Design in 1984.
Total cost 3.46$ billion
-
7/31/2019 46964240 History of Kalabagh Dam
2/13
Kalabagh Dam Project was designed in 1984,with the assistance of the United Nations
Development Program; supervised by theWorld Bank, for the client Water and PowerDevelopment Authority of Pakistan.
It was estimated to be US$ 3.46 Billion at June
1987 level and was scheduled to be completedin 6 years.
-
7/31/2019 46964240 History of Kalabagh Dam
3/13
Near Main Wali
Famous for Nawb of Kala Bahg
-
7/31/2019 46964240 History of Kalabagh Dam
4/13
Hydrology (Indus river at site)
Area 110500 square meter
Water storage capacity 7.9 MAF
Maximum height above river bed 260 feet
-
7/31/2019 46964240 History of Kalabagh Dam
5/13
Turbine frames types
Installed capacity 2400-3600 MW
-
7/31/2019 46964240 History of Kalabagh Dam
6/13
Providing additional storage to meet existingwater shortage.
Control of high flood
Irrigation to the river area in Sindh
-
7/31/2019 46964240 History of Kalabagh Dam
7/13
Producing hydro power for growing demandof agricultural, industrial and domestic needs
Producing employment for 30000 personsduring construction
-
7/31/2019 46964240 History of Kalabagh Dam
8/13
Drainage of surrounding area of Mardan
Area of Pabbi and Swabi plains would beaffected
Large number of people would be displaced
-
7/31/2019 46964240 History of Kalabagh Dam
9/13
-
7/31/2019 46964240 History of Kalabagh Dam
10/13
-
7/31/2019 46964240 History of Kalabagh Dam
11/13
-
7/31/2019 46964240 History of Kalabagh Dam
12/13
Physical Model of Dam
-
7/31/2019 46964240 History of Kalabagh Dam
13/13
Current Picture of Kala Bagh