Minutes of 265th SEAC Meeting Date 11/04/2016 -...
Transcript of Minutes of 265th SEAC Meeting Date 11/04/2016 -...
Minutes of 265th
SEAC Meeting Date 11/04/2016
The 265th meeting of SEAC was held in Directorate of Environment, U.P. on
11/04/2016. Following members were present in the meeting along with Secretary, SEAC:
1. Dr. M. S. Khan, Chairman
2. Dr. S.N. Singh, Member
3. Dr. A. K. Singh, Member
4. Dr. D. C. Gupta, Member
5. Smt. Shruti Shukla Secretary, SEAC / Director (I/C), Environment
The Chairman welcomed the members to the 265th
SEAC meeting.
General Discussion:
The committee discussed that the agenda framed and listed for the SEAC meetings, is based
on the sector wise chronological order in continuation to the decision taken in joint meeting of
SEIAA/SEAC dated 10/03/2014 and guideline issued by the SEAC in its meeting dated 16/07/2014.
Moreover, the priority is also given to various projects of Government/Joint venture/PPP model
based on the recommendations made by the Government from time to time, in view of their
importance in public interest.
Different projects of various sectors such as building construction/area development,
Mining, Industrial, Infrastructural, etc. are being submitted to the SEIAA for the Environmental
Clearances, where the chronological order is not differentiated sector-wise. The committee also
noted that Govt. of India has sector wise committees to dispose the projects received under various
sectors, whereas at SEIAA, UP, there is only one committee. Therefore, the SEAC should continue
the practice of maintaining the sector wise list in chronological order and to provide the total list
and the agenda list to the Chairman, SEAC by the Secretary, SEAC. The decision of the Chairman
SEAC be final. The same practice should be followed for online applications also.
The Members of SEAC unanimously taken following decisions on the agenda points
discussed:
1. Proposed “Revamping of HPCL” Meerut Oil Installation. - Sri Satish Kumar, Sr. Instt.
Manager, HPCL, Meerut IRD. File No. 3196/OSD-T
The committee noted that an application dated 01/06/2015 was made by the project
proponent for environmental clearance of Proposed “Revamping of HPCL” Meerut Oil Installation,
U.P. M/s Hindustan Petroleum Corp. Ltd. The terms of reference were prescribed in SEAC meeting
dated 23/07/2015. Final EIA was submitted by the project proponent through letter dated
18/01/2016.
A presentation was made by Shri Sonil Khare, Sr. Officer (Maintenance and Safety, HPCL)
along with Shri A.K. Singh Sr. Manager, HPCL and their consultant M/s Mantec Consultants Pvt.
Ltd., Noida. The proponent, through the documents submitted and the presentation made, informed
the committee that:-
Minutes of 265th
SEAC Meeting Dated 11/04/2016
Page 2 of 43
1. The environmental clearance is sought for Proposed “Revamping of HPCL” Meerut Oil
Installation, U.P. M/s Hindustan Petroleum Corp. Ltd.
2. HPCL Meerut Oil Terminal was constructed in Aug-1994 and supplying Petroleum products
to 8 districts from last 20 years.
3. HPCL is planning to augment and revamp the existing Meerut (UP) Oil terminal to meet the
increasing demand of petroleum products in the National Capital Region (NCR) and UP
west of India.
4. HPCL Meerut Terminal after augmentation and revamp shall be energy efficient,
environment- friendly and shall meet the increasing requirement of MS (Motor Sprit), HSD
(High Speed Diesel) and SKO (Superior Kerosene Oil) of 9 cities in UP west.
5. The company intends to establish storage and distribution facilities for 29625 KL petroleum
product (MS, HSD, SKO and Ethanol) at Village- Vedvyaspuri, Pootha Partapur industrial
area in Meerut district of Uttar-Pradesh.
6. HPCL Meerut terminal spread over an area of 12.54 acres, the Meerut terminal was built in
1994, next to an IOCL terminal at Partapur Industrial Area in Meerut.
7. Existing capacity of 9472 KL.
8. Salient features details:
PARTICULARS DETAILS
Name of Project Revamping of HPCL Meerut oil Installation.
Proposed Capacity Class A-14235 KL, Class B-15390 KL, Total capacity 29625KL
Category of Project Category B
Location Village- Vedvyaspuri, Pootha Partapur industrial area, District –Meerut , Uttar-Pradesh.
Corner
Co-ordinates (1)28⁰57’1.40”N 77⁰39’31.02” (2)28⁰56’57.08”N 77⁰39’37.03”
(3)28⁰56’54.44”N 77⁰39’26.58” (4)28⁰56’50.91”N 77⁰39’33.82”
Toposheet No (SoI) Study Area : Toposheet No 53G12, 53H9, 53H13,
Land Requirement 12.57 Acres (5.07 Hectare) existing
Raw Water Requirement 2 KL water required for domestic purpose, Water will stored for firefighting purpose.
Power supply UPSEB Maliyana (Partapur, Meerut) Substation through 800 KVA, 11KV/415V
transformer.
9. Detailed storage facility after revamp:
10. 2 Nos. of 8 Bay TT Gantries.
11. Other Facilities : ETP, Fire fighting system, Electrical system, Pump house, pipeline,
Boundary walls, Internal roads, Truck Parking, TLF pump house, TWD pump house,
Admin building, Bore-well, DG Sets etc.
12. Area around the project site: PARTICULARS DETAILS
North MDA green belt (RAF Campus)
East Agriculture land
South Tank Wagon unloading siding ,Railway track and Agriculture land
West IOCL terminal
13. Terminal operation process is as follows:
• RECEIPT: Petroleum Products are received thru Tank wagons from Tank wagon
loading locations Bahadurgarh , HMEL as per monthly distribution plan .
Minutes of 265th
SEAC Meeting Dated 11/04/2016
Page 3 of 43
• STORAGE: Petroleum Products are stored in closed storage tanks ( Internal floating
Roof, fixed cone roof, Underground tanks) . All the storage tanks are connected to Tank
wagon decantation Pumps and tank trucks loading pumps through MS pipelines.
• DELIVERY: Delivery to retail outlets are done by tank trucks of capacity
12KL/18KL/20KL which are filled at Automated Tank truck loading gantry thru
centrifugal product pumps.
14. Water requirement details:
• 02 KLD water required for domestic purposes (Service + Drinking):
Water requirement Description Water uses (L)
2 KLD Kitchen 600
Bathroom 400
Drinking Purpose 500
Gardening 500
15. The project proposals are covered under category 6"b" of EIA notification, 2006, as
amended.
The committee discussed the matter and directed the project proponent to submit
following information:
1. Area details showing proposed uses as facilities area, parks, parking, roads, other services of
the project also in percentage.
2. Submit green belt plan with minimum 33% of plot area also showing the same on layout
plan. Minimum 10 m Peripheral green shall be provided. Details of landscape plan with area
calculation along with plantation of trees @ one tree for every 85.0 sq.metre of area is to be
submitted.
3. As per proponent, a separate ETP will be installed with a cost of 1.5 crore. Plan to be
submitted.
4. Provision of 100% solar lighting along the road side, stair cases, common places.
5. Use of reflecting paints on rooftops and side walls. Plan submitted.
6. Submit the schedule of EIA monitoring/data collection in the months of October-December
to the Office of Directorate of Environment, Member Secretary, UP Pollution Control Board
and District Magistrate. Submit photographs of monitoring period. Study report regarding
Ambient Air Quality to be submitted.
7. NOC from Fire Department shall be taken.
8. Total project cost is 146 Cr. Corporate Social Responsibility (CSR) plan (need based and
phase wise) along with budgetary provision amounting to 2% of project cost shall be
prepared and approved by Board of Directors of the company. A copy of resolution as above
shall be submitted to the authority along with list of beneficiaries with their mobile
nos./address.
9. The project proponent has claimed that they should be exempted from the requirement of
public hearing. Submit necessary provisions/rules/documents as per law in support to this
claim for further consideration by the committee on this point.
10. Vapour recovery system should be installed to prevent evaporational lose.
The matter shall be discussed after submission of information as above.
Minutes of 265th
SEAC Meeting Dated 11/04/2016
Page 4 of 43
2. Proposed Expansion of 4.00 lacs TPA single super phosphate 4.0 lacs TPA Granulated
Single Super Phosphate, 1.50 lacs TPA Sulphuric Acid & 5 MW Captive Power Plant at
A-1, UPSIDC Industrial Area, Malwan, Fetehpur,U.P. Mr. S.P.Jain, Sr. Vice President
(Project & Dvelopment), KCFL, 301-308, Apollo Arcade, Old Palasia, Indore -
452018(M.P.) File No. 1313/OSD-T/(DD-D)
The project proponent neither appeared nor he sent any communication in this
regard. The committee discussed and deliberated that project file should be closed and should be opened only after request from the project proponent. The file shall not be treated
as pending with SEIAA/SEAC.
3. Group Housing Project "French Apartment" at Plot No-GH-07B, Sector-16B, Greater
Noida- Sri Shashank, 5th Floor, Sachdeva Corporat Tower, Plot No-17, DDA Commercial
Complex, Karkardooma, New Delhi. File No. 2797/SPO-V
The committee noted that the matter was earlier discussed in SEAC meeting dated
31/10/2015 wherein the committee deliberated as follows:
" The committee discussed the matter, during discussion Shri Sundeep Rustagi, project
proponent/representative along with their consultant M/s Ind Tech House Consult, Delhi. Informed
the committee regarding the construction has been made without achieving Environmental
clearance:
At this the committee discussed the matter and deliberated that Hon'ble NGT in its order
dated 07/07/2015 in the matter of S.P. Muthuraman V/s Union of India and Ors. (Original
Application No. 37 Of 2015 (M.A. No. 291, 293 & 294 Of 2015) and Original Application No. 213
Of 2014 (Ma 755 Of 2014 & M.A. No. 177 Of 2015) has quashed the MoEF OMs dated
12/12/2012 and 27/06/2013 related to provisions for dealing the violation matters.
In reference to Hon'ble NGT decision dated 07/07/2015 the SEIAA has already forwarded a
letter no- 638/Praya/SEIAA-3/GOI-SG/Ptra/14 dated 234-07-2015 to Ministry of Environment,
Forest & Climate change ( MoEF& CC) for providing the valuable suggestion to the SEIAA, U.P.
so that necessary action may be taken in such cases. The SEAC directed the project proponent to
stop the construction work immediately at the site. A reference in this regard should also be made to
District Administration. The SEAC deliberated that the matter shall be considered after receipt for
the information from MoEF&CC regarding Hon'ble NGT decision dated 07/07/2015.The file shall
not be treated as pending at SEIAA/SEAC."
2. The SEIAA, discussed the matter in its meeting dated 26/11/2015 and directed as follows:
" The SEIAA gone through the SEAC recommendations regarding the matter and noted that -
1. The Application has been made by the project proponent for the environmental clearance for
Expansion of Group Housing "French Apartment" at Plot No-GH-07B, Sector-16B, Greater
Noida, U.P., M/s Anthem Infrastructure Pvt. Ltd.
2. Environmental clearance for the earlier proposal was issued through SEIAA, U.P. letter no.
465/Parya/678/SEAC/2011/AAS, dated 04-06-2012 for plot area 25305 sqm, built-up area
1,02,417.37 sqm and 797 dwelling units.
3. The SEAC discussed the matter, during discussion Shri Sundeep Rustagi, representative of the
project proponent along with their consultant M/s Ind Tech House Consult, Delhi. Informed the
committee that the construction has been made without achieving Environmental clearance.
4. The SEAC discussed the matter and deliberated that Hon'ble NGT in its order dated 07/07/2015
in the matter of S.P. Muthuraman V/s Union of India and Ors. (Original Application No. 37 Of
2015 (M.A. No. 291, 293 & 294 Of 2015) and Original Application No. 213 Of 2014 (Ma 755 Of
2014 & M.A. No. 177 Of 2015) has quashed the MoEF OMs dated 12/12/2012 and 27/06/2013
related to provisions for dealing the violation matters. In reference to Hon'ble NGT decision
Minutes of 265th
SEAC Meeting Dated 11/04/2016
Page 5 of 43
dated 07/07/2015 the SEIAA has already forwarded a letter no- 638/Praya/SEIAA-3/GOI-
SG/Ptra/14 dated 234-07-2015 to Ministry of Environment, Forest & Climate change ( MoEF&
CC) for providing the valuable suggestion to the SEIAA, U.P. so that necessary action may be
taken in such cases. The SEAC directed the project proponent to stop the construction work
immediately at the site. A reference in this regard should also be made to District
Administration. The SEAC deliberated that the matter shall be considered after receipt for the
information from MoEF&CC regarding Hon'ble NGT decision dated 07/07/2015.The file shall
not be treated as pending at SEIAA/SEAC.
The SEIAA noted that in reference to the SEAC meeting minutes dated 31/10/2015
regarding the title projects the project proponent has submitted a representation dated
26/11/2015.The SEIAA discussed the project proponent representation dated 26/11/2015 and
directed the SEAC to consider the same in its meeting.
The SEIAA also directed the SEAC that such cases in which construction has been done
without obtaining the Environmental clearance, i.e. in which the violation of E P Act, 1986 has
been made may be considered in light of Hon’ble Supreme Court Decision dated 14/9/2015 in
Civil Appeal No(s).6896/2015, M/s VIVEKANAND ASHRAM SOCITY & ANOTHER Vs KRISHAN LAL
GERA & OTHERS."
The committee discussed the matter and representation dated 26/11/2015 of project
proponent and directed the project proponent to submit following information:
1. It is case of revised E.C. as the details of presentation shows that the tower no A to J were
initially proposed 14 floor and in every tower, construction has started as well as done
which carries from maximum 12 to minimum 03 floors. Where as in revised proposal as
submitted, it is 19 Floor it means adding +05 floors in each towers except no construction in
tower K and L. The proponent should submit Proof of date of start of construction i.e. copy
of mandatory communication to be made to development authority in this regard alongwith
photographs. 2. Submit structural stability certificate with sign of architect and vetted by competent
agency/institute, regarding expansion proposal. 3. Comparative statement of area with tower wise and floor wise details alongwith no. of units.
4. Comparative statement regarding various uses like population, area, water uses and management, solid waste and management, power uses and backup, parking etc. should be
submitted. 5. Details of green area also on layout plan.
6. Copy of approved layout plan/maps/services plans.
7. Provision of Parking is to be made as per building bye laws only. Rest of the parking to be
deleted from parking plan.
8. Revised NOCs from Fire and AAI are to be submitted.
The committee discussed that it appeared to be a case of violation as additional floors five
no are proposed to be added. So Proponent is directed to stop the construction till EC is issued and
submit the information as above. The matter shall be discussed after submission of information as
above.
4. Group Housing Project at Plot No-A-01/A, Sector-124, Noida. Sri S J Raza, Flat No-G-25,
Bloc-C, Gaur Global Village, Crossing Republic, Ghaziabad. . File No. 3615/DD-Sh.
The committee noted that an application dated 08/02/2016 was made by the project
proponent for environmental clearance of Group Housing Project at Plot No-A-01/A, Sector-124,
Noida, U.P. M/s ATS Heights Pvt. Ltd.
A presentation was made by Shri Varun Juneja, authorized representative of project
proponent along with their consultant M/s J M Enviro Net Pvt. Ltd. The proponent, through the
documents submitted and the presentation made, informed the committee that:-
Minutes of 265th
SEAC Meeting Dated 11/04/2016
Page 6 of 43
1. The environmental clearance is sought for Group Housing Project at Plot No-A-01/A,
Sector-124, Noida, U.P. M/s ATS Heights Pvt. Ltd.
2. Salient features details of the project: Particulars Residential Commercial Total Entire project
Total Plot
area
46340 sq. m (60% area under Commercial & 40 % area under Residential)
Built-up area 165955.47 sq. m 240021.76 sq. m 405977.23 sq. m [F.A.R (242095.0sq. m) +
Area Under Services (37392.2 sq.m)+
Covered Parking/NON F.A.R.(126490.0sq.
m )]
Ground coverage
Proposed: 5141.344 sq.
m
Proposed: 11985.296 sq.
m
Permissible: 18536.00 sq. m (40.0%) Proposed: 17303.50 sq. m (37.3%) {176.829
sq.m. others + 17126.64 commercial
/residential)
F.A.R. Permissible: 97314.0 sq.
m
Proposed: 97273.3 sq. m
Permissible: 145971.0 sq.
m
Proposed: 144821.6 sq.
m
Permissible: 243285.00sq. m (5.25%)
Proposed: 242095.00 sq. m (5.22%)
Maximum
Building
height
204.30 Meters 130 meters 204.30 Meters
No. of floors
& basements
2 Basement + Ground
floor + Lobby + 46 upper
floors + 2 Service Floor
2 Basement + Ground
floor + 1st Floor + 4
Podium + 25 Upper
Floor
2 Basement + Ground floor + Lobby + 46
upper floors + 2 Service Floor
No. of dwelling
units
215 MDU 80 shops (on Ground floor & 1st Floor), plus
Food court & offices
Main Dwelling Units – 215 in Residential & 80 shops (on Ground floor & 1st Floor), plus
Food court & offices in Commercial
Parking
facilities
Required - 1216 ECS
Provided - 1565 ECS
Required - 2896 ECS
Provided - 3426 ECS
Required Parking- 4112 ECS
Provided Parking- 4991 ECS
Power
requirement
& source
3615 KVA 20591 KVA Total – 24206 KVA
(Source :- Local grid supply of Noida)
Power
backup
3 D. G capacity of 3030
KVA (3X 1010 KVA)
10 D. G capacity of
19010 KVA (9 X 2000
KVA + 1 X 1010 KVA)
13 No of DG Sets capacity of 22040 KVA
(9 X 2000 KVA + 4 X 1010 KVA)
Water
requirement
& source
Total Water 236 KLD
Fresh Water : 127 KLD
Recycled Water: 109
KLD
Total Water 1198 KLD
Fresh Water : 738 KLD
Recycled Water: 460
KLD
Total Water 1434 KLD
Fresh Water : 865 KLD
Recycled Water: 569 KLD
Source: Ground Water, Municipal Water
supply & Private Water Tankers Supply
Capacity of STP
200 KLD 500 KLD Total Capacity 700 KLD
Solid wastes
generation
Total solid waste 574
kg/day
(Residential – 484 kg/day
+ Floating – 90 kg/day)
Total solid waste – 3019
kg/day
Total solid waste – 3593 kg/day
(Residential – 484 kg/day + Floating – 3109
kg/day)
Estimated
population
1433 Persons
(Resident: 1075 Persons
+ Floating- 358 Persons)
12078 Persons 13511 Persons
(Resident: 1075 Persons + Floating- 12436
Persons)
Green-area Landscape Area – 15254 sq. m (32.91 % of total plot area)
3. Parking details: • PROPOSED PARKING FOR RESIDENCIAL PLOT:
S. NO PARTICULAR AREA FOR PARKING NO. OF ECS
1 Open/Surface Parking (@ 20 sq. m) 4457 sq. m 223
2 Upper Basement (@ 30 sq. m.) 19967.90 sq. m 666
3 Lower Basement (@ 30 sq. m.) 20290.29 sq. m 676
Total Provided Parking 1565 ECS
• PROPOSED PARKING FOR COMMERCIAL PLOT
S. NO PARTICULAR AREA FOR PARKING NO. OF ECS
1 Open/Surface Parking (@ 20 sq. m) 7820 sq. m 391
Minutes of 265th
SEAC Meeting Dated 11/04/2016
Page 7 of 43
2 Stilt Parking (@ 30 sq. m) 5312 sq. m 177
3 Stilt Mechanical Parking (@ 18 sq. m) 2603 sq. m 145
4 Upper Basement (@ 30 sq. m.) 33983.3 sq. m 1132
5 Podium 1, 2, 3 & 4 (@ 30 sq. m.) 47428.54 sq. m 1581
Total Provided Parking 3426 ECS
• Total No. of Parking Required (Commercial+ Residential) = 4112 ECS
4. Water calculation details: S.
No.
Particulars Expected
Population
Base of
Calculation
(lpcd)
Recycled Treated
Water (KLD)
Fresh Water
(KLD)
Total Water
Consumption
(KLD) Flushing Others Domestic Others
1. Dwelling Units
(215 DU)
1075
@ 5
persons/DU
135 48.37 - 96.75 - 145.12
2. Visitors 108
@ 10% of the total
population
45 3.24 - 1.62 - 4.86
3. Community
Building
(4431 sq. m)
250 Person 45 7.50 - 3.75 - 11.25
4. Commercial
Tower
10980
Persons
45 329.40 - 164.70 - 494.10
5. Visitors 1098 Persons 15 15.37 - 1.09 - 16.47
6. Green Belt - - - 52.00 - - 52.00
7. Soft Water for
cooling
(HVAC / DG)
- - - - - 660.00 660
8. Swimming
Pool
- - - - 25.00 25.00
9. Road Washing - - - 25.00 - - 25.00
Total 13511
Persons
- 403.88
say 404
KLD
77.00
KLD
267.89
say
268 KLD
685
KLD
1433.8 say
1434 KLD
481 KLD 953 KLD
5. 13 nos. of rain water harvesting pits are proposed for the project. 6. The project proposals are covered under category 8"b" of EIA Notification, 2006, as
amended.
The committee discussed the matter and recommended following TORs and general
guidelines for conducting EIA studies regarding the proposals:
Additional TORs :
1. Master plan of the area showing proposed project. Permissible uses of the proposed site as
per zoning regulation.
2. Allotment letter from concerned development authority.
3. All approved drawings/maps alongwith approved services plans.
4. Structural design certificate signed by architect and vetting authority should be submitted.
All structural design drawings should be signed by architect and counter signed by vetting
authority.
5. Area details showing proposed uses as residential, commercial, parks, parking, roads, other
services, facilities of the project also in percentage.
6. Physical features within 30 m of the project sites with their ownership.
7. Complete Details of facilities to be developed by the project proponent i.e. for which
environment clearance is sought.
8. Use of reflecting paints on roof top and side walls.
9. Details of rain water harvesting are to be given.
Minutes of 265th
SEAC Meeting Dated 11/04/2016
Page 8 of 43
10. Provision of 100% solar lighting along the road site, stair cases, common places.
11. Plan for EWS / LIG housing provision as per Development Authority bye-laws.
12. Examine in detail the proposed site with reference to impact on infrastructure covering
water supply, storm water drainage, sewerage, power, etc., and the disposal of treated/raw
wastes from the complex on land/water body and into sewerage system. Consider soil
characteristics and permeability for rainwater harvesting proposals, should be made to
prevent ground water contamination. Maximize use of treated water by recycling and
utilization of rainwater.
13. Water requirement and water management plan along with necessary permissions for
discharge.
14. An underground Pucca tank for collection/reuse of rain water may be constructed.
15. Hydro-geological investigations be carried out and obtain permission from Central Ground
Water Authority for withdrawal of ground water.
16. Make provision for safety against failure in the operation of wastewater treatment facilities.
Identify acceptable outfall for treated effluent.
17. Details of green belt as a measure for mitigation of dust and noise and buffer between
habitation and proposed project.
18. Landscape plan, green belts and open spaces may be described separately.
19. Study the existing flora and fauna of the area and the impact of the project on them. There
should be no basement below 15 m setback. Accordingly Plan should be revised and
submitted.
20. Section of all internal roads should be provided. Right of way and carriage way width
should be clearly marked on the map. Avoid entry/exit at point of junction of roads. Traffic
movement plan in and out should be shown.
21. Examine existing crèche, education, health facilities, police, post Office, Banks and other
services and make adequate provisions in the proposal.
22. Assess soil erosion in view of the soil characteristics, topography and rainfall pattern.
23. Application of renewable energy/alternate energy, such as solar and wind energy may be
described including solar water heating in the guidelines for entrepreneurs.
24. Consider solid wastes, including e-waste in addition to other solid wastes and their disposal.
25. Identification of recyclable wastes and waste utilization arrangements may be made.
26. Explore possibility of generating biogas from biodegradable wastes.
27. Arrangements for hazardous waste management may be described as also the common
facilities for waste collection, treatment, recycling and disposal of all effluent, emission and
refuse including MSW, biomedical and hazardous wastes. Special attention should be made
with respect to bird menace.
28. Provisions made for safety in storage of materials, products and wastes may be described.
29. Disaster management plan should be prepared.
30. Traffic management plan including parking and loading/unloading areas may be described.
Traffic survey should be carried out both on weekdays and weekend.
31. Parking provision is to be made for higher ECS worked out either as per state bye-laws or
construction manual of the MoEF. Additional parking more than required nos. as per norms
will not be permitted.
32. Exclusive Parking area in the basement (excluding other facilities) and surface is to be
clearly mentioned.
33. Provide service road for entry and exit to project site.
Minutes of 265th
SEAC Meeting Dated 11/04/2016
Page 9 of 43
34. Use of local building materials should be described.
35. Consider provision of DG Flue Gas emissions to be treated in a scrubber. Stack details with
provisos of sampling port for monitoring be described. Power backup should be restricted to
50-60 % of power requirement. Plan should be revised and submitted.
36. Work out MGLC for the combined capacity of DG sets.
37. Provide for conservation of resources, energy efficiency and use of renewable sources of
energy in the light of ECBC code.
38. Application of resettlement and rehabilitation policy may be described. Project affected
persons should be identified and rehabilitation and resettlement plan should be prepared.
39. Examine separately the details for construction and operation phases both for Environmental
Management Plan and Environmental Monitoring Plan.
40. Corporate Social Responsibility (CSR) plan along with budgetary provision amounting to
2% of project cost shall be prepared and approved by Board of Directors of the company. A
copy of resolution as above shall be submitted to the authority along with list of
beneficiaries with their mobile nos./address.
41. Required no of trees should be proposed @ 01 tree/80 sqm, submit plan.
42. Project falling with in 10 Km. area of Wild Life Sanctuary is to obtain a clearance from
National Board Wild Life (NBWL) even if the eco- sensitive zone is not earmarked.
43. Declare/submit the running cost of STP and other environmental management services (e.g.,
Municipal Solid Waste Disposal, Green belt Maintenance, Water Management etc.) in the
proposals which are to be including in the allotment letters. Vendors should be identified for
Municipal Solid Waste Management and submitted.
44. The proponent will submit the schedule of monitoring/data collection programme to the
Office of Directorate, Member Secretary, UP Pollution Control Board and District
Magistrate of related District.
General Guidelines:
a. A legal affidavit by the Project proponent on Rs. 100/- non-judicial Stamp Paper, duly
attested by Public Notary, stating that:
I. “There is no litigation pending against the project and/or land in which the project is
proposed to be set up (please give name & ownership etc. of the project) and that for any
such litigation what so ever, the sole responsibility will be borne by the Project
proponent.”
II. “No activity relating to this project (i.e. name of the project) including civil construction
has been undertaken at site except fencing of the site to protect it from getting
encroached and construction of temporary shed(s) for the guard(s). (if fencing has not
been done, then the same may be deleted).
III. “I/We hereby give undertaking that the data and information given in the application,
enclosures and other documents are true to the best of my knowledge and belief and
I/We am/are aware that if any part of the data and information submitted is found to be
false or misleading at any stage, the project will be rejected and clearance given, if any
to the Project will be revoked at our risk and cost.”
IV. Project does not fall under any buffer zone of no-development as declared /identified
under any law.
b. Another legal affidavit by the consultant stating “(a) that the prescribed TORs have been
complied with (to be deleted if not applicable) & (b) that details and the data presented are
Minutes of 265th
SEAC Meeting Dated 11/04/2016
Page 10 of 43
factually correct”, as per MoEF circular dated 04.08.2009 is also to be submitted along with
EIA.
c. Current, site photographs viewing towards the project area from four directions indicating
date of photograph taken, direction from which taken, name of the project, and signature of
Project proponent along with consultant with seal should be submitted, so as to ensure that
no construction has been started before the grant of EC.
d. EIA should strictly follow the guidelines prescribed in annexure-III to the EIA notification
of 2006 and the Methods of Monitoring and analysis (Annexure-IV): Guidance for
assessment of representativeness and reliability of baseline environmental attributes detailed
under EIA manual January, 2001 and other guidelines in the matter.
e. The status of accreditation of the EIA consultant with NABET/QCI shall be specifically
mentioned. The consultant shall certify that his accreditation is for the sector for which this
EIA is prepared.
f. On the front page of EIA/EMP reports, the name of the consultant/consultancy firm along
with their complete details including their accreditation, if any shall be indicated.
g. While submitting the EIA/EMP reports, the name of the experts associated with/involved in
the preparation of these reports and the Name of laboratory through which the samples have
been got analysed should be stated in the report. It shall clearly be indicated whether said
laboratory is accredited by NABL or approved under the Environment (Protection) Act,
1986 (Please refer MoEF office memorandum dated 4th August, 2009). The name project
leader of the EIA study shall also be mentioned.
h. The EIA document shall be printed on both sides, as for as possible.
The Information’s no (a I , II, III & c) asked under the general guidelines is to be
submitted within 15 days from the date of receipt of the letter and remaining of the
information’s is to be submitted along with the EIA.
5. Expansion of Group Housing Project “Sunworld Arista” at Plot No-GH-01/C, Sector-168,
Noida. Sri Anoop Negi, AGM, A-4, Sector-4, Noida. . File No. 3618/AD-Sub.
The committee noted that an application dated 04/02/2016 was made by the project
proponent for environmental clearance of Expansion of Group Housing Project “Sunworld Arista”
at Plot No-GH-01/C, Sector-168, Noida, U.P. M/s Sunworld Residency Pvt. Ltd.
A presentation was made by Shri Anoop Nagi, authorized representative of project
proponent along with their consultant M/s Ind Tech House Consult, Delhi. The proponent, through
the documents submitted and the presentation made, informed the committee that:-
1. The environmental clearance is sought for Expansion of Group Housing Project “Sunworld
Arista” at Plot No-GH-01/C, Sector-168, Noida, U.P. M/s Sunworld Residency Pvt. Ltd.
2. Environmental clearance for the earlier proposal was issued thorough SEIAA, U.P. letter no. 220/parya/SEAC/1143/2013/DD(sh) dated 30
th July, 2013.
3. Post expansion project comprises 11 (10+1) number of residential towers along with community hall, commercial building and adequate parking facilities.
4. Total dwelling units 978. 5. Total plot area of the project is 40,221.30 sq. m, whereas, total built-up Area is 2,32,014.96
sq. m 6. Comparative details for earlier proposal and proposed expansion proposal:
SN Description As per EC letter * Proposed Difference %
Change
1 Plot Area 40,221.30 sq. m. 40,221.30 sq. m. No change -
Minutes of 265th
SEAC Meeting Dated 11/04/2016
Page 11 of 43
2 Proposed Built Up Area 1,92,855.86 sq. m. 2,32,014.96 sq. m. 39,159.1 sq.
m.
20.30
3 Basement Area 71,044.80 sq. m. 71,041.48 sq. m. -3.32 sq. m.
4 FAR 1,16,106.8 sq. m. 1,46,240 sq. m. 30,133.2 25.95
5 Total no of DU's
(including informal)
- 978 - -
6 Proposed Parking 2,163 ECS 1,852 ECS -311 ECS -14.38
7 Total Water Requirement 471 KLD 608 KLD 137 KLD 29.08
8 Fresh Water Requirement 315 KLD 411 KLD 96 KLD 30.47
9 Total Wastewater
Generation
351 KLD 464 KLD 113 KLD 32
10 STP Proposed 420 KLD 560 KLD 140 KLD 33.33
11 Total Power Requirement 9,162 KVA 6,780 KW -2382 KVA -26
12 No. and Capacity of DG
Sets
09 (13000 KVA)
(8x1500 + 1x1000
KVA)
07(7500 KVA)
(2X1500+2X1250+2X750+1X
500)
-5500 -42
13 Proposed Green Area 16,767.9 sq. m. 15,925 sq. m. -842.9 sq. m. -5.027
14 Total Quantity of MSW 1.72 TPD 3.18 TPD 1.46 TPD 84.88
TPD
15 No. of RWH Pits 10 10 No Change -
7. Tower wise construction details: Particulars (Name
of Tower)
No. of Floor (As per
Approved EC)
No. of Floor (As per
Revised Proposal)
Difference Construction
Status as on
10.02.2016
Lower Basement - - -
Upper Basement - - -
Tower-T1 2B+G+18 2B+G+18 - 2B+G+17
Tower-T2 2B+G+18 2B+G+18 - 2B+G+17
Tower-T3 2B+G+18 2B+G+18 - 2B+G+17
Tower-T4 2B+G+18 2B+G+18 - 2B+G+17
Tower-T5 2B+G+26 2B+G+33 +7 Const not
started
Tower-T6 2B+G+18 2B+G+18 - 2B+G+17
Tower-T7 2B+G+17 2B+G+25 +8 Excavation
Tower-T8 2B+G+17 2B+G+25 +8 Excavation
Tower-T9 2B+G+10 2B+G+31 +21 Excavation
Tower-T10 2B+G+28 2B+G+31 +3 2B+G+25
8. Salient features / details for the proposed expansion project: S. No. Description Details
AREA DETAILS
1. Plot Area 40221.30 sq. m.
2. Permissible FAR Area 350 +5% for Green Rating (367.5) 147813 sq. m.
3. Proposed FAR Area (363.59) 146240 sq. m.
4. Ground coverage area permissible (30%) 12066.3 sq. m.
5. Ground Coverage Proposed (21.02%) 8453 sq. m.
6. Total Built up area 232014.96 sq. m.
7. Total no of Saleable DU's 978
8. Max Height of Building upto terrace 114.7 meters
9. Max No of Floors (Residential Tower) 2B+G+34
GREEN AREA
10. Required Green Area (39.49% of Plot Area) 15884 sq. m,
11. Proposed Green Area (39.59% of Plot Area) 15925 sq. m.
PARKING DETAILS
12. No. of ECS required 1848 ECS
13. No. of ECS proposed 1852 ECS
POPULATION DETAILS
14. Expected Population Total 7070 person
• Residential - 6098
• Floating - 972
WATER REQUIREMENT
Minutes of 265th
SEAC Meeting Dated 11/04/2016
Page 12 of 43
15. Total water requirement 608 KLD
16. Fresh water requirement 411 KLD
17. Horticulture water requirement 16 KLD
18. Water Body / Swimming Pool 06 KLD
19. Water Cooled DG Cooling (for 6 Hrs.) 41 KLD
WASTEWATER AND SOLID WASTE GENERATION
20. Waste water Generation 464 KLD
21. STP Capacity 560 KLD
22. Solid waste generation 3.18 TPD
POWER DETAILS
23. Maximum Power Demand 6780 KW, Uttar Pradesh Power Corporation Ltd
(UPPCL)
24. DG set backup 7500 KVA
9. Population details: RESIDENTIAL DU'S POP/DU TOTAL
Saleable DU‘s 978 4.5 4401
EWS 0 2 0
Servant RM Attached with Main DU 754 2.25 1697
Total 6098
Non-residential
Facilities - Club/Commercial etc (Employees) Area
Commercial (Shopping) 1327 133
Community Building 2006 40
Facility Management Staff LS 28
Total 201
Visitors
772
Total No of Visitors 772
Total Population 7070
10. Water requirement details: Sl. No. Description Occupancy /
Capacity / Area
Rate (Liters) Total Water
Demand (KLD)
A. Residents
Domestic 6098 65 396
Flushing 6098 21 128
B. Non-residential / Working
Domestic 201 18 04
Flushing 201 27 05
C. Visitors
Domestic 772 6 05
Flushing 772 9 07
D. Gardening 15925.0 1 16
E. Water Cooled DG Cooling (For 6
Hrs.)
7500 0.9 40
F. Water Body / Swimming Pool 1 LS 06
Total Water Requirement 608
Head Source Quantity
Fresh Water Requirement
Treated Water Requirement
(Operation Stage)
New Okhla Industrial Development Authority 411 KLD
On site STP 197 KLD
Water Requirement(Construction Stage) From nearby STP
11. Waste water calculation details: Head Quantity, KLD
Total Water Requirement 608
Fresh Water Requirement 411
Treated Water Requirement 197
Water for Flushing 140
Gardening 16
DG Cooling 41
Minutes of 265th
SEAC Meeting Dated 11/04/2016
Page 13 of 43
Waste Water Generation (80% of total domestic fresh water demand + 100% of
Flushing Water)
464
Capacity of STP 560
Treated Water Generation 371
Surplus Treated Water 174
12. Parking details: Particulars Area (In sq.m) Number (ECS)
Required Parking as per bylaws(@1ECS/80 SQM FAR Area) 147813 (FAR Area) 1848 ECS
Proposed Parking - 1852 ECS
Surface Parking - 110 ECS
Upper Basement Parking 25920 864 ECS
Lower Basement Parking 26340 878 ECS
13. Solid waste generation details: Total Waste Generation 3.18 TPD
Organic Waste Generation 1.91 TPD
E- Waste Generation 21 KG/Day
Sludge Generation 167.07 KG/Day
Hazardous Waste Generation (DG Waste Oil) 8.21 Lts/ Annum
14. The project proposals are covered under category 8"b" of EIA Notification, 2006, as
amended.
The committee discussed the matter and observed that as per project report submitted
Construction has started in tower no T1,T2,T3,T4 on 10/02/2016. The tower no T5 2B+G + 26 is
additional 7 no of floors are being added to be proposed to 33 floors. The tower no T-7 and T-8 is
initially was proposed for 17 floors which is revised for 25 floors adding 8 floor extra. Where as the
Tower no 9 is adding from 17 to 31 floors and Tower no 19 adding from 20 to 31 floors. On the
basis of factual status the proponent has to submit Comparative statement showing no of Towers
with no of floors for which EC was issued with date of approval from Competent Authority along
with Structural Design Signed and Vetted by Structural Engineer and Revised approval of map with
additional floors and revised Structural Design with date of Construction started along with
photographs and letter submitted to the Authority for work started. Revised NOC to be submitted
from Fire and Air Port Authority as required. Revised Comparative area statement of existing and
proposed plan to be also submitted.
The committee discussed that it appeared to be a case of violation as additional floors are proposed to be added. So Proponent is directed to stop the construction till EC is issued and submit
information as above. The matter shall be discussed after submission of information as above.
6. Group Housing Project at GH-03C, Sector-144, Noida- Sri Umasshankar Sharma, Sr.GM,
Gulshan Home and Infrastructure Pvt. Ltd., . File No. 3619/OSD-T
The committee noted that an application dated 16/02/2016 was made by the project
proponent for environmental clearance of Group Housing Project at GH-03C, Sector-144, Noida,
U.P. M/s Gulshan Homes and Infrastructure Pvt. Ltd. The committee noted that the matter falls
under category 8"a" hence TORs are not to be issued. The committee directed to take up the case
for appraisal as per chronology of category 8 "a" cases.
Minutes of 265th
SEAC Meeting Dated 11/04/2016
Page 14 of 43
7. Expansion of proposed Integrated Township “One World” at Vill-Baghamau, Lucknow.-
Sri Anwar Rizvi, Director, 302, Shalimar Square, BN Road, Lalbagh, Lucknow. . File No.
3623/AD-Sub.
The committee noted that an application dated 17/02/2016 was made by the project
proponent for environmental clearance of Expansion of proposed Integrated Township “One
World” at Vill-Baghamau, Lucknow. M/s ANS Developers Pvt. Ltd
A presentation was made by Shri Pulkit Yadav, authorized representative of project
proponent along with their consultant M/s ENV DAS India Pvt. Ltd. The proponent, through the
documents submitted and the presentation made, informed the committee that:-
1. The environmental clearance is sought for Expansion of proposed Integrated Township “One World” at Vill-Baghamau, Lucknow. M/s ANS Developers Pvt. Ltd
2. Environmental Clearance for the earlier proposal was issued through SEIAA, U.P. letter no. 2003/Parya/SEAC/1665/2013/TA(J) dated 12/10/2013.
3. Comparative details of earlier project and proposed expansion: Items As per EC issued in 2013 Expansion Details
Total project area 89.937 Ha
(222.24 Acre) 857500 m
2
(211.833 Acre)
excluding Abadi area (22.67 ac)
Area under Master plan road 12.01 Acre
46647.43 m2
11.52 acre
Area under Village abadi 22.67 acre already excluded
Area under Shamshan & graveyard - 1740.135 m
2
Net project area 7,59,283.36 m2
(187.57 Acre) 809112.57 m
2
(199.879 Acres)
Area of Group Housing- High Rise 3,37,223.33 m
2
291996.70 m2
Permissible F.A.R 843058.325 (@2.5) 7,29,991.75 m
2
(@2.5)
Area of Group Housing – Low Rise - 94501.10 m
2
Permissible F.A.R - 2,36,252.75 m
2
(@2.5)
Area of Group Housing – LIG/ EWS 32718.17 m2 32,116.93 m
2
Permissible F.A.R 65436.34 (@2) 65,436.34 (@2)
Total achieved Unit 8430 7052+1030+1700
Total Achieved population @5 person/unit 42150 48910
Commercial 37,216.06 m
2
64,026.05 m2
Public Semipublic 80,540.35 m
2
82,409.25 m2
Park & Open spaces 1,14,028.44 m
2
1,22,412.38 m2
Roads and Circulation 1,57,557.01 m
2
121650.15 m2
Total 7,59,283.36 m
2
8,09,112.57 m2
Fresh water Requirement 2907 KLD 3350 KLD
Recycled water Requirement 1700 KLD 2126 KLD
Total water requirement 4607 KLD 5476 KLD
Waste Water 3250 KLD 4332 KLD
Proposed STP 4 x 1000 KL 2 x 2500 KL
Municipal Solid waste 26.5 TPD 30 TPD
E- waste 17 kg/day 20 kg/day
Biomedical waste 11.25 kg/day 160 kg/day
4. Area details of the project: I Total Project Area excluding Baghamau Village abadi area
(22.67 Acre) 857500 m
2
211.833 Acre
Minutes of 265th
SEAC Meeting Dated 11/04/2016
Page 15 of 43
Area under Master plan road 46647.43 m2
11.524 Acre
Area under shamshan & graveyard 1740.135 m2
0.43Acre
II Net project area 809112.57 m2
199.879 Acre
1 Residential
a Area of Group Housing – High Rise 291996.70 m2
Permissible Ground Coverage 35%
Permissible F.A.R 7,29,991.75m2
(@2.5)
Permissible Density 1650 person/Ha
Permissible units 7052
Achieved population @5 person/unit 35260
b Area of Group Housing – Low Rise 94501.10 m2
Permissible Ground Coverage 35%
Permissible F.A.R 2,36,252.75 m2
(@2.5)
Permissible Density 1000 person/Ha
Permissible units 1030
Achieved population @5 person/unit 5150
c For Economical Weaker Sections (EWS) 32,116.93 m2
Permissible Ground Coverage 50%
Permissible F.A.R 65,436.34 (@2)
Achieved units 1700
Achieved population @5 person/unit 8500
d Total Residential Population 48910
2 Commercial 64026.05 m2
3 Public Semipublic 82,409.25 m2
4 Park & Open spaces 1,22,412.38 m2
5 Roads and Circulation 121650.15 m2
6 Total 8,09,112.57 m2
5. Land use distribution details of the project: S.No. Description Area % Achieved Built-up Area
(sqm)
Sqm Acre Shall be given
in EIA Report 1 Residential
Group Housing 386497.80 95.51
EWS & LIG 32116.93 7.94
Sub Total 4,18,614.73 103.44 48.72 %
2 Commercial 64026.05 15.82 4.9 %
3 Public Semipublic
Educational 34630.99 8.56
Health Centre/ Child welfare and
Maternity Centre
4646.58 1.15
Hospital 12574.18 3.11
Community Centre 5503.89 1.36
Electricity Substation 4051.32 1.00
Police Chowki 3078.63 0.76
Entertainment/ Cultural hub 5037.33 1.24
STP 4381.18 1.08
Rain Basera 1113.84 0.28
Sub Post Office/ Police Chowki 1917.52 0.47
Garbage Disposal 1823.79 0.45
Informal Sector 241.73 0.06
Community Facility 839.0 0.21
Sub Total 82,409.25 20.36 10.61 %
4 Park & Open spaces 1,22,412.38 30.25 15.02 %
5 Roads and Circulation 121650.15 30.06 20.75 %
Total 8,09,112.57 199.94 100.00 %
Minutes of 265th
SEAC Meeting Dated 11/04/2016
Page 16 of 43
6. Proposed utilities details:
• Group Housing- High Rise
• Group Housing- Low Rise
• Group Housing- EWS/ LIG Apartments
• Commercial
• Community Center
• Entertainment/ Cultural hub
• Educational (Secondary, Primary, Nursery Schools, Aanganwadi)
• Hospital
• Health center & Child Welfare & Maternity Center
• Police Chowki
• Rain Basera
• Electrical Sub Station
• STP- 1 & 2
• Garbage Collection centers
7. Water calculation details of the project: Particulars Units Population Rate of
Fresh
water
LPCD
Fresh water
required
in (KLD)
Rate of Flushing
water
LPCD
Flushing/Recycled water (KLD)
Total water (KLD)
Residential
Group Housing 7052+
1030+
1700
48910 65 3179 21 1027 4206
Visitors (10%) 5000 5 25 10 50 75
Staff (5%) 2500 13 25 38
Commercial
Visitors 12400 5 63 10 125 188
Staff 1000 30 15 45
Public & Semi-Public
Nursery 10 1000 5 5 10 10 15
Primary 3 600 5 3 10 6 9
High School 2 1000 5 5 10 10 15
Inter College 5 2500 5 13 10 25 38
Aanganwadi 10 500 5 3 10 5 8
Health Centre 30 beds 340 10 0 10
International
Hospital
1 350 beds 450 158 0 158
Other staff 200+70 30 8 8 4 12
Club
&Community
centre
20 Staff 5 0 0 0 0
1000 Visitors 5 5 5 10 15
Total Domestic 3518 1312 4830
Horticulture (@ 5litre /Sqm122412.58
m2
)
612 612
HVAC (2500 tonnes; 6 hrs operation) 34 34
Total Water Requirement 3518 1958 5476
8. Waste water details: Water/Waste Water Details
Fresh Water for domestic uses 3350KLD
Fresh Water for Health services 168 KLD
Recycled water for Flushing 1312KLD
Recycled water for Horticulture / Landscape 612KLD
Recycled water for HVAC* 34 KLD
Total Water Requirement (Fresh + Recycled) 5476KLD
Source of water - Ground Water Supply + Tertiary Treated Water
Minutes of 265th
SEAC Meeting Dated 11/04/2016
Page 17 of 43
Waste water - 4332KLD
STP Capacity - 5000KLD(~15 % extra) [2 modules of 2.5 MLD each]
Requirement of HVAC cooling water as per calculation is 135 KLD. However, this is one time requirement. Make
up water required for HVAC Cooling is 34 KLD (11 KLD considering 5% evaporation losses + 23 KLD blow down
considering cycle of concentration (COC) equal to 6)
9. The project proposals are covered under category 8"b" of EIA Notification, 2006, as
amended.
The committee discussed the matter and noted that land, on which expansion of the project is proposed, is not under possession of the project proponent. The committee directed that land
documents should be submitted for further discussion of the matter. The matter should be deferred and should be listed after submission of land documents for issuance of TOR.
8. Expansion of Group Housing Project “Cherry County” at Plot No.GH-5B, Tech Zone-IV,
Greater Noida - Sri Sunil Kumar Totlani. File No. 3625/DD-Sh.
The committee noted that an application dated 22/02/2016 was made by the project
proponent for environmental clearance of Expansion of Group Housing Project “Cherry County” at
Plot No.GH-5B, Tech Zone-IV, Greater Noida, U.P. M/s County Infrastructure Pvt. Ltd.
A presentation was made by Shri M.K. Vimal, authorized representative of project
proponent along with their consultant M/s Grass Roots Research & Creation India (P) Ltd. The
proponent, through the documents submitted and the presentation made, informed the committee
that:-
1. The environmental clearance is sought for Expansion of Group Housing Project “Cherry
Country” at Plot No.GH-5B, Tech Zone-IV, Greater Noida, U.P. M/s County Infrastructure
Pvt. Ltd.
2. Environmental Clearance for the earlier proposal was issued through SEIAA, U.P. letter no.
1121/SEAC/539/2010/DD(S) dated 10/05/2011.
3. Comparative details of earlier project and expansion project: S.
No.
Particulars Existing
(m2
)
Expansion
(m2
)
Total (Existing
+ Expansion)
(m2
)
1. Plot Area 48,000
2. Permissible Ground Coverage (@ 35%) 16,800
3. Achieved Ground Coverage (@ 27.308%) 11,225.116 1882.731 13,107.847
4. Permissible Residential FAR including 0.75 purchasable & 5% Green building FAR (@ 3.675)
1,76,400
5. Proposed Residential FAR
1,31,932.52
(@ 2.748)
44,452.77 1,76,385.29
6. Permissible Convenient Shopping/Commercial FAR --- 1680 1680
7. Proposed Convenient Shopping/Commercial FAR 1319.507 349.627 1669.134
8. Permissible Service FAR (@15%) 19,800 5400 25,200
9. Proposed Service FAR including Fire staircase + lift lobby +
lift shafts + service shafts + cupboard + guard room + STP +
U.G. Water tank + Community Centre
14970.675 6653.635 21,624.31
10. Basement Area
• Basement 1
• Basement 2
14,059.4
11,595.24
2,464.16
23,030.358
21,158.615
1,871.743
37,089.758
32,753.855
4335.903
11. Podium 15,313.175 933.366 16,246.541
12. Stilt Area 5463.3 - 687.342 4775.958
13. Built Up Area 1,63,568.56 71,437.735 257790.95
14. Number of DUs
• General units
• Servant units
1420
1420
Nil
354
354
576
1774
1774
576
Minutes of 265th
SEAC Meeting Dated 11/04/2016
Page 18 of 43
15. Open Area (@ 72.70%) 36774.884 - 1882.731 34,892.153
16. Required Landscape Area (@ 50% of open area) 17,446.077
17. Proposed Landscape Area 18482.369 -717.942 17,764.427
18. Maximum height of the building G + 19
(59.8 m)
G + 28
(86.31 m)
4. Built-up area break up details: S.
No.
Particulars Existing Area
(m2
)
Expansion
Area (m2
)
Total (Existing +
Expansion) (m2
)
1. Proposed Residential FAR 1,31,932.52 44,452.77 1,76,385.29
2. Proposed Convenient shopping/ Commercial
FAR
1,319.507 349.627 1,669.134
3. Proposed Service FAR including Fire staircase +
lift lobby + lift shafts + service shafts + cupboard + guard room + STP + U.G. Water tank +
Community Centre
14,970.675 6,653.635 21,624.31
4. Basement Area 14,059.4 23,030.358 37,089.758
3. Podium 15,313.175 933.366 16,246.541
4. Stilt 5,463.3 -687.342 4775.958
Total Built Up Area 1,63,568.56 71,437.735 2,57,790.95
5. Salient features details of expansion project: PROJECT FEATURES DESCRIPTION
Estimated Population 10,644 persons (Residents, staffs and visitors)
Estimated Water Requirement
Construction Phase
Operation Phase
983 ML (Source: Private Water Tanker)
841 KLD (Fresh water = 576 KLD) (Source: Municipal Supply)
Estimated waste water Generation Approx. 708 KLD
Power Demand
Power Back-up
5,708 KW
6 nos. Of DG sets 3,750 kVA capacity (6 x 625 kVA each)
Source of Power Uttar Pradesh State Electricity Board (UPSEB)
Green area (50.91% of open area) 17,764.427
Rain Water Harvesting Pits & Tanks Pits = 8
Tanks = 3
Solid Waste Generation 4,904 kg/day
Parking Facilities Required
Proposed
As per MoEF norms: 1797 ECS
As per Greater Noida bye-laws: 2261 ECS
2316 ECS
6. Population details: S. No. Description Total (Existing + Expansion)
DU PPU Population
1. Residential Population 1774 4.5 7,983
2. Servant Units 576 2.25 1,296
3. Visitors 1078
4. Staff 287
Total 10,644
7. Water calculation details for existing and expansion project:
S. No.
Description Area
(in m2
)
Total
Occupancy
Rate of water
demand (lpcd)
Total Water
Requirement (KLD)
A. Domestic Water
a) Residential 7983 86 687
b) Servant Unit 1,296 86 111
c) Visitors 1078 15 16
d) Staff 287 30 9
Total domestic water demand (A) = 823 KLD
B. Horticulture and Landscape
development
17764.427
m2
1 l/sqm/day 18
Grand Total (A+B+C) = 841 KLD
8. Solid waste generation details: S.
No.
Particular EC Accorded
(kg/day)
Expansion
(kg/day)
Total (EC Accorded + Expansion)
(kg/day)
Minutes of 265th
SEAC Meeting Dated 11/04/2016
Page 19 of 43
1 Residents 3,550 441.5 3992
2 Servant Unit - 648 648
3 Visitors 43 119 162
4 Staff 5 66 72
5 Landscape Waste - 1 1
6 Sludge 30 30
Total 3598 1306 4904
9. Rain water harvesting pits details: Type of
Area
Area
(in m2
)
Coefficient of
run-off
Peak rainfall intensity during one
hour of rainfall
(in m)
Rain water harvesting
potential/hour
(in m3
)
Roof-top
area
13,107.847 0.8 0.05 524.29
Total storm water load on the site with per hour retention is = 524.29 m3
/hr
Considering 15 minutes retention time, total storm water load 131.0725 m
3
Capacity of recharge pit (π r2
h ) = 3.14 x1.5 x 1.5 x 3.5 24.72 m3
Hence no. of pits required in approx = Total storm water load considering 15 minutes
retention time / Volume of RWH pit
131.0725/24.72 = 6 Pits
Proposed no. of Pits 8 Pits
10. Parking details: S. No. Particular Area proposed for Parking (m2) Area
required
/ECS
ECS Proposed
1. Surface 9123.24 20 456
2. Basement
• Basement I
• Basement II
35330.007
31,342.575
3,987.432
30
30 1177
1044
133
3. Stilt 4775.285 30 159
4. Podium 15732.936 30 524
Total Parking Proposed 2316
11. The project proposals are covered under category 8"b" of EIA Notification, 2006, as
amended.
The committee discussed the matter and recommended following TORs and general
guidelines for conducting EIA studies:
Additional TORs:
1. Any additional FAR granted by development authority due to green building proposal shall
be applicable only for expansion and not for the earlier proposal. .
2. Proof of date of start of construction i.e. copy of mandatory communication to be made to
development authority in this regard.
3. Specific area statements regarding proposed expansion.
4. Comparative area and other environmental parameter statements showing values earlier and
proposed as expansion.
5. All approved revised drawings/maps alongwith all approved revised services plans. All
original maps should be shown during EIA presentation.
6. Structural design certificate signed by architect and vetting authority for already existing
structure should be submitted. All structural design drawings should be signed by architect
and counter signed by vetting authority.
7. Structural design certificate signed by architect and vetting authority after incorporating
proposed expansion structure should be submitted. All structural design drawings should be
signed by architect and counter signed by vetting authority.
8. Status of construction undertaken till date (block wise/tower wise/floor wise).
Minutes of 265th
SEAC Meeting Dated 11/04/2016
Page 20 of 43
9. Compliance of earlier EC.
10. Master plan of the area showing proposed project.
11. Permissible uses of the proposed site as per zoning regulation.
12. Allotment letter from concerned development authority.
13. Physical features within 30 m of the project sites with their ownership.
14. Section details of all road.
15. Area details showing proposed uses as residential, commercial, parks, parking, roads, other
services, facilities of the project also in percentage.
16. Details of landscape plan with park furniture.
17. Land use approved by the competent authority.
18. Complete details of facilities to be developed by the project proponent i.e. for which
environment clearance is sought.
19. Plan for no of trees, one tree per 80 sq.mt. of area.
20. Use of reflecting paints on roof top and side walls.
21. Details of rain water harvesting are to be given.
22. Provision of 100% solar lighting along the road side, stair cases, common places.
23. A site plan showing the project site and its surroundings with physical features and
topographical details, such as land use, contours and drainage pattern, along with
photographs of the site from all four sides, should be included in the background
information.
24. 10% EWS/LIG housing provision shall be made as per Development Authority bye-laws.
25. Sanctioned plans/maps regarding the project with all services plans.
26. All plans and elevation sections/all service plan/landscape plan/standard electrification
plan/drainage/sewerage plan.
27. All service plans like sewer drainage water supply rain water harvesting fire fighting
landscape plan is to be submitted.
28. Section of all internal roads as proposed along R/W and C /W as well dimension is to be
to map.
29. Examine in detail the proposed site with reference to impact on infrastructure covering
water supply, storm water drainage, sewerage, power, etc., and the disposal of treated/raw
wastes from the complex on land/water body and into sewerage system.
30. Water requirement and water management plan alongwith necessary permissions for
discharge. STP details.
31. Hydro-geological investigations be carried out and obtain permission from Central Ground
Water Authority for withdrawal of ground water.
32. Consider soil characteristics and permeability for rainwater harvesting proposals, should be
made to prevent ground water contamination. Maximize use of treated water by recycling
and utilization of rainwater.
33. Make provision for safety against failure in the operation of wastewater treatment facilities.
Identify acceptable outfall for treated effluent.
34. Details of green belt as a measure for mitigation of dust and noise and buffer between
habitation and proposed project.
35. Landscape plan, green belts and open spaces may be described separately.
36. Study the existing flora and fauna of the area and the impact of the project on them.
37. Examine existing crèche, education, health facilities, police, post Office, Banks and other
services and make adequate provisions in the proposal.
Minutes of 265th
SEAC Meeting Dated 11/04/2016
Page 21 of 43
38. Assess soil erosion in view of the soil characteristics, topography and rainfall pattern.
39. Application of renewable energy/alternate energy, such as solar and wind energy may be
described including solar water heating in the guidelines for entrepreneurs.
40. Consider solid wastes, including e-waste in addition to other solid wastes and their disposal.
41. Identification of recyclable wastes and waste utilization arrangements may be made.
42. Explore possibility of generating biogas from biodegradable wastes.
43. Arrangements for hazardous waste management may be described as also the common
facilities for waste collection, treatment, recycling and disposal of all effluent, emission and
refuse including MSW, biomedical and hazardous wastes. Special attention should be made
with respect to bird menace.
44. All community facilities is to be proposed as per norms and is to be submitted.
45. Provisions made for safety in storage of materials, products and wastes may be described.
46. Disaster management plan should be prepared.
47. Traffic management plan including parking and loading/unloading areas may be described.
Traffic survey should be carried out both on weekdays and weekend.
48. Parking provision is to be made for higher ECS worked out either as per state bye-laws or
construction manual of the MoEF.
49. Exclusive Parking area in the basement (excluding other facilities) and surface is to be
clearly mentioned.
50. Provide service road for entry and exit to project site.
51. Use of local building materials should be described.
52. Consider provision of DG Flue Gas emissions to be treated in a scrubber. Stack details with
provisos of sampling port for monitoring be described.
53. Work out MGLC for the combined capacity of DG sets.
54. Provide for conservation of resources, energy efficiency and use of renewable sources of
energy in the light of ECBC code.
55. Application of resettlement and rehabilitation policy may be described. Project affected
persons should be identified and rehabilitation and resettlement plan should be prepared.
56. Examine separately the details for construction and operation phases both for Environmental Management Plan and Environmental Monitoring Plan.
57. Corporate Social Responsibility (CSR) plan along with budgetary provision amounting to 2% of project cost shall be prepared and approved by Board of Directors of the company. A
copy of resolution as above shall be submitted to the authority alongwith list of beneficiaries with their mobile nos./address.
58. Details of all internal and peripheral roads width. 59. Source and quantity of required water during construction and management of generated
waste water.
60. Project falling with in 10 Km. area of Wild Life Sanctuary is to obtain a clearance from
National Board Wild Life (NBWL) even if the eco- sensitive zone is not earmarked.
61. Declare/submit the running cost of STP and other environmental management services (e.g.,
Municipal Solid Waste Disposal, Green belt Maintenance, Water Management etc.) in the
proposals which are to be including in the allotment letters.
62. The proponent will submit the schedule of monitoring/data collection programme to the
Office of Directorate, Member Secretary, UP Pollution Control Board and District
Magistrate of related District.
General Guidelines:
a. A legal affidavit by the Project proponent on Rs. 100/- non-judicial Stamp Paper, duly attested
by Public Notary, stating that:
Minutes of 265th
SEAC Meeting Dated 11/04/2016
Page 22 of 43
I. “There is no litigation pending against the project and/or land in which the project is
proposed to be set up (please give name & ownership etc. of the project) and that for any
such litigation what so ever, the sole responsibility will be borne by the Project proponent.”
II. “No activity relating to this project (i.e. name of the project) including civil construction
has been undertaken at site except fencing of the site to protect it from getting encroached
and construction of temporary shed(s) for the guard(s). (if fencing has not been done, then
the same may be deleted).
III. “I/We hereby give undertaking that the data and information given in the application, enclosures and other documents are true to the best of my knowledge and belief and I/We
am/are aware that if any part of the data and information submitted is found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the
Project will be revoked at our risk and cost.” IV. Project does not fall under any buffer zone of no-development as declared /identified under any
law.
b. Another legal affidavit by the consultant stating “(a) that the prescribed TORs have been
complied with (to be deleted if not applicable) & (b) that details and the data presented are
factually correct”, as per MoEF circular dated 04.08.2009 is also to be submitted along with
EIA.
c. Current, site photographs viewing towards the project area from four directions indicating date
of photograph taken, direction from which taken, name of the project, and signature of Project
proponent along with consultant with seal should be submitted, so as to ensure that no
construction has been started before the grant of EC. d. EIA should strictly follow the guidelines prescribed in annexure-III to the EIA notification of
2006 and the Methods of Monitoring and analysis (Annexure-IV): Guidance for assessment of representativeness and reliability of baseline environmental attributes detailed under EIA
manual January, 2001 and other guidelines in the matter. e. The status of accreditation of the EIA consultant with NABET/QCI shall be specifically
mentioned. The consultant shall certify that his accreditation is for the sector for which this EIA is prepared.
f. On the front page of EIA/EMP reports, the name of the consultant/consultancy firm along with their complete details including their accreditation, if any shall be indicated.
g. While submitting the EIA/EMP reports, the name of the experts associated with/involved in
the preparation of these reports and the Name of laboratory through which the samples have
been got analysed should be stated in the report. It shall clearly be indicated whether said
laboratory is accredited by NABL or approved under the Environment (Protection) Act, 1986
(Please refer MoEF office memorandum dated 4th August, 2009). The name project leader of
the EIA study shall also be mentioned.
h. The EIA document shall be printed on both sides, as for as possible.
The Information’s no (a I , II, III & c) asked under the general guidelines is to be submitted
within 15 days from the date of receipt of the letter and remaining of the information’s is to be
submitted along with the EIA.
The project proponent informed that base line data for the month of March to May, 2015 of
a proposal for which E.C. has already been granted (VVIP Homes, Plot no. GC 03K/GH 03, Sector-
16C, Noida Extension, Greater Noida, M/s Solitaire Infrahome Pvt. Ltd.) has been considered by
the project proponent as no monitoring can be done in monsoon period and have requested to
consider the same baseline study for present project. The committee discussed and directed that
baseline data for one additional month should be undertaken alongwith the data as proposed by
project proponent.
Minutes of 265th
SEAC Meeting Dated 11/04/2016
Page 23 of 43
9. Revision & Expansion of Group Housing at Plot No-04, Sector-Techzone-IV, Greater
Noida- Sri Suresh Kumar Garg, CMD, H-61, Sector-63, Noida. File No. 3626/DD-Y
The project proponents neither appeared nor sent any communication in this regard.
The committee discussed and deliberated that project file should be closed and should be opened only after request from the project proponent. The file shall not be treated as
pending with SEIAA/SEAC.
10. Affordable Housing-Samajvadi Yojna at Sector-7D, Awadh Vihar Yojna Zonal
Development Plan, Amar Shaheed Path, Lucknow- Sri V P Singh, Ex. Engg., IP. Avas
Evam Vikas Parishad, Bhootnath, Indira Nagar, Lucknow. . File No. 3627/AD-H
The project proponents neither appeared nor sent any communication in this regard. The committee discussed and deliberated that project file should be closed and should be
opened only after request from the project proponent. The file shall not be treated as pending with SEIAA/SEAC.
11. tuin bykgkckn esa xaxk unh ij laxe rV ls Mkmu LVz~he esa lsrq ,oa igqap ekxZ dk fuekZ.k & Jh ds0 tuin bykgkckn esa xaxk unh ij laxe rV ls Mkmu LVz~he esa lsrq ,oa igqap ekxZ dk fuekZ.k & Jh ds0 tuin bykgkckn esa xaxk unh ij laxe rV ls Mkmu LVz~he esa lsrq ,oa igqap ekxZ dk fuekZ.k & Jh ds0 tuin bykgkckn esa xaxk unh ij laxe rV ls Mkmu LVz~he esa lsrq ,oa igqap ekxZ dk fuekZ.k & Jh ds0 th0 falag] mi egkizcU/kd] dkULVªD’ku ,.M fMtkbu lfoZl] m0 ith0 falag] mi egkizcU/kd] dkULVªD’ku ,.M fMtkbu lfoZl] m0 ith0 falag] mi egkizcU/kd] dkULVªD’ku ,.M fMtkbu lfoZl] m0 ith0 falag] mi egkizcU/kd] dkULVªD’ku ,.M fMtkbu lfoZl] m0 iz0 tyz0 tyz0 tyz0 ty fuxe] Vhfuxe] Vhfuxe] Vhfuxe] Vh----lhlhlhlh----&38 oh] foHkwfr &38 oh] foHkwfr &38 oh] foHkwfr &38 oh] foHkwfr [k.M] xkserh uxj] y[kuÅ[k.M] xkserh uxj] y[kuÅ[k.M] xkserh uxj] y[kuÅ[k.M] xkserh uxj] y[kuÅ (letter no. 13/Maha Prabandhak/Karya-1/12 dated 09/03/2016 of
Shri A.K. Saxena, Director, Construction and Design Services, UP Jal Nigam) File No.
3612/AD
The committee noted that a letter no. 13/Maha Prabandhak/Karya-1/12 dated 09/03/2016
was communicated by Shri A.K. Saxena Director, Construction and Design Services, UP Jal Nigam
to Director, Environment through which it has been informed that:
bykgkckn uxj esa xaxk unh ij laxe rV ls 1250 eh0 Mkmu LVªhe esa iqy dk fuekZ.k izLrkfor gSA bl lsrq dks >walh lkbM esa ok;kMDV dk fuekZ.k dj 04 ysu ekxZ }kjk 'kkL=h lsrq ls tksM+us dk ,oa vjsy lkbM esa cU/ks ds fdukjs ls gksrq gq, uohu ;equk lsrq ds lehi rd 04 ysu igqWap ekxZ ds fuekZ.k dk izkfo/kku gSA bl dk;Z ds fuekZ.k gsrq vkids foHkkx ls vukifRr izek.k i= dh vko';drk gSA iz'uxr dk;Z vR;Ur egRoiw.kZ ,oa 'kklu dh 'kh"kZ izkFkfedrkvksa esa gSA vr% vkils vuqjks/k gS fd bl dk;Z gsrq vukifRr izek.k i= fuxZr djus dh d`ik djsaA
The committee discussed the matter and noted that the matter has already been discussed in
SEAC meeting dated 21/10/2014 and SEIAA meeting dated 30/10/2014. In continuation to the
direction of SEIAA letter no. 2054/Parya/igqWap ekxZ&bykgkckn@2014 dated 08/12/2014 was
communicated to Director, Construction and Design Services, Lucknow and were directed to
submit required information. The same has not yet been replied. Therefore, the matter is not
pending with SEAC/SEIAA. The committee directed the proponent to submit reply to the letter
dated 08/12/2014 for further discussion of the matter. The committee also directed that proposal
should be made on prescribed format as given in EIA Notification (Form-1, 1A, Conceptual Plan).
Minutes of 265th
SEAC Meeting Dated 11/04/2016
Page 24 of 43
12. Proposed "Retail Mall" at Plot No-A 267/1 to A-267/4, Sector-43, Noida, G B Nagar. Sri A
C Goel, Additional GM, C-4, District Centre, Saket, New Delhi. File No. 3483/DD-Y
The committee noted that an application dated 28/10/2015 was made by the project
proponent for environmental clearance of Proposed "Retail Mall" at Plot No-A 267/1 to A-267/4,
Sector-43, Noida, G B Nagar, U.P. M/s IRCON International Limited.
A presentation was made by Shri Ramesh Gupta, authorized representative of project
proponent along with their consultant M/s Ascenso Enviro Private Limited. The proponent, through
the documents submitted and the presentation made, informed the committee that:-
1. The environmental clearance is sought for Proposed "Retail Mall" at Plot No-A 267/1 to A-267/4, Sector-43, Noida, G B Nagar, U.P. M/s IRCON International Limited.
2. Salient feature details of the project: Name and Location of the
Project
Proposed Retail Mall at Plot No. A-267/1 to A-267/4, Sector-43, Noida, Gautam
Buddha Nagar, Uttar Pradesh.
Developers of the project M/s Ircon International Limited
Total Plot Area 7,760.0 m
2
Built-up Area 27,728.7 m
2
Total Water Consumption 174 KLD
Total Freshwater
Requirement
In Non Monsoon Season= 53 KLD
In Monsoon Season=47 KLD
Power Requirement Connected Load-2,457 KW
Estimated maximum demand-1500 KW
Source: NPCL
Power Backup 3 DG Sets of total capacity of 2,320 KVA
(2x1000 + 1x320 KVA)
Total Parking provided 311 ECS
Solid Waste to be
Generated
442.65 kg/day
No. of RWH Pits 2 pits
Height of the Tallest
Building
24 m
3. Area details of the project: S.
No.
Particulars Area in Sq.m. Percentage
1 Total Plot Area 7,760.0
2 Permissible Ground Coverage @ 40% of plot area 3,104.0 40% of plot area
3 Proposed Ground Coverage @ 39.9% of plot area 3,103.86 39.9% of plot area
4 Permissible FAR @2 of plot area 15,520 200% of Plot Area
5 Proposed FAR @1.99 15,470.12 199% of Plot Area
6 Permissible Ancillary area@15% of Permissible FAR 2,328 30% of Plot Area
7 Proposed Ancillary area @ 14.36 of Permissible FAR 2,228.9 28.7% of Plot Area
8 Proposed Non FAR(staircase, mummty machine area,
ESS and Lift Lobby including basement area)
10,029.7 129.2% of Plot Area
9 Basement area 9,495.87 122.2% of Plot Area
10 Open Area ( plot area - achieved ground coverage) 4,656.1 60.0% of Plot Area
11 Green area required @25% of open area 1,164.0 15.0% of Plot Area
12 Green area proposed @ 25.09 % of open area 1,168.5 15.0% of Plot Area
13 Builtup Area (FAR+Non FAR+Ancillary Area) (5+7+8)
27,728.7 ….
14 Paved Area 3,487.5 44.94% of Plot Area
15 Maximum Height of Building 24 meter …
4. Land use details: S. No. Description
Area (m2
) Percentage
1. Total Plot Area 7,760.0 100%
2. Achieved Ground Coverage 3,103.86 39.99% of Plot Area
3. Atrium 731.93 9.43% of Plot area
Minutes of 265th
SEAC Meeting Dated 11/04/2016
Page 25 of 43
4. Green Area 1,168.5 15.05% of Plot Area
5. Ramp Area 401.58 5.17% of Plot Area
6. Road Area 1206.41 15.54% of Plot Area
7. Surface Parking Area 1001.25 12.9% of Plot Area
8. Electrical Sub Station 119.47 1.53% of Plot Area
5. Building block details: S. No. Description Provided Facilities at Each Floor
1. Ground Floor Retail Shops 31+Anchor Shops 2
2. First Floor Retail Shops 31+Anchor Shops 2
3. Second Floor Retail Shops 31+Anchor Shops 2
4. Third Floor Retail Shops 31+Anchor Shops 2
5. Fourth Floor Multiplex+12 Retail Shops+1 Fine Dining+1 Entertainment Zone
6. Fifth Floor 3 Fine Dining +Multiplex
7. Basement-1 --
8. Basement-2 --
6. Population details: S. No. Types No of Seats/ Area
in m sq Population
1. Commercial Population @1person per 3 sqm of Ground Floor 2,884.99 962
2. Commercial Population @1 person per 6 sqm of 1st to 3rd floor 9,341.32 1,557
3. Multiplex population (3rd
and 4th
Floor) 332 332
4. Staff 100
Total 2,951
7. Water calculation details: S.
No.
Description Area in
Sq. m.
Population Unit water
consumption
(litres)
Total
water
required
(KLD)
water
requirement
for domestic
use (KLD)
Flushing
water
(KLD)
Total
Waste
water
(KLD)
1 Retail …. 2,851 15 42.76 25.6 17.1 37.63
2 Staff …. 100 45 4.50 3.0 1.50 3.90
3 Kitchen &
Pantry.
Restaurant Kitchen , Food
Court
…. …. ….. 15.00 1.3 0.9 1.98
4 Horticulture 1168.5 …. 5 liter/sqm 5.84 …. ….. ….
5 DG Sets
(2000+320
KVA)
2320.0
KVA
…. 1 lt/KVA/6
hours
12.52 …. …. ….
6 HVAC 550.0 T ….. ….. 90 …. …. …..
7 Filter backwash …. 10 % of total
water
requirement
1.70 …. …. …..
8 Fire fighting 1% of total
water
requirement
1.72 …. …. …..
9 TOTAL 174 30 19 43
8. Waste water calculation details: Details Water (KLD)
Water requirement for domestic purpose 30
Wastewater generating from domestic use (@ 80% of consumptive losses) 24
Water requirement for Flushing Purpose 19
Wastewater generating from Flushing (@ 100% of flushing requirement) 19
Total Wastewater generation 24+19 = 43
9. Parking details: Description As Per Noida Building Byelaws Parking
(E.C.S.) Parking Required 1 ECS/50 sq m FAR area
FAR= 15,470.12 sq m
= 310 ECS
310
Total ECS required 310 ECS
Minutes of 265th
SEAC Meeting Dated 11/04/2016
Page 26 of 43
Parking Proposed
In Basement Area-1 @ 1ECS/30 m
2
Basement Area (3,983.302 m2
)
133 ECS
But Provided only 125
ECS
In Basement Area-2 @ 1ECS/30 m2
Basement Area ( 4,843.98 m2
)
161 ECS
But provided only 136 ECS
In Open area @ 1 ECS/20 m2
Open area (1001.25 m2
)
50 ECS
Total ECS provided 125+136+50 = 311 ECS
10. Power requirement details: Power Requirement and Source Connected load -2,457 KW
Maximum demand -1500 KW
Source:-Noida Power Company Limited (NPCL)
Power Back up 3 DG sets of total capacity of 2,320 KVA (2*1000 + 1*320)
11. Solid waste generation details: Category of Solid
Waste
Waste Generation Rate Formula Total Population Waste
Generated
Commercial population 0.1 to 0.2 kg/cap/day Total Population*0.15 2,951 442.65
12. The project proposals are covered under category 8"a" of EIA Notification, 2006, as
amended.
The committee discussed the matter and recommended grant of environmental clearance on
the project proposals alongwith general conditions as earlier prescribed by the authority for
construction project and following specific conditions:
A. Construction Phase: 1. "Consent to establish" shall be obtained from UP Pollution Control Board under Air
(Prevention & Control of Pollution) Act, 1981 and Water (Prevention & Control of Pollution) Act, 1974.
2. All required sanitary and hygienic measures should be in place before starting construction activities and to be maintained through out t h e construction phase.
3. A first aid room will be provided in the project both during construction and operation phase of the project.
4. All the topsoil excavated during construction activities should be stored for use in horticulture landscape development within the project site.
5. Disposal of muck during construction phase should not create any adverse effect on the neighboring communities and be disposed off after taking the necessary precautions for general safety and health aspects of people with the approval of competent authority.
6. Construction spoils, including bituminous material and other hazardous material, must not be allowed to contaminate watercourses and the dump sites for such material must be secured, so that they should not leach into the ground water.
7. The diesel generator sets to be used during construction phase should be of low sulphur diesel type and should conform to the provisions of Environment (Protection) Act, 1986 prescribed for air and noise emission standards.
8. Vehicles hired for bringing construction material to the site and other machinery to be used during construction should be in good condition and should conform to applicable air and noise emission standards.
9. Ambient nois levels should conform to prescribed standards both during day and night. Incremental pollution loads on the ambient air and noise quality should be closely monitored during construction phase.
10. Fly ash should be used as construction material in the construction as per the provisions of Fly Ash Notification of September, 1999 and as amended on August, 2003 (This condition is applicable only if the project is within 100 Km of Thermal Power Station).
11. Ready mixed concrete should be used in building construction as far as possible.
12. Water demand during construction should be reduced by use of premixed concrete, curing
Minutes of 265th
SEAC Meeting Dated 11/04/2016
Page 27 of 43
agents and other best practices.
13. Separation of drinking water supply and treated sewage supply should be done by the use of different colours.
14. Fixtures for showers, toilet flushing and drinking should be of low flow either by use of aerators or pressure reducing devices or sensor based control.
15. Adequate steps shall be taken to conserve energy by limiting the use of glass, provision of proper thermal insulation and taking measures as prescribed under the Energy Conservation Building Code.
16. The approval of competent authority shall be obtained for structural safety of the buildings due to earthquakes, adequacy of fire fighting equipments etc. as per National Building Code including protection measures from lightning.
17. Provision shall be made for the housing of construction labour within the site with all necessary infrastructure and facilities such as fuel for cooking, mobile toilets, mobile STP, disposal of waste water & solid waste in an environmentally sound manner, safe drinking water, medical health care, creche etc. The housing may be in the form of temporary structures to be removed after the completion of the project.
B. Operation Phase:
1. Parking is to be provided as per building bye laws and no additional parking will be
permitted. Rest to be deleted from parking plan. 2. The installation of sewage treatment plant (STP) and adequacy of disposal system should
be certified by UP Pollution Control Board. The discharge of treated sewage shall conform to the norms and standards prescribed by UP Pollution Control Board for such discharges. Necessary permissions shall be taken for any discharge outside the premises.
3. The project proponent shall provide electromagnetic flow meter at the outlet of the water supply, outlet of the STP and any pipeline to be used for re-using the treated wastewater back into the system for flushing I HVAC and for horticulture purpose etc. and shall maintain a record of readings of each such meter on daily basis.
4. Adequate & appropriate pollution control measures should be provided to control fugitive emissions to be emitted within the commercial complex.
5. Adequate treatment facility for drinking water shall be provided, if required. 6. Rainwater harvesting for roof run-off should be implemented. Before recharging the roof
run-off, pretreatment must be done to remove suspended matter, oil and grease. However, no run off from gardens/green area/roads/pavements shall be connected with the ground water recharging system.
7. The solid waste generated should be properly collected and segregated. The recyclable solid waste shall be sold out to the authorized vendors and inerts shall be sent to disposal facility. The Bio-degradable solid waste shall be adequately treated as per the scheme submitted by the project proponent. Prior approval of competent authority should be obtained, if required.
8. Hazardous waste/E-waste should be disposed off as per Rules applicable and with the necessary approval of the UP Pollution Control Board.
9. The green belt design along the periphery of the plot shall achieve attenuation factor conforming to the day and night noise standards prescribed for residential land use. The open spaces inside the plot should be suitably landscaped and covered with vegetation of indigenous species/ variety.
10. The project proponent should take adequate and appropriate measures to contain the ambient air quality within the prescribed standards.
11. Incremental pollution loads on the ambient air quality, noise and water quality should be periodically monitored after commissioning of the project.
12. Application of solar energy should be incorporated for illumination of common areas, lighting for gardens and street lighting in addition to provision for solar water heating.
13. Traffic congestion near the entry and exit points from the roads adjoining the
Minutes of 265th
SEAC Meeting Dated 11/04/2016
Page 28 of 43
proposed project site must be avoided. Parking should be fully internalized and no public space should be utilized.
14. Total cost of the project is Rs. 190 Cr. Corporate Social Responsibility (CSR) plan along with budgetary provision amounting to Rs. 3.80 Cr. shall be prepared and approved by Board of Directors of the company. A copy of resolution as above shall be submitted to the authority alongwith list of beneficiaries with their mobile nos./address.
15. Environment Management Cell shall be formed during operation phase which will supervise and monitor the environment related aspects of the project.
13. Proposed Samajwadi Awas Yojna at Sector-118, Noida- Sri H N Singh, Project Engineer,
WC-06, Sector-20, Noida. File No. 3484/ AD-H
The committee noted that an application dated 02/11/2015 was made by the project
proponent for environmental clearance of Proposed Samajwadi Awas Yojna at Sector-118, Noida,
U.P. M/s New Okhla Industrial Development Authority.
A presentation was made by Shri Vedram Sharma, APE, Department of Industries, Govt. of
U.P. authorized representative of project proponent along with their consultant M/s Ind Tech House
Consult, Delhi. The proponent, through the documents submitted and the presentation made,
informed the committee that:-
1. The environmental clearance is sought for Proposed Samajwadi Awas Yojna at Sector-118,
Noida, U.P. M/s New Okhla Industrial Development Authority. 2. The Samajwadi Awas Yojna is proposed at Sector-118, Noida, Gautam Budh Nagar, Uttar
Pradesh, provides housing for Lower Income Group and Economically Weaker Section. 3. Total Plot Area and Built-up Area of the project is 72,433 sq. m. and 79,811.53 sq. m.
respectively.
4. Total number of dwelling units is 1376.
5. Maximum no. of proposed floors for residential tower is G+3.
6. Salient feature details of the project: S. No. Description Details
AREA DETAILS
1. Plot Area 72,433 sq. m.
2. Permissible FAR Area (275) 199191 sq. m.
3. Proposed FAR Area (97.51)% 70633.90 sq. m.
4. Ground coverage area permissible (40%) 28973 sq. m.
5. Ground Coverage Proposed (35.27%) 25549.93 sq. m.
6. Total Built up area 79,811 sq. m.
7. No. of DU’s 1376
8. Maximum No. of Floors G+3
9. Height of Tallest Building 12.5 meter
10. No. of Blocks 51
GREEN AREA
11. Green area required (16.18 % of Plot Area) 11720.8 sq. m.
12. Green area proposed (17.22% of Plot Area) 12475.07 sq. m.
PARKING DETAILS
13. No. of ECS required 706 ECS
14. No. of ECS proposed 716 ECS
POPULATION
15. Expected Population Total 6876 person
• Residential - 6192
• Floating -684
WATER REQUIREMENT
16. Total water requirement 562 KLD
Minutes of 265th
SEAC Meeting Dated 11/04/2016
Page 29 of 43
17. Fresh water requirement 549 KLD
18. Horticulture water requirement 12 KLD
19. Water Cooled DG Cooling 01 KLD
WASTEWATER & SOLID WASTE GENERATION
20. Waste water Generation 464 KLD
21. Solid waste generation 3.17 TPD
POWER DEMAND
22. Maximum Power Demand 2420 KVA (Source-UPPCL)
23. DG set backup 50 KVA
7. Population details: POPULATION
RESIDENTIAL DU'S POP/DU TOTAL
(NO.S)
SALEABLE DU'S 1376 4.5 6192
TOTAL 6192
NON RESIDENTIAL (Employees) Area (in sqm)
COMMUNITY HALL 7369.97 3
COMMERCIAL (SHOPPING) 466.36 47
FACILITY MANAGEMENT STAFF LS 15
TOTAL 65
VISITORS 619
TOTAL POPULATION 6876
8. Water calculation details: Sl. No. Description Occupancy /
Capacity / Area
Rate (Liters) Total Water
Demand (KLD)
A. Residents
Domestic 6192 65 402.48
Flushing 6192 21 130.03
B. Non-residential
Domestic 65 30 0.97
Flushing 65 15 1.94
C. Visitors
Domestic 619 09 3.72
Flushing 619 06 5.57
D. Gardening 12475.07 01 12.48
E. Water Cooled DG Cooling ( For 6
Hrs.)
500 0.9 0.27
F. Filter Back wash LS LS 5
Total Water Requirement 562.45
Head Source Quantity
Fresh Water Requirement Greater Noida Industrial Development Authority 549 KLD
Treated Water Requirement From Common STP 13 KLD
9. Waste water details: Head Quantity, KLD
Total Water Requirement 562
Fresh Water Requirement 549
Treated Water Requirement 13
Gardening 12
DG Cooling 01
Waste Water Generation (80% of total domestic fresh water demand + 100% of
Flushing Water)
464
Sewage to be discharged to Common STP at Sec-123 464
� Estimated Sewage Generation: 464 KLD
� Waste water generated will be treated in a common STP at Sec-123, Noida. (Uninterrupted power supply
through DG set)
� Treated waste water will be used for horticulture and DG cooling.
10. Waster generation details: Total Waste Generation 3.17 TPD
Organic Waste Generation 1.90 TPD
Minutes of 265th
SEAC Meeting Dated 11/04/2016
Page 30 of 43
E- Waste Generation 21 KG/Day
Sludge Generation 166.78 KG/Day
Hazardous Waste Generation (DG Waste Oil) 10 Lts/ Annum
The committee discussed the matter and directed the project proponent to submit following
information:
1. Office order related to approval of maps.
2. Area details showing proposed uses as residential, commercial, parks, parking, roads, green
area, other services, facilities of the project also in percentage.
3. Road width should be shown on maps.
4. Structural design certificate signed by structural engineer and vetting authority should be
submitted. All structural design drawings should be signed by structural engineer and counter
signed by vetting authority.
5. Copy of layout plan/maps/services plans as approved by competent Development Authority.
6. Municipal solid waste management plan alongwith list of identified vendors. Solid Waste will be collected from Municipal Authority. It is to be given in writing and affidavit to be
submitted in this regard. 7. Provision of dual plumbing system should be provided. Plan submitted.
8. At least 30% of total water requirement shall be met from treated water. Plan to be submitted. 9. Required no. of trees should be proposed @ 01 tree/80 sqm, submit plan.
10. Provision of 100% solar lighting along the road side, stair cases, common places. 11. Proposal for rain water harvesting only from the rooftop. Plan for water body with Kachha
base should be submitted for storm water utilization for water recharge.
12. Parking and green area should be specifically mentioned on layout plan. Parking standards for
LIG/EWS for two wheeler should also be provided. Section of all internal roads should be
provided. Right of way and carriage way width should be clearly marked on the map.
13. Dual plumbing System is to be proposed. Plan should be submitted.
14. Total cost of the project is 96 Cr. Corporate Social Responsibility (CSR) plan along with
budgetary provision amounting to Rs. 1.92 Cr. shall be prepared and approved by Board of
Directors of the company. A copy of resolution as above shall be submitted to the authority
alongwith list of beneficiaries with their mobile nos./address.
15. The proponent submitted that it is a Govt. Project as such the works under CSR as being
executed by the Authority its detail to be submitted for record for EWS and LIG projects.
16. All Community facilities and infrastructure services are to be provided as per proposed
population of the project area. 17. A provision for door to door collection of wastes has to be made. Plan should be submitted.
The matter shall be discussed after submission of information as above.
14. Type-V Residential for Judicial Officers (Multi Storied Apartment) at Khasra No-513M &
514M, Vill-Nasarpur, Loni, Ghaziabad.-Sri Shivraj Singh, Sr. Project Manager, Unit-28,
C & D S, U P Jal Nigam, Shastri Nagar, Ghaziabad. File No. 3548/ DD(Y)
The committee noted that an application dated 01/12/2015 was made by the project
proponent for environmental clearance of Type-V Residential for Judicial Officers (Multi Storied
Apartment) at Khasra No-513 M & 514 M, Vill-Nasarpur, Loni, Ghaziabad.
A presentation was made by Shri Shivraaj Singh, Project Manager, Construction and Design
Services, UP Jal Nigam, representative of project proponent along with their consultant M/s
Development Consultants Pvt. Ltd., Kolkata. The proponent, through the documents submitted and
the presentation made, informed the committee that:-
1. The environmental clearance is sought for Type-V Residential for Judicial Officers (Multi
Storied Apartment) at Khasra No-513 M & 514 M, Vill-Nasarpur, Loni, Ghaziabad.
Minutes of 265th
SEAC Meeting Dated 11/04/2016
Page 31 of 43
2. The deposit work for above mentioned project is awarded to Unit-28, Construction &
Design Services, U.P. Jal Nigam (A U.P. Government Undertaking) by the Uttar Pradesh
Shashan, Lucknow in the Judgeship of Chairman Infrastructure Committee, Honable High
Court, Allahabad in the year 2012.
3. Previously, the project was proposed for the built-up area 18,107.93m2 and this office
obtained the NOC for “Consent to Establishment” from State Pollution Control Board to
start the construction at the site and subsequently we started the construction. But Later the
area of each floor is revised from 985.35m2 to 1145.90 m2 by U.P. Govt. So the total proposed built-up area for the project gets changed to 20,817.77 m2
4. It has been brought to our notice that when the built-up area of the project is > 20,000 sq. mtrs. it comes under the purview of EIA Notification 2006 of schedule 8(a), Category B.
Hence, we have applied for Environmental Clearance (EC) under schedule 8(a), Category B. 5. Project details:
FEATURES PROPOSED PROJECT
Name of the Project Type-V Residence for Judicial Officers
(Multi-Storeyed Apartment)
Location of Project Khasra No. 513M, 514M
Village: Nasarpur, Tehsil/Pargana: Loni
District: Ghaziabad (U.P.)
Name of the Applicant District Judge, Ghaziabad Model Town, Ghaziabad (U.P.)
Pin Code: 201001
Email: [email protected]
S. No. in the schedule 8 (a)
Category of Project i.e. `A’ or `B’ ‘B’
Total Plot Area 21,751.99 m2
Total Built-up Area of the Project 20,817.77 m
2
Coordinate of the Proposed Project Site Pillars Latitude Longitude
A 28° 39.157'N 77° 26.310'E
B 28° 39.112'N 77° 26.368'E
C 28° 39.187'N 77° 26.433'E
D 28° 39.232'N 77° 26.374'E
Toposheet No. 53H/6
Altitude MSL 216 m
6. Salient features details: Project Requirements DETAILS
Total Plot Area 21,751.99 m2
Permissible Maximum Ground Coverage 6,525.59 m2
Existing Ground Coverage 758.68 m2
Proposed Ground Coverage 3,859.01 m2
Total Ground Coverage (Existing +
Proposed)
4,617.69 m2
Permissible [email protected] of Total Plot Area 32,626.49 m2
Achieved FAR 19,480.30 m2
Total Built up Area 20,817.77 m2
Exclusive Green Area 22.98% of Total Plot
Area 5000.00 m
2
No. of Towers 2
No. of Floors Stilt + 11 (Block A)
Stilt + 4 (Block B)
Building Height 44.85 m
Parking Facilities Provided Space for 90 Cars
Power Requirement and Source Connected Load : 961.40 KW
Max. Demand : 737.12 KW
Total Demand Load : 644 KW
SOURCE: Power Supply Receiving from UPPCL Substation (Uttar
Pradesh Power Corporation Limited)
Power Backup DG Sets (3 Nos.) : 2 x 200 KVA + 1 x 62.50 KVA
Minutes of 265th
SEAC Meeting Dated 11/04/2016
Page 32 of 43
Stack Height of DG Set 47.67 meter
Water Requirement and Source Fresh/Domestic Water Requirement
Treated Waste water use from STP
SOURCE : Bore Wells
Sewage Treatment and Disposal The waste water generated during operation phase will be disposed
in the existing Trunk Sewer line on the Arya Samaj Mandir road
demarcated in the site layout plan.
Application for obtaining the consent for the disposal of sewage in
the main sewer lines of Municipal Corporation of Ghaziabad is
applied and letter related to which is attached as Annexure in the
Project Report.
Estimated Population 318 (+ 86 floating)
Project Cost Rs. 2747.93 Lacs
7. Area statement of the project: Land Use Detail % Land Use Area Statement
(m2
) Total Plot Area 100% 21,751.99 m
2
Permissible Maximum Ground Coverage 30% 6,525.59 m2
Existing Ground Coverage 3.49% 758.68 m2
Proposed Ground Coverage 17.74% 3,859.01 m2
Total Ground Coverage
(Existing + Proposed)
21.23% 4,617.69 m2
Permissible F.A.R.
(all existing structures to be demolished except Anticorruption
Judge Residence)
1.5 times of total plot
area. 32,626.49 m
2
Achieved F.A.R. - 19,480.30 m2
Covered Area of Existing Anticorruption Judge Residence 3.49% 758.68 m2
Proposed Covered Area of District Judge Residence (Existing
Structure)
2.238% 486.88 m2
Proposed Covered Area of Barrack Building 0.86% 188.74 m2
Proposed Covered Area of Garrage + Servant Room
(52.65 + 46.48) {Existing Structure}
0.45% 99.13 m2
Proposed Covered Area of Guard Barrack {Existing Structure}
0.31% 67.75 m2
Proposed Covered Area of Club Building 5.23% 1,139.47 m2
Proposed Covered Area of Sentry Post 0.0004% (4.63 x 2) 9.26 m2
Proposed Covered Area of All floors of Type-V, Block-A, (Stilt +
11)
(1145.90 x 12) 13,750.80 m2
Proposed Covered Area of All floors of Type-V, Block-B, (Stilt + 4) (1145.90 x 5) 5,729.50 m2
Total Covered Area of the Project (Existing + Proposed) 19,947.67 m2
Landscape Area 22.98% of Total Plot
Area
5000.00 m2
Total Constructed Built-up Area of the Project 20,817.77 m2
No. of Towers 2 (Block A + Block B)
No. of Floors Stilt + 11 (Block A)
Stilt + 4 (Block B)
Max. Height of Tower 44.850 m
Total No. of Flats 60
Total Occupancy 300
8. Parking details: Required No. of Cars
No. of Unit 60 1.5@100 m
2
90
Permissible Parking :
Stilt Open
28 ECS
23 ECS
Total No. of Cars 90
PROVIDED
Minutes of 265th
SEAC Meeting Dated 11/04/2016
Page 33 of 43
Ground (stilt) 2291.8/28 81
Ground (open) 214.32/23 09
Total No. of Car parking Provided 90
9. Water requirement details: S.No. Description Area (m
2
) Population Rate of water
demand (lpcd)
Total Water Requirement
(KLD)
% in term of total water
requirement
A. Domestic Water
• Type V
Block A
• Type V
Block B
• Barrack
• Club
Building
• Floating
Population (@25% of total Population)
13,750.80 m2
220 86 18.920 63.16%
5,729.50 m2
80 86 6.880
188.74 m2
18 86 1.548
1,139.47 m2
25 30 0.750
86 15
1.290
Total domestic water demand 29.388 Say 30 KLD
B. Landscape Waste
5000 m2 1
l/sqm/day
5.0 KLD 10.52%
C. Miscellaneous use like back
wash and make up for water body and decorative fountain
and general washing (L.S.)
- - - 10 KLD 21.05%
D. DG Sets (3 Nos.): 2 x 200 KVA + 1 x 62.50
KVA
0.9 l/KVA/hr
(Assuming 6 hours of operation
per day)
2.5 KLD 5.27%
Total Water Requirement (predicted values) KLD (A+B+C+D) 47.5 KLD 100%
1. Domestic Water Requirement 30 KLD
2. Total Fresh water = Fresh (@ 70% of domestic) 21 KLD
• Quantification: Total water requirement of the project is 47.5 KLD (Fresh Water)
Overhead Water Storage Tank: a. Domestic water tank: 50 KL
b. Fire Water tank: 5 KL
• Under Ground Water Tank: a. Domestic water tank: 100 KL b. Fire Water tank: 75 KL
• Source of Water Supply: 1. Bore well: 2 Nos.
2. Municipal Water Supply
• Waste Water Generation & Disposal: � It is expected that the project will generate 38 KLD (@ 80% of total fresh water used) of
wastewater. The waste water generated during operation phase will be disposed in the
existing Trunk Sewer line on the Arya Samaj Mandir Road demarcated in the site layout plan. STP is not proposed in the plan.
• Usage: Breakup of water requirements for various usages:
� Irrigation: 5.0 KLD
� Domestic: 30 KLD
� Miscellaneous use like back wash and make up for water body and decorative fountain
and general washing (L.S.): 10 KLD
� D.G. Sets: 2.5 KLD
Minutes of 265th
SEAC Meeting Dated 11/04/2016
Page 34 of 43
10. Power requirement details: Power Requirement 644 KW
Transformer Selection Connected Load : 961.40 KW
Max. Demand : 737.12 KW
Total Demand Load : 644 KW
Transformers 1 Nos. of 1000 kVA capacity
Source of Power Supply UPPCL Substation
Backup power supply arrangement No. of DG Sets: 3 Nos. Capacity : 2x 200 kVA + 1 x 62.50 kVA
Location of DG Sets DG sets shall be placed at ground floor
Stack Height of DG Set 47.67 meter
Consumption of Fuel Individual DG Set shall be provided with a day oil tank of capacity 990
liters, near DG set.
HSD tank location shall be minimum 4.5 meter or dia. Of tank away
from the building as per the Petroleum Acts 30 vide GSR 204 (E) date
13.02.2002.
11. Waste generation details: S.No. Category Population Kg per capita per
day (kg/capita/day)
Waste generated
(kg/day)
% in term of
total waste generation
1. Residents
• Type V Block
A
• Type V Block
B
• Barrack
220
80
18
@ 0.5
159
90.34
Total Occupancy 318
2. • Club Building 25 @0.15 3.75 2.13
3. Floating Population
(@25% of total Population)
86 @ 0.15
12.9
7.33
4. Landscape Waste @0.2
Kg/acre/day
0.040 0.023
Total Solid Waste Generated
(predicted values) kg/day
175.69
Say 176 kg/day
100%
1. Biodegradable Waste 88 kg/day 50%
2. Non-Biodegradable Waste 52.80 kg/day 30%
3. Other Waste 35.20 kg/day 20%
12. The project proposals are covered under category 8"a" of EIA Notification, 2006, as
amended.
The committee discussed the matter and directed to submit following information:
1. Comparative details of the project as earlier with builtup area 18,107.93 sqm and revised
proposal with builtup area 20817.77 sqm alongiwth present status of construction.
2. Setback details as per building bye-laws.
3. Location of proposed site as per master plan should be submitted.
4. Copy of approved layout plan/maps/services plans. 5. Physical features within 30 m of the project site with their ownership.
6. Details about approach roads to proposed site. Internal roads layout alongwith width of the road, within the project. Section of all internal roads should be provided. Right of way and
carriage way width should be clearly marked on the map. Vehicular movement/circulation plan. Revised parking plan as per bye-laws. It is also to be ensured that the width of the
proposed road as to be admissible as per building bye laws specially 4.5 metre wide road bye laws to be submitted.
7. Area statement with tower wise and floor wise details alongwith no. of units also in
percentage. Details of all block with dimensions set back and area chart details are to be
submitted.
Minutes of 265th
SEAC Meeting Dated 11/04/2016
Page 35 of 43
8. Green area details have to be submitted.
9. Structural design certificate signed by structural engineer and vetting authority should be
submitted. All structural design drawings should be signed by structural engineer and
counter signed by vetting authority.
10. Structural design certificate signed by architect and vetting authority after incorporating
proposed expansion structure should be submitted. All structural design drawings should be
signed by architect and counter signed by vetting authority.
The mater shall be discussed after submission of information as above.
15. Group Housing Project "Janeshwar Enclave" at Khasra No-7, Vill-Jahidpur, Sector-J,
Jankipuram Extension, Lucknow, U.P. Sri D C Sachan, Ex. Engg., (Z-5), LDA, Gomti
Nagar, Lucknow. File No. 3603/DD(Y)
The committee noted that an application dated 29/01/2016 was made by the project
proponent for environmental clearance of Group Housing Project "Janeshwar Enclave" at Khasra
No-7, Vill-Jahidpur, Sector-J, Jankipuram Extension, Lucknow, U.P. M/s Lucknow Development
Authority.
A presentation was made by Shri Sanjay Bhati, JE, LDA, authorized representative of
project proponent along with their consultant M/s Sawen Consultancy Services Pvt. Ltd. The
proponent, through the documents submitted and the presentation made, informed the committee
that:-
1. The environmental clearance is sought for Group Housing Project "Janeshwar Enclave" at
Khasra No-7, Vill-Jahidpur, Sector-J, Jankipuram Extension, Lucknow, U.P. M/s Lucknow
Development Authority.
2. Salient feature details of the project: Plot Area 21000.0
Built Up Area 91071.78
Allowed FAR 2.5
Allowed Purchasable FAR 50% FAR of basic FAR
Achieved FAR 3.51
Allowed Ground Coverage 35%
Achieved Ground Coverage 21.53%-4522.30 sqm
Height of Building B+S+19; 60.45 m
Depth of Water Table 17.0-20.5 m bgl
Total Expected Population 2694 Personnel
Floating Population 600 Visitors
Transformer (No. & Capacity) 02 X 2000 KVA
Standby Power Supply(D.G. Sets) 04 x 250 KVA
Sources of Water Supply Municipal Supply
Total Consumption of Water 280.0 KLD
Total Waste Water Generated 190.0 KLD
Total MSW Generated 1742.0 Kg/Day
Proposed Rain Water Harvesting 04 Nos.
STP Capacity 250 KLD Based on FAB Technology
Stack Height 6.0 meter
Approved Project Cost Rs. 244.25 Crore
3. Land use details: S.No. DESCRIPTION AREA %
1 Total Ground Coverage 4522.30 22.0
2 Total Green Area 3540.0 16.86
3 Road Area 6484.11 30.88
4 Surface Parking Area 6453.59 31.0
21000.0 100.0
Minutes of 265th
SEAC Meeting Dated 11/04/2016
Page 36 of 43
4. Proposed tower details: Tower NOS. No. of Floors Type of Flats Total Nos. of Flats 1 S+15 E E = 130 2 S+19 A
B
C
A = 35
B = 38
C = 35
TOTAL 108 3 S+19 B
C
B = 38
C = 70
TOTAL 108 4 S+19 A
B
C
A = 34
B = 38
C = 35
TOTAL 107 5 S+19 A
B
D
A = 34
B = 19
D = 19
TOTAL 72 TOTAL 5 TOWERS TOTAL 525 NOS FLATS
5. Built up area calculation details: S.NO DETAILS TOTAL AREA (M
2
)
1 1st
Floor Area 3887.80
2 2nd
to 11th
Floor Area 41664.48
3 12th
Floor Area 4050.34
4 13th
Floor Area 3921.36
5 14th
Floor Area 3794.51
6 15th
Floor Area 3662.74
7 16th
Floor Area 3461.27
8 17th
Floor Area 3461.27
9 18th
Floor Area 2584.38
10 19th
Floor Area 1704.66
11 Ent. Lobby + Core 614.91
12 Shops Area 319.70
13 Club House Ground Floor 291.25
14 Club House First Floor 297.55
Sub Total (A) 73716.22
15. Basement Floor Area (B) 17355.56
Total Built up Area (A+B) 91071.78
6. Population details: Sr. No. STAFF DESIGNATION POPULATION
1 Residents (525 Dwelling Units @ 5 person per unit) 2625
2 Service Facility Staff 25
3 Commercial Staff (11 shop @ 04 person per shop) 44
4 Floating Population 600
TOTAL EXPECTED POPULATION 3294
7. Parking details:
� Proposed ECS at Basement Floor- 280 nos.
� Proposed ECS at Stilt Floor – 151 nos.
� Proposed ECS at Open Parking = 281 nos.
� Hence total 712 ECS shall be proposed.
8. Water calculation details: S. No. Water Use Population Per Capita in
(LPCD)
Water
Requirement
(KLD)
Waste Water
Generation
(KLD)
1 Residents 2625 86 226.0 181.0
2 Service Facility Staff 25 45 1.0 0.9
Minutes of 265th
SEAC Meeting Dated 11/04/2016
Page 37 of 43
3 Commercial Staff 44 45 2.0 1.6
4 Visitors 600 15 9.0 7.0
TOTAL DOMESTIC WATER REQUIREMENT 238 190
5 Pool (Swimming Pool,
Kids Pool)
- Lump sum 30.0 NIL
6 D.G. Set Cooling 250KVA x 4 no. 0.9 l/KVA/4
hr
4.0 NIL
7 Gardening 1810.0 m2
1 l/m2
1.81 NIL
8 Plantation 1730.0 m2
3.5 l/m2
6.055 NIL
TOTAL WATER REQUIREMENT 279.8~ 280 190.0
9. The project proposals are covered under category 8"a" of EIA Notification, 2006, as
amended. The committee discussed the matter and directed the project proponent to submit following
information 1. Letter of approval of FAR.
2. Site photographs to be submitted to proof that no construction work has started at the project site.
3. The details of all community facilities and services are to be proposed as per population projection.
4. Details of area statement showing as per proposed land uses and their percentage wise
distribution. Calculation of green areas along with land scape plan is to be submitted.
5. Minimum 03 m wide peripheral green should be provided. Submit plan.
6. Section of all internal roads should be provided. Right of way and carriage way width
should be clearly marked on the map.
7. Revised layout plan as per building bye-laws should be submitted.
8. Green area and landscape plan should be clearly indicated on layout. Calculation in this
regard should also be submitted. Landscape plan with park furniture to be submitted along
with list of ornamental trees.
9. Structural design certificate signed by structural engineer and vetting authority should be
submitted. All structural design drawings should be signed by structural engineer and
counter signed by vetting authority.
10. The parking plan for only 657 cars will be permissible. Rest will have to be deleted from parking plan. Revised plan should be submitted.
11. Permission from Central Ground Water Board should be obtained for drilling of bore well for Drinking water.
12. Basement area as proposed 17355.0 sqm will have to be reduced may be up to 15000 Sqm. Plan to be submitted.
13. Dual plumbing system is to be proposed and submitted. Modular STP is to be provided with a capacity as per norms and requirements. Plan should be submitted.
14. 100% Solar Energy is to be provided on all roads and common places .At least 15% of solar
energy of total power requirement is to be proposed.
15. Use of reflecting paints on roof top and side walls to be submitted..
16. NOC from Fire and AAI.
17. All maps and layout plan as presented and submitted is not clearly visible so all revised
visible maps to be submitted which should be well presentable.
18. Total cost of the project is Rs. 244.25 Cr. Corporate Social Responsibility (CSR) plan along
with budgetary provision amounting to Rs. 4.88 Cr. shall be prepared and approved by
Board of Directors of the company. A copy of resolution as above shall be submitted to the
authority alongwith list of beneficiaries with their mobile nos./address. The proponent
submitted that it is a Govt. Projects. The Committee asked the proponent to submit the CSR
plan as being executed by the Authority in various sectors like LIG and EWS housing and
for informal sectors projects being executed by the Authority.
The mater shall be discussed after submission of information as above.
Minutes of 265th
SEAC Meeting Dated 11/04/2016
Page 38 of 43
16. Plotting & Services Development of Vridavan Yojna-04, (Sub City) at Gram-Haibat Mau
Mawaiya, Barauli Khalilabad, Birura & Kalli Paschim, Raibareilly Road, Distt-Lucknow-
Sri U C Singh, Ex. Engg., Construction Div., Avas Evm Vikas Parishad, Sector-9,
Vrindavan Yojna, Lucknow. File No. 3604/AD(H)
The committee noted that an application dated 02/02/2016 was made by the project
proponent for environmental clearance of Plotting & Services Development of Vridavan Yojna-04,
(Sub City) at Gram-Haibat Mau Mawaiya, Barauli Khalilabad, Birura & Kalli Paschim, Raibareilly
Road, Distt-Lucknow, U.P. M/s Uttar Pradesh Awas Evam Vikas Parishad.
A presentation was made by Shri U.C. Singh, Executive Engineer, Awas EvamVikas
Parishad, Lucknow, authorized representative of project proponent along with their consultant M/s
Sawen Consultancy Services Pvt. Ltd. The proponent, through the documents submitted and the
presentation made, informed the committee that:-
1. The environmental clearance is sought for Plotting & Services Development of Vridavan
Yojna-04, (Sub City) at Gram-Haibat Mau Mawaiya, Barauli Khalilabad, Birura & Kalli Paschim, Raibareilly Road, Distt-Lucknow, U.P. M/s Uttar Pradesh Awas Evam Vikas
Parishad. 2. Salient features details:
Description Area in SQMT
Net Plot Area 3914019.0 (967.36 Acres)
Total number of houses to be constructed 18600 Nos.
Total Parking Required 21220 ECS
Power Demand 08 nos. ESS (capacity 2 x 10 MVA) from UPPCL
Source of Water Supply Municipal supply in sectors through OHT’s
Total Consumption of Water 9150.0 KLD
Total Waste Water Generated 6823.0 KLD
Total MSW Generated 62463.33 Kg/Day
Proposed Rain Water Harvesting 250 Nos.
STP Capacity 37.5 MLD STP at Sector-10, Vrindavan Yojana -04
(Common for Vrindavan -1, 02, 03, 04)
3. Land use details of the project:
S. NO Infrastructures Total Area (m
2
) %
A Residential
Residential plots 821944.0 21.0
Group Housing 313121.5 8.0
1135066 29%
B Institutional
Educational 195701.0 5.0
Police/fire/Sub Station 78280.36 2.0
Police line 313121.5 8.0
Public utility for (village) 39140.18 1.0
Public utility for (Govt.) 97850.43 2.5
18.5%
C Commercial 195701.0 5.0 %
D Transportation and
communication
743663.6 19.0 %
E Parks, playgrounds and open spaces
Green belt 430542.1 11.0
Landscape 430542.1 11.0
Pond 156560.8 4.0
26%
F Community Centers 97850.43 2.5 %
Total Plot Area 3914019 100
Minutes of 265th
SEAC Meeting Dated 11/04/2016
Page 39 of 43
4. Population details: S.
No
Land Use Total Area
(m2
)
Total Area
(Hac.)
Population
Density
assumed
(Person/Hac.)
- BYE LAWS
Total
Population
1 Residential 821944.0 82.19 750 61646
2 Group Housing 313121.5 31.31 1000 31312
3 Institutional - Fire Fighting, Post Offices, Educational , Hospitals, Police Station etc.
- - - 500
4 Commercial (Market Complexes within
Sector)
- - - 500
5 Community Centers/ Social Gatherings - - - 100
Total Township Population 94058
6 Floating Population Residential =
27887
(30% approx.)
- - - 29887
Commercial,
Hospitals,
Community
Centers etc. =
2000
(approx.)
TOTAL POPULATION 1,23,945
5. Water calculation details: S.
N
o
Land Use Total
Area
(m2
)
Total
Area
(Hac.
)
Population
Density
assumed
(Person/Hac
.) - LDA
BYE LAWS
Total
Populatio
n
Per
Capita
in
(LPCD
)
Water
Consumptio
n
(KLD)
Waste
Water
Generatio
n (KLD)
1 Residential 821944.
0
82.19 750 61646 86 5302 4242
2 Group Housing 313121.
5
31.31 1000 31312 86 2693 2154
3 Institutional - Fire
Fighting, Post Offices,
Educational , Hospitals, Police Station etc.
- - - 500 45 23 18
4 Commercial (Market
Complexes within
Sector)
- - - 500 45 23 18
5 Community Centers/
Social Gatherings
- - - 100 45 5 4
Total Township Population 94058 8044 6437
6 Floating
Populatio
n
Residential
= 27887
(30%
approx.)
- - - 29887 15 448 358
Commercia
l,
Hospitals,
Community
Centers etc. = 2000
(approx.)
TOTAL DOMESTIC 8492 6795
7 Hospital 100 bed 350 l/ bed 35 28
8 Landscape Area 430542.1 sqm - @ 1litre per sqm 430 0
9 Green Belt
Development
430542.1 sqm @ 4.5 Ltr/ Sqm 193 0
TOTAL WATER REQUIREMENT & DISCHARGE 9150 6823
Minutes of 265th
SEAC Meeting Dated 11/04/2016
Page 40 of 43
6. 250 nos. rain water harvesting pits are proposed for the project.
7. Waste generation details:
Type of Waste Color of
Bins
Category Disposal
Method
Total Waste
(Kg/ day)
Organics Green Bio Degradable Municipal Solid Waste Site 32230
Paper Blue Recyclable Approved Recycler 7617
Metals
Glass
Textiles
Plastic
Ash & Dust Grey Non-Bio degradable Municipal Solid waste Site 18751
Total 58598
Population Category Total
Waste
Bio-degradable Recyclable Non-Biodegradable
Nos. Floating Kg/ day Kg/day Kg/ Day Kg/ Day
1900 Visitors 4483 2466 583 1435
• Total expected MSW: 58598.33 + 275+4483 = 63356 Kg/day or 63 MTPD
8. The project proposals are covered under category 8"b" of EIA Notification, 2006, as
amended.
The committee discussed the matter and recommended following TORs and general
guidelines for conducting EIA studies regarding the proposals:
Additional TORs :
1. Master plan of the area showing proposed project. Permissible uses of the proposed site as
per zoning regulation.
2. Submit DPR of the project as prepared with cost details.
3. Approval and recommendations for issuing EC will be only for Plotted development under
Zonal Development plan. The projects like Group Housings, Institutional and Commercial
etc. will have to apply for Environmental Clearance separately under the provisions of
MoEF guidelines.
4. Details of activities/facilities for which environmental clearance is proposed.
5. Allotment letter from concerned development authority.
6. All approved drawings/maps alongwith all services plans as approved by Development
Authority.
7. All services plan like Water Supply, Drainage, Sewerage, Electrification with transformer or
Substation Landscape plan with list of Ornamental trees, Rain water Harvesting, provision
of 100% Solar Energy, all roads and Common places etc.
8. The green converge will have to be left in High Tension lines passing through the Project
area as per provision in the State Electricity rules and bye laws.
9. Structural design certificate signed by architect and vetting authority should be submitted.
All structural design drawings should be signed by architect and counter signed by vetting
authority.
10. Area details showing proposed uses as residential, commercial, parks, parking, roads, other
services, facilities of the project also in percentage.
11. All community facilities and infrastructures are to be proposed as per projected population
of the area, which is about 1.25 lakhs for the proposed Zonal plan.
12. Green area is to be provided at least 22% at Zonal Plan level and in other project as per building bye
Minutes of 265th
SEAC Meeting Dated 11/04/2016
Page 41 of 43
laws and use of the project as to be proposed.
13. Physical features within 30 m of the project sites with their ownership.
14. Complete Details of facilities to be developed by the project proponent i.e. for which
environment clearance is sought.
15. Provision of a water body and water supply from the housing board instead of the tube wells
should be made.
16. Use of reflecting paints on roof top and side walls.
17. Details of rain water harvesting are to be given.
18. Provision of 100% solar lighting along the road site, stair cases, common places.
19. Plan for EWS/LIG housing provision as per Development Authority bye-laws.
20. All existing villages in the project area to be developed.
21. Examine in detail the proposed site with reference to impact on infrastructure covering
water supply, storm water drainage, sewerage, power, etc., and the disposal of treated/raw
wastes from the complex on land/water body and into sewerage system. Consider soil
characteristics and permeability for rainwater harvesting proposals, should be made to
prevent ground water contamination. Maximize use of treated water by recycling and
utilization of rainwater.
22. Water requirement and water management plan along with necessary permissions for
discharge.
23. An underground Pucca tank for collection/reuse of rain water may be constructed.
24. Hydro-geological investigations be carried out and obtain permission from Central Ground
Water Authority for withdrawal of ground water.
25. Make provision for safety against failure in the operation of wastewater treatment facilities.
Identify acceptable outfall for treated effluent.
26. Details of green belt as a measure for mitigation of dust and noise and buffer between
habitation and proposed project.
27. Landscape plan, green belts and open spaces may be described separately.
28. Study the existing flora and fauna of the area and the impact of the project on them.
29. Section of all internal roads should be provided. Right of way and carriage way width
should be clearly marked on the map. Avoid entry/exit at point of junction of roads. Traffic
movement plan in and out should be shown.
30. Examine existing crèche, education, health facilities, police, post Office, Banks and other
services and make adequate provisions in the proposal.
31. Assess soil erosion in view of the soil characteristics, topography and rainfall pattern.
32. Application of renewable energy/alternate energy, such as solar and wind energy may be
described including solar water heating in the guidelines for entrepreneurs.
33. Consider solid wastes, including e-waste in addition to other solid wastes and their disposal.
34. Identification of recyclable wastes and waste utilization arrangements may be made.
35. Explore possibility of generating biogas from biodegradable wastes.
36. Arrangements for hazardous waste management may be described as also the common
facilities for waste collection, treatment, recycling and disposal of all effluent, emission and
refuse including MSW, biomedical and hazardous wastes. Special attention should be made
with respect to bird menace.
37. Provisions made for safety in storage of materials, products and wastes may be described.
38. Disaster management plan should be prepared.
39. Traffic management plan including parking and loading/unloading areas may be described.
Minutes of 265th
SEAC Meeting Dated 11/04/2016
Page 42 of 43
Traffic survey should be carried out both on weekdays and weekend.
40. Parking provision is to be made for higher ECS worked out either as per state bye-laws or
construction manual of the MoEF. Additional parking more than required nos. as per norms
will not be permitted.
41. Exclusive Parking area in the basement (excluding other facilities) and surface is to be
clearly mentioned.
42. Provide service road for entry and exit to project site.
43. Use of local building materials should be described.
44. Consider provision of DG Flue Gas emissions to be treated in a scrubber. Stack details with
provisos of sampling port for monitoring be described. Power backup should be restricted to
50-60 % of power requirement.
45. Work out MGLC for the combined capacity of DG sets.
46. Provide for conservation of resources, energy efficiency and use of renewable sources of
energy in the light of ECBC code.
47. Application of resettlement and rehabilitation policy may be described. Project affected
persons should be identified and rehabilitation and resettlement plan should be prepared.
48. Examine separately the details for construction and operation phases both for Environmental
Management Plan and Environmental Monitoring Plan.
49. Corporate Social Responsibility (CSR) plan along with budgetary provision amounting to
2% of project cost shall be prepared and approved by Board of Directors of the company. A
copy of resolution as above shall be submitted to the authority along with list of
beneficiaries with their mobile nos./address.
50. Required no of trees should be proposed @ 01 tree/80 sqm, submit plan.
51. Project falling with in 10 Km. area of Wild Life Sanctuary is to obtain a clearance from
National Board Wild Life (NBWL) even if the eco- sensitive zone is not earmarked.
52. Declare/submit the running cost of STP and other environmental management services (e.g.,
Municipal Solid Waste Disposal, Green belt Maintenance, Water Management etc.) in the
proposals which are to be including in the allotment letters. Vendors should be identified for
Municipal Solid Waste Management and submitted.
53. The base line data to be studied for 15th April to 15th July. The proponent will submit the
schedule of monitoring/data collection programme to the Office of Directorate, Member
Secretary, UP Pollution Control Board and District Magistrate of related District.
General Guidelines:
a. A legal affidavit by the Project proponent on Rs. 100/- non-judicial Stamp Paper, duly
attested by Public Notary, stating that:
I. “There is no litigation pending against the project and/or land in which the project is
proposed to be set up (please give name & ownership etc. of the project) and that for any
such litigation what so ever, the sole responsibility will be borne by the Project
proponent.”
II. “No activity relating to this project (i.e. name of the project) including civil construction
has been undertaken at site except fencing of the site to protect it from getting
encroached and construction of temporary shed(s) for the guard(s). (if fencing has not
been done, then the same may be deleted).
III. “I/We hereby give undertaking that the data and information given in the application,
enclosures and other documents are true to the best of my knowledge and belief and
I/We am/are aware that if any part of the data and information submitted is found to be
Minutes of 265th
SEAC Meeting Dated 11/04/2016
Page 43 of 43
false or misleading at any stage, the project will be rejected and clearance given, if any
to the Project will be revoked at our risk and cost.”
IV. Project does not fall under any buffer zone of no-development as declared /identified
under any law.
b. Another legal affidavit by the consultant stating “(a) that the prescribed TORs have been
complied with (to be deleted if not applicable) & (b) that details and the data presented are
factually correct”, as per MoEF circular dated 04.08.2009 is also to be submitted along with
EIA.
c. Current, site photographs viewing towards the project area from four directions indicating
date of photograph taken, direction from which taken, name of the project, and signature of
Project proponent along with consultant with seal should be submitted, so as to ensure that
no construction has been started before the grant of EC.
d. EIA should strictly follow the guidelines prescribed in annexure-III to the EIA notification
of 2006 and the Methods of Monitoring and analysis (Annexure-IV): Guidance for
assessment of representativeness and reliability of baseline environmental attributes detailed
under EIA manual January, 2001 and other guidelines in the matter.
e. The status of accreditation of the EIA consultant with NABET/QCI shall be specifically
mentioned. The consultant shall certify that his accreditation is for the sector for which this
EIA is prepared.
f. On the front page of EIA/EMP reports, the name of the consultant/consultancy firm along
with their complete details including their accreditation, if any shall be indicated.
g. While submitting the EIA/EMP reports, the name of the experts associated with/involved in
the preparation of these reports and the Name of laboratory through which the samples have
been got analysed should be stated in the report. It shall clearly be indicated whether said
laboratory is accredited by NABL or approved under the Environment (Protection) Act,
1986 (Please refer MoEF office memorandum dated 4th August, 2009). The name project
leader of the EIA study shall also be mentioned.
h. The EIA document shall be printed on both sides, as for as possible.
The Information’s no (a I , II, III & c) asked under the general guidelines is to be
submitted within 15 days from the date of receipt of the letter and remaining of the
information’s is to be submitted along with the EIA.
(Dr. M. S. Khan)
Chairman, SEAC,UP
(Dr. S. N. Singh)
Member, SEAC, UP
(Dr. A. K. Singh)
Member, SEAC,UP
(Dr. D. C. Gupta)
Member, SEAC, UP
(Shruti Shukla) Secretary, SEAC, UP/
Director(I/C), Environment