Swan Lake Hydroelectric Project (FERC Reservoir Expansion ... · 5/22/2013  · By letter dated...

25
Swan Lake Hydroelectric Project May 22, 2013 FERC No. 2911 Page 1 Final Meeting Summary Swan Lake Hydroelectric Project (FERC No 2911) Reservoir Expansion Joint Meeting and Public Meeting Summary May 22, 2013 ATTENDANCE: Name Organization Attended Site Visit Attended Joint Meeting Attended Public Meeting Steve Lindamood US Army Corps of Engineer No Yes Yes Ted Deats Alaska Department of Natural Resources No Yes Yes Mark Manillo Alaska Department of Fish and Game Yes Yes No Monte Miller Alaska Department of Fish and Game Yes Yes Yes Barbara Stanley USDA Forest Service No Yes Yes Jennifer Holstrom Ketchikan Public Utilities No Yes No Shawn Johnson Alaska Department of Fish and Game Yes Yes Yes Steve Negri Tetra Tech No Yes Yes Clint Gundelfinger Alaska Department of Natural Resources No Yes No Finlay Anderson McMillen LLC No Yes Yes Cory Warnock McMillen LLC Yes Yes Yes Andy Rauwolf Tongass Construction No Yes Yes Andy Donato Ketchikan Public Utilities No Yes Yes Tim McConnell Ketchikan Public Utilities No Yes Yes Mark Fairhart Hatch Acres No Yes Yes Eric Wolfe SEAPA Yes Yes Yes Italics indicates that the participant joint by conference call/web meeting Background and Meeting Objectives The Southeast Alaska Power Agency (SEAPA) owns the Swan Lake Hydroelectric Project (Project; FERC Project No. 2911), on the Northeast side of Carroll Inlet in Southeast Alaska. SEAPA is currently evaluating the engineering feasibility and value of increasing the reservoir’s storage capacity through an

Transcript of Swan Lake Hydroelectric Project (FERC Reservoir Expansion ... · 5/22/2013  · By letter dated...

  • Swan Lake Hydroelectric Project    May 22, 2013 FERC No. 2911  Page 1  Final Meeting Summary 

     

    Swan Lake Hydroelectric Project (FERC No 2911)Reservoir Expansion Joint Meeting and Public Meeting Summary May 22, 2013  

     

    ATTENDANCE: 

    Name  Organization  Attended Site Visit 

    Attended Joint Meeting 

    Attended Public Meeting 

    Steve Lindamood  US Army Corps of Engineer 

    No  Yes  Yes 

    Ted Deats  Alaska Department of Natural Resources 

    No  Yes  Yes 

    Mark Manillo  Alaska Department of Fish and Game 

    Yes  Yes  No 

    Monte Miller  Alaska Department of Fish and Game 

    Yes  Yes  Yes 

    Barbara Stanley  USDA Forest Service  No  Yes  Yes Jennifer Holstrom  Ketchikan Public 

    Utilities No  Yes  No 

    Shawn Johnson  Alaska Department of Fish and Game 

    Yes  Yes  Yes 

    Steve Negri  Tetra Tech  No  Yes  Yes Clint Gundelfinger  Alaska Department of 

    Natural Resources No  Yes  No 

    Finlay Anderson  McMillen LLC  No  Yes  Yes Cory Warnock  McMillen LLC  Yes  Yes  Yes Andy Rauwolf   Tongass Construction  No  Yes  Yes Andy Donato  Ketchikan Public 

    Utilities No  Yes  Yes 

    Tim McConnell  Ketchikan Public Utilities 

    No  Yes  Yes 

    Mark Fairhart  Hatch Acres  No  Yes  Yes Eric Wolfe  SEAPA  Yes  Yes  Yes Italics indicates that the participant joint by conference call/web meeting 

    Background and Meeting Objectives  The Southeast Alaska Power Agency  (SEAPA) owns  the Swan Lake Hydroelectric Project  (Project; FERC Project  No.  2911),  on  the  Northeast  side  of  Carroll  Inlet  in  Southeast  Alaska.    SEAPA  is  currently evaluating the engineering feasibility and value of increasing the reservoir’s storage capacity through an 

  • Swan Lake Hydroelectric Project    May 22, 2013 FERC No. 2911  Page 2  Final Meeting Summary 

    increase  in dam height.    SEAPA  is proposing  to  raise  the dam height by up  to 15  feet.   Powerhouse operations would not change and the nameplate capacity will remain at 22 MW.   Under the proposed operations,  the  reservoir  could  fluctuate  annually  from  271.5  feet  to  345  feet,  depending  on precipitation, load, and operations at other facilities associated with the Southeast Alaska Intertie (STI). In order to increase the size of the reservoir, a non‐capacity amendment application will need to be filed with and approved by FERC.    SEAPA  filed  an  Initial  Consultation  Document  (ICD)  with  agencies,  Indian  tribes  and  affected stakeholders  on  April  15,  2013.      The  ICD  initiates  consultation  pursuant  to  18  CFR  4.38.      This consultation process requires an opportunity for a site visit, and a  joint meeting that was open to the public.  Additionally, SEAPA hosted a public meeting for interested parties in the evening to discuss the proposal.   As provided  for  in  18 CFR  4.38,  the meetings were noticed  two weeks prior  to  the meeting  in  local newspapers.    Affidavits  of  Publication  from  the  Petersburg  Pilot,  the  Wrangell  Sentinel,  and  the Ketchikan  Daily  News  are  attached.    By  letter  dated  February  7,  2013,  SEAPA  notified  FERC  of  the proposed site visit and Joint Meeting.  The purpose of the Joint Meeting was to:  

    Respond to questions raised by the Initial Consultation Document (ICD)   Provide confirmation that SEAPA and stakeholders are in agreement on path forward, since 

    SEAPA “front‐loaded” the ICD with study results and informal consultation.  Confirm or amend “process” and schedule identified in the Initial Consultation Document (ICD) – 

    i.e., waivers. 

    Joint Meeting Summary 

    The  definitive meeting  record  for  both  the  Joint Meeting  and  Public Meetings  are  the  distributed material and presentations and the audio/video recordings provided to FERC. These are available to the public upon request (contact SEAPA).  For convenience, a summary of discussions and action items from the meeting follows. 

    Discussion included:  Purpose of meeting and path forward  Permitting and anticipated National Environmental Policy Act (NEPA) Process  Construction methods  Summary of consultation to date and Initial Consultation Document (ICD) 

    processes/stages  Feedback from Site Visit 

     Action Items and Agreements: 

      There was discussion about how the NEPA process will be informed by the Resource Reports.  

    Table 3 of the ICD is a schedule with draft Resource Reports and an opportunity for agency 

  • Swan Lake Hydroelectric Project    May 22, 2013 FERC No. 2911  Page 3  Final Meeting Summary 

    review, but did not show issuance of final Resource Reports.  Stakeholders requested that SEAPA issue revised and final Resource Reports prior to issuance of the Preliminary Draft Environmental Assessment (PDEA).  Action Item:  SEAPA will revise the ICD Table 3 to include this additional step (note: the revised Table 3 is attached).  SEAPA noted that updated schedules will be posted on the Project website as modifications are required.   

    The Alaska Department of Fish and Game (ADFG) discussed observations from the site visit.   The tour included an exploration of Lost Creek, the area around the powerhouse and dam, and an overhead flight in the Lost Creek drainage above Lost Lake.   ADFG commented on the significant amount of quality habitat in the Lost Creek drainage that is above the area to be inundated by the proposed pool raise.  They stated that they believe Lost Lake and its tributaries are the most likely source of fish production, and noted that the proposed action does not appear to limit access to this habitat; rather, access may be improved.      

    ADFG noted that because the drainage above the dam is a non‐catalogued water body, it falls under AS 16.05.841 – Fish Passage.  This project does not impact fish passage, and in fact would improve access to habitat.  Therefore, no need for permits has been identified.    

    There was discussion regarding the section of creek (Falls Creek) below the dam and associated natural barriers.   There are two barriers in Falls Creek, one of which is just above tidewater.   SEAPA noted that they have noticed fish milling in the tailrace below the dam, but that historically, fish use in Falls Creek has been minimal; historic observations have noted milling behavior at the mouth rather than any pre‐spawning or spawning  activity.  ADFG stated that they believe no permits are necessary.  

    There was discussion about potential need for regulating construction to limit activity in the creek.  Eric Wolfe noted that most of the construction is in the laydown areas and near the dam.  There is minimal chance of any impact to the water and no need to cross the stream is currently anticipated.  There will be best practices for keeping sediment in the river (typically an Erosion and Sediment Control Plan is a required submittal at FERC).    SEAPA noted there are no construction plans yet. As such, some of these construction methods not yet fully fleshed out.  The appropriate approach for tree removal is still being developed as well.   

    There was discussion about potential permitting needs from the US Army Corps of Engineers (Corps). 

    o The Corps inquired about potential wetland impacts from construction and whether there would be fill or removal below the ordinary high water (OHW) line.     SEAPA noted that the construction activities include 6 feet of material being 

    placed on top of the existing dam, and placement of gates in the spillway.  A road on the right abutment would need to be re‐graded.   

  • Swan Lake Hydroelectric Project    May 22, 2013 FERC No. 2911  Page 4  Final Meeting Summary 

    SEAPA noted that fill material for road, and aggregate and sand for concrete would be barged in.   

    While wetlands are inundated because of the raise, the impacts to wetlands are not a result of fill.   

     o The Corp noted their responsibility to regulate discharge of fill material that is in the 

    waters of the United States, including wetlands.  If there is no fill in waters regulated by the Corps under Section 10 or Section 404, then they are likely not going to be requiring a permit.  SEAPA indicated that there was not going to be any fill removed.  There was 

    discussion about whether there might be excavation in tidelands to allow barge access to the dock.   SEAPA indicated that they did not know whether barge access would be an issue, but would take a close look at this.    

    o USACE asked whether wetlands identified in the ICD and Resource Reports were delineated using the Corps delineation manual and if a delineation report was available.    SEAPA indicated that they did not formally delineate the wetlands, though survey‐grade Timble™ units were used.   The Corps noted that area of concern with respect to this project is if and where fill is being placed below the dam.   The Corps is responsible for determining if a wetland is present; if a formal delineation has not been conducted below the dam where direct impacts are possible, there is some concern that there might be wetlands.    SEAPA has information below the dam assuming original staging areas would be used; Tetra Tech indicated that they have information available on the required parameters, but this has not been formed into a delineation reports.   The Corps will need site photos and datasheets.  Tetra Tech confirmed that they can take the information they have and put it in the required form.     

    o The Corps’ initial conclusion was that there would likely not be permits required, but without plans to look at and the delineation of areas around the construction areas, they can’t make a firm determination.  The Corps could use plans and supporting design report (when ready) as a “pre‐application” to advise SEAPA whether permits will be required.  A “no permit required” letter would be issued if appropriate.  

    SEAPA discussed the ICD and the approach taken to develop information for the document that was consistent with discussions previously held with Agencies.   As previously discussed, no new field work is being planned for Stage 2 consultation in advance of the Draft License Application, with the exception of continuing raptor surveys.     

    SEAPA noted that in one instance, the ICD references a minimum pool elevation of 290 feet (section 5.4.1.2, page 44).  This is incorrect; the minimum pool will be unchanged from its current low of 271.5 ft.    

  • Swan Lake Hydroelectric Project    May 22, 2013 FERC No. 2911  Page 5  Final Meeting Summary 

    ADFG asked if the 350 foot FERC boundary was adequate to accommodate project operations and potential impacts (zones of influence) at the new normal maximum reservoir surface elevation.  SEAPA indicated that they believe that 5 feet of buffer between the boundary and the normal maximum pool elevation should be adequate, but that was what motivated some of the 2012 efforts, including the soils study.  If agencies, in conducting their review of the Proposed Action, feel that the boundary does not adequately contain impacts, then the parties can discuss potential adjustments.     

    No new information needs requiring field studies were identified.  Agencies and Indian tribes will have until July 12 to make additional information needs known.  

    Public Meeting Summary 

    Following the joint meeting, a public meeting was held in the same location (see attendance list above).  Topics for this meeting included: 

    Background and need for the Proposed Action  Summary of the Proposed Action  Overview of the FERC and permitting process  Role of the agencies versus public in the process and opportunities for involvement  Review of natural resource information presented in the ICD. 

    Action items and discussion included: 

    Background discussion on electrical load in SE Alaska and the role Swan Lake will play in preventing current and future hydroelectric power plants from being “stranded”. 

    Land surveys conducted in 2012 to confirm location of the FERC boundary and land ownership boundary.   It was noted that these surveys identified approximately 26 acres that are within the existing FERC boundary on the Tongass National Forest that will be mostly inundated as a result of the pool raise.  This land will be the subject of a Special Use Permit to be issued by the Forest Service. 

    A discussion of the engineering process with respect to dam safety.  SEAPA outlined the role of FERC and the Independent Board of Consultants in the iterative process of design. 

    A discussion of the Tongass National Forest Land Use Designations, and whether ICD Figure 5.7‐1 might need some additional commentary/clarification.   Action Item:  Barb Stanley agreed to include the US Forest Service’s suggestions in their comments on the ICD that will be submitted mid‐July.   

    A discussion of wolf sightings in the area and whether there may be some confusion between Management Indicator Species (MIS) that may occur in the vicinity and what species was actually documented (see Table 5.5‐3 of the ICD).  Action Item:  SEAPA’s contractor will review and discuss with appropriate agency resources.  

  • Swan Lake Hydroelectric Project    May 22, 2013 FERC No. 2911  Page 6  Final Meeting Summary 

    Distributed /Attached Material  

    Agenda for 04‐22‐2013 Joint Meeting   Agenda for 05‐22‐2013 Public Meeting   PowerPoint Presentation (PDF) for Joint Meeting  PowerPoint Presentation (PDF) for Public Meeting  Draft Study Reports (available at www.seapahydro.org/slhp.htm)   Video/audio recording of both the ICD and the Public Meeting have been provided to FERC and 

    are available from SEAPA upon request.  

       

  • Swan Lake Hydroelectric Project    May 22, 2013 FERC No. 2911  Page 7  Final Meeting Summary 

    RevisedTable3–ForAgencyComment

    Proposed amendment schedule 

    Activity Responsible Party Schedule Regulatory Reference

    First Stage Consultation

    File ICD SEAPA Fri 4/15/13 18 CFR 4.38 (b)

    Request designation as Non-Federal Representative status SEAPA Fri 4/15/13 50 CFR 402.8

    Agency Site Visit SEAPA, Agencies Weds 5/22/13 18 CFR 4.38(b)(3)

    Notice Public Meeting (FERC) SEAPA Tue 5/7/13 18 CFR 4.38(b)(4)

    Notice Public Meeting (Newspaper) SEAPA Wed 5/8/13 18 CFR 4.38(b)(4)

    Joint Meeting (Public) SEAPA, Participants Wed 5/22/13 18 CFR 4.38 (b)(3)

    Public Meeting SEAPA, Participants Wed 5/22/13 18 CFR 4.38 (b)(3)

    Comments on ICD, Study Requests (if any) Agencies Mon 7/12/13 18 CFR 4.38(b)(5)

    1/

    Second Stage Consultation

    Request to waive second stage consultation (as appropriate) SEAPA, Participants Wed 5/09/13 18 CFR (e)

    Draft Resource Reports SEAPA Thu 8/01/13

    Agency Comments on Draft Resource Reports Participants Mon 9/02/13

    Final Resource Reports SEAPA Mon 10/07/13

    Draft Amendment Application, including Preliminary Draft

    Environmental Assessment (PDEA)

    BE/BA

    SEAPA Mon 11/04/13 18 CFR 4.201(b), 18 CFR 4.38, 18 CFR 4.61

    Comments on Draft Amendment Application Agencies Mon 01/06/13 18 CFR(c)(5)

    Joint Meeting (as necessary) SEAPA, Agencies Mid-February 18 CFR 4.83(c)(6)(i)

    Third Stage Consultation

    File Application for Non-Capacity Amendment SEAPA April 2014

    18 CFR 4.38(c)(9), and 18 CFR 4.38(d)

    /1Per section 18 CFR 4.38(b)(5), agencies typically have 60 days following the Joint Meeting to provide comments and study requests.  SEAPA proposes to truncate this to 50 days to conserve remaining field season, should additional work be necessary.  In light of extensive informal consultation already completed, SEAPA requests that agencies support this modified schedule.    

  • Joint Meeting

    Proposal to Increase Storage Swan Lake Hydroelectric Project

    (FERC Project No. 2911)   

    Page 1. 1900 First Avenue, Suite 318, Ketchikan, Alaska 99901 • P (907) 228-2281 F (907) 225-2287 • www.seapahydro.org  

    Date May 22, 2012

    Location

    Best Western Sunny Point Conference Ball Room 3434 Tongass Avenue, Ketchikan

    Conference Call Information

    See below Agenda 3:00 pm Convene and Coffee 3:15 pm Welcome and Introductions

    Goals for the day Review purpose and need for pool raise Proposed action Recap of site visit

    3:30 pm Review Discussions to Date

    2012 scoping and studies Review of study results, understandings of next steps

    4:00 pm Initial Consultation Document Discussion

    Approach Process steps and schedule Questions/suggestions

    4:30 pm Adjourn (Note: Public meeting to follow in same location)

    Process for joining Web meeting (note, if conference call can be joined separately if you are unable to or don’t want to join the webmeeting): 

    1. Join GOTO meeting ‐ Wednesday, May 22, 2013 at 3:00 PM Alaska Daylight Time. https://global.gotomeeting.com/join/685241597

    2.  Join the conference call:  1‐800‐315‐6338; Use access code:  73272#  Meeting ID: 685‐241‐597 

  • 6/17/2013

    1

    Joint MeetingMay 22, 2013

    Joint Meeting is required by 18 CFR 4.38(b) To be open to the public and recorded Intended to respond to questions raised by the

    Initial Consultation Document (ICD) Because SEAPA has “front-loaded” ICD with

    study results and informal consultation, this meeting provides confirmation that we are in agreement on path forward Confirms or amends “process” identified in the

    Initial Consultation Document (ICD) – i.e., waivers.

    Additional height to existing dam, resulting in 15 additional feet of storage in Swan Lake

    Full pool changes from EL. 330 ft. to 345 (PMF at 347). Minimum pool remains at EL. 271.5 ft.

    Increase water right by 97,000 acre-feet to fully utilize storage

    Update on Corps of Engineers (CWA, 404, Section 10)

    Confirm ADFG / Permitting needs Water Rights USFS Special Use Permit DNR/Timber SHPO Clearance EFH Analysis Debrief of Site Visit

    Early consultation with agencies in spring of 2012 Issue Identification Study Panning

    Information Gathering Land Ownership Surveys 2012 Natural Resource Surveys Study Reports

    February 2012 Study Results Meeting Initial Consultation Document (ICD)

    ICD Filed April 15, 2013 Intended to summarize information developed

    in 2012 on a level sufficient to meet consultation requirements

    Incorporated final study reports by reference As much as possible, directed readers to

    Response to Comments (Attachment 1 to each report) for planned/agreed to approach to resolving questions discussed in agency review and February 27 2013 meeting.

  • 6/17/2013

    2

    Limited additional fieldwork needed to complete natural resource studies

    A series of desktop exercises will be completed in advance of comprehensive reporting

    A series of natural resource specific Resource Reports will be created prior to development of NEPA documents and the License Amendment

    An agency review process associated with formal NEPA documents was established

    General consensus: Except where noted, additional field data collection and surveys are not necessary given relatively small risk of impacts

    Water Resources SEAPA has filed for an additional water right of 97,000 acre-feet to take advantage of

    increased storage No additional fieldwork needs ADNR indicated that they had all the data needed to analyze water use in the Project

    area

    Fish and Aquatic Resources No additional fieldwork needs Effects to fish and fish habitat on and off National Forest Service lands will be

    documented Additional GIS analysis to quantify existing fish habitat and document existing

    conditions outside FERC boundary will be done Changes to tributary spawning availability as a result of the proposed action will be

    analyzed

    Botanical Resources No additional fieldwork needs Appropriate management measures will be identified for the two

    newly documented plant species A Biological Evaluation (BE) will be developed associated with the

    three sensitive plant species with potential habitat in the Project area

    Wetland acreage on and off National Forest Service land will be delineated

    Wildlife Resources Goshawk and bald eagle surveys in June 2013 Reach an agreement on appropriate analysis area Time construction activities to minimize potential impacts to

    migratory birds Site staging area to minimize potential impacts to wildlife

    Geology and Soils No additional fieldwork needs Resource Report will Distinguish between soil types and associated abundances

    on and off National Forest Service land Clarify methods associated with the assessment of mass

    wasting

    Rare, Threatened and Endangered Species No additional fieldwork needs Additional work in Resource Reports to expand area of

    analysis

    Cultural Resources No additional fieldwork needs SEAPA will forward the Cultural Resource Report to

    the State Historical Preservation Officer (SHPO) after formal designation as the non-federal representative

    Socioeconomics No additional fieldwork needs Tongass National Forest (TNF) has reviewed their

    special use permits and provided contacts with hunting/fishing guides using the area

    Aesthetic Resources No additional fieldwork needs SEAPA will work with the TNF to acquire a special use

    permit at the appropriate time

    Tribal Resources No additional fieldwork needs Three Tribes were identified as needing inclusion in

    initial consultation: Ketchikan Indian Corporation (KIC) Organized Village of Saxman (OVS) Metlakatla Indian Community (MIC)

  • 6/17/2013

    3

    ICD filed with FERC on April 15, 2013

    At this point, SEAPA is assuming that the ICD accurately captures all agreements made on Feb. 27

    Observations from site visit

    Next step

    Activity Responsible Party Schedule

    File ICD SEAPA 4/15/13

    Request Non-Federal Representative Status SEAPA 4/15/13

    Public Meeting Notice SEAPA 5/7-5/8/13

    Agency Site Visit SEAPA, Agencies 5/22/13

    Joint Meeting and Public Meeting SEAPA, Agencies,Public

    5/22/13

    Comments on ICD (if any) Agencies 7/12/13

    Draft Resource Reports SEAPA 8/1/13

    Comments on Draft Resource Reports Agencies 9/2/13

    Draft Amendment Application (DEA) SEAPA 10/14/13

    Comments on DEA Agencies 12/2/13

    Joint Meeting (if needed) SEAPA, Agencies Mid-January 2014

    File Amendment Application SEAPA 3/14

  • Public Meeting

    Proposal to Increase Storage Swan Lake Hydroelectric Project

    (FERC Project No. 2911)   

    Page 1. 1900 First Avenue, Suite 318, Ketchikan, Alaska 99901 • P (907) 228-2281 F (907) 225-2287 • www.seapahydro.org  

    Date May 22, 2012

    Location

    Best Western Sunny Point Conference Ball Room 3434 Tongass Avenue, Ketchikan

    Conference Call Information

    See below Agenda 5:00 pm Convene and Coffee 5:15 pm Welcome and Introductions

    Goals for the day 5:30 Presentation

    SE Alaska Energy Picture Proposed action Project description FERC process and other regulatory steps Summary of existing information and outstanding analysis needs

    6:30 pm Discussion

    7:00 pm Adjourn

    Process for joining Web meeting (note, if conference call can be joined separately if you are unable to or don’t want to join the webmeeting): 

    1. Join GOTO meeting ‐ Wednesday, May 22, 2013 at 3:00 PM Alaska Daylight Time. https://global.gotomeeting.com/join/685241597

    2.  Join the conference call:  1‐800‐315‐6338; Use access code:  73272#  Meeting ID: 685‐241‐597 

  • 6/17/2013

    1

    Public MeetingMay 21, 2013

    2

    Why it’s a good idea

    How long will it take, what’s the process?

    How much will it cost?

    Introductions Project background FERC process and other regulatory steps Summary of existing information and

    outstanding analysis needs Discussion

    • Wholesale delivery rate is $68/MWh, same rate for 13 years

    • We own the Tyee and Swan Lake projects and provide wholesale power and energy to the utilities in Ketchikan, Wrangell and Petersburg

    • Also own the transmission lines linking those communities together – around 175 miles including 14 miles of submarine cable

    • Hydro Projects were built by the State in the early 1980’s

    5

    Initiatives- to meet our future demand

    • Swan Lake Reservoir Expansion• Request for Offers • DCCED Grant

    6Note: KPU hydro and diesel generation is shown lumped simply as KPU generation for space saving reasons.

  • 6/17/2013

    2

    7

    Expansions (MWh)TYL CW....... 1,000TYL Outlet...4,000Whitman...16,000SWL Res......7,500Total 28,500 MWh

    8

    Expansions (MWh)TYL CW....... 1,000TYL Outlet...4,000Whitman...16,000SWL Res......7,500Total 28,500 MWh

    These small projects give us time so we can plan the big expensive project

    This would be a 10% offset if 30,000 MWh

    A very involved FERC process governs dam safety: Dam Safety Surveillance Monitoring Plan and

    Report requirements Each non-federal dam owner must certify the

    DSSMP using independent consultant Probable Failure Mode Analysis requires a

    painstaking review of construction records, current geology, earthquake, and flood values.

  • 6/17/2013

    3

    Modifications to existing dams Two separate FERC offices with dam safety

    responsibilities will be involved Requires an independent review of the owners

    plan using board of consultants Swan Lake’s Board of consultants includes a

    member of the original dam design team

    “One of the hardest things to do is time a hydro expansion”- Tim McCloud AEL&P

    If you’re not burning some diesel, then you’re over-built. While diesel is bad, bad debt that doesn’t displace

    diesel is a whole lot worse. The bad debt would be a stranded hydro plant.

    Right now diesel is less than 6% of the KPU Load, and this was a strange hydro year.

    Early consultation with agencies in spring of 2012 Issue Identification Study Panning

    Information Gathering Land Ownership Surveys 2012 Natural Resource Surveys Study Reports

    February 2012 Study Results Meeting Initial Consultation Document (ICD)

    Additional height to existing dam, resulting in 15 additional feet of storage in Swan Lake

    Full pool changes from EL. 330 ft. to 345 (PMF at 347). Minimum pool remains at EL. 271.5 ft.

    Increase water right by 97,000 acre-feet to fully utilize storage

    Project lands were conveyed to state in 1997 (except for small sliver that extends into forest)

    Falls Creek has impassable falls at Carroll Inlet; salmon can’t access Swan Lake

    Minimal sport fishery; area above dam occasionally used/accessed by hunters

    Under proposed action Approximately 140 acres of lands inundated around

    reservoir The lower 1.04 miles of Lost Creek inundated from

    September to January

  • 6/17/2013

    4

    FERC regulates non-federal dams Issues licenses that define what can be built,

    how it can be operated, and imposes other conditions

    FERC provides the structure whereby other agencies and regulatory processes come together

    Other agencies have separate authorities that are independent of FERC but coordinated by FERC.

    The Proposed Action requires a non-capacity license amendment of the existing project license from FERC

    Because of the pool raise aspect, 3-stage consultation is required unless waived by the agencies. Stage 1- Project proponent educates stakeholders Stage 2 – Collection of information and analysis

    requested by stakeholders at end of stage 1 Stage 3 – FERC conducts NEPA, consults with

    agencies, issues order amending license

    Internal Decision

    FERC Dam Safety

    Stage 3 Consultation

    Stage 2 Consultation

    Stage 1 Consultation

    SEIRP – Identified need for hydro

    storage

    SEAPA –Analyzed

    available options

    Swan identified as viable

    Engineering and economic feasibility

    Begin FERC regulatory process

    Collect relevant informationCompile for agencies and stakeholders

    Informal consultation with

    agencies

    Initial Consultation Document

    Study requests or requests for

    additional analysis

    Collect requested information

    Submit amendment to

    FERC

    FERC prepares Environmental Assessment (EA)Consults with resource agenciesProduces Final EA

    FERC issues Order Amending License

    Provide draft amendment and

    environmental analysis to agencies

    Revise documents Meet as necessary to

    resolve questions

    Civil Design

    Division of Dam Safety and Inspections

    Regional Engineer

    Independent Board of

    ConsultantsStart of

    Construction Letter

    30%, 60%, 100%iterations

    Internal Decision

    FERC Dam Safety

    Stage 3 Consultation

    Stage 2 Consultation

    Stage 1 Consultation

    SEIRP – Identified need for hydro

    storage

    SEAPA –Analyzed

    available options

    Swan identified as viable

    Engineering and economic feasibility

    Begin FERC regulatory process

    Collect relevant informationCompile for agencies and stakeholders

    Informal consultation with

    agencies

    Initial Consultation Document

    Study requests or requests for

    additional analysis

    Collect requested information

    Submit amendment to

    FERC

    FERC prepares Environmental Assessment (EA)Consults with resource agenciesProduces Final EA

    FERC issues Order Amending License

    Provide draft amendment and

    environmental analysis to agencies

    Revise documents Meet as necessary to

    resolve questions

    Civil Design

    Division of Dam Safety and Inspections

    Regional Engineer

    Independent Board of

    ConsultantsStart of

    Construction Letter

    30%, 60%, 100%iterations

    Additional analysis and reporting

    At this stage of FERC process, requests and comments from resource agencies and Tribes (Native groups) are weighed heavily since SEAPA must respond to their information requests in Stage 2 consultation

    Following filing of amendment applications, public can “intervene” in proceeding and have comments considered by FERC

    Other regulatory requirements also have public process

  • 6/17/2013

    5

    Website (www.seapahydro.org/slhp.htm) ICD, Study Reports, Background Documents

    SEAPA Office (1900 First Ave., Suite 318) FERC Docket P-2911

    elibrary at www.ferc.gov Eric Wolfe (907) 230-1424

    Process Step SEAPA Proposed schedule

    “Pre-formal” consultation and information development

    January 2012 through March 2013

    File Initial Consultation Document (ICD) April 15, 2013

    Joint Meeting May 22, 2013Comments on ICD and requests for information

    July 12, 2013

    Develop Information per requests August 1, 2013

    Draft Amendment October, 2013Final Amendment March 2014 NEPA Consultation (FERC) (depending on supplemental information)

    April 2014 - March 2015

    Amended License Order April 2015

    Inform Stakeholders and SEAPA of any natural resource assets that may be adversely impacted by the proposed pool raise

    Collect natural resource information early in the process to assist in decision making

    Potentially minimize the need for additional intensive studies during the formal process

    Study plans finalized with agencies in May 2012 in advance of studies

    SEAPA received comments on draft study reports, and met with agencies in February 2013 to discuss findings

    Land Verification Survey Cultural Resources Wildlife Fish Community, Aquatic Habitat, Spawning

    and Tributary Access Botany and Wetlands Soils Study

    An inventory of cultural resources for the Project was conducted in August 2012

    No cultural resource sites were located during the assessment

    Contact with Native people indicated that the Swan Lake area was not an important location for hunting, trapping or harvesting

    No additional surveys or studies are planned in advance of the proposed pool raise

    Appropriate agencies will need to concur with findings

  • 6/17/2013

    6

    None of the 6 Threatened/Endangered Species (TES) with potential to occur were observed Goshawk, yellow-billed loon and dusky Canada goose

    have the potential to be impacted

    Forest Service Management Indicator Species Observed: Alexander Archipelago Wolf Bald Eagle Black Bear Brown Creeper Red-breasted Sapsucker Red Squirrel Sitka Black-tailed Deer Vancouver Canada Goose

    Complete goshawk surveys in 2013

    Complete aerial bald eagle/raptor surveys at lake and Carroll Inlet in 2013

    Agreements on appropriate analysis area for wildlife and timing of construction activities

    Review results of these studies and comprehensively discuss any necessary management measures

    Produce a Resource Report that comprehensively describes all data collected and analysis conducted in support of the pool raise

    Dolly Varden, kokanee and sculpin present

    Suitable spawning habitat available in the lake

    Lost Creek the primary tributary related to fish productivity

    Other tributaries provide limited fish habitat

    No spawning observed

    Quality habitat observed upstream to offset loss near mouth of Lost Creek

    Swan Lake Kokanee

    Swan Lake Dolly Varden

  • 6/17/2013

    7

    Distinguish between effects to fish and fish habitat on National Forest Service lands versus state lands

    Conduct additional GIS analysis to quantify fish habitat and document existing conditions outside the existing FERC boundary

    Develop additional documentation associated with the changes in tributary spawning availability and location as a result of the pool raise

    Produce a Resource Report that comprehensively describes all data collected and analysis conducted in support of the pool raise

    None of the 8 sensitive plant species with potential to occur were documented 3 previously documented in the (KMFRD)

    2 rare plant species were observed Northern bugleweed Pacific buttercup

    2 newly documented species in Alaska Wallace’s spikemoss bog St. John’s wort

    No invasive species observed

    Wetlands Wetlands -- 55% (77 acres) of impacted area Forested wetlands (43.4%) Emergent wetlands (10.7%) Moss muskeg (1.5%)

    Identify appropriate analysis measures associated with the two newly documented species

    Develop a Biological Evaluation (BE) associated with the 3 sensitive plant species with potential habitat in the Project area

    Delineate the wetland acreage that will be affected National Forest Service land versus state lands

    Produce a Resource Report that comprehensively describes all data collected and analysis conducted in support of the pool raise

  • 6/17/2013

    8

    A majority of the Swan Lake shoreline is steep; numerous mass wasting features are visible

    Along existing shoreline, erosion occurs as a result of frequent inundation, erosive wave action, and variable lake levels; exposing unvegetated soil to erosion by rain drops, runoff and wind

    The project will result in an irreversible loss of approximately 138 acres of soil productivity

    Distinguish soil types and relative abundances on and off Nation Forest Service lands

    Clarification of methods used to assess mass wasting potential

    Collaboratively delineate locations for timber removal prior to pool raise

    Produce a Resource Report that comprehensively describes all data collected and analysis conducted in support of the pool raise

    Attachments.pdfAffidavit of Publication - Petersburg Pilot Re Joint-Public MeetingsAffidavit of Publication - Wrangell Sentinel Re Joint-Public MeetingsAffidavit of Publication -Ketchikan Daily Newst Re Joint-Public MeetingsAgenda for 5-22-2013 Joint MeetingAgenda for 5-22-2013 Public MeetingPublic Meeting Presentation_REV4Swan Lake Reservoir Expansion Joint Meeting_REV2