amount and legal status of assets 06. 2014
2. Receive compensation and clear land 09. 2014
Bid Invitation:
Equipment Bidding: 04. 2013
Construction work:
Implement construction 01. 2015
(Construction progress is expected to complete the project within 10 months)
Supervision: 06. 2014 ÷ 11. 2015
Note:
- With insignificant impact (without resettlement) and with appropriate personnel
force, community annoucement, detailed measurement and drawings and inventory
are expectedly completed within 2 months, and actual compensation work will also
be completed within 2 months.
- Above implementation progress has bên discussed between Consultant and PMU
with consideration of construction amount of the project, number of related
communes in each district, appropriate personnel force and ability of implementing
parallely several activities. All activities of Resettlement Plan must be well
completed before World Bank issues document on not objecting subprojects. Any
change in the Resettlement plan after World Bank‟s approval needs to be considered
by World Bank‟s Hanoi representative office before deployment.
Tay Ha Noi 220kV Substation Resettlement Plan
Institute of Energy - IE 42
8. COSTS
Cost for the implementation of Resettlement Plan: from EVNNPT.
EVNNPT will transfer this cost to PMU, NPPMB and Compensation Committee for
them to take charge:
(i) Compensation payment for AP, and
(ii) Payment for costs of all activities of Resettlement Plan.
8.1. COSTS FOR IMPLEMENTATION OF RESETTLEMENT PLAN
Costs for implementation of Resettlement Plan include:
8.1.1. Costs for Resettlement Plan establishment and detailed measurement
Resettlement Plan establishment cost
In the beginning stage preparing for Resettlement Plan establishment, a workforce for
survey is established. This force will carry out: (a) study design and survey site, (b) establish
survey and statistics forms (with preliminary measurement of real estates and asset inventory),
(c) organize community consultation and other meetings, deliver Flyers/questionaires related
to the project, etc., (d) process data, and (e) establish Resettlement Plan for approval.
PMU has signed a contract with the Consultant for the implementation of above works.
Value of contract with the Consultant (While this Resettlement Plan is prepared, the
contract has not been signed. The above value is estimated and proposed by the Consultant):
210,000,000 dong
Detailed measurement, drawing and inventory cost
Preparing for implementation of Resettlement Plan, work support groups of DCC are
mobilized to: (a) prepare for deatiled measurement and drawing, statistics forms, materials on
resettlement, (b) organize community meetings, (c) deatiled measurement and drawing and
inventory, (d) negociate with AP and (e) complete compensation form for AP and submit to
DCC for approval.
Cost for deatiled measurement and inventory (temporary): 220,000,000 dong
Total cost for Resettlement Plan establishment and detailed measurement: 430,000,000
dong
8.1.2. Cost for compensation
- Compensation for permanently acquired lands.
- Compensation for permanently affected perennials (including tree cut cost), food
crops and crops.
(For more details see Section 4.1.5. Total project compensation cost)
8.1.3. Cost for management
Cost for personnel of PMU and Compensation Council: include basic salary and
allowance for administrative organization. Local PMU and Compensation Committee will
deploy numerous works during the implementation of the project, and only few members are
contracted for work in a given period of time.
Cost for training, meetings and information annoucement: One intermediate and one
primary training course are expectedly organized at the beginning of the implementation of
Resettlement Plan, and one workshop is expectedly organized at the beginning of
compensation payment. For the convenience of project-related local authorites, training
courses and workshop are proposed as short-term ones: 01 day.
Total cost for Management: 786,891,370 dong
(estimated 2% of total cost for Resettlement Plan establishment and compensation)
Tay Ha Noi 220kV Substation Resettlement Plan
Institute of Energy - IE 43
8.1.4. Cost for supervision
Cost for independent offline consultant unit: still cannot estimate exact cost yet, thus
approximately 2% of total cost for Resettlement Plan establishment and compensation.
8.1.5. Contingency
Up until expected time for implementing Resettlement Plan (2012) and from experience
gained through executed and executing projects with similar nature, contingency is calculated
as about 20% of total cost for compensation and Resettlement Plan establishment.
8.2. TOTAL COST ESTIMATE OF RESETTLEMENT PLAN
Bảng 8.2 – Total cost estimate of Resettlement Plan
Unit: dong
STT Items Cost
I Resettlement Plan preparation and Detailed Measure 430,000,000
1.1 Begining stage (Resettlement Plan Preparation) 210,000,000
1.2 Implementating stage (detailed measure and draw,
inventory) 220,000,000
II Compensation cost 38,914,568,500
2.1 Farmland 8,542,935,000
2.2 Living stability and training support (section 2.1 x 3,5) 29,900,272,500
2.3 Compensation cost for perennials 28,000,000
2.4 Compensation cost for food crop (plain rice) 389,809,000
2.5 Compensation cost for crops 53,552,000
III Compensation ost for land acquisition (2%(I+II)) 786,891,370
IV Cost for compensation supervision (TT 2%(I+II)) 786,891,370
VI Contingency (10%(I+II)) 3,934,456,850
TOTAL COST
Rounded
44,852,808,090
44,853,000,000
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 44
APPENDICES
1. Project Areas
2. Entitlement Matrix
3. Agreements on T/L Routes
4. Minutes and photos of Community Meetings
5. Samples of 'Questionnaire'
6. Samples of 'Pamphlet'
7. Inventory of Sub-project Affected People
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 45
Appendix 1
SUBPROJECT’S AREA
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 46
The position of Tay Ha Noi 220kV Sbstation
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 47
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 48
Appendix 2
ENTITLEMENT MATRIX
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 49
Appendix matrix
No. Type of loss Application Definition of
entitled DPs Compensation Policy Implementation Issues
1 Temporary
acquisition of
productive land
in ROW
All DPs have
trees, crops,
other assets in
ROW
DPs with/without
land certificate
included in the
inventory or able to
prove land
occupancy prior to
cut-off date.
- Cash compensation for affected trees
at the replacement cost plus cost for
cutting trees, crops at market price.
Number of crop patterns to be
compensated based on the time of
temporarily acquired of land.
- No compensation for land
- Rehabilitate land after the project
construction.
- Trees have to be cut are regulated by Article 5
of the Government Decree 106/2005/ND-CP
dt.Aug 17th, 2005 on the protection of the high
voltage networks and additional issues as stated
in decree 81/2009/ND-CP, dated on October
12, 2009, revising and supplementing a number
of articles under decree 106/2005/ND-CP..
- PCs and local authorities determine and
ensure that compensation for trees will be at the
replacement cost and for crops at the market
price. If DP is requested for cutting affected
trees, PCs or Provinces will pay money for this
work. DP has right for using salvageable trees.
- Full compensation at least 01 month before
land clearance. Payment to DPs will be
delivered by PC and/or District Resettlement
Committees (DRCs).
- Affected land in ROW will be rehabilitated
by contractors after the project construction and
land in ROW could be used with the restricted
purposes.
- Finance available for compensation and well
information disclose/ disseminate to DPs and
key stake holders.
2 Temporary
acquisition of
residential and
garden land in
All DPs with
orchards or
trees in ROW
-do- Cash compensation for affected fruit
trees and trees at replacement cost.
No compensation for land
Rehabilitate land after the project
Trees have to be cut are regulated by Article 5
of the Government Decree 106/2005/ND-CP
dt.Aug 17th, 2005 on the protection of the high
voltage networks and additional issues as stated
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 50
No. Type of loss Application Definition of
entitled DPs Compensation Policy Implementation Issues
ROW without
house or
structures in
ROW
construction. in decree 81/2009/ND-CP, dated on October
12, 2009, revising and supplementing a number
of articles under decree 106/2005/ND-CP..
PCs and local authorities determine and ensure
that compensation for trees will be at the
replacement cost. If DP is requested for cutting
affected trees, PC or Provinces will pay money
for this work. DP has right for using
salvageable trees.
Full compensation to DPs at least 01 month
before land clearance. Affected land in ROW
will be rehabilitated by contractors after the
project construction
Payment to DPs will be delivered by PCs and
DRCs
Finance available for compensation and well
information disclose/ disseminate to DPs and
key stake holders.
3 Temporary
impact on
residential and
garden land.
Partial
house/building
within ROW
and the
demolished
area does not
impact to the
remaining
All DPs have
house/building
and trees/fruit
trees in ROW
-do- House/ building:
- DP can opt for : i) Remain their
houses or building in ROW with the
conditions regulated by Article 6 of
the Government Decree
106/2005/ND-CP dt.Aug 17th, 2005
on the protection of the high voltage
networks and additional issues as
stated in decree 81/2009/ND- CP,
dated on October 12, 2009, revising
and supplementing a number of
articles under decree 106/2005/ND-
- House and building have to be demolished or
could be existed are regulated by Article 5,6 of
the Government Decree 106/2005/ND-CP
dt.Aug 17th, 2005 on the protection of the high
voltage networks and additional issues as stated
in decree 81/2009/ND-CP, dated on October
12, 2009, revising and supplementing a number
of articles under decree 106/2005/ND-CP.
- PCs and local authorities determine and
ensure that compensation will be paid at the
replacement cost, without deduction for
salvageable materials.
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 51
No. Type of loss Application Definition of
entitled DPs Compensation Policy Implementation Issues
house/building.
Residential
land and
garden land
outside of
ROW is
sufficient for
re-organizing
(not less than
60 m2).
CP. Subsidy allowance for fireproof
materials and lightning arrestors for
the existing house/building; or ii)
Cash compensation for the directly
affected rooms at the replacement cost
and cost for demolishing an affected
room.
- No compensation for land.
- Rehabilitate land after the project
construction by contractors.
Tree and fruit tree
- Compensation for affected trees and
fruit trees at the replacement cost.
Allowances:
- Relocating allowance of 30 kg of rice
equivalent per person per month in six
months.
- DPs will demolish the impacted part/ room
and reconstruct/or improve their houses
themselves.
- Full compensation for trees and fruit trees at
least 01 month before land clearance. If DP is
requested for cutting affected trees, PC or
project provinces will pay money for this work.
DP has right for using salvageable trees.
- Full entitlement payment to DPs impacted
on house/building at least 03 months before
land clearance.
- Payment to DPs will be delivered by PCs
and/or DRCs
- Land in ROW could be used with restricted
purposes.
- Finance available for compensation and well
information disclose/ disseminate to DPs and
all key stake holders.
4 Temporary
impact on
residential and
or garden land,
but the
demolished
area will
impact to the
remaining of
house/structure.
Land outside of
ROW is
All DPs have
house/building
and trees/fruit
trees in ROW
-do- House/ building:
- DP can opt for : i) Remain their
houses or building in ROW with the
conditions regulated by Article 6 of
the Government Decree
106/2005/ND-CP dt.Aug 17th, 2005
on the protection of the high voltage
networks and additional issues as
stated in decree 81/2009/ND- CP,
dated on October 12, 2009, revising
and supplementing a number of
articles under decree 106/2005/ND-
- House and building have to be demolished or
could be existed are regulated by Article 6 of
the Government Decree 106/2005/ND-CP
dt.Aug 17th, 2005 on the protection of the high
voltage networks and additional issues as stated
in decree 81/2009/ND-CP, dated on October
12, 2009, revising and supplementing a number
of articles under decree 106/2005/ND-CP..
- Consultation for DP‟s options on remains
their house in ROW or move out of ROW.
- PCs and local authorities determine and
ensure that compensation will be replacement
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 52
No. Type of loss Application Definition of
entitled DPs Compensation Policy Implementation Issues
sufficient for
reorganizing
(not less than 60
m2 for urban
areas and 100
m2 for urban
areas).
CP. Subsidy allowance for fireproof
materials and lightning arrestors for
the existing house/building; or ii)
Cash compensation at replacement
cost for full areas of impacted
house/building and demolish DP‟s
house in ROW.
- No compensation for land.
- Rehabilitate land after the project
construction by contractors.
Tree and fruit tree
- Compensation for affected trees and
fruit trees at the replacement cost.
Allowances:
Relocation allowance of 30 kg of rice
equivalent per person per month in six
months.
cost at the time of payment.
- DPs will demolish the impacted areas and
reconstruct/or improve their houses themselves.
- Full compensation for trees and fruit trees to
DPs at least 01 month before land clearance. If
DP is requested for cutting affected trees, PMB
will pay money for this work. DP has right for
using salvageable trees.
- Full compensation payment for impacted
house and allowances to DPs at least 03
months before land clearance.
- Payment to DPs will be delivered by PCs and
DRCs
- Cleared residential could be reused with other
restricted purposes.
Finance available for compensation/
rehabilitation and well information disclose/
disseminate
5 Temporary
impact on
residential and
or garden land
in ROW. Full
or partial
house/building
impacted and
land outside of
is not
sufficient for
reorganizing
All DPs have
house/building
and trees, fruit
trees in ROW
-do- DPs can opt for one of the followings:
i) Remain their houses or building in
ROW with the conditions regulated by
Article 6 of the Government Decree
106/2005/ND-CP dt.Aug 17th, 2005
on the protection of the high voltage
networks and additional issues as
stated in decree 81/2009/ND-CP,
dated on October 12, 2009, revising
and supplementing a number of
articles under decree 106/2005/ND-
CP. Subsidy allowance for fireproof
- House and building have to be demolished or
could be existed are regulated by Article 6 of
the Government Decree 106/2005/ND-CP
dt.Aug 17th, 2005 on the protection of the high
voltage networks and additional issues as stated
in decree 81/2009/ND-CP, dated on October
12, 2009, revising and supplementing a number
of articles under decree 106/2005/ND-CP..
Consultation for DP‟s options on remain their
house in ROW or move out of ROW
- PMB and local authorities determine and
ensure that compensation will be at
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 53
No. Type of loss Application Definition of
entitled DPs Compensation Policy Implementation Issues
(less than 60
m2)
materials and lightning arrestors for
the existing house/building; or ii)
Cash compensation for the whole
residential area which DP occupied
(not only for the impacted areas) and
properties associated with occupied
land at replacement cost. Impacted
land will be obtained by local
authorities; or ii) “Land for land” with
the same area which DP occupied and
cash at replacement cost for the
affected assets associated with land.
Land occupied by DP will be obtained
by local authorities.
- Compensation for affected trees and
fruit trees at the replacement cost.
Allowances:
- Relocating allowance of 30 kg of
rice equivalent per person per month
in six months
- Transportation allowance for
relocating DP according to the
Compensation Decree 197/2004/ND-
CP dated Dec 3rd , 2004 of GOV.
- Rehabilitation assistance if DPs
permanently losing business or more
than 10% of their incomes.
Incentive for relocating in a timely
manner: maximum 5,000,000
VND/HH
replacement cost at the time of payment.
- Replacement land, and resettlement sites
development
- DPs receive compensation will demolish the
impacted house areas and reconstruct/or
improve their houses themselves.
- Full compensation payment for trees and fruit
trees to DPs at least 01 month before land
clearance. If DP is requested for cutting
affected trees, PCs or project provinces will
pay money for this work. DP has right for
using salvageable trees.
- Full compensation for impacted house and
allowances to DPs at least 05 months before
land clearance.
- Payment to DPs will be delivered by PCs and
DRCs
- Cleared residential could be used with other
restricted purposes.
- Finance/ land available for rehabilitation and
restoration and well information disclose/
disseminate to DPs and key stake holders..
- PCs and local authorities will consult with DP
who are eligible to restoration programs for
their options and prepare proposal for
restoration programs in the period of RAP
implementation.
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 54
No. Type of loss Application Definition of
entitled DPs Compensation Policy Implementation Issues
Permanent
acquisition of
land for tower
foundations,
substation and
access roads
etc.
All DPs
occupied
land and
properties
associated
with land
permanently
impacted by
towers
foundations,
substation
and access
roads etc
-do- For DP losing productive land:
a. Land loss less than 20% of their
total landholdings, and 10% for the
poor and vulnerable group
Cash compensation for the lost area
if the remaining plot is still
economically viable.
Cash compensation for the whole
impacted plot if the remaining plot is
not economically viable.
Cash compensation for properties
associated with land
b. Land loss equal or more than 20%
of their total landholdings, and 10%
or more for the poor and vulnerable
group:
DP can opt for the followings:
“Landfor land” with the same area
and productive of impacted area if
the remaining plots are still
economic viable and for the whole
impacted plots if the remaining plots
are not economic viable
Cash for land at the replacement
cost.
Compensation for trees and affected
fruit trees at the replacement cost.
Rehabilitation assistances.
For DP losing Residential and garden
land:
Consultation for DP‟s options on land
compensation.
PMB and local authorities determine and
ensure that compensation will be at
replacement cost at the time of payment.
Replacement land, and resettlement sites
development.
DPs receiving compensation will demolish the
impacted areas and reconstruct/or improve
their houses themselves.
Full compensation for trees and fruit trees to
DPs at least 01 month before land clearance.
If DP is requested for cutting affected trees,
PMB will pay money for this work. DP has
right for using salvageable trees.
Full compensation for impacted house and
allowances to DPs at least 05 months before
land clearance.
No award civil work contract before
completion of compensation and reorganizing
houses or relocation.
Payment to DPs will be delivered by PCs and
DRCs
Finance/ land available for compensation/
rehabilitation and well information disclose/
disseminate.
PCs and local authorities will consult with DP
who are eligible to restoration for their
options and prepare proposal for restoration
programs in the period of RAP
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 55
No. Type of loss Application Definition of
entitled DPs Compensation Policy Implementation Issues
With respect to garden land or ponds
which are attached to the affected
residential land, and the affected
agricultural land which is located
within the residential/settlement area,
the Project will provide an assistance
of 50% of price of the neighboring
residential land in addition to
compensation at replacement cost for
agricultural land as regulated by the
laws.
With respect to residential land, DP
will be entitled to:
If remaining land is sufficient for
reorganizing (not less than 60 m2):
Cash compensation for lost area and
assets associated with land.
If remaining land is not sufficient for
reorganizing:
DP can opt for i) cash compensation
at replacement cost for land and
assets on land, or ii) “land for land”
compensation for the whole
residential area which DP occupied
(not only for the impacted areas) and
properties associated with occupied
land. For affected house and
building, the same entitlement to DP
of categories 3 or 4 or 5.
implementation.
DPs will be granted with Land Use Right
Certificate without payment of administrative
fees.
7 DP impacted on All DPs -do- Temporary impact on business or Full compensation for incomes lost to DPs at
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 56
No. Type of loss Application Definition of
entitled DPs Compensation Policy Implementation Issues
business or
other services
impacted on
business and
other services
other services.
Compensation for income lost in the
affected time
Permanent impact on business or other
services.
Rehabilitation assistance.
least 01 month before land clearance.
PCs and local authorities will consult with DP
who are eligible to rehabilitation for their
options and prepare proposal for rehabilitation
programs in the period of RAP implementation.
8 Public Work
Temporary
Impacts
All
impacted
institutional
DPs (who
directly
manage and
operate
such
impacted
public work
system)
All impacted
institutional DPs
shall be
approached in
advance for
cooperation for
impact mitigation
measure as well
as measure for
maintaining the
normal
functioning of
their impacted
system by the
Contractor (s)
Alternative measures to maintain
the normal functional of the public
work (i.e road, water supply,
drainage system, telephone line ect)
Reinstatement after the project
construction
All expense on alternative measures
to maintain the normal functioning
of the impacted system shall be
born by Contractor (s)
Contract (s) with Contractor (s) should bear
one article on this specific responsibility of
the contractor (s)
Approach for institutional DPs for
cooperation
Arrange and pay the expenses for te
alternative measures to maintain the normal
functioning of the impacted system to the
satisfaction of the institutional DPs.
Permanent
Impacts
-do- -do- Alternative measures to maintain
the normal functional of the public
work (i.e road, water supply,
drainage system, telephone line ect)
-do-
Complete the work for “alternative solution”
prior to commencement of the project work.
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 57
Appendix 3
AGREEMENTS ON SUBSTATION’S POSITION
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 58
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 59
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 60
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 61
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 62
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 63
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 64
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 65
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 66
Appendix 4
SAMPLES OF MINUTES OF COMMUNITY MEETINGS
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 67
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 68
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 69
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 70
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 71
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 72
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 73
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 74
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 75
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 76
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 77
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 78
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 79
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 80
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 81
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 82
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 83
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 84
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 85
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 86
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 87
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 88
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 89
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 90
Appendix 5
PHOTOS
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 91
Working with Dong Quang People‟s Community
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 92
Conducting survey
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 93
Appendix 6
BROCHURES
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 94
TẬP ĐOÀN ĐIỆN LỰC VIỆT NAM
TỔNG CÔNG TY TRUYỀN TẢI
ĐIỆN QUÔC GIA
Dự án truyền tải hiệu quả (TEP) sử dụng vốn vay của Ngân hàng Thế giới cho việc xây dựng cơ sở hạ tầng truyền tải điện ở các khu vực phát triển kinh tế trọng điểm của quốc gia Cơ cấu đầu tư của dự án: nghành điện vay vốn của WB thông qua Chính phủ để đầu tư ĐZ và TBA 220kV, 500kV
12. Khi hộ ảnh hưởng không chấp nhận kết quả đo đếm tài sản bị ảnh hưởng, muốn thắc mắc về các vấn đề khác, đơn khiếu nại gửi đi đâu? - Bước 1: Gửi lên UBND xã để xem xét giải quyết trong vòng 15 ngày. - Bước 2: Nếu những người khiếu nại không đồng ý với quyết định trong bước 1 thì người đó có quyền khiếu nại lên UBND huyện và đơn vị này sẽ ra quyết định trong vòng 30 ngày. - Bước 3: Nếu người khiếu nại vẫn chưa thỏa mãn với quyết định ở cấp huyện thì người đó có thể
gửi đơn khiếu nại lên đơn vị có trách nhiệm của UBND tỉnh và đơn vị này sẽ ra quyết định về khiếu nại này trong vòng 30 ngày. - Bước 4: Nếu người HBAH vẫn tiếp tục không thoả mãn với quyết định của chính quyền cấp tỉnh thì họ sẽ gửi đơn khiếu nại lên trung ương.
CÁ
C B
IỆN
PH
ÁP
ĐỀ
PH
ÒN
G T
AI
NẠ
N Đ
IỆN
3. Dùng sào tre, cây gỗ khô gạt dây điện ra khỏi nạn
nhân
4. Không dựng anten gần đường dây điện, khi có khả
năng va quệt vào đường dây điện
5. Không trèo lên trụ điện để sửa chữa hoặc tháo dỡ bất
cứ vật gì
6. Không chặt các cây cao gần đường dây điện
1. Thế nào là hộ bị ảnh hưởng của dự án?
Tất cả các tổ chức, gia đình, cá nhân (gọi chung là hộ bị ảnh hưởng – HBAH) đang
sử dụng đất và có tài sản trên đất như: nhà cửa, công trình xây dựng, cây cối, hoa
màu trong phạm vi bảo vệ trạm biến áp được xây dựng trong dự án.
2. Ai sẽ xác định các khu vực bị ảnh hưởng và các loại tài sản bị ảnh hưởng?
- Ban QLDA các công trình điện miền Bắc thuộc Tổng Công ty Truyền tải điện Quốc gia sẽ cung cấp bản vẽ mặt bặng vị trí trạm biến áp cho Ban đền bù của huyện/ xã liên quan. - Hội đồng đền bù của huyện có trách nhiệm xác định các khu vực bị ảnh hưởng và điều tra, thống kê các loại tài sản bị ảnh hưởng.
- Khu vực bị ảnh hưởng là phần xác định chiều rộng, chiều dài, chiều cao của trạm biến áp được quy định trong Nghị định 106/2005/NĐ-CP (ngày 17 tháng 8 năm 2005 hướng dẫn thực hiện một số điều của Luật Điện lực về bảo vệ an toàn lưới điện cao áp) và Nghị định 81/2009/NĐ-CP (ngày 12 tháng 10 năm 2009 về sửa đổi, bổ sung một số điều của Nghị định số 106/205/NĐ-CP)
13. Cơ quan nào giám sát việc chi trả tiền đền bù? Ban QLDA và Cơ quan giám sát độc lập về đền bù giải phóng mặt bằng sẽ theo dõi đánh giá về việc này
14. Hộ bị ảnh hưởng có trách nhiệm gì? - Hộ bị ảnh hưởng cần chuẩn bị sẵn sàng các loại giấy tờ có liên quan đến việc sử dụng đát, sở hữu tài sản của mình và các loại giấy tờ có liên quan đến việc cư trú tại địa phương.
- Cùng tham gia kiểm kê tài sản trong phạm vi giải phóng mặt bằng, xem xét biểu mẫu điều tra về tài sản bị ảnh hưởng và ghi ý kiến vào phiếu. - Khi nhận đủ tiền đền bù và các khoản hỗ trợ, hộ bị ảnh hưởng phải giao mặt bằng đúng thời hạn quy định, không làm chậm tiến độ thi công dự án. DỰ ÁN TRUYỀN TẢI HIỆU QUẢ VAY
VỐN NGÂN HÀNG THẾ GIỚI 3. Có mấy loại ảnh hưởng?
Ảnh hưởng vĩnh viễn: đất đai, nhà cửa, các công trình xay dựng và các tài sản khác (cây lâu năm và mùa vụ) trong phạm vi vị trí trạm biến áp.
4. Ai sẽ được đền bù, ai không được đền bù?
- Tất cả các HHBAH có tài sản (nhà cửa, cây cối, hoa màu, đất) thuộc phạm vi thu
hòi, giải tỏa để xâ dựng công trình, hoặc có đủ chứng cớ hợp pháp chứng minh được quyền sử dụng đất đai, quyền sở hữu tài sản bị ảnh hưởng trước ngày khóa sổ điều tra đều được đền bù và hỗ trợ. - Hộ lấn chiếm đất, xây dựng sau ngày khóa sổ điều tra là hộ trục lợi, bất hợp pháp. Các hộ này sẽ phải tự tháo dỡ, giải phóng mặt bằng và không được đền bù.
15. Bất cứ khi nào cần, hộ bị ảnh hưởng có thể viết đơn, thư hoặc trực tiếp đến các cơ quan sau: Địa chỉ: * Tổng Công ty Truyền tải Quốc gia * Hội đồng đền bù thành phố/ huyện * Ban QLDA các công trình điện miền Bắc
Số 1111 Hồng Hà, quận Hoàn Kiếm, tp Hà Nội
5. Giá đền bù như thế nào?
Giá trị đến bù được tính theo đơn giá đền bù của UBND thành phố trên cơ sở phản
ánh đúng giá thị trường về đất và các loại tài sản khác ở địa phương tại thời điểm chi trả đền bù, không có khấu hao về nhà cửa, không trừ các loại vật liệu có thể tháo dỡ, sử dụng lại được. Đất đai được đền bù bằng đất cùng hạng và diện tích tương đương (nếu địa phương còn quỹ đất) hoặc bằng tiền mặt. 6. Nhà bị ảnh hưởng một phần được đền bù như thế nào? Nếu phần bị ảnh hưởng không liên quan đến kết cấu của nhà và không ảnh hưởng
đến việc bố trí sử dụng phần nhà còn lại thì HBAH chỉ được đền bù phần diện tích bị ảnh hưởng. Nếu phần bị ảnh hưởng do dự án có liên quan đến kết cấu hoặc phần còn lại không thể sử dụng thì HBAH sẽ được đền bù toàn bộ căn nhà
CÁ
C B
IỆN
PH
ÁP
ĐỀ
PH
ÒN
G T
AI
NẠ
N Đ
IỆN
1. Không tuốt lúa gần đường dây điện
2. Không dùng tre, gỗ…có kích thước nhỏ làm cột điện
7. Khi nào được đền bù, khi nào phải di chuyển hoặc chặt dọn các loại cây và
hoa màu?
- Nếu hộ phải chuyển nhà đi nơi khác thì đền bù đầy đủ đất và nhà ít nhất trước khi thu hồi là 3 tháng. - Hộ tái bố trí trên phần đất của mình thì đền bù nhà và các công trình xây dựng ít nhất trước khi thu hồi đất là 2 tháng. - Cây cối và hòa màu sẽ được đền bù ít nhất 1 tháng trước khi xây dựng công trình.
8. Ngoài việc đền bù các hộ phải di chuyển có được hưởng quyền lợi nào nữa
không? - Có, hộ bị ảnh hưởng thuộc loại này còn được hỗ trợ về di chuyển, ổn định cuộc sống, đặc biệt là các gia đình chính sách. Các khoản hỗ trợ thực hiện theo quy định của Nghị định 197/NĐ-CP ngày 3/12/2004.
9. Nếu Ban đền bù chi trả một phần đền bù và các khoản hỗ trợ và yêu cầu HBAH giao đất cho dự án thì HBAH sẽ xử lý như thế nào? Chỉ khi nào được trả đầy đủ đền bù và các khoản hỗ trợ theo đúng thời gian quy định thì hộ bị ảnh hưởng mới giao đất hoặc giải tỏa mặt bằng cho dự án.
NHỨNG ĐIỀU CẦN BIẾT VỀ
CHÍNH SÁCH ĐỀN BÙ,
GIẢI PHÓNG MẶT BẰNG
VÀ AN TOÀN ĐIỆN
SỐ 4, NGUYỄN KHẮC NHU, QUẬN BA ĐÌNH, TP HÀ NỘI
10. Nếu khi nhận đền bù mà có ai hoặc có tổ chức nào yêu cầu đóng góp hoặc giữ
lại một phần tiền thì HBAH sẽ xử lý như thế nào? Không ai được phép giữ, thu bất cứ khoản nào từ tiền đền bù của các hộ bị ảnh hưởng. Nếu ai hoặc tổ chức nào yêu cầu giữ lại tiền, đề nghị hộ báo ngày cho Ban đền bù huyện, Ban QLDA hoặc chính quyền địa phương biết để xử lý.
11. Ai có trách nhiệm thông báo về thời gian đền bù, thời gian đền bù, thời gian thu hồi đất và các loại thông tin có liên quan đến dự án?
Ban chỉ đạo của thành phố và Ban đền bù của huyện có trách nhiệm thông báo rõ ràng với địa phương và các hộ bị ảnh hưởng về thời gian chi trả đền bù, thời gian thu hồi đất để xây dựng dự án, công khai thông tin về các chính sách quyền lợi cho các hộ bị ảnh hưởng.
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 95
Cấm vượt qua hàng rào trạm biến áp
Cấm bố trí ăngten, dây phơi, giàn giáo,
biển, hộp, đèn quảng cáo tại các vị trí
mà khi đổ, rơi có thể va quệt vào dây
điện
Cấm đốt nương rẫy trong và gần hành
lang lưới điện
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 96
Cấm thả diều hoặc vật bay gần công trình lưới
điện
Cấm đòa ao, kênh, mương… gần công trình lưới
điện làm mất an toàn lưới điện
Cấm bắn chim hoặc ném bất cứ vật gì lên dây
dẫn và các bộ phần của công trình lưới điện
Cấm xây dựng cây xăng, sắp xếp các chất dễ
cháy nổ trung bình trong hành lang bảo vệ lưới
điện
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 97
Appendix 7
INVENTORY OF PROJECT AFFECTED PEOPLE
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 98
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 99
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 100
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 101
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 102
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 103
Subproject: Tay Ha Noi 220kV Substation
Resettlement Plan 104