Baker Rd. WWTP PPCP and MSP Update - Niagara Region...• Yuraima –Project Coordinator (copied on...

28
1 Niagara Region Baker Rd. WWTP PPCP & MSP Update October 22 nd , 2019 2:00 – 4:00 pm

Transcript of Baker Rd. WWTP PPCP and MSP Update - Niagara Region...• Yuraima –Project Coordinator (copied on...

  • 1

    Niagara Region

    Baker Rd. WWTP PPCP & MSP Update

    October 22nd, 2019

    2:00 – 4:00 pm

  • 2

    Presentation Overview

    1. Welcome & Introduction

    2. Project Overview

    3. Project Objectives

    4. Environmental Assessment

    5. Next Steps

  • 3

    Welcome & Introduction

  • 4

    Region Point of Contact

    • Ilija – project manager

    • Gillian – assistant project manager

    • Anastasia copied on all communications

    GMBP Point of Contact:

    • Julien – project manager

    • Bryan – technical lead & assistant

    • Yuraima – Project Coordinator (copied on

    all communications)

    • David - Advisor

    TSC

    • Bob (Grimsby)

    • Steve (West Lincoln)

    • Shawn (MECP)

  • 5

    Project Overview

  • 6

    Project Objectives

    Pollution Prevention and

    Control Plan

    &

    Master Plan

    Quantify Levels of Service

    Action Plan to Maintain and Improve Levels of Service

    Reduce or Eliminate Environmental Impacts at CSO and SSO Locations

    Facilitate Long Term Growth and Sustainability

    Reduce Inflow and Infiltration into the Wastewater System

  • 7

    Key Project Components

    Problem and Opportunity

    Data Collection and Review

    System Characterization

    Level of Service

    Growth

    Alternatives Solutions

    System Characterization

    Alternative Development and Review

    Capital Program Development

    80 Y Program Development

    Priority Areas

    Communications

    EA Communications Process

    Project Management & Meetings

  • 8

    Understanding of Systems

  • 9

  • 10

  • 11

  • 12

  • 13

    Key Issues

  • 14

    Target Levels of Service

    • Performance•F-5-5

    •Facility Capacity

    •Growth

    •Basement Flooding

    •I&I Reductions

    • Condition and Maintenance

    Main driver for upgrade needs

    •Different system condition and performance

    •Different project needs and outcomes

    •Potential for municipality based LoS

    •Target LoS will be a guideline for flexibility and resilience

    3 Municipalities & Region

    •Understand current system hydraulic performance, review areas of concern, set target levels of service

    •Review existing system condition and determine maintenance, staffing and resourcing strategies to maintain or improve LoS

    Approach

  • 15

    Growth Projections

    • Timing,

    • Scenarios,

    • Resiliency of project recommendations

    Availability and precision of growth will impact:

    • Next meeting dedicated to review growth in detail

    • Coordination and communication with Planning Staff

    • Leverage MSP growth scenarios and complete sensitivity analysis of ranges and densities

    • Develop capital plan project triggers in terms of development units instead of time/year

    • Potential oversizing for resiliency and flexibility

    Mitigation Strategy

  • 16

    Model

    •Updated and Consolidated Model

    •Support local and regional needs for PPCP

    Hydraulic Model Needs

    •3 models in different states

    •Data availability and maturity to update and calibrate

    •Flow monitoring

    •Network

    •Facilities

    •Smithville Community Master Plan

    Model Challenges

    •Follow Region MSP Model build guidelines

    •Dynamic Wet Weather flow Model

    •Separate workshop to review approach (TM#3 & TM#5)

    Approach

  • 17

    Pump Station Performance

  • 18

    Class Environmental Assessment

  • 19

    Key EA Communication Activities

    Communication & Consultation Plan

    • Stakeholder Contact List Development & Maintenance

    • Stakeholder Meetings

    • Internal Workshops

    • Class EA communication requirements

    • Website Updates

    Public Notices

    • Study Commencement

    • PIC’s

    • Study Completion

    Public Information Centers

    • PIC #1 – Problem & opportunities / background

    • PIC #2 – Constraints, strategy options, evaluation, preliminary recommendations

    Report & Documentation

  • 20

    PIC #1 Content & Timelines

    • Project Overview & Objectives

    • EA Process

    • Project Schedule

    • Baker Rd WWTP System Overview

    • Key Objectives

    • Problem & Opportunity Statement

    • Key Areas of Concern

    • Long List of Alternatives

    • Thanks & Contact Info

    Dec. 2019• Draft NOC

    Jan. 2020

    • Issue Notice of Commencement

    Feb - March 2020

    • Draft & Finalize PIC Boards

    April 2020• PIC #1

  • 21

    Project Schedule

  • 22

  • 23

    Confirm Deliverables

    If Flow Monitoring included in scope:

    • 2 months project delayed

    • $ 4,910 / site additional cost

    • Opportunities to leverage parallel

    Regional Flow Monitoring Program

    Benefits:

    • Fill data gaps

    • More representative baseline of existing

    system performance

  • 24

    Next Steps

  • 25

    Request for Information

  • 26

    Request for Information

    • Draw down testing

    • Recommended at all stations

    • Ilija to confirm which stations have been done in past two years and who will complete

    work if required

    • Combination of pumps to be considered to define operational vs install capacity

    • Lincoln CCTV data to be provided end of 2019

    • Different system have different GIS detail, will be identified in data gap analysis

  • 27

    Next Steps

    • Continue Collect and review of Background Information

    • TM#1 & TM#2

    • Background tech memo to identify available information

    • Recommendations for flow monitoring needs

    • Prepare Project Communication Plan

    Next Steps

  • 28

    Closing

    Thank You

    GM BluePlan Team

    David Watt – [email protected]

    Julien Bell – [email protected]

    Bryan Bortolon – [email protected]

    mailto:[email protected]:[email protected]:[email protected]

    Structure BookmarksSectFigure111

    Niagara RegionNiagara RegionNiagara RegionBaker Rd. WWTP PPCP & MSP Update

    October 22October 22October 22nd, 2019

    2:00 2:00 –4:00 pm

    FigureFigureFigureFigure

    SectArtifact222

    Presentation OverviewPresentation OverviewPresentation Overview

    1.1.1.1.1.Welcome & Introduction

    2.2.2.Project Overview

    3.3.3.Project Objectives

    4.4.4.Environmental Assessment

    5.5.5.5.Next Steps

    Figure

    SectFigure333

    Welcome & IntroductionWelcome & IntroductionWelcome & Introduction

    Figure

    SectFigure444

    Region Point of ContactRegion Point of ContactRegion Point of Contact

    ••••Ilija–project manager

    •••Gillian –assistant project manager

    •••Anastasia copied on all communications

    GMBP Point of Contact:GMBP Point of Contact:

    ••••Julien –project manager

    •••Bryan –technical lead & assistant

    •••Yuraima –Project Coordinator (copied on all communications)

    •••David -Advisor

    TSCTSCTSC

    ••••Bob (Grimsby)

    •••Steve (West Lincoln)

    •••Shawn (MECP)

    SectFigure555

    Project OverviewProject OverviewProject Overview

    Figure

    SectFigure666

    Project ObjectivesProject ObjectivesProject Objectives

    FigureSpanPollution Pollution Prevention and Control Plan

    & &

    Master PlanMaster Plan

    ArtifactFigureQuantify Levels of ServiceQuantify Levels of ServiceQuantify Levels of Service

    Action Plan to Maintain and Improve Action Plan to Maintain and Improve Action Plan to Maintain and Improve Levels of Service

    Reduce or Eliminate Environmental Impacts Reduce or Eliminate Environmental Impacts Reduce or Eliminate Environmental Impacts at CSO and SSO Locations

    FigureFacilitate Long Term Growth and SustainabilityFacilitate Long Term Growth and SustainabilityFacilitate Long Term Growth and Sustainability

    FigureFigureFigureFigureFigureReduce Inflow and Infiltration into the Reduce Inflow and Infiltration into the Reduce Inflow and Infiltration into the Wastewater System

    Figure

    SectFigure777

    Key Project ComponentsKey Project ComponentsKey Project Components

    DiagramFigureSpanProblem and Problem and Problem and Opportunity

    FigureSpanData Collection and ReviewData Collection and ReviewData Collection and Review

    FigureSpanSystem CharacterizationSystem CharacterizationSystem Characterization

    FigureSpanLevel of ServiceLevel of ServiceLevel of Service

    FigureSpanGrowthGrowthGrowth

    FigureSpanAlternatives SolutionsAlternatives SolutionsAlternatives Solutions

    FigureSpanSystem CharacterizationSystem CharacterizationSystem Characterization

    FigureSpanAlternativeAlternativeAlternativeDevelopment and Review

    FigureSpanCapital Program DevelopmentCapital Program DevelopmentCapital Program Development

    FigureSpan80 Y Program Development80 Y Program Development80 Y Program Development

    FigureSpanPriority AreasPriority AreasPriority Areas

    FigureSpanCommunicationsCommunicationsCommunications

    FigureSpanEA Communications EA Communications EA Communications Process

    FigureSpanProject Management & Project Management & Project Management & Meetings

    SectFigure888

    Understanding of SystemsUnderstanding of SystemsUnderstanding of Systems

    Figure

    SectArtifact999

    FigureFigure

    SectArtifact101010

    FigureFigure

    SectArtifact111111

    FigureFigure

    SectArtifact121212

    FigureFigure

    SectFigure131313

    Key IssuesKey IssuesKey Issues

    Figure

    SectFigure141414

    Target Levels of ServiceTarget Levels of ServiceTarget Levels of Service

    DiagramFigureSpanMain driver for upgrade needsMain driver for upgrade needs

    FigureSpan•••••Performance

    ••••F-5-5

    •••Facility Capacity

    •••Growth

    •••Basement Flooding

    •••I&I Reductions

    •••Condition and Maintenance

    FigureSpan3 Municipalities & Region3 Municipalities & Region

    FigureSpan•••••Different system condition and performance

    •••Different project needs and outcomes

    •••Potential for municipality based LoS

    •••Target LoSwill be a guideline for flexibility and resilience

    FigureSpanApproachApproach

    FigureSpan•••••Understand current system hydraulic performance, review areas of concern, set target levels of service

    •••Review existing system condition and determine maintenance, staffing and resourcing strategies to maintain or improve LoS

    SectFigure151515

    Growth ProjectionsGrowth ProjectionsGrowth Projections

    DiagramFigureSpanAvailability and precision of growth will impact:Availability and precision of growth will impact:

    FigureSpan•••••Timing,

    •••Scenarios,

    •••Resiliency of project recommendations

    FigureSpanMitigation StrategyMitigation Strategy

    FigureSpan•••••Next meeting dedicated to review growth in detail

    •••Coordination and communication with Planning Staff

    •••Leverage MSP growth scenarios and complete sensitivity analysis of ranges and densities

    •••Develop capital plan project triggers in terms of development units instead of time/year

    •••Potential oversizing for resiliency and flexibility

    SectFigure161616

    ModelModelModel

    DiagramFigureSpanHydraulic Model NeedsHydraulic Model Needs

    FigureSpan•••••Updated and Consolidated Model

    •••Support local and regional needs for PPCP

    FigureSpanModel ChallengesModel Challenges

    FigureSpan•••••3 models in different states

    •••Data availability and maturity to update and calibrate

    ••••Flow monitoring

    •••Network

    •••Facilities

    •••Smithville Community Master Plan

    FigureSpanApproachApproach

    FigureSpan•••••Follow Region MSP Model build guidelines

    •••Dynamic Wet Weather flow Model

    •••Separate workshop to review approach (TM#3 & TM#5)

    SectFigure171717

    Pump Station PerformancePump Station PerformancePump Station Performance

    FigureFigureFigure

    SectFigure181818

    Class Environmental AssessmentClass Environmental AssessmentClass Environmental Assessment

    Figure

    SectFigure191919

    Key EA Communication ActivitiesKey EA Communication ActivitiesKey EA Communication Activities

    Communication & Consultation PlanCommunication & Consultation PlanCommunication & Consultation Plan

    ••••Stakeholder Contact List Development & Maintenance

    •••Stakeholder Meetings

    •••Internal Workshops

    •••Class EA communication requirements

    •••Website Updates

    Public NoticesPublic Notices

    ••••Study Commencement

    •••PIC’s

    •••Study Completion

    Public Information CentersPublic Information Centers

    ••••PIC #1 –Problem & opportunities / background

    •••PIC #2 –Constraints, strategy options, evaluation, preliminary recommendations

    Report & Documentation Report & Documentation

    SectFigure202020

    PIC #1 Content & TimelinesPIC #1 Content & TimelinesPIC #1 Content & Timelines

    •••••Project Overview & Objectives

    •••EA Process

    •••Project Schedule

    •••Baker Rd WWTP System Overview

    •••Key Objectives

    •••Problem & Opportunity Statement

    •••Key Areas of Concern

    •••Long List of Alternatives

    •••Thanks & Contact Info

    DiagramArtifactSpanDec. 2019Dec. 2019

    FigureSpan•••••Draft NOC

    FigureSpanJan. 2020Jan. 2020

    FigureSpan•••••Issue Notice of Commencement

    FigureSpanFeb Feb -March 2020

    FigureSpan•••••Draft & Finalize PIC Boards

    FigureSpanApril 2020April 2020

    FigureSpan•••••PIC #1

    SectFigure212121

    Project ScheduleProject ScheduleProject Schedule

    Figure

    SectArtifact222222

    FigureFigureFigureFigure

    SectFigure232323

    Confirm DeliverablesConfirm DeliverablesConfirm Deliverables

    FigureIf Flow Monitoring included in scope:If Flow Monitoring included in scope:If Flow Monitoring included in scope:

    ••••2 months project delayed

    •••$ 4,910 / site additional cost

    •••Opportunities to leverage parallel Regional Flow Monitoring Program

    Benefits:Benefits:

    ••••Fill data gaps

    •••More representative baseline of existing system performance

    SectFigure242424

    Next StepsNext StepsNext Steps

    Figure

    SectFigure252525

    Request for InformationRequest for InformationRequest for Information

    Figure

    SectFigure262626

    Request for InformationRequest for InformationRequest for Information

    •••••Draw down testing

    ••••Recommended at all stations

    •••Ilijato confirm which stations have been done in past two years and who will complete work if required

    •••Combination of pumps to be considered to define operational vs install capacity

    •••Lincoln CCTV data to be provided end of 2019

    •••Different system have different GIS detail, will be identified in data gap analysis

    SectFigure272727

    Next StepsNext StepsNext Steps

    •••••Continue Collect and review of Background Information

    •••TM#1 & TM#2

    ••••Background tech memo to identify available information

    •••Recommendations for flow monitoring needs

    •••Prepare Project Communication Plan

    Next StepsNext StepsNext Steps

    Figure

    SectFigure282828

    ClosingClosingClosing

    Thank YouThank YouThank You

    GM BluePlan TeamGM BluePlan Team

    David Watt David Watt –[email protected]@gmblueplan.caSpan

    Julien Bell Julien Bell –[email protected]@gmblueplan.caSpan

    Bryan Bortolon Bryan Bortolon –[email protected]@gmblueplan.caSpan