KSPC Newsletter Vol15 June09

download KSPC Newsletter Vol15 June09

of 12

Transcript of KSPC Newsletter Vol15 June09

  • 8/14/2019 KSPC Newsletter Vol15 June09

    1/121

    KSPC Achieves Another Major Milestone:THE STEAM DRUM LIFTING OF BOILER UNIT NO. 1

    epco SPC Power Corporation completed another major project milestone

    with the successful lifting of the steam drum of Boiler Unit No. 1 last May 29,

    2009. Top management officials of KSPC, Doosan Heavy Industries and its

    sub-contractors attended the ceremony held at the construction site.

    Before the drum lifting was performed, several preparations were done to make

    sure that the activity can proceed smoothly. First, the steel structure was

    completed and checked for its structural stability. This is one of the essential

    preparations to ensure that the steam drum is properly supported.

    The Steam Drum Lifting of

    EDITION NO. 15 June 20, 2009The Cebu CFBC Plant Chronicle

    KKKK

    Steam Drum Lifting of Boiler Unit No. 1

    (May 29, 2009)

  • 8/14/2019 KSPC Newsletter Vol15 June09

    2/122

    Steam Drum Lifting (cont.)

    econd, the steam drum fabrication was completed on time as earlierscheduled. Third, the steam drum underwent shop inspection tests to make

    sure that the drum is of reliable design and construction, and that this could

    withstand pressure during operations.

    Fourth, the steam drums packaging, transportation, handling and storage

    were carefully done to guarantee that there will be no damage to the parts.

    Fifth, the equipment used for the lifting was tested to make sure that this is

    capable of supporting the drum up to the specified height.

    After lifting the drum, pressure parts installation followed. These pressure

    parts included water and steam headers and furnace water walls, among

    others.

    KSPC and Doosan officials during the Ceremony(May 29, 2009)

    SSSS

  • 8/14/2019 KSPC Newsletter Vol15 June09

    3/123

    Coal Silo Shell Lifting of Boiler Unit No. 1

    fter the steam drum lifting, the coal silo shell lifting of Boiler Unit No. 1

    followed last June 5, 2009.

    The coal silo is one of components of the fuel feeding system. It provides

    temporary storage of crushed coal for continuous operation. The coal silo is

    composed of the top frame, shell, middle shell, cone and chute.

    Of these components, the coal shell is the only part fabricated at the

    construction site. The rest were fabricated at the contractors shops.

    Meanwhile, the two coal silo shells were lifted and installed in the boiler

    structure and then connected to the silo cone.

    Before the shells were lifted, the shell plate dimensions, diameter, welded

    connection and painting quality, among other parameters were inspected to

    make sure that the specification was properly followed.

    Coal Silo Lifting of Boiler Unit No. 1(June 5, 2009)

    AAAA

  • 8/14/2019 KSPC Newsletter Vol15 June09

    4/124

    Coal Silo Shell Lifting (cont.)

    Several preparations were also made before the coal silo shell lifting was

    conducted. The cone-chute-middle shell assembly was lifted first since it islocated below the shell. The top frame was also installed above the shell as

    part of the fabrication plan.

    Lifting the shell was not easy because the winds may cause the shell to

    abruptly swing and trigger the collision of the steel structure and the shell. If

    this happens, the shell and the steel structure may be damaged.

    The other works related to the fuel handling system are now proceeding as

    scheduled.

    The coal silo before it was lifted and installed in the boilerstructure (June 5, 2009)

  • 8/14/2019 KSPC Newsletter Vol15 June09

    5/125

    Shop Test for Steam Turbine

    he steam turbine is one of the most important equipment in the operation

    of the Cebu Power Plant. To make sure that all of its major parts will perform

    to its designed working condition, it is inspected and tested using the following

    methods: hydraulic pressure test, assembly inspection, over speed & dynamic

    balancing test, function test for actuators, ultrasonic inspection of generator

    rotor, and seat contact check for valves, among others.

    The inspection and test of Cebu Power Plants steam turbine was performed in

    Japan where it is manufactured. This was done in the presence of the supplier,

    representatives of Doosan and KSPC in accordance with the approved Shop

    Inspection Test Plan and EPC Contract.

    Prior to the activities, the Shop Test Procedures were submitted for KSPCs

    approval. This started last February 25, 2009 while the succeeding tests were

    done after each test had been carried out and had satisfactorily passed the

    criteria.

    Shop Test Inspection of KSPCs Steam Turbine in Japan

    TTTT

  • 8/14/2019 KSPC Newsletter Vol15 June09

    6/126

    Successful Completion of theChimney Concrete Shell

    or about a month of round-the-clock

    construction, the chimney concrete shell

    was successfully completed. The

    construction of the chimney shell using

    the modern slip forming technology

    started on May 4, 2009 and was finished

    on June 9, 2009 with the combined effort

    of a team of two dozen Korean and Filipino

    men led by a Hungarian. Blessed with a

    good weather, works on the reinforced

    concrete shell proceeded smoothly without

    any interruption.

    FFFF

    Cebu Power Plants 110-meter high Chimney(June 9, 2009)

  • 8/14/2019 KSPC Newsletter Vol15 June09

    7/127

    Completion of the ChimneyConcrete Shell (cont.)

    After the successful erection of the reinforced concrete shell, the final works ofthe main structure of the chimney will follow. This will include the

    construction of its duct opening, the inner lining, stairs and platforms, among

    others. Surely, the 110-meter high chimney will permanently change the

    skyline of Naga and will standout as the landmark of KSPCs Cebu Power Plant.

    Construction Progress of the Chimney

    May 29, 2009

    May 27, 2009

    May 14, 2009

    May 6, 2009

  • 8/14/2019 KSPC Newsletter Vol15 June09

    8/128

    Project Progress

    View of Turbine No. 1 Building Steel Structure Erection(June 18, 2009)

    Rebar and form works for Turbine No. 2 GeneratorPedestal (June 18, 2009)

  • 8/14/2019 KSPC Newsletter Vol15 June09

    9/129

    Project Progress

    On-going Fabrication of Coal Silo Shell of Boiler Unit No. 2(June 18, 2009)

    View of Boiler Unit No. 2 Building 3r Tier Steel StructureErection (June 18, 2009)

  • 8/14/2019 KSPC Newsletter Vol15 June09

    10/1210

    Project Progress

    Concrete Pouring Works for Circulating Water IntakeStructure (June 18, 2009)

    View of the Discharge Seal Pit after Concrete Pouring(June 18, 2009)

  • 8/14/2019 KSPC Newsletter Vol15 June09

    11/1211

    Project Progress

    Rebar and Form Works for Control Building 3r Floor(June 18, 2009)

    On-going Finishing Work for the Administration Building(June 18, 2009)

  • 8/14/2019 KSPC Newsletter Vol15 June09

    12/12

    PROJECT PROPONENT : KEPCO SPC Power Corporation (KSPC)

    CAPACITY : 100 MW x 2 Units

    PLANT TECHNOLOGY : CFBC (Circulating Fluidized Bed Combustion)

    LOCATION : Colon, City of Naga (20 Km from Cebu City)

    TARGET COMPLETION : Unit No. 1: February 2011; Unit No. 2: May 2011

    Project Information

    Contact us

    Mr. Bag Woon ChoiMs. Jasmin Suma-oy

    Tel. No. (032) 272 6290~91, 93Fax No. (032) 489 7010