Minutes of 275 th SEAC Meeting Date...
Transcript of Minutes of 275 th SEAC Meeting Date...
Minutes of 275th
SEAC Meeting Date 17/06/2016
The 275th meeting of SEAC was held in Directorate of Environment, U.P. on
17/06/2016. Following members were present in the meeting along with Secretary,
SEAC:
1. Dr. S.N. Singh, Chairman
2. Dr. S.C. Bramhchari, Member
3. Dr. D. C. Gupta, Member
4. Shri Bhawani Singh Khangarot Secretary, SEAC /
Director (I/C), Environment
The Chairman welcomed the members to the 275th
SEAC meeting.
The Members of SEAC unanimously taken following decisions on the agenda points
discussed:
1- “Integrated Industrial Township” at Naini, Allahabad. Sri Rajeev Kapoor, Ex.
Engg., UPSIDC Campus, A-1/4, Lakhanpur, Kanpur. File no- 3075 AD(sub)
A presentation was made by Shri A.K. Jain, Astt. Engineer, UPSIDC, authorized
representative of project proponent alongwith their consultant M/s Perfact Enviro Solutions Pvt.
Ltd. The proponent, through the documents submitted and the presentation made, informed the
committee that:-
1. The environmental clearance is sought for “Integrated Industrial Township” at Naini,
Allahabad, M/s U.P. State Industrial Development Corporation Ltd.
2. The Total plot area of the project site is 5085793.52 sqm after deduction net plot area is
4616204.52 sqm (461.62 ha) and the built-up area of the project will be 6833817.70 sqm.
3. Sector wise details:-
• Sector-1 comprises of Institutional area.
• Sector-2 & 3 area will have Industrial plots of sizes varies from 5000 sq m to 22653 sq
m.
• Sector -4 will have flatted factory .
• Sector-5 will have Industrial Housing and amenities.
• Sector-6 will have mixed use plots. These plots will have plots, star tower and urban
plaza . Plot size will varies from 1107.49 sqm – 16889.27 sq m.
• Sector-7 will also have mix use plots and urban plaza.
• Sector-8 will have Group Housing plots of sizes 4200 sq m -17200 sqm .
• Sector-9, 10& 11 will be used for plotted development of residential area will have HIG,
LIG & MIG.
• Sector-12 will have small industries of size 906 sq m-2000 sqm .
• Sector-12 A will have small industrial plots of sizes 906 sqm – 2000 sqm.
• Sector-14 will have industrial plot of size 2000 sqm – 5000 sqm .
Minutes of 275th
SEAC Meeting Date 17/06/2016
Page 2 of 28
4. Summary of project details :-
Sl. No Description Details
1. Total Plot Area 5085793.52 sqm (1256.7 acres)
2. Deducted Area 469589 sqm
3. Plot Area 4616204.52 sq m (1140.69192 acre)
4. No. of plots 1814
5. Ground Coverage (Permissible) (sqm) 1015470.05sq m
6. Ground Coverage (Achieved) (sqm) 937465.2 sq m
7. F.A.R (Permissible) (sqm) 6561572 sq m
8. F.A.R(Achieved) (sqm) 6561572 sq m
9. Basement area sq m 272245.65 sq m
10. Built-up area sqm 6833817.65
11. Green Area sq m(Within plot) 674512.5sq m
12. Green Area sqm (master plan) 1407884 sqm
13. Open & road area (sq m) (Within plot) 674512.5 sq m
14. Open & road area (sq m) (master plan) 803261 sqm
15. No. of DU 5526
5. Other services details :-
Sl. No Description Details
1. Total Water Requirement 18174 KLD
2. Fresh water Requirement 10624 KLD
3. Total Waste water generation 7946 KLD
4. Source of water Municipal Corporation
5. STP Capacity 9600 KLD (4 STPs of 700 KLD each )
6. Power requirement 101031.64 KV
7. DG Sets 5 x 1000 KVA, 2 x 500 KVA and 3 x 250 KVA
8. Rain water harvesting pond 249
9. Parking required 34200 ECS
10. Parking Provision 46612 ECS
6. Activity wise area detail :-
Residential
(HIG)(Area
in Sqm)
Industrial Mixed use Amenities Group
housing
Industrial
group
housing
Institutional
Area 313369 sq m
777756 sqm
430163 sq m 267340 sqm
83339 sqm 77234 sqm
455858.54 Sqm
No. of plots 1562 148 59 20 10 14 1
Ground
Coverage
(Permissible)
(sqm)
235026.8
sqm (75%)
349990
(45%)
107540.75
(25%)
80202
(30%)
33335.6
(40%)
27031.9
(35%)
182343
(40%)
Ground
Coverage
(Achieved)
(sqm)
235026.8
(75%)
349990
(45%)
107540.75(25%) 80202
(30%)
12500.85
(15%)
15446.8
(20%)
136758
(30%)
F.A.R
(Permissible)
(sqm)
564064.2
(180%)
2722146
(350%)
2150815 (500%) 347542
(130%)
166678
(200%)
154468
(200%)
455859
(100%)
F.A.R
(Achieved)
(sqm)
564064.2
(180%)
2722146
(350%)
2150815 (500%) 347542
(130%)
166678
(200%)
154468
(200%)
455859
(100%)
Basement area sqm
- Nil 107540.75 Nil 12500.85 15446.8 136758
Built-up area 564064.2 2722146 2258355.75 347542 179178.9 169914.8 592616
Minutes of 275th
SEAC Meeting Date 17/06/2016
Page 3 of 28
sqm
Green Area
sq m
47005.35 233326.8 129048.9 80202 25001.7 23170.2 136757.6
Open &
road area (sq
m)
31336.9 194439 193573.4 106936 45836.45 38617 182343.4
Max. No. of
floors
G + 2 G+2 B+G+10 G+3 B+G+11 B+G+5 B+G+8
No. of
Basements
- Nil 1 level Nil 1 level 1 level 1 level
Max. height
of
building(m)
12 12 35 14 40 19.2 24.5
No. of DU 1562 - - - 1389 2575
7. Population
Residential
(HIG)
Industrial Mixed
use
Amenities Group
housing
Industrial
group
housing
Institutional Total
Factors [email protected] - - FAR/10 DU@5 DU@5 FAR/100
Resident 21087 - - - 6945 12872 - 40904
Staff 211 30000 - - 69 129 456 30865
Visitors 500 2000 71694 34754 500 500 4559 114507
Total
population
21798 32000 71694 34754 7515 13501 5014 186275
8. Water management :-
SOURCE OF WATER DURING CONSTRUCTION PHASE Tanker Supply
WATER REQUIREMENT DURING CONSTRUCTION
PHASE
35 KLD
SOURCE OF WATER DURING OPERATIONAL PHASE Public supply
TOTAL WATER REQUIREMENT 18174 KLD
WASTE WATER GENERATION 7946 KLD
FRESH WATER REQUIREMENT 10624 KLD
RECYCLED WATER USE 7550 KLD
STP CAPACITY Total Capacity-9600 KLD (4 STP)
Particular Population Factor In LPCD
Total Requirement (KLD) Waste Water Discharge(KLD)
Resident 40904 86 3518
Staff 30865 45 1389
Visitor 114507 15 1717
Total 186276 6624 KLD
Domestic: 3394 KLD
Flushing: 3230 KLD
5946 KLD
Domestic: 2716 KLD
Flushing: 3230 KLD
Gardening 7250 Nil
Water Body 300 Nil
Misc. 4000 2000
Total 18174 KLD 7946 KLD
9. Rain water collection scheme :-
Soil Quality Silt Loam
Average annual Rainfall 623 mm
Peak hourly Rainfall 60 mm/hr
Minutes of 275th
SEAC Meeting Date 17/06/2016
Page 4 of 28
Porosity 34 %
Infiltration Rate 15.2 mm/hr
Water Table 5-6 m
Number of collection tanks 1015 Nos.
Size of Collection tanks 2.5 m x 2.5 m x 2.0 m
10. Parking management :-
Particulars Parking
Required(ECS)
Parking
Provision(ECS)
Residential(HIG) As per By laws Within plots
Industrial As per By Laws Within plots
Mixed use 21508 22612
Amenities 3475 3500
Group housing 2083 2304
Industrial group housing 2574 2875
Institutional 4558 15321
Total 34200 46612
11. The project proposals are covered under category 8"b" of EIA Notification, 2006.
The committee discussed the matter and directed the project proponent to submit
following information:
1- FAR component details have to be verified. Copy of bye-laws of UPSIDA for
substantiating the 3.5 FAR for industrial Development.
2- EWS/LIG/MIG details percentage wise as per byelaws.
3- Declaration for non polluting industry.
4- Under taking that project proponent will provide battery operated/CNG operated vehicles
with in 5 km of the premises.
5- Sanctioned letter of approval of layout from UPSIDA.
6- Amenities like hospital, Police station, Fire station, shelter home, sports facility, yoga and
health centre, eco club to be added and same should be marked on the plan.
7- STP details to be corrected as 9600 it is mentioned in the report that 4 STP of 700 KLD
to be provided.
8- Natural pond to be provided instead of pits. The details of ponds to be provided.
9- Scheme of the zero discharge will be provided and under taking that no natural drainage
will be hampered and there will be no outlet to the river.
10- Biological Study for the sub soil to be conducted for the terrestrial animals.
11- Submit the details of water supply and waste water discharge.
12- Undertaking that during the construction treated waste water from Allahabad STP shall
be taken.
13- Landscaping plan to be submitted giving 10 mt. peripheral green.
14- Real time air quality water quality monitoring stations shall be installed. Provision to be
made in EMP.
15- Under taking from UPSIDA for execution of EMP.
16- Justification for more ECS than permissible.
17- Proposal of 100KW solar power station with in the premises be submitted.
18- Plastic waste/fly ash to be used during the construction.
The matter shall be discussed after submission of information as above.
Minutes of 275th
SEAC Meeting Date 17/06/2016
Page 5 of 28
2- Expension of Sand Mining Project at Gata No-293/1, 293/2, 294/6, 298/10, 299/1
& 718/1, Vill-Kachhla Kham, Tehsil & Distt-Badaun (Area 45.66 Hac)- Sri Moti
Lal, Manpur Nagaria, Tehsil & Distt-Kasganj. File no- 3487 DD(Sh.)
The project proponent did not appear. The committee discussed and deliberated that
project should be delisted. The file shall not be treated as pending at SEIAA/SEAC.
3- Affordable Housing Saryu at Village-Savai, Pocket-1 Sector-7D, Awadh Vihar
Yojna, Zonal Development Plan, Amar Shaheed Path, Lucknow, Shri V.B.
Singh, Ex. Engineer, Division-7, UPAVP, Indiara Nagar, Lucknow. File no- 3678
The committee noted that an application dated 25-04-2016 was made by the project
proponent for environmental clearance of Affordable Housing Saryu at Village-Savai, Pocket-1
Sector-7D, Awadh Vihar Yojna, Zonal Development Plan, Amar Shaheed Path, Lucknow.
A presentation was made by V.B. Singh, authorized representative of project proponent
along with their consultant M/s Sawen consultancy Services Pvt. Ltd. The committee discussed
the matter and directed the project proponent to submit following information:
1- Area Chart Approved by Competent Authority should be submitted.
2- Submit revised calculation of generation and use of recycle water.
3- Certificate should be submitted stating that peripheral green will not be less than 2 meter.
4- Calculation for revised surface parking should be submitted.
5- Certificate should be submitted stating that zonal green having a kuccha pond is being
provided by housing board which will be used for the collection of surface run off.
6- Letter from Nagar Nigam should be submitted for municipal solid waste disposal .
7- Justification required for 4200 kw.
8- Solar based lighting details to be submitted.
9- Structural design vetted by Reputed Institute should be submitted.
10- Certificate stating that NOC from Airport is not required.
The matter shall be discussed after submission of information as above.
4- Exemption for project construction of Yamuna River Bridge connecting
Chapraoli Baduat Road, Baghpat, U.P. and Bilaspur-Khojipur road in Panipath
Haryana. Project Manager, UP State Bridege Corporation Ltd. BCU, Meerut.
File no- 3680
The project proponent did not appear. The committee discussed and deliberated that
project should be delisted. The file shall not be treated as pending at SEIAA/SEAC.
Minutes of 275th
SEAC Meeting Date 17/06/2016
Page 6 of 28
5- Group Housing Flats at Plot no- 3/GH2, Sector-3, Vrindavan Yojna No.2,
Lucknow. Er. Anil Kumar Mishra, Executive Engineer, U.P. HDB, Construction
Division-11, Office Complex, Sector 9A, Vrindavan Yojna Lucknow.File no-
3682
The committee noted that an application dated 20-05-2016 was made by the project
proponent for environmental clearance of Group Housing Flats at Plot no- 3/GH2, Sector-3,
Vrindavan Yojna No.2, Lucknow.
A presentation was made by Ramayan Saran, authorized representative of project
proponent along with their consultant M/s Ecomen Laboratories Pvt. Ltd. The proponent,
through the documents submitted and the presentation made, informed the committee that:-
1. The environmental clearance is sought for Group Housing Flats at Plot no- 3/GH2,
Sector-3, Vrindavan Yojna No.2, Lucknow. M/s Uttar Pradesh Housing & Development
Board.
2. Project description :- S. No. Particulars Details %
1 Plot Area (m2) 20431.66
2 Total covered Area (Permissible = 40%) (m2) 5215.11 26
3 Built up area (m2) 64792.08
4 F.A.R. Permissible 2.5
5 F.A.R. Achieved 2.5 100
6 Open Space (m2) 15216.55 74
7 Area under road and Parking (m2) 13086.04 64
8 Basement Area (m2) 13701.73
9 Total No. of Blocks/Towers 8 (A,B,C , D, E, F, G &
H)
10 Height of the tallest building (m) 41.5 up to mumty level
11 Green area proposed (m2) – Hard Landscape 2130.51 10.42
12 Total No. of Flats 384
13 Project Cost (Rs.) 243.31 Crores
14 Residential Population (Residential + Floating) 2120
15 Total Parking Area (m2)
Covered
Open
22570.0
17120.0
5450.0
16 Parking Required 766
Proposed 766
17 Total Fresh Water Requirement (KLD) 184
18 Total waste water generation(KLD) 147
19 Quantity of MSW (kg/day) 1257
20 Quantity of Rain Water to be harvested (m3/hr) 26
21 Volume of RWH pit (m3) 6.28
22 Total no. of RWH pit 7 nos.
23 Total Power requirement (KW) & Source 2008.44 from
UPPCL
24 Power backup, DG set (KVA) 2 x1000
3. Details of Flats & Population :- Tower Floor Type No. of Flats
Tower A Basement + 12 3BHK+Servant 48
Tower B Basement + 12 3BHK+Servant 48
Tower C Basement + 12 3BHK+Servant 48
Tower D Basement + 12 3BHK+Servant 48
Minutes of 275th
SEAC Meeting Date 17/06/2016
Page 7 of 28
Tower E Basement + 12 2BHK+Store 48
Tower F Basement + 12 2BHK+Store 48
Tower G Basement + 12 2BHK+Store 48
Tower H Basement + 12 2BHK+Store 48
Total 384
4. Details of Parking :-
• REQUIRED PARKING: Total FAR = 51090.35
Total required parking=766 nos. (@ 1.5 car per 100 m2 of FAR)
• Open Parking :@ 23 m2/ECS
Open Car Parking provided: 218ECS = 5450 m2
• Basement Parking: @32m2/ECS
Basement Car Parking provided= 444 ECS = 14208 m2
• Stilt Parking Provided: @ 28 m2/ECS
Stilt Car Parking = 104 ECS =2912m2
• Total number car parking provided = 766 ECS = 22570m2
5. Total area for greenery (hard & soft landscape) will be 4906.15m2 (24.01%) HARD LANDSCAPE
S. No. Green Area Area (m2)
1. Green - 01 1202.23
2. Green - 02 548.25
3. Green - 03 380.04
Total 2130.51 (10.42%)
6. Total No. of trees required = 20431.66/80 = 255
7. Trees to be planted = 260 8. Details of Water Management :-
• Fresh Water Requirement Residential units : 165120 liter (@ 86 liters for 1920 populations)
Floating Population : 900 liter @ 45 liters for 20 persons
Total Fresh Water Demand: 184 KLD Water requirement for landscaping = 11 KLD (STP treated water from Avas Vikas STP)
Total Water requirement = 195 KLD Water required for firefighting (One time requirement) = 10KL (STP treated water from Avas Vikas STP)
9. Total of 147 KLD of waste water will be generated after consumption for drinking 69 and
loss. This waste water will be discharged into Avas Vikas Sewerage System. Horticulture : 11 KLD
Fire fighting : 10 KL
10. Electricity requirement 2008.44 KW (Source: UPPCL, Lucknow) Standby power 2No.
DG Sets of 1000 KVA.
11. 7 nos. of recharge pits.
12. During operation stage total 1257Kg/day solid waste will be produced.
13. The project proposals are covered under category 8"a" of EIA Notification, 2006, as
amended.
The committee discussed the matter and recommended grant of environmental
clearance on the project proposals alongwith general conditions as earlier prescribed by the authority for construction project and following specific conditions:
Minutes of 275th
SEAC Meeting Date 17/06/2016
Page 8 of 28
1. Structural design vetted by Reputed Institute should be submitted within one month.
2. Fire and Airport Authority NOC should be submitted within a month.
3. As per suggestion of SEAC 3 large RWH pits with increased dimension should be
constructed instead of 7 pits.
4. Surface parking will be allowed only when basement parking is insufficient for parking.
5. In house STP of appropriate capacity should be installed with dual plumbing system to
reduce fresh water consumption by 30%.
6. Necessary planning for any anticipated expansion should be incorporated in present
design in view of structural stability.
7. Municipal solid waste shall be disposed/managed as per Municipal Solid Waste
(Management and Handling) Rules, 2000 (as amended). The name and address of
registered Vendors is to be submitted with agreement.
8. 03 m peripheral green shall be provided around the project inside the project boundary.
9. 15% area of the total plot area shall be compulsorily made available for the green belt
development including the peripheral green belt.
10. Project falling with in norm distance of Wild Life Sanctuary is to obtain a clearance from
National Board Wild Life (NBWL) even if the eco- sensitive zone is not earmarked.
11. Criteria/ norms provided by competent Authority regarding the seismic zone be followed
for construction work. Provision of alarm system, to timely notify the residents, in case of
occurrence of earthquake/other natural disasters/fire should be provided. A well defined
evacuation plan should also be prepared and regular mock drills should be arranged for
the residents. Rise of stairs should be constructed in a way, so that it should provide
smooth movement.
12. Modular STP is provided in basement. For the treatment for total sewage, a full-fledged
STP is to be provided with 20% more capacity than waste water generated during
operation phase.100% waste water is to be treated in captive STP conforming to
prescribed standards of receiving body for designated use. Monitoring of STP to be done
daily till its stabilization.
13. Dual plumbing should be adopted. Recycling of water as proposed shall be undertaken
with regular testing and monitoring of treated water.
14. Dedicated power supply for STPs is to be ensured during operation. Sludge of STP is to
be used in-house as manure and surplus manure should be managed by giving it to end
users. STP shall be suitably located nearest to back side boundary with shortest out let.
Operation and the maintenance cost of the STP shall also be informed along with the
compliance of the E-waste and municipal solid waste disposal.
15. LEDs should be used in all common areas and corridors. 100% solar lighting is to be
provided in the open areas/ stairs cases.
16. Parking guideline as per Development Authority should be followed. Parking for disabled
persons should be explored.
17. All entry/exit point should be bell mouth shaped.
Minutes of 275th
SEAC Meeting Date 17/06/2016
Page 9 of 28
18. To discharge excess treated waste water into public drainage system, permission from the
competent authority to be taken prior to any discharge.
19. 100 % provision of Rain Water Harvesting is to be made. RWH shall be initially done
only from the roof top. RWH from green and other open areas shall be done only after
permission from CGWB.
20. Kutcha tank for collection/reuse of rain water may be constructed.
21. Height of the stack should be provided based on combined DG sets capacity and be 6mt
higher than the tallest building.
22. Post project monitoring for air, water (surface + ground), Stack noise of D.G. sets, STP to
be carried out as CPCB Guidelines.
23. Crèche to be provided during the construction/operation phase.
24. LIG & EWS housing to be provided as per U.P. Govt. Orders and building bye laws.
25. Provision of separate room for senior citizen with proper amenities shall be made.
26. Protection shall be provided on the windows of the high rise flats for security of
residents.
27. Unless and until all the environmental issues are sorted out the occupancy will be
restricted and would be only allowed after achieving the Permission from the competent
authority.
28. The project proponent shall ensure that the project site does not attract/infringe any buffer
zone of no activity identified/declared under law.
29. For any extraction of ground water, prior permission from CGWB shall be taken.
30. Sprinkler to be used for curing and quenching and ready mix concrete may be used for
construction.
31. Possibilities of use of treated waste water for irrigation purposes should be explored. Drip
irrigation should be tried upto extent possible. No fresh water will be used for irrigation
purpose.
32. Mobile toilets, safe drinking water facility, sanitation facility and eco friendly fuels etc.
Shall be made available to the temporary residents/workers at the project site including
the proper treatment and the disposal of the wastes.
6- Construction of Proposed Samajwadi Awas Yojna at Sector-118, Noida. Sri H N
Singh, Project Engineer, WC-06, Sector-20, Noida. File no- 3484
The committee noted that an application dated 02/11/2015 was made by the project
proponent for environmental clearance of Proposed Samajwadi Awas Yojna at Sector-118,
Noida, U.P. M/s New Okhla Industrial Development Authority.
A presentation was made by Shri Vedram Sharma, APE, Department of Industries, Govt.
of U.P. authorized representative of project proponent along with their consultant M/s Ind Tech
House Consult, Delhi. The proponent, through the documents submitted and the presentation
made, informed the committee that:-
1. The environmental clearance is sought for Proposed Samajwadi Awas Yojna at Sector-
118, Noida, U.P. M/s New Okhla Industrial Development Authority.
Minutes of 275th
SEAC Meeting Date 17/06/2016
Page 10 of 28
2. The Samajwadi Awas Yojna is proposed at Sector-118, Noida, Gautam Budh Nagar,
Uttar Pradesh, provides housing for Lower Income Group and Economically Weaker
Section.
3. Total Plot Area and Built-up Area of the project is 72,433 sq. m. and 79,811.53 sq. m.
respectively.
4. Total number of dwelling units is 1376.
5. Maximum no. of proposed floors for residential tower is G+3.
6. Salient feature details of the project: S. No. Description Details
AREA DETAILS
1. Plot Area 72,433 sq. m.
2. Permissible FAR Area (275) 199191 sq. m.
3. Proposed FAR Area (97.51)% 70633.90 sq. m.
4. Ground coverage area permissible (40%) 28973 sq. m.
5. Ground Coverage Proposed (35.27%) 25549.93 sq. m.
6. Total Built up area 79,811 sq. m.
7. No. of DU’s 1376
8. Maximum No. of Floors G+3
9. Height of Tallest Building 12.5 meter
10. No. of Blocks 51
GREEN AREA
11. Green area required (16.18 % of Plot Area) 11720.8 sq. m.
12. Green area proposed (17.22% of Plot Area) 12475.07 sq. m.
PARKING DETAILS
13. No. of ECS required 706 ECS
14. No. of ECS proposed 716 ECS
POPULATION
15. Expected Population Total 6876 person
• Residential - 6192
• Floating -684
WATER REQUIREMENT
16. Total water requirement 562 KLD
17. Fresh water requirement 549 KLD
18. Horticulture water requirement 12 KLD
19. Water Cooled DG Cooling 01 KLD
WASTEWATER & SOLID WASTE GENERATION
20. Waste water Generation 464 KLD
21. Solid waste generation 3.17 TPD
POWER DEMAND
22. Maximum Power Demand 2420 KVA (Source-UPPCL)
23. DG set backup 50 KVA
7. Population details: POPULATION
RESIDENTIAL DU'S POP/DU TOTAL
(NO.S)
SALEABLE DU'S 1376 4.5 6192
TOTAL 6192
NON RESIDENTIAL (Employees) Area (in sqm)
COMMUNITY HALL 7369.97 3
COMMERCIAL (SHOPPING) 466.36 47
FACILITY MANAGEMENT STAFF LS 15
TOTAL 65
VISITORS 619
Minutes of 275th
SEAC Meeting Date 17/06/2016
Page 11 of 28
TOTAL POPULATION 6876
8. Water calculation details: Sl.
No.
Description Occupancy /
Capacity / Area
Rate (Liters) Total Water
Demand (KLD)
A. Residents
Domestic 6192 65 402.48
Flushing 6192 21 130.03
B. Non-residential
Domestic 65 30 0.97
Flushing 65 15 1.94
C. Visitors
Domestic 619 09 3.72
Flushing 619 06 5.57
D. Gardening 12475.07 01 12.48
E. Water Cooled DG Cooling ( For
6 Hrs.)
500 0.9 0.27
F. Filter Back wash LS LS 5
Total Water Requirement 562.45
Head Source Quantity
Fresh Water Requirement Greater Noida Industrial Development Authority 549 KLD
Treated Water Requirement From Common STP 13 KLD
9. Waste water details: Head Quantity, KLD
Total Water Requirement 562
Fresh Water Requirement 549
Treated Water Requirement 13
Gardening 12
DG Cooling 01
Waste Water Generation (80% of total domestic fresh water demand + 100% of
Flushing Water)
464
Sewage to be discharged to Common STP at Sec-123 464
� Estimated Sewage Generation: 464 KLD
� Waste water generated will be treated in a common STP at Sec-123, Noida. (Uninterrupted power supply
through DG set)
� Treated waste water will be used for horticulture and DG cooling.
10. Waster generation details: Total Waste Generation 3.17 TPD
Organic Waste Generation 1.90 TPD
E- Waste Generation 21 KG/Day
Sludge Generation 166.78 KG/Day
Hazardous Waste Generation (DG Waste Oil) 10 Lts/ Annum
11. Structural design vetted by Reputed Institute not required because the height of the
building is less than 15 meter.
12. CSR not applicable since it is the housing project for weaker section.
13. The project proposals are covered under category 8"a" of EIA Notification, 2006, as
amended.
The committee discussed the matter and recommended grant of environmental
clearance on the project proposals alongwith general conditions as earlier prescribed by
the authority for construction project and following specific conditions:
1. All maps/plan signed/stamped by competent Authority should be submitted.
Minutes of 275th
SEAC Meeting Date 17/06/2016
Page 12 of 28
2. As per suggestion of SEAC 6 Big RWH pits with increased dimension should be
constructed instead of 9 pits.
3. ECS for only 259 four wheeler and 650 two wheeler allowed.
4. Minimum of 900 trees should be planted.
5. Dual plumbing undertaking is to be submitted.
6. Necessary planning for any anticipated expansion should be incorporated in present design
in view of structural stability.
7. Municipal solid waste shall be disposed /managed as per Municipal Solid Waste
(Management and Handling) Rules, 2000 (as amended). The name and address of
registered Vendors is to be submitted with agreement.
8. 03 m peripheral green shall be provided around the project inside the project boundary.
9. 15% area of the total plot area shall be compulsorily made available for the green belt
development including the peripheral green belt.
10. Project falling with in norm distance of Wild Life Sanctuary is to obtain a clearance from
National Board Wild Life (NBWL) even if the eco- sensitive zone is not earmarked. 11. Criteria/ norms provided by competent Authority regarding the seismic zone be followed for
construction work. Provision of alarm system, to timely notify the residents, in case of
occurrence of earthquake/other natural disasters/fire should be provided. A well defined
evacuation plan should also be prepared and regular mock drills should be arranged for the
residents. Rise of stairs should be constructed in a way, so that it should provide smooth
movement.
12. Modular STP is provided in basement. For the treatment for total sewage, a full-fledged
STP is to be provided with 20% more capacity than waste water generated during operation
phase.100% waste water is to be treated in captive STP conforming to prescribed standards
of receiving body for designated use. Monitoring of STP to be done daily till its
stabilization.
13. Dual plumbing should be adopted. Recycling of water as proposed shall be undertaken
with regular testing and monitoring of treated water.
14. Dedicated power supply for STPs is to be ensured during operation. Sludge of STP is to be
used in-house as manure and surplus manure should be managed by giving it to end users.
STP shall be suitably located nearest to back side boundary with shortest out let.
Operation and the maintenance cost of the STP shall also be informed along with the
compliance of the E-waste and municipal solid waste disposal.
15. LEDs should be used in all common areas and corridors. 100% solar lighting is to be
provided in the open areas/ stairs cases.
16. Parking guideline as per Development Authority should be followed. Parking for disabled
persons should be explored.
17. All entry/exit point should be bell mouth shaped.
18. To discharge excess treated waste water into public drainage system, permission from the
competent authority to be taken prior to any discharge.
19. 100 % provision of Rain Water Harvesting is to be made. RWH shall be initially done only
from the roof top. RWH from green and other open areas shall be done only after
permission from CGWB.
20. Kutcha tank for collection/reuse of rain water may be constructed.
21. Height of the stack should be provided based on combined DG sets capacity and be 6mt
higher than the tallest building.
22. Post project monitoring for air, water (surface + ground), Stack noise of D.G. sets, STP to
be carried out as CPCB Guidelines.
Minutes of 275th
SEAC Meeting Date 17/06/2016
Page 13 of 28
23. Crèche to be provided during the construction/operation phase.
24. LIG & EWS housing to be provided as per U.P. Govt. Orders and building bye laws.
25. Provision of separate room for senior citizen with proper amenities shall be made.
26. Protection shall be provided on the windows of the high rise flats for security of residents.
27. Unless and until all the environmental issues are sorted out the occupancy will be restricted
and would be only allowed after achieving the Permission from the competent authority.
28. The project proponent shall ensure that the project site does not attract/infringe any buffer
zone of no activity identified/declared under law.
29. For any extraction of ground water, prior permission from CGWB shall be taken.
30. Sprinkler to be used for curing and quenching and ready mix concrete may be used for
construction.
31. Possibilities of use of treated waste water for irrigation purposes should be explored. Drip
irrigation should be tried upto extent possible. No fresh water will be used for irrigation
purpose.
32. Mobile toilets, safe drinking water facility, sanitation facility and eco friendly fuels etc.
Shall be made available to the temporary residents/workers at the project site including the
proper treatment and the disposal of the wastes.
7- Affodable Housing under ''Samajwadi Yojna'', G.H Plot No- 01 Amrapali
Yojna, village -Barvan Kurd, Lucknow, Sri K.C. Srivastava, Excutive Engineer,
Cunstruction Division-21, UPAVP, Virndavan Yojna, Lucknow. File no- 3670
The committee noted that an application dated 05/05/2016 was made by the project
proponent for environmental clearance of Proposed for Affordable Housing under '' Samajwadi
Yojna'', G.H Plot No- 01 Amrapali Yojna, village -Barvan Kurd, Lucknow, G.H. Plot No-01 H-
6/G.H-01, Amrapali Yojna, Lucknow.
The case was put up before 271st SEAC meeting held on 16/05/2016. A presentation was
made by Shri Kailash Chandra Srivastava, project proponent along with their consultant M/s
ECE & Sajag Consultants. The committee discussed the matter and directed the project
proponent to submit following information:
1. The committee directed the project proponent to submit the project report to all the
member including Chairman of SEAC.
2. Authorization letter from PP should be submitted.
3. Total project cost is Rs. 280.16 Cr, Additional 50% FAR purchased indicating costing
detail should be given in written if it is in persistence.
4. Correction of the road width on map should be done and be submitted.
5. Road section plan showing all the services should be submitted.
6. Give the legends on layout plan showing all features.
7. Revised water balance diagram in view of 86 LPCD should be submitted.
8. In form-1 it is said 30% recycled water shall be used while during the presentation the 30
% factor has been, removed. Clarification in this regard should be submitted.
9. Waste water management plan should be submitted along with NOC from Nagar Nigam.
10. Fire fighting plan which facility of OHT and hydrant to the park should be adopted.
11. Show parking as per the norms. Detailed parking plan is to be submitted.
12. As committed, SWM shall be conducted; permission letter issued by the competent
authority should be submitted.
Minutes of 275th
SEAC Meeting Date 17/06/2016
Page 14 of 28
13. Page no. 39 shows air conditioning; explain the term used for the need of very project.
14. Final disposal of unused water to the natural drain, specify the drain nearby.
15. Evacuation route plan along with the alarming system should be submitted.
16. The structure design certificate by qualified structure engineer should be submitted. The
structural design certificate should preferably be vetted by IITs/CBRI. Provision of alarm
system, to timely notify the employees/residents, in case of occurrence of
earthquake/other natural disasters/fire should be provided.
17. Submit RWH design and the plan.
18. For run of water management tank with kaucha base should be provided.
19. Plan for 30 m peripheral green is to be submitted.
20. The Green area should be kept 15%to the total area.
21. Area detail of all proposed land use with percentage to be submitted.
22. Details of towers and type of housing proposed to be submitted.
23. Revised numbers of tree, one tree per 80 SQM of total area.
24. Definite proposal for STP and water recycling with undertaking shall also be submitted.
25. Provision of 100% solar lighting along the road side, stair cases, common area; at 10% of
total power requirement with signage’s, entry gate and boundary wall shall be made also
solar energy conservation calculation should be submitted in this regard.
The case was put up on 275th
SEAC meeting dated 17-06-2016. A presentation was made
by Shri Kailash Chandra Srivastava, project proponent along with their consultant M/s ECE &
Sajag Consultants. The project proponent submitted the reply on 26 points. The proponent,
through the documents submitted and the presentation made, informed the committee that:-
1. The environmental clearance is sought for Proposed Affordable Housing under ''
Samajwadi Yojna'', G.H Plot No- 01 Amrapali Yojna, village -Barvan Kurd, Lucknow.
2. Area Details- S.No. Details Area (sqmt.) Percentage (%)
1. Total Ground Coverage 8752.0 27.56
2. Total Green Area 4778.0 15.05
3. Total Road Area 7966.26 25.1
4. Total Surface Area 10255.16 32.29
Total plot area 31751.45 100.0
S.No. Description of Item AREA (sqmt.)
1 Total Plot Area 31751.45
2 Permissible Ground Coverage (35%) 11113.0
3. Achieved Ground Coverage (27.56%) 8752.0
4. Permissible F.A.R. (2.5) 79378.62
5. Purchasable FAR (Max. 50% of permissible)
i.e.1.25)
15875.725
6. Total Achieved FAR 3.08
Proposed Set back 15.0 m on all sides
3. Infrastructure details :-
Total residential population 6300
Floating Population 2000
Total Parking Provision 975 ECS
Total Electric Load Demand 4053.0 KW
DG Sets for emergency electric demand 04 x 200 KVA
Total Consumption of Water 1105.87 KLD
Total Waste Water Generation 876.5 KLD
Minutes of 275th
SEAC Meeting Date 17/06/2016
Page 15 of 28
Total MSW Generation 4046 Kg/Day
Rain Water Harvesting Recharge Pits 04
Proposed Number of Trees 412
Setback 12 m
Driveways 6 m
4. Solid Waste - 4046Kg/day
5. Water use calculation :- S.NO Water Use Population/ Area Per Capita in
(LPCD)
Water
Requirement
(KLD
Waste Water
Generation
(KLD)
1. Residents 6300 150 945.0 756.0
2. Service Staff 20 45 9.0 7.0
3. Commercial
Staff
150 36000Litre
/Ha/Day
0.054 0.039
4. TOTAL DOMESTIC WATER
REQUIREMENT
954.054 763.039
5 DG Set Cooling 2 X 400 KVA 0.91/4hr/KVA 2.184 NIL
6 Gardening 4778.0 m2 25 Litres per
100/m2
1.2 NIL
7 Tree Plantation 250 nos. sapling 4.5 lt. / sapling 1.0 NIL
TOTAL WATER REQUIREMENT 958.438 763.04
6. Total 830.0 KLD of waste water i.e. Grey (547.0 KLD) and Black (283.0 KLD) water
shall be diverted to 850 KLD STP based on FAB Technology for the treatment.
7. About 299.45 KLD of the treated Water shall be reused for- - Flushing - 283.0 KLD - DG Set Cooling - 0.90 KLD
- Green Area/Landscaping – 1.2 KLD
- Street Washing- 14.35 KLD
- Balance 298.15 KLD treated water will be discharged to the Yojna sewer line.
8. Sludge will be generated from 850 KLD STP. It will be passed through filter press where
it will be dried and form a cake, and then used as manure in green area.
9. The project proposals are covered under category 8"a" of EIA Notification, 2006, as
amended.
The committee discussed the matter and recommended grant of environmental
clearance on the project proposals alongwith general conditions as earlier prescribed by the authority for construction project and following specific conditions:
1. The project proponent will submit the structural design certificate duly vetted by IIT within
a month time failing which E.C. will deem to be cancelled.
2. 2 meter staggered peripheral tree plantation along the project boundary wall. The parking
to be planned accordingly.
3. Dual plumbing system to be adopted in order to utilise minimum 30 % treated waste water
and to reduce fresh water consumption.
4. As the provision has been made under UPAVP notification 1965 to dispose the solid waste
through the local municipal Authority. Therefore, the project proponent will ensure that at
the time of handing over the project a written commitment from nagar nigam for collection
of solid waste will taken.
5. The Storm water shall be disposed off through already existing natural drainage system.
The project proponent will ensure that the natural drainage system is not hindered and no
untreated waste water is added to the stream.
Minutes of 275th
SEAC Meeting Date 17/06/2016
Page 16 of 28
6. A kuccha pond for RWH will be constructed and maintained.
7. Provision of parking should be restricted to ECS as required under Development Authority
bye-laws.
8. Provision of setback on all sides should be made as per Development Authority bye-laws.
9. Copy of all NOCs as obtained from different Department should be submitted.
10. Necessary planning for any anticipated expansion should be incorporated in present design
in view of structural stability.
11. Kacha Tank shall be planned within the premises for storage of rain water.
12. Municipal solid waste shall be disposed/managed as per Municipal Solid Waste
(Management and Handling) Rules, 2000 (as amended). The name and address of
registered Vendors is to be submitted with agreement.
13. Minimum 15% area of the total plot area shall be compulsorily made available for the
green belt development including the peripheral green belt.
14. Project falling with in norm distance of Wild Life Sanctuary is to obtain a clearance from
National Board Wild Life (NBWL) even if the eco- sensitive zone is not earmarked.
15. Criteria/ norms provided by competent Authority regarding the seismic zone be followed
for construction work. Provision of alarm system, to timely notify the residents, in case of
occurrence of earthquake/other natural disasters/fire should be provided. A well defined
evacuation plan should also be prepared and regular mock drills should be arranged for the
residents. Rise of stairs should be constructed in a way, so that it should provide smooth
movement.
16. For the treatment for total sewage, a full-fledged STP is to be provided with 20% more
capacity than waste water generated during operation phase.100% waste water is to be
treated in captive STP conforming to prescribed standards of receiving body for designated
use. Monitoring of STP to be done daily till its stabilization.
17. Dual plumbing should be adopted. Recycling of water as proposed shall be undertaken
with regular testing and monitoring of treated water.
18. Dedicated power supply for STPs is to be ensured during operation. Sludge of STP is to be
used in-house as manure and surplus manure should be managed by giving it to end users.
STP shall be suitably located nearest to back side boundary with shortest out let.
Operation and the maintenance cost of the STP shall also be informed along with the
compliance of the E-waste and municipal solid waste disposal.
19. LEDs should be used in all common areas and corridors. 100% solar lighting is to be
provided in the open areas/ stairs cases.
20. Parking guideline as per Development Authority should be followed. Parking for disabled
persons should be explored.
21. All entry/exit point should be bell mouth shaped.
22. To discharge excess treated waste water into public drainage system, permission from the
competent authority to be taken prior to any discharge.
23. 100 % provision of Rain Water Harvesting is to be made. RWH shall be initially done only
from the roof top. RWH from green and other open areas shall be done only after
permission from CGWB.
24. Height of the stack should be provided based on combined DG sets capacity and be 6mt
higher than the tallest building.
25. Post project monitoring for air, water (surface + ground), Stack noise of D.G. sets, STP to
be carried out as CPCB Guidelines.
26. Crèche to be provided during the construction/operation phase.
Minutes of 275th
SEAC Meeting Date 17/06/2016
Page 17 of 28
27. LIG & EWS housing to be provided as per U.P. Govt. Orders and building bye laws.
28. Provision of separate room for senior citizen with proper amenities shall be made.
29. Protection shall be provided on the windows of the high rise flats for security of residents.
30. Unless and until all the environmental issues are sorted out the occupancy will be restricted
and would be only allowed after achieving the Permission from the competent authority.
31. The project proponent shall ensure that the project site does not attract/infringe any buffer
zone of no activity identified/declared under law.
32. For any extraction of ground water, prior permission from CGWB shall be taken.
33. Sprinkler to be used for curing and quenching and ready mix concrete may be used for
construction.
34. Possibilities of use of treated waste water for irrigation purposes should be explored. Drip
irrigation should be tried upto extent possible. No fresh water will be used for irrigation
purpose.
35. Mobile toilets, safe drinking water facility, sanitation facility and eco friendly fuels etc.
Shall be made available to the temporary residents/workers at the project site including the
proper treatment and the disposal of the wastes.
8- Bhaunrat Dam Irrigation Project having CCA 9850 Ha., Mahrouni, Lalitpur.
Sri K.K.Agrawal, Ex. Engg, Irrigation Construction Div-II, Lalitpur. File no-
2641
Environmental Clearance for Bhaunrat Dam Irrigation Project having CCA 9850 Ha., at
Village- Mahrouni, District- Lalitpur was issued vide letter no- 1382/Praya/SEAC/
2641/2014/OSD(T) dated 27-11-2015. Vide letter no- 229/ICD-II/EC/ dated 24-05-2016 the
Executive Engineer Irrigation construction division –II lalitpur made an application requesting
some amendments in the approved E.C due to design aspect as finalized by Central Water
Commission. The case was put up before SEAC. Shri S.K. Agrawal Executive Engineer,
Irrigation, Department and Environmental consultant CEMC Pvt. Ltd. made the presentation
before the SEAC. The following parameters which needed corrections were bought to the
notice of the SEAC
S.
No.
Parameters Approved in
Original EC
Revised
Values
Reason and Impact on Environment
1. Top of dam 363.10 m 365.25 m Due to free board requirement as per IS
Code. FRL of dam is same as approved in
original EC. So no impact on environment.
2. Maximum height of
dam above river bed
19.93 m 22.08 m Due to increase in free board. No impact on
environment.
3. Length of dam 4.20 Km 4.75 Km Due to Change in top of dam for tying the
dam with hills up to top of dam level.
4. Water for Irrigation 34.90 MCM 56.21 MCM This value was original submitted in the
EIA/EMP report but due to mistake this
value was not taken care of.
5. Benefits 331100 Qtl 318800 Qtl Finalization of output as per CWC
guidelines. There is no impact on
environment.
Minutes of 275th
SEAC Meeting Date 17/06/2016
Page 18 of 28
6. Cost of Irrigation /ha 2.63 Lac/ha 3.83 Lac/ha Due to finalization of cost at CWC.
7. Cost of Project 44003.77 Lac 61277.49 Lac Due to finalization of cost at CWC.
8. Land Requirements 1266.78 Ha 1511 Ha Due to detailed survey, quantities have
been finalized.
9. Benefit Cost ratio 1.61 1.16 Due to finalization of cost and benefits at
CWC.
The SEAC discussed the matter and decided that the modified EIA clearly indicating the
changed parameters and associated environmental impact is to be submitted; as the area has
increased from 1266.78 ha. to 1511 ha. the project proponent has to bring a certificate from
mining department lalitpur for no impact on minerals over the land to be submerged.
The matter shall be discussed after submission of information as above.
9- Group Housing Project at Plot No-GH-5 & 6, Sector-8B, Vrindavan Awas Yojna,
Lucknow- Col. C N Rawat, Project Director, Chappan Chauraha, Lal Bahadur
Shashtri Marg, Luckcnow Cantt. File no- 2822
Environmental Clearance for Group Housing Project at Plot No-GH-5 & 6, Sector-8B,
Vrindavan Awas Yojna, Lucknow was issued vide letter no-
1660/Praya/SEAC/2822/2015/AD(H) dated 04-01-2016. Vide letter no-
8/3030/97/LUCK/AWHO/21 dated 01-062016 the project director AWHO made an application
requesting for some amendments in the approved E.C regarding sewerage discharge. The case
was put up before SEAC. Col. C.N. Rawat, and consultant M/s Ascenso Environ Pvt. Ltd made
the presentation before the SEAC. It was informed in the presentation that for the said project
following recertification are required.
1- There is no separate STP is constructed at site because UPAVP is established his own
STP in this location and give the consent letter vide his letter no- 327/Y-6/AVP- NK-
19/Lucknow/19 dated 17-02-2016
2- ECR- In thus matter it is submitted that the army welfare housing organization work on
NO Profit NO loss basis and providing dwelling units to its soldiers with priority to
widows, battle casualties, serving and retired soldiers, Hence, this conditions needs
rectification.
The SEAC discussed the matter and recommended to modify the E.C. conditions
viz General Condition No. 49, General Condition No. 53, General Condition No. 55,
General Condition No. 57, General Condition No. 66, General Condition No. 68, General
Condition No. 19, General Condition No. 27, specific Condition No. 14, specific
Condition No. 15, specific Condition No. 16, specific Condition No. 20, specific
Condition No. 24 by incorporating the following:-
1- Water requirement for Landscaping, DG sets, Fire Fighting Tank amounting to
approx 30 KLD shall be met through UPAVP STP treated waste water.
2- Measure shall be taken to reduce the water losses up to 15 %.
3- CSR will not be applicable as project proponent is non profitable welfare origination.
Minutes of 275th
SEAC Meeting Date 17/06/2016
Page 19 of 28
10- Group Housing Project at Plot No-6A/GH-2, 6A/GH-3 & 6A/GH-4, Sector-6A,
Vrindavan Yojna -1, Lucknow. Col. C N Rawat, Project Director, Chappan
Chauraha, Lal Bahadur Shashtri Marg, Lucknow. File no- 3264
Environmental Clearance for Group Housing Project at Plot No-GH-5 & 6, Sector-8B,
Vrindavan Awas Yojna, Lucknow was recommended in SEAC meeting dated 13-05-2016 and
agreed in SEIAA meeting dated 08-06-2016. Vide letter no- 8/3030/97/LUCK/AWHO/21 dated
01-062016 the project director AWHO made an application requesting for some amendments in
the approved E.C regarding sewerage discharge. The case was put up before SEAC. Col. C.N.
Rawat, and consultant M/s Ascenso Environ Pvt. Ltd made the presentation before the SEAC. It
was informed in the presentation that for the said project following recertification are required.
1- There is no separate STP is constructed at site because UPAVP is established his own
STP in this location and give the consent letter vide his letter no- 580/NK-12/06 dated
09-03-2016.
2- CSR- In thus matter it is submitted that the army welfare housing organization work on
NO Profit NO loss basis and providing dwelling units to its soldiers with priority to
widows, battle casualties, serving and retired soldiers, Hence, this conditions needs
rectification.
3- The project category as mentioned under point no. 12 in the minutes 269th SEAC meeting
held on 13.05.2016 is 6B. However, the project is actually categorized under 8(a) of the
schedule of EIA notification. Thus, the said project category need to be rectified.
4- The Proposed project is being developed on the total plot area of 14,455.51 m2. As a
small plot area, 03 meter green belts leads to problems of surface parking. Project has
provision of surface parking of 136 ECS but in case of broader green belt we will not
able to provide the surface parking in absence of adequate space and residents of these
projects will face the problem of parking of vehicle.
The SEAC discussed the matter and recommended to modify the conditions viz
specific Condition No. 06, specific Condition No. 12, specific Condition No. 17, specific
Condition No. 21, specific Condition No. 30, specific Condition No. 13 by incorporating
the following:-
1- Water requirement for Landscaping, DG sets, Fire Fighting Tank shall be met through
UPAVP STP treated waste water.
2- Measure shall be taken to reduce the water losses up to 15 % .
3- CSR will not be applicable as project proponent is non profitable welfare origination.
4- 2 mt. peripheral green will be provided as the plot area is less than 20,000sqm.
5- The project is classified under 8 (a) category.
11- Expansion of “Oxygen Boulevard” IT SEZ at Plot No-7, Sector-144, Noida- Sri
Deepak Khurana, Sr. VP, C-23, Greater Kailash Enclave, Part-I, New Delhi. File
no- 2748
A presentation was made by Shri Vikas Anand, authorized representative of project
proponent alongwith their consultant M/s Perfact Enviro Solutions Pvt. Ltd. The project
proponent informed the committee that:
Minutes of 275th
SEAC Meeting Date 17/06/2016
Page 20 of 28
1- The proposed project is an expansion of commercial complex IT/SEZ “Oxygen
Boulevard” which is located at Plot No.-7 sector 144, Noida, Uttar Pradesh. The project
has been developed by M/s Aachvis Softech Pvt. Ltd.
2- The project has already been granted Environmental Clearance vide letter No.
131/SEAC/07 dated 17/10/2008 for the existing plot area 100498 Sqm and built up area
220300 Sqm under category 8(b).
3- The project is now proposed to be further expanded due to additional FAR, now the built-
up area will increase from 102415.4 sq m to 211045.8 sq m.
4- The project will be comprising of IT/ITES offices, Retail space Utility Block, food court
etc.
5- The land was allotted by Okhla Development Authority to M/s Aachvis Softech Pvt. Ltd.
6- Project details as compared to constructions done against the proposals for which
environmental clearance was issued earlier are as follows:
S. No. Details Already
Constructed
Proposed
Construction
Total Project
Details
1. Total Plot area 100498.0 Sqm -- 100498.0 Sqm
2. Cost of project 640 cr. 120 cr. 760 cr.
3. Ground coverage
Permissible
(30.0%)
30150 sq m - 30150 sq m
4. Ground coverage proposed (24.48%)
13738.98 Sqm 10865.17 sqm 24604.15 Sqm
5. FAR (permissible) (2.0) 200996 sqm - 200996.0 Sqm
6. FAR (proposed) 102415.4 Sqm(1.02) 96689.15 Sqm (0.96) 199104.55 Sqm (1.98)
9. Basement area 36876.61 Sqm 35438.51 Sqm 72315.12 Sqm
10. Stilt area (podium) 21236.57 Sqm 31854.85 Sqm 53091.42 Sqm
11. Other Non-FAR 7758.35 Sqm 10859.69 Sqm 18618.04 Sqm
12. Total Build-up area (FAR,
Non-FAR, Stilt,
basement)
168286.93 Sqm 174842.20 Sqm 343129.13 Sqm
13. Green Area 8388 Sqm 31729 Sqm 40117 Sqm (39.92 %)
14. No. of basement 2 locations 1 location 2 location
15. No. of towers 6 5 11
16. Max. No. of floors G+8 G+15 G+15 (Max.)
17. Height of building in m 32 65 65
18. Population
Staff 8500 12500 21000
Staff Support 225 25 250
visitors 100 100 200
Total population 8825 12625 21450
19. Total Power Load 12000 KVA 13000 KVA 25000 KVA
20. No. of DG sets 4 X 2000 KVA, 2 X
1500 KVA
& 2 x 1250
KVA (on
standby)
Nil 4 X 2000 KVA, 5 X
1500 KVA & 2
x 1250 KVA
(on standby)
21. No. of Rainwater
Harvesting pits
8 2 10
22. Parking required 2048 ECS 1934 ECS 3982 ECS
23. Parking proposed - - 5085 ECS
24. Water requirement 503 KLD 719 KLD 1222 KLD
Minutes of 275th
SEAC Meeting Date 17/06/2016
Page 21 of 28
25. Waste water discharge 362 KLD 520 KLD 882 KLD
26. STP capacity 550 KLD 550 KLD (Existing
STP will be
enhanced)
1100 KLD
27. Solid waste generated 1355 kg/day 1893 kg/day 3218 kg/day
7- Proposed land use details are as follows :-
S.no. Coverage type Area (sq m) Percentage
1. Ground Coverage 24604.15 24.48 %
2. Green Area 40117 39.91 %
3. Surface parking 21367 21.26 %
4. Road & Open area 14409.85 14.33 %
Total plot area 100498 100 %
8- The area of 40117 sq m (39.9 %) is designated for plantation including big foliage trees,
Avenue plantation & herbs & shrubs.
9- Total 1200 trees will be planted. Out of which 500 tress are already planted
10- Green area details
Detail Area in sq m % of Plot Area
Area under Shelter Belt (Trees around the
periphery)
15074.7 sq m 15 %
Area under Avenue Plantation (Trees around
roadside & water body area)
10049.8 sq m 10 %
Sub Total Area under Trees 25124.5 sq m 25 %
Area under Shrubs & Herbs 10049.8 sq m 10 %
Area under Landscape/water body (Saucer
shaped)
4942.7 sq m 5 %
Total Plantation Area 40117.0 sq m 40 %
11- Total Water Management :-
Population Factor
(LPCD)
Water
requirement
(KLD)
DOMESTIC
(KLD)
FLUSHING
(KLD)
WASTE
WATER
(KLD)
Domestic
Staff
Support
21000 45 945
Staff 250 45 11
Visitor 200 15 3
Total 961 384 575
waste water
discharge
307 575 882
Gardening 15 Nil
HVAC 241 Nil
Misc. 5 Nil
Total 21450 1222 KLD 882 KLD
Minutes of 275th
SEAC Meeting Date 17/06/2016
Page 22 of 28
12- 02 rain water harvesting pits in addition to existing 08 pits with 3.7 m dia x 3.5 m depth
are proposed.
13- Parking details:
Details Factor Total
Parking for already Constructed Area FAR/50 =102415.4/50
2048
Parking for Proposed Area FAR/50
=98580.6/50
1971
Total Parking Provided 4019
Parking provisions:
Details Parking Area ( sqm) Factor ECS
Basement 72315.12 32 2260
Podium 53091.42 28 1896
Surface 21367 23 929
Total Parking Provision 5085
14- Power requirement and provisions details:
S. No. Description Proposed
1 Electric Load 17000 KVA 2 DG Set Capacity 4 X 2000 KVA, 5 X 1500 KVA & 2 x 1250 KVA (Stand by)
3 Stack height 6 m above roof level
4 Location of DG Sets Basement
15- The project proposals are covered under category 8"b" of EIA Notification, 2006, as
amended.
The committee discussed the matter and recommended grant of environmental clearance on
the project proposals along with general conditions as earlier prescribed by the authority for
construction project and following specific conditions:
1. Zero discharge treatment will be provided.
2. No D.G. sets will be provided as existing D.G. sets will be brought will use.
3. 1934 ECS will be provided.
4. 550 KLD additional STP will be provided.
5. Kuccha tank for collection and protection of rain water will be provided.
6. Approximately 700 trees will be provided.
7. Solar invertors will be provided.
8. 03 m peripheral green shall be provided around the project inside the project boundary.
9. 15% area of the total plot area shall be compulsorily made available for the green belt
development including the peripheral green belt.
10. Project falling with in norm distance of Wild Life Sanctuary is to obtain a clearance from
National Board Wild Life (NBWL) even if the eco- sensitive zone is not earmarked.
11. Criteria/ norms provided by competent Authority regarding the seismic zone be followed for
construction work. Provision of alarm system, to timely notify the residents, in case of
occurrence of earthquake/other natural disasters/fire should be provided. A well defined
evacuation plan should also be prepared and regular mock drills should be arranged for the
residents. Rise of stairs should be constructed in a way, so that it should provide smooth
movement.
12. For the treatment for total sewage, a full-fledged STP is to be provided with 20% more
capacity than waste water generated during operation phase.100% waste water is to be treated
in captive STP conforming to prescribed standards of receiving body for designated use.
Monitoring of STP to be done daily till its stabilization.
Minutes of 275th
SEAC Meeting Date 17/06/2016
Page 23 of 28
13. Dual plumbing should be adopted. Recycling of water as proposed shall be undertaken with
regular testing and monitoring of treated water.
14. Dedicated power supply for STPs is to be ensured during operation. Sludge of STP is to be
used in-house as manure and surplus manure should be managed by giving it to end users. STP
shall be suitably located nearest to back side boundary with shortest out let.
Operation and the maintenance cost of the STP shall also be informed along with the
compliance of the E-waste and municipal solid waste disposal.
15. Environmental Corporate Responsibility (ECR) plan along with budgetary provision
amounting to 2% of total project cost (120 cr) shall be prepared and approved by Board of
Directors of the company. A copy of resolution as above shall be submitted to the authority. A
list of beneficiaries with their mobile nos./address should be submitted alongwith six monthly
compliance reports.
16. LEDs should be used in all common areas and corridors. 100% solar lighting is to be provided
in the open areas/ stairs cases.
17. Parking guideline as per Agra Development Authority should be followed. Parking for disabled
persons should be explored.
18. All entry/exit point should be bell mouth shaped.
19. To discharge excess treated waste water into public drainage system, permission from the
competent authority to be taken prior to any discharge.
20. 100 % provision of Rain Water Harvesting is to be made. RWH shall be initially done only
from the roof top. RWH from green and other open areas shall be done only after permission
from CGWB.
21. Height of the stack should be provided based on combined LPG/CNG based DG sets capacity
and be 6 m higher than the tallest building.
22. Post project monitoring for air, water (surface + ground), Stack noise of LPG/CNG based DG
sets, STP to be carried out as CPCB Guidelines.
23. Crèche to be provided during the construction/operation phase.
24. Provision of separate room for senior citizen with proper amenities shall be made.
25. Protection shall be provided on the windows of the high rise flats for security of residents.
26. Unless and until all the environmental issues are sorted out the occupancy will be restricted and
would be only allowed after achieving the Permission from the competent authority.
27. The project proponent shall ensure that the project site does not attract/infringe any buffer zone
of no activity identified/declared under law.
28. For any extraction of ground water, prior permission from CGWB shall be taken.
29. Sprinkler to be used for curing and quenching and ready mix concrete may be used for
construction.
30. Possibilities of use of treated waste water for irrigation purposes should be explored. Drip
irrigation should be tried upto extent possible. No fresh water will be used for irrigation
purpose.
31. Mobile toilets, safe drinking water facility, sanitation facility and eco friendly fuels etc. Shall
be made available to the temporary residents/workers at the project site including the proper
treatment and the disposal of the wastes.
12- Group Housing Project “Panchsheel Green-II” at Plot No-GH-01A, Sector-16,
Greater Noida- Sri Gulshan Kumar, H-169, Sector-63, Noida. File no- 2560
The environmental clearance is sought for Expansion of Group Housing Project
“Panchsheel Green-II” at Plot No-GH-01A, Sector-16, Greater Noida, U.P. M/s
Panchsheel Buildtech Pvt. Ltd. The project proponent Mr Sri Gulshan Kumar and Mr
Minutes of 275th
SEAC Meeting Date 17/06/2016
Page 24 of 28
Mahendra Pandey from M/s Eco Pro Engineers Pvt. Ltd consultant appeared before the
SEAC. The SEAC members has asked Mr. Mahendra Pandey from M/s ECO PRO
engineers to state the reason as why the head of the consultancy firm has not appeared
before SEAC, as was told in last meetings to be present before SEAC to present this case.
Mr. Pandey has not submitted satisfactory reply.
The SEAC members have observed that the consultant has submitted wrong and
misleading information in the EIA report; may be copied from other reports. The SEAC
members took a serious view and warned the consultant for not to repeat such
discrepancies/errors in the report. The SEAC recommended the project proponent to
submit the revised EIA report with original analysis reports with adequate proof of
monitoring date wise and station wise. The case shall be heard on 28-06-2016.
The matter shall be discussed after submission of information as above.
13- Biomedical Waste Treatment Facility at Vil-Mahuar, Distt-Chandauli-. Sri J
Rai, CEO, S-5/ 38C, 212, Ganpati Apartment, Vindhya Vasini Nagar, Varanasi.
File no- 3629
The SEAC observed that the application for Environmental Clearance that the
Biomedical Waste Treatment Facility at Vil-Mahuar, Distt-Chandauli has been received
on 03-03-2016. A presentation was made by Shri Janaren Rai, authorized representative
of project proponent.
The SEAC took the notice of objection raised by association of common bio
medical waste facility operators of U.P. in letter dated 21-03-2013 and objection raised
by Sangam Mediserve Pvt.Ltd. letter dated 21-03-2016. The SEAC after discussion has
decided that matter may be referred to UPPCB for seeking their opinion in this case in
light of CPCB guidelines on common bio medical waste facility. The SEAC also
recommended that advice from UPPCB may be obtained by directorate of Environment
within a week.
The matter shall be discussed after submission of information as above.
14- Sand/Morum Mining Project at Zone-16, Khand-18, Yanmuna River, Vill-
Yamunapur, Distt-Kaushambhi , U.P. (Leased Area-30.00 Acres) Sri Karan
Singh, Vill-Dasharathpur Sachwrara, Distt-Kayshambhi.File no- 2136
The SEAC noted that the Environmental Clearance in this case has already been
recommended therefore, the case is delisted.
Minutes of 275th
SEAC Meeting Date 17/06/2016
Page 25 of 28
15- Expansion of the Aakriti Shantiniketan Group Housing at GH-01B, Sector-
143B, Noida . Sri Manoj Kumar , MD , A-1, Ist Floor, Commercial Complex, F-
Block, Sector-Beta-2, Greater Noida. File no- 3276 OSD(T) File no- 3276
The committee noted that the project reports were not circulated to the SEAC members
and the report has been received on 18-06-2016. The project Proponent and consultant appear
before the SEAC and requested to make a presentation. The SEAC members decided to defer the
case to the next SEAC meeting scheduled on 20-06-2016. The Committee also directed to submit
all the documents as desired by today as requested by the project proponent.
16- Mega Leather Cluster located at Vill-Kuraina Bahadurnagar & Senpuirabpara
Near Ramaipur, Distt-Kanpur, U.P. File no- 2070 OSD(T)
Upon the request of the project proponent the case is deferred to next SEAC meeting
dated 18-06-2016.
17- Development of Samajwadi Purvanchal Expressway (Green field) from Village-
Chand Sarai on NH-56 (Lucknow-Sultanpur Road) till Kabirpur (Ghazipur-
Balia Road) on NH-19. File No. 3696
The committee noted that the application for environmental clearance for development of
Samajwadi Purvanchal Expressway (Green field) from Village-Chand Sarai on NH-56
(Lucknow-Sultanpur Road) till Kabirpur (Ghazipur-Balia Road) on NH-19 was submitted on
07/06/2016. The Expressway will traverse via Lucknow, Barabanki, Amethi, Sultanpur,
Ambedkar Nagar, Faizabad, Azamgarh, Mau and Ghazipur. The Expressway is proposed to be
linked with Azamgarh-Varanasi road through a link expressway.
A presentation was made by Shri Vishwa Deepak, Chief Engineer, U.P. Expressways
Industrial Development Authority representative of the project proponent along with their
consultant M/s IIDC Ltd. The case was considered in SEAC meeting on the basis of form-1, 1A
and pre-feasibility report. The proponent, through the documents submitted and the presentation
made, informed the committee that:-
1. The environmental clearance is sought for Samajwadi Purvanchal Expressway (Green
Field) from Village-Chand Sarai on NH-56 (Lucknow-Sultanpur Road) till Kabirpur
(Ghazipur-Balia Road) on NH-19, M/s U.P. Expressways Industrial Development
Authority.
2. Proposed project Corridor start from Chand Sarai District Lucknow (Km -0.456) to
Kabirpur District Ghazipur (Km 340.500) with Varanasi Link (Km 0.000 to Km 12.450)
3. Provide fast and direct connectivity between Lucknow and nine districts of agriculturally
important rural hinterland areas of eastern Uttar Pradesh, where it meets the junction of
NH-19 at Ghazipur. This expressway will also be linked to Varanasi by a 4-lane wide
access controlled link road.
4. Seamless connectivity of the proposed Expressway to the Agra-Lucknow Expressway
and on to the Yamuna Expressway would link the rural hinterland of eastern Uttar
Pradesh to the cities of Lucknow, Agra and Delhi National Capital Region.
Minutes of 275th
SEAC Meeting Date 17/06/2016
Page 26 of 28
5. The proposed Access Controlled Expressway Corridor traverses through nine districts
i.e. Lucknow, Barabanki, Amethi, Faizabad, Sultanpur, Ambedkar Nagar, Azamgarh,
Mau and Ghazipur of Uttar Pradesh State. 410 villages are likely to be affected by the
proposed corridor. Approximately 4250 Ha. of land is proposed to be used for the
proposed expressway
6. This Expressway will lead to economic development of rural areas of Uttar Pradesh by
way of their faster linkages to the vast consumer markets. Proposed carriageway is 6-
Lane Expressway (expandable to 8-Lane) with 8-Lane Structures. The Right of Way of
the proposed Expressway is 120 metres .
7. Minimal Impact on the flora and fauna. Six lane carriageway with 22.5 m wide Central
Median to accommodate future expansion. 120 m wide land will be acquired for the
expressway Way-side amenity in each of the 8 Packages will be provided for the
convenience of commuters. Provision of Air Strip near Azamgarh which can use by
Airforce in emergency situations.
8. Technical Salient Features:
• Starting Chainage : 0.456 Km.
• Latitude : 260 77’ N
• Longitude : 810 07’ E
• End Chainage : 340.500 Km.
• End Latitude : 250 98’ N
• End Longitude : 830 07’ E
• Length : 340.956 Km
• Districts : 9 nos.
• ROW : 120m
• No. of Interchange : 7 nos.
• Flyover : 14 nos.
• Estimated no. of VUP : 36 nos.
• Estimated no. of LVU : 112 nos.
• Estimated no. of PUP : 29 nos.
• ROB : 7 nos.
• Major Bridges : 7 nos.
• Minor Bridges : 110 nos.
9. The proposed project is covered under category 7 "f "of EIA Notification, 2006 (as
amended).
The committee discussed the matter and recommended following additional ToRs along
with the TOR prescribed by the MoEF for conducting EIA regarding the project:
Additional ToRs:
1. Provided the land details with acquisition status.
2. Details of water consumption, treatment and water quality to the provided to work out.
Minutes of 275th
SEAC Meeting Date 17/06/2016
Page 27 of 28
3. Explore the possibility for treated water for contraction.
4. Top soil management details.
5. For soil excavation areas below 5 ha permission from DEIAA to be taken.
6. Tree cutting permission.
7. Bitumen layer to be provided on road.
8. Mobile bio toilets to be provided.
9. Use of the plastic waste in road construction as per MoEF guild line.
10. Tree is to be provided on the both side of the road. Number of the trees to be worked out.
11. Both side drain to be connected to RWH structures.
12. Air Quality monitoring stations to be provided at toll plaza.
13. Base line data for air quality monitoring water quality monitoring till 31-07-2016 to be
submitted.
14. The EIA should include the fly ash generating potential of the surrounding areas and
submit a plan for utilizing fly ash generation within 100 km of the project.
15. The EIA should have clear cut recommendations on resettlement and rehabilitation
options for the population effected.
16. The EIA should also address to the impacts of vehicular emissions and air quality and
river water quality and the aquatic life.
17. The prediction of impacts on water balance should also include the effects of compaction
on marginal bund overlaid by road traffic on the permeability of underlying sub soils and
the ground water flow to the river, if any.
18. The Wetlands in the study area should be suitably mapped. The report should examine
the impact of the proposed activities on wetlands.
19. The EIA should address to the environmental impacts of ancillary activities of projects
which are likely to come up such as garages, petrol pumps and motels etc.
20. The EIA should also address to the migratory paths of wild life.
21. The EIA should also address to all the phases (acquisition of land, preparation,
construction and operation) of the project while evaluating the impact on environment
and drawing up the management plan.
22. The report should try to analyze the impact of the project as a catalyst to development of
slums and other unorganized activities. The EMP should control this through well
defined land use provisions.
23. All sampling locations studied should be strictly mapped using digital mapping/GIS
techniques.
24. Water conservation, reduction in use and waste water management during construction.
25. Provision of housing, fuel, safe drinking water and sanitations for the contract labour.
26. The EIA should strictly follow the methods of monitoring and analysis, annexure-iv:
Guidance for assessment of representativeness and reliability base line environmental
attributes detailed under EIA manual, January, 2001 and other guidelines in the matter.
In addition to above, you are also required to include following information/studies in the
environment impact assessment report:
Minutes of 275th
SEAC Meeting Date 17/06/2016
Page 28 of 28
1. Details of borrow areas along with the coordinates and quantity to be extracted should be
mentioned.
2. Pre-feasibility report on the mining of soil/earth providing details of location, physical
features such as land use, water bodies etc. should also be provided.
3. Likely impact on environment due to proposed mining of soil/earth for the project.
4. Details of mining methodology/techniques proposed to be adopted in the borrow areas.
5. A copy of the approved mining plan from the State Government.
6. An NOC from the Gram Panchayat / Local body.
7. A separate chapter on the details on mining of soil/earth from borrows areas along with
the EMP to be included in the EIA Report.
(Dr. S.N. Singh)
Vice-Chairman, SEAC,UP
(Dr. S.C. Bramhchari)
Member, SEAC, UP
(Dr. D. C. Gupta)
Member, SEAC, UP
(Shri Bhawani Singh Khangarot)
Secretary, SEAC, UP