1.0 Executive Summary2 2.0 Introduction · 3 2.0 Introduction 2.1 Purpose of Investigation The...
Transcript of 1.0 Executive Summary2 2.0 Introduction · 3 2.0 Introduction 2.1 Purpose of Investigation The...
1.0 Executive Summary .................................................................................................2 2.0 Introduction..............................................................................................................3
2.1 Purpose of Investigation.......................................................................................3 2.2 Project Location and Site Description .................................................................3 2.3 Limitations of Analysis........................................................................................4
3.0 Methodology ............................................................................................................5 3.1 Fluvial Geomorphology .......................................................................................5 3.2 Digital Data ..........................................................................................................6 3.3 Field Data.............................................................................................................6 3.4 Water Quality and Fisheries.................................................................................7 3.5 Soil Testing ..........................................................................................................7 3.6 Geotechnical Conditions......................................................................................7 3.7 Basemap and Planset............................................................................................7
4.0 Field Investigation Results.......................................................................................8 4.1 Fluvial Geomorphology .......................................................................................8 4.2 Riparian Zone Conditions..................................................................................10 4.3 Water Quality and Fisheries...............................................................................11 4.4 Soil Testing ........................................................................................................11
5.0 Performance Criteria ..............................................................................................12 5.1 Introduction........................................................................................................12 5.2 Flood Protection.................................................................................................12 5.3 Bank Stabilization..............................................................................................12 5.4 Impacts to Lake Michigan..................................................................................12 5.5 Fisheries Management .......................................................................................12 5.6 Floodplain Management ....................................................................................13 5.7 Hydrologic Conditions.......................................................................................13 5.8 Safety .................................................................................................................13 5.9 Maintenance.......................................................................................................13 5.10 Regulatory Requirements...................................................................................13
6.0 Alternative Analysis...............................................................................................14 6.1 Introduction........................................................................................................14 6.2 Alternative #1 - No Action.................................................................................14 6.3 Alternative #2 - Channel Elevation....................................................................14 6.4 Alternative #3 – Lowering Floodplain elevation ...............................................15
7.0 Selected Alternative Restoration Plan....................................................................15 7.1 Design and Construction....................................................................................15 7.2 Cost ....................................................................................................................23 7.3 Permitting issues ................................................................................................23 7.4 Construction limitations.....................................................................................24
8.0 Additional Funding ................................................................................................24 9.0 Schedule .................................................................................................................24 10.0 Glossary .................................................................................................................25
2
1.0 Executive Summary This report details the assessment of Centerville Creek and outlines a plan for restoring the
creek to a natural condit ion. A basic fluvial geomorphic assessment of Centerville Creek and
regional streams was used with elementary hydraulic analysis to estimate stable stream
planform and cross section geometry under restoration condit ions. Existing water quality,
fisheries and land use spatial data were incorporated to give a complete picture of the
watershed and to assess the potential for restoration. A cost estimate of the restoration plan is
provided, and alternatives for funding are discussed.
The Centerville Creek Dam was removed by the Wisconsin Department of Natural Resources
(WDNR) in 1998. Sediment that accumulated behind the dam during its design life was not
excavated at the t ime of dam removal. This has resulted in an incised channel with steep
eroding banks and degraded in-stream and riparian habitat. The eroded sediment is
transported directly into Lake Michigan. The restoration alternative proposed by Inter-Fluve
Inc. involves the removal of large amounts of accumulated sediment behind the former dam
site and stabilization of the stream channel using bioengineering methods. The proposed
floodplain restoration will return the impoundment area to a forested riparian condit ion,
reducing sediment load to Lake Michigan, improving fish habitat and increasing recreational
opportunit ies.
3
2.0 Introduction
2.1 Purpose of Investigation
The Village of Cleveland, under a River Planning and Protection Grant from the Wisconsin
Department of Natural Resources, contracted Inter-Fluve Inc. to investigate possible
restoration alternatives for Centerville Creek. This report was prepared to assist the Village of
Cleveland in the restoration process and to identify potential funding sources.
The parameters involved in restoring Centerville Creek in the former impoundment area was
evaluated with regard to three primary factors: spatial (stream channel dimensions);
geomorphic (ensuring proper channel grade, sinuosity, and stability); and habitat (improving
condit ions for fish and wildlife). Provided funding for full restoration is obtained in the
future, this assessment provides valuable information that can be used in developing Final
Design plans for the restoration of Centerville Creek.
2.2 Project Location and Site Description
Centerville Creek drains directly into Lake Michigan approximately 1.2 miles east of
Cleveland, Wisconsin. The former dam site is located 600 feet upstream of Lake Michigan
and the impoundment is approximately 1500 feet long and averages 120 feet wide,
encompassing an area of approximately 7 acres (see Figure 1). The original Centerville Dam
was built sometime prior to 1895 and a larger concrete structure was built in 1935 (Appendix
A). A 1988 inspection of the dam revealed structural deterioration and after subsequent
inspections, the WDNR ordered the dam to be repaired or removed. The dam remained in
place until 1998, when the WDNR removed the dam. Impoundment sediment depths remain
as much as 10 feet, and the stream has incised through the sediments to the former valley
floor.
The project area is defined by steep bluffs that confine the former valley. Lincoln Avenue
borders south side of the downstream end of the project site, and residential homes are
common along the northern bluff above the impoundment. The Centerville Creek restoration
site is free of structures such as home sites, bridges and other infrastructure. A bridge is
located approximately 300 feet downstream of the former dam site but presents no grade
control or other problems.
4
2.3 Limitations of Analysis
This report is designed to provide conceptual design plans and a preliminary cost estimate for
restoration and should not be used for any construction activity. Final design plans will
require detailed hydraulic analysis, flow modeling and detailed engineering specifications.
This assessment does provide an excellent start ing point for restoration, and addresses many
of the issues surrounding stream restoration activit ies.
In addit ion, this report is based on site condit ions for September of 2001, and any Final
Design for restoration should incorporate changing land use and site.
Survey data was collected in August of 2001 and thick vegetation prevented adequate
surveying of the upper reaches of the impoundment and of the slopes around the outside of
the impoundment. However, some areas were surveyed and assumptions are made based on
these measurements. These bluff slope areas are not crit ical to the concept design phase of the
project, but addit ional surveying may be required for Final Design to further define project
limits and construction access.
5
3.0 Methodology
3.1 Fluvial Geomorphology
Stable stream systems are in a delicate balance between the processes of erosion and
deposit ion. Streams are continually moving sediment eroded from the bed and banks, and
some of this material is deposited in the form of bars on the inside of meander bends. The
process by which streams meander slowly within the confines of a floodplain is called
‘dynamic equilibrium’ and refers mainly to this balance of sediment erosion and deposit ion.
Many factors can influence this equilibrium, including vegetation that holds soil in place,
flashy flows that erode banks, and increased sediment pollut ion that deposits in the channel.
Once a stream channel is in equilibrium, it may move across the floodplain, but several
parameters remain relatively constant over t ime. Included among these are the average stream
depth, stream width, belt width (generally the same as floodplain width), the meander
wavelength (distance between bends) and the radius of curvature (the radius of a circle
superimposed on a meander bend). Figure 2 gives a diagram of each of these measurements.
Understanding these parameters and their relationship to each other is the first step in creating
a stable stream restoration project.
The fluvial geomorphic assessment of Centerville Creek involved establishing several
reference streams draining into Lake Michigan between Kewaunee and Cedar Grove, WI.
These streams were used to obtain regional information regarding channel dimensions,
planform geometry, riparian condit ion and stability. These reference streams were chosen
based on the following criteria:
o Direct drainage to Lake Superior
o Perennial flow
o Proximity to Centerville Creek
o Watershed under 30 square miles
o Agricultural land use 50% or more
o Urban land use 20% or less
o Similar drainage pattern
Digital information was obtained from existing data, and field information was also collected.
Based on the data collected, statist ical equations were developed to better predict channel
cross-section and planform dimensions such as bankfull width, mean bankfull depth, meander
length and radius of curvature.
6
3.2 Digital Data
Digital Orthophotographic Quadrangles (DOQ) for Manitowoc and Sheboygan Counties were
obtained from the United States Geological Survey (USGS) and from the Bay-Lake Regional
Planning Commission. USGS topographic quadrangle maps were obtained from the Map
Store (Milwaukee, WI). DOQ information was incorporated into ArcView Geographic
Information Systems (GIS) software for manipulation.
Reference streams – Aerial photography was examined for each of the reference streams.
This analysis yielded meander wavelength, radius of curvature, belt width, riparian cover,
land use, watershed area, sinuosity and meander patterns.
3.3 Field Data
3.3.1 Survey
A topographic survey of the entire impoundment area was completed by Inter-Fluve Inc. and
Robert E. Lee and Associates (Green Bay, WI). Global Posit ioning System survey equipment
was used to establish true elevations and a total station survey level was used to map
individual survey points. Approximately 1200 data points were surveyed to create a 1-foot
interval contour map of exist ing condit ions (Figure 3). Horizontal datum was obtained
through the Manitowoc County Coordinate System and vert ical datum was obtained with
North American Vertical Datum (NAVD) 88. A base map was created using AutoCAD v.14.
3.3.2 Reconnaissance (Coastal streams)
Field geomorphic data was collected for each of the reference streams and for Centerville
Creek. Parameters measured include bankfull width, mean depth, width of the floodplain and
channel substrate size gradation. General observations were made regarding vegetative cover,
erosion potential, and fish habitat quality. Observations were also made to determine overall
channel stability. This process involves determining channel forming flow elevations from
indicators such as woody vegetation growth, sediment deposit ion, watermarks and bank
slope.
Planform geometry patterns were measured in the field for both the north and south branch of
Centerville Creek upstream of the confluence.
7
3.3.3 Geologic controls
To determine the extent of channel incision into the impounded sediment, and to measure the
depth of sediment deposit ion in the channel, the vert ical distance to apparent historic bed was
measured. Depth of sediment deposit ion was estimated by measuring the depth of refusal
using a #4 iron rebar T-post.
Composit ion of impoundment sediments was measured by visual observation of erosion
patterns, color and texture. Shovel samples were taken for close inspection.
3.4 Water Quality and Fisheries
As a part of the restoration plan, WDNR Fisheries biologists completed the Wisconsin DNR
Wadeable Stream Survey Protocol on Centerville Creek in August of 2001. Three reaches
were surveyed, one on the main stem and one on each of the two branches upstream of the
impoundment area. The Wadeable Streams Protocol uses an Index of Biotic Integrity (IBI) to
evaluate stream health based on the relative abundance of certain fish species. The IBI
concept assumes a score for fish species based on each species’ tolerance to pollutants. The
total score for a stream reflects the overall water quality of the system.
3.5 Soil Testing
According to Wisconsin Statutes NR347 regulating sediment sampling and analysis,
monitoring protocol and disposal criteria for dredging projects, some analysis of accumulated
sediment may be necessary. The State Solid Waste Disposal Engineer and the local WDNR
Water Management Specialist were contacted regarding the Centerville Creek Restoration.
The Centerville Dam sediments are considered non-hazardous due to the agricultural nature
of the watershed. Further soil testing will be required prior to disposal to determine proper
disposal site methodology. This testing will be completed in accordance with WDNR
requirements.
3.6 Geotechnical Conditions
A preliminary boring program has been developed.
3.7 Basemap and Planset
Conceptual drawings were completed for the proposed restoration site using ArcView and
AutoCAD 2000.
8
4.0 Field Investigation Results
4.1 Fluvial Geomorphology
4.1.1 Former dam site and grade control
Portions of the dam structure still remain in place and may be providing some grade control
throughout the project area (Figure 4). Removal of this port ion of the dam may require
replacement with a grade control structure. Typical grade control structures are made of
natural rock and traverse the entire width of the floodplain, however only the port ion in
contact with the active channel bed would be visible as a rock riffle. See section 5.1.4 for
further details.
4.1.2 Incision and erosion
The stream has incised through the sediments and appears to be reaching vert ical equilibrium.
Reconnaissance surveys show armored sections of gravel throughout the main channel area,
suggesting a cessation of vert ical migration. Both the north and south branch tributaries show
active nickpoints (Figure 5), but these are cutt ing into extremely hard, cohesive clay lenses,
again suggesting that the stream has reached its natural bed elevation. Point Creek, Fischer
Creek and the upstream reaches of Centerville Creek all show stable, cohesive clay
streambeds with some gravel bar and riffle formation.
The entire project area has extremely high vert ical banks from five to 10 feet in height
(Figure 6). Because of their sheer drop and the abundance of tall grasses, these banks
represent a significant safety hazard. Spring sources have created deeply incised small
gullies, some as much as 4 feet deep and completely obscured by vegetation, creating a
trapping hazard. Floodplain excavation as called for in this restoration plan will eliminate
these problems.
Having established a vert ical boundary, the stream has begun eroding laterally to establish a
stable slope. This process will continue until the stream has established enough sinuosity to
create a stable equilibrium. Unless the stream is restored, the high sediment input from
eroding banks will continue to fill the channel bottom with fine silt and clay, and excess
sediment will continue to pollute Lake Michigan for many years.
4.1.3 Fish habitat
The main channel of Centerville Creek contains very litt le fish habitat. Some large woody
debris has drifted down from upstream or fallen from the eroding banks and has created scour
9
pools with less than 2 feet of residual depth. Sedimentation of pools is preventing deep pool
habitat from forming, and most gravels have a high degree of sedimentation.
No overhanging bank cover exists in the form of undercut banks, as large areas of mass
wasting and slumps prevent any undercuts from forming. No woody vegetation is present and
so there is litt le in the way of stream shading apart from that provided by the high vert ical
banks.
4.1.4 Stream classification and channel evolution
Currently, the main channel and lower port ions of the two branches of Centerville Creek are
designated as G5 under the Rosgen stream classification system. Highly unstable, incised,
steeply eroding banks, no floodplain and sand dominated substrate characterize this stream
type. As the banks erode laterally and the bed elevation rises to create a new floodplain, this
stream would move toward an F5 stream type. Under the Schumm channel evolution model,
Centerville Creek represents a Stage II channel progressing to a Stage III. This classification
demonstrates that the init ial incision is nearly complete and that the channel is now beginning
to erode horizontally.
4.1.5 Floodplain function
A major factor in the physics of erosive processes is the depth of water, which relates directly
to the weight or force of the water on an eroding bank. Floodplains dissipate the energy of
large rainfall events by spreading the stream flow out over large areas, thereby decreasing the
stress on any part icular section of stream channel. These floodplains also serve as nurseries
for riparian vegetation and provide crit ical wildlife habitat and green corridors between
adjacent river systems.
The main stem of Centerville Creek has incised to the point where the stream is now
completely cut off from its floodplain. This is misleading in this case since the actual historic
floodplain is buried under several feet of deposited sediment. Large flood events are
completely contained within the canyon-like walls of the stream, thereby increasing the
forces that cause erosion.
4.1.6 Channel grade, length and sinuosity
According to exist ing survey data, the average grade of the valley from the confluence of the
north and south branches to the dam site is 0.0062 (0.62 %). The channel slope in this reach is
0.0056 (0.56 %). The total stream length from the confluence to the dam site is 1280 ft. The
10
south branch surveyed in the impoundment area has a thalweg, or mid-channel length of 260
ft, while the north branch section has a length of 470 ft.
Sinuosity is the ratio of channel, or thalweg, length to valley length. Sinuosity for the main
channel is 1.12. Based on data obtained from regional reference streams, this low value
represents lateral instability. Regional streams of similar drainage area demonstrate sinuosity
in the range of 1.8 to 2.5.
4.1.7 Regional streams
Reconnaissance of reference streams revealed 13 streams that fit the proposed criteria for
inclusion in the regional regression data set. Sandy Bay Creek, Litt le Sandy Bay Creek, Two
Creeks South, Molash Creek, Silver Creek, Calvin Creek, Pine Creek, Point Creek, Fisher
Creek, Centerville Creek, Centerville Tributary, the Black River, and Barr Creek were
included in the data analysis. Using regression analysis of regional condit ions, the suggested
channel dimensions for the main stem restoration are a bankfull width of 17 feet with a mean
depth of 1.7 feet. Predictions of planform geometry for the restored stream suggest an
average meander wavelength of 120 feet with an average bend radius of 38 feet. Appendix B
shows the distribution of values in a regional regression curve.
Upstream of the impoundment area, both branches show signs of increased channel incision.
Current stream condit ions show bankfull or channel forming flow depths approximately one
foot deeper than some abandoned channel fragments. Centerville Creek upstream of the
impoundment and some of the reference streams show a box-like channel with relatively few
deposit ional bar features. Active erosion can be seen throughout these systems, and it is likely
that these streams may have stabilized to accommodate the higher peak flows typical of
agricultural streams in the Midwest. The stable stream is now deeper and wider than historic
channels. As the watershed develops, increased urbanization will cause changes to the local
hydrology. Final design plans should incorporate development effects on hydrology, and
appropriate measures should be taken to prevent project failure.
4.2 Riparian Zone Condit ions
4.2.1 Vegetative cover
Vegetation in the riparian zone and floodplain of the main stem currently consists mainly of
aggressive exotic species including reed canarygrass (Phalaris arundinacea) and giant reed
grass (Phragmites australis), two highly aggressive and nuisance exotic grass species. The
area also has significant populations of cattail (Typha latifolia) and stinging nett le (Urtica
11
dioica), two species common to disturbed areas. No woody vegetation currently exists and
there are no bank stabilizing shrubs such as willow or dogwood.
The upstream areas of the south and north branches of Centerville Creek show overstory and
understory vegetation typical of streams in this area. The South branch tributary is dominated
by large trees, principally white cedar (Thuja occidentalis), basswood (Tilia americana), and
black willow (Salix nigra), which form a nearly complete canopy. Because of the thick
canopy in this reach, very litt le understory shrub species are present. The north branch of
Centerville Creek upstream of the impoundment also contains some white cedar, but the
riparian zone is dominated by large black willow of moderate density, result ing in canopy
coverage of approximately 75%. The floodplain in this area is dominated by young sugar
maple (Acer saccharum) and basswood, while the upper terraces are populated mainly by
paper birch (Betula papyrifera). Understory shrubs are common in the north branch
floodplain and near bank areas, and consist mainly of gray dogwood (Cornus foemina), box-
elder (Acer negunda) and red osier dogwood (Cornus stolinifera).
4.3 Water Quality and Fisheries
The Wisconsin DNR survey of fish and habitat in the Centerville Creek system shows a
degraded stream with water quality problems (Appendix C). In the main stem, 323
individuals from 16 different taxa were captured with a final IBI score of 35, indicating fair
water quality. Site 2 on the south branch yielded 36 fish from 4 different taxa, indicating poor
water quality. Site 3 on the north branch yielded 44 fish from 5 different taxa, indicating very
poor water quality. It should be noted, however, that the IBI is based on a total of at least 100
fish captured per sample. Because fewer than 100 fish were captured in sites 2 and 3,
conclusions based on these results should be made with caution. Regardless, it appears that
water quality upstream of the impoundment area is poor. To assist in long-term management,
further water quality data should be collected to determine actual amounts of pollutants.
Although this project focuses on restoring habitat in the impoundment area, an effort should
be made to address watershed-scale problems that effect water quality. Some of these issues
include water quality, runoff volumes and discharge rates. All restoration projects should
consider these large-scale influences on water quality, hydrology and fisheries.
4.4 Soil Testing
Results of soil testing are pending further core sampling.
12
5.0 Performance Criteria
5.1 Introduction
The following criteria outline the level of performance desired for various elements within an
acceptable level or risk. These criteria st ipulate general requirements for design elements such as
bank erosion protection, type and amount of fish habitat or densit ies for vegetation.
5.2 Flood Protection
This project have no adverse impact on the flood damage potential for the areas upstream, within
or downstream of the project area.
5.3 Bank Stabilization
Dynamic equilibrium describes the migration of stream channels through cutt ing or erosion on
outer banks and the deposit ion of eroded material on inside meander bends, or point bars. Streams
migrate over t ime (years to decades), but have lateral stability over shorter temporal spacing
(months to years). Lateral stability is accomplished through resistance to erosion and proper
planform geometry. Natural channel design incorporates bioengineering methods and fluvial
geomorphology analysis to impart init ial stability until bank-stabilizing vegetation can fully
establish. This method designs deformable banks that allow for minor changes in planform and
bank shape, but retains overall lateral stability.
Design elements for erosion protection including biodegradable blankets, stakes and the
associated design methods will protect the banks, bed and floodplain over the short-term until
vegetation becomes established. Native grasses, shrubs and trees will provide long-term erosion
protection and channel stability. The preferred design alternative presented here provides stable
channel morphology up to the 100-year flood event.
5.4 Impacts to Lake Michigan
Because of the proposed bank restoration and stabilization, this project will reduce non-point
source sediment loading to Lake Michigan. This project will have no effect on Lake Michigan
water levels.
5.5 Fisheries Management
In-stream habitat structures, bank cover and vegetation will provide adequate cover based on all
life stages of smallmouth bass (Micropterus dolomieu), northern pike (Esox lucius), and
13
migratory Lake Michigan salmonids. Spawning size gravel wil l be incorporated into design
where possible.
5.6 Floodplain Management
The majority of the project area will remain in public ownership and will be managed as wild
riparian land and floodplain forest. The Village of Cleveland will pursue options for landowners
such as conservation easements and land trust donations.
Recreational use will be limited to passive use, with a single non-paved walking trail on either the
southern or northern edge of the newly constructed floodplain.
5.7 Hydrologic Conditions
Preliminary project design is based on exist ing hydrologic condit ions. Final design components
will consider future hydrologic condit ions based on the Village of Cleveland Comprehensive
Plan. Stormwater management by the Village of Cleveland will consider project success criteria
in planning future watershed developments.
5.8 Safety
Grading of the floodplain and lowering streambank height will reduce the risk of injury from
falling.
5.9 Maintenance
Maintenance of floodplain and riparian vegetation will be limited to watering and replanting
where necessary. Once native vegetation has become established in approximately 5 years,
further vegetation maintenance will not be required.
Minor repair and maintenance of structural impacts may be necessary until vegetation is
established. Further maintenance following >100 year flood events may also be necessary.
5.10 Regulatory Requirements
This project requires adherence to permit condit ions for permits according to Wisconsin State
Statutes 30.12 (placement of structures), 30.19 (grading in excess of 10,000 square feet, and
30.195 (realignment of a navigable waterway). The Wisconsin DNR will complete any
Environmental Assessment deemed necessary.
This project also requires adherence to Army Corps of Engineers General Permit GP-001-WI for
specified activit ies permitted, authorized or approved by the Wisconsin DNR.
14
Disposal of impounded sediments is subject to permitt ing under Wisconsin Administrative Code
289.43(8) covering disposal of low-hazard waste.
6.0 Alternative Analysis
6.1 Introduction
A preliminary alternative analysis was performed as part of the concept design process. Three
approaches were reviewed.
6.2 Alternative #1 - No Action
The implications of no action were considered. Lateral migration of Centerville Creek will
eventually scour out the floodplain and become a stable system that is reflective of its
geomorphic influences. However, this process will require a long t ime period for recovery.
Exactly how long this recovery will take is unkown, but it is reasonable to assume that full
geomorphic recovery will take several decades and vegetative recovery will take a century or
more. The implications of no action are as follows:
� Continued excessive sediment release to Lake Michigan
� Continued safety concerns associated with the incised channel
� Limited recreational use
� Limited aesthetic value
� Limited fishing opportunit ies
� Limited fishery potential for the upstream reaches
Based upon these considerations, the no action or “do-nothing” alternative was rejected.
6.3 Alternative #2 - Channel Elevation
The second alternative examined was raising the channel bed elevation to reduce bank height and
restore floodplain function. This would include the construction of mult iple grade control
structures across the valley width to provide a vert ical transit ion between the channel invert
downstream of the dam and the channel invert upstream of the dam’s influence.
In effect this method would require constructing the historical grade control (dam) with mult iple
smaller grade control structures. These structures can be made of large rock material and
designed to allow fish passage. A detailed cost estimate was not prepared for this alternative, but
the construction cost would be significantly less than lowering the floodplain elevation.
15
However, construction of this type of system would not allow future lateral or vert ical migrations
that occur naturally and are an important part of functional riverine corridors. Raising the channel
invert would give the appearance of a restored corridor but would not create a fully functioning
riverine system. In addit ion, these grade control structures would require future maintenance
effort and expense. Based on these considerations, this alternative was rejected.
6.4 Alternative #3 – Lowering Floodplain elevation
The third alternative involves the excavation of the impounded sediments and restoration of the
channel. Interfluve Inc. believes that this plan mimics more closely the original, pre-dam stream
condit ion and also represents the most geomorphically stable and environmentally sound
restoration. This plan is the most expensive of the three alternatives, but this alternative
eliminates sediment pollut ion, restores fish habitat and riparian function, allows for natural
channel processes and provides aesthetic value. Based on these considerations, floodplain
excavation and restoration is the selected alternative and is detailed in Section 7.0 below.
7.0 Selected Alternative Restoration Plan
7.1 Design and Construction
Interfluve Inc. recommends a plan based on floodplain establishment and removal of
impoundment sediment. This restoration plan calls for the excavation of approximately
30,000 cubic yards of accumulated sediment from the impoundment area, establishment of a
functioning floodplain and a stable stream channel with complex habitat features. The
following paragraphs address potential issues and make recommendations for the Final
Design phase of the project.
This preliminary design report is based on current development condit ions. Future land use
will play an important role in determining the evolution of the Centerville Creek stream
channel, and attention should be paid to the effect of development in the watershed.
7.1.1 Floodplain restoration
Upon excavation of the bulk of accumulated sediment, a floodplain will be established. The
stream will maintain an average bank height of 2.0 feet with a floodplain width averaging 100
feet. The planting plan for floodplain forest restoration is based on plant species data
collected and outlined in Section 5.1.6. The constructed floodplain will slope up away from
16
the stream banks at a 2% slope to ensure proper drainage and to minimize shear stress on the
floodplain surface. In some areas plateaus 1-2 foot in height will be established to further
minimize shear stress on the floodplain surface and thus prevent eroded pockets and chutes
from forming. Erosion control of floodplain areas should include stabilization with erosion
control fabric that is t ied into bank stabilization measures. Figure 7 shows the general concept
of floodplain excavation.
Floodplain borders will slope up from the floodplain to the terrace walls at an approximate
3:1 slope where possible. In some areas where there are geologic restraints, slopes may
approach a 2:1 grade. These slopes will follow the floodplain erosion control and planting
plans.
7.1.1.1 Disposal of floodplain sediments
The Wisconsin DNR has stated that the sediments accumulated upstream of the Centerville
Creek dam are not to be considered hazardous, and can therefore be disposed of using
methods and permitt ing for non-hazardous dredged material. The disposal procedure outlined
below assumes non-hazardous waste. Disposal of more than 3,000 cubic yards of sediment in
any one location will require the Village of Cleveland or its contractor to submit a request for
a grant of exemption from solid waste regulations for a low hazard waste. The WDNR will
review the proposed disposal site as well as contaminant concentrations of the sediments. The
WDNR is required to hold a public meeting to solicit comments before making a decision on
permitt ing. The application for the Grant of Exemption should be submitted well in advance
of the project start date so that the project is not delayed.
In general, the process to request a grant of exemption includes the following:
A letter requesting an init ial site inspection (ISI) of the proposed disposal site. ISI submittal
requirements:
o Cover letter identifying the owner, location, and present land use
o Letter from DNR Bureau of Endangered Resources identifying any crit ical habitat areas
o Letter from State Archeology Office identifying the presence of any historical areas
o An enlarged 7.5 minute USGS map showing relief, surface waters, floodplains, exist ing land use condit ions and all water supply wells and residences within 1200 ft of the disposal site.
o Any potential conflicts with wetlands, crit ical habitat, surface water, or groundwater
17
A proposal requesting a Grant of Exemption for low hazard waste under Wisconsin Statutes
s. 289.43(8) for disposal of dredged sediments. There is a $500 plan review fee for this
submittal that may be waived in the event that the State or the WDNR provides part ial
funding for the project. The proposal should include the following:
o Name, address, and telephone number of the owner and consultant
o Total acreage of property and disposal site.
o Life of disposal site, capacity, types and sources of sediments
o Depth to groundwater
o Boring logs identifying USCS classification of major soil units encountered at the
disposal site. Analysis of USCS grain size distribution
o Proposed operation of the disposal site (hours of operation, etc.) The disposal site
must be operated, maintained and closed in a nuisance free manner. The WDNR may
require that the site be closed from view to residences within ¼ mile.
o Restricted access to site through use of gate (required) and fencing or equivalent
o Stormwater/runoff considerations.
o Results of sediment analyses. This would require that the collection of representative
core samples of the proposed dredge site and have them analyzed for the RCRA
metals (arsenic, barium, cadmium, lead, mercury, and selenium), pesticides, and
PCBs.
o Closure plan. This plan details coverage of the site, and the WDNR may require that
the site be final graded, seeded, fert ilized and mulched. Under the right
circumstances, this would be the responsibility of the contractor.
7.1.2 Channel restoration
Stable natural channel design requires design based on a mult iple step, iterative process. The
first step in this process is the determination of the design discharge based on either hydraulic
modeling such as HEC-RAS or XPSWMM or empirical or analytical data analysis. Interfluve
Inc. recommends the use of exist ing regional hydrology information and analog reaches to
determine design discharge based on parameters such as watershed area. Regional data
collected in this investigation is likely more accurate than any hydraulic model in this case.
Sandy Bay Creek, Calvin Creek and some portions of Fisher Creek and Centerville Creek
18
were determined to be relatively undisturbed and will serve as models for designing the
riparian zone and in-stream restoration (Figure 8). These streams were characterized by thick
canopy coverage, excellent large woody debris distribution, deep pool habitat, clean gravel
riffles and overhanging vegetative cover, all desirable attributes for fish and wildlife habitat.
Also common to these systems was a forested riparian at least 500 feet in width with large
white cedar, cottonwood or willow trees dominating the near shore areas. It should be noted
that although the lower port ions of these streams remain undisturbed, the headwater areas of
these systems are completely developed for row crop agriculture. Despite the excellent
habitat condit ions observed, these streams all suffer from excess sand deposit ion.
Data collected regarding substrate and flow condit ions at part icular sites will be used in the
Final Design process to determine maximum scour depth and shear stress values for given
flow condit ions in the newly constructed channel. Scour analysis and incipient motion
calculations determine the proper sizes of bed and bank part icles, and determine the type of
bank treatments allowed for the design discharge.
The next step in the design process is balancing the hydraulic and sediment size information
with slope and planform geometry information to determine the cross-sectional geometry and
planform geometry of the channel. Regional data again becomes valuable in determining the
ult imate shape of the channel. Preliminary design data suggests the newly constructed
Centerville Creek should maintain a variable bankfull top width between 15 and 17 ft, a
bottom width of 5-6 ft with a mean depth at riffles of 1.5-1.7 ft. Maximum residual pool
depth may vary from 2 to 4 ft. Regional planform geometry fitted to the Centerville Creek
watershed predicts a stable planform with meander wavelengths between 100 and 110 ft, and
a mean radius of curvature of 38 ft.
Following dewatering of the site, the new channel will be constructed in the following
sequence. Pre-sorted and properly sized bed material, likely in the form of gravel and
cobbles, will be installed to the determined maximum depth of scour (Figure 9). To ensure
proper stability in the event of local lateral scour, this imported bed material will extend
under the floodplain for approximately 0.5-1.0 * channel bottom width on either side of the
stream. Pools and riffles will be constructed to final grade and woody debris structures will
be installed (Figure 10). Bank stabilization with bioengineering methods and floodplain
detailing will complete the restoration of the channel (Figure 11).
19
7.1.3 Grade Control
Unstable channel areas such as the former dam site may require the installat ion of grade
control structures. Vertical instability is usually manifested in the form of nickpoints, or
abrupt head changes (headcuts) that continue to erode and advance upstream until a stable
channel grade is reached. To prevent the formation of a headcut at the former dam site, a rock
weir would be buried just below the grade of the stream bottom and would extend across the
entire width of the floodplain (Figure 12). Further grade controls may be installed in other
reaches to add vert ical stability to the newly constructed channel.
7.1.4 Bioengineering methods
Most of the bank restoration for this project involves the construction of new banks from
deposited sediment. Construction of these banks is best accomplished using fabric-
encapsulated soil (FES) in the form of 1.0-1.5 foot layers of soil enclosed in biodegradable
erosion fabric. Fabric and live willow or dogwood stakes are placed and t ied into the stream
bed. A layer of soil is installed and compacted. The erosion control fabric is then wrapped
around the soil and staked down with heavy-duty wooden stakes. The erosion control fabric
prevents piping and erosion of the soil until the native vegetation becomes established. Figure
13 shows the general concept of FES lift construction following floodplain excavation.
Alternatively, soil can be compacted and erosion blanket can be used to secure slopes without
the use of encapsulated lifts. This technique is useful with highly cohesive soils in segments
with low banks (Figure 14). Again, live plants in the form of cutt ings or mats can be used to
stabilize newly constructed slopes.
7.1.5 Planting
7.1.5.1 Near bank
Installat ion of bioengineered bank stabilization will require the installat ion of live cutt ings of
various native willow species, usually black willow, sandbar willow or pussy willow.
Dogwood shrubs in cutt ing, bare root stock, potted plants or live mat form can also be
incorporated into bank stabilization (Figure 15).
7.1.5.2 Riparian zone
A buffer will be established along the entire project length, and will serve to provide
overhead cover and stream shading as well as erosion control. The buffer will be
approximately 20 feet wide on either side of the stream channel and will be composed mainly
of potted understory shrubs, basswood, white cedar and black willow trees.
20
7.1.5.3 Floodplain
Floodplain planting will incorporate a variety of local native trees and shrubs. Trees and
shrubs of varying sizes will be planted in randomly assigned clumps to encourage shading.
All areas will be seeded with a mixture of native grasses to create temporary erosion
protection. Seed and plant species are listed below:
Native seed
Dropseed prairie grass Sporobolus Red top grass Agrostis alba Seed oats Avena sativa Annual rye Lolium multiflorum Indian grass Sorghastrum nutans Little bluestem Andropogon scoparius Sideoats Grama Bouteloua curtipendula Switch grass Panicum virgatum Timothy Phleum pratense
Native Wisconsin Shrubs and Trees Black Cherry Prunus serotina Black Walnut Junglans nigra Bur Oak Quercus macrocarpa Dwarf bush honeysuckle Diervilla lonicera Elderberry Sambucus canadensis Gray Dogwood Cornus racemosa Green Ash Fraxinus pennsylvanica Hazelnut Corylus americana Highbush cranberry Viburnum trilobum Northern Pin Oak Quercus palustris Sand serviceberry Amelanchier sanguinea Shagbark Hickory Carya ovata Silver Maple Acer saccharinum Sugar Maple Acer saccharum White Oak Quercus alba Willow Salix spp.
7.1.5.4 Timing
Seeding should take place immediately following construction, to provide temporary erosion
protection. Shrubs and trees should be planted in Fall or late Spring. A watering plan must be
established to ensure that grasses and trees have adequate moisture in dry periods. Bare root
stock and potted plants should be protected with either tubing or wrap to prevent rodent and
ungulate damage.
21
7.1.6 Other design issues
Other design parameters include dewatering, walking trail and staging area design.
Dewatering design will be the responsibility of the contractor, but that the consult ing
engineer must approve any dewatering design, and that the plan must be prior approved by
the Wisconsin DNR.
7.1.7 Other Construction Issues
7.1.7.1 Staging
Due to the amount of excavation required, large equipment such as front-end loaders,
scrapers, bulldozers and excavators will be required on site. The exist ing floodplain near the
dam site may be used for staging, and the high terrace near the former boat launch may also
be a good staging area and headquarter location. The wastewater treatment facility parking lot
and shed should also be considered as the main staging area, but traffic issues should be
considered when using this area. Access using residential lots may be a requirement, but will
need to be arranged between the Village of Cleveland and part icipating landowners.
7.1.7.2 Utilities
Utilit ies such as fiber optic cable, electric lines, gas mains and sanitary sewers will need to be
located and marked prior to construction. Utility location would be included in the design
phase of the Final Design and Construction process.
7.1.7.3 Haul roads
The designation of haul roads depends on the location of the disposal site. A disposal site
north of the project area would require the use of North Avenue. Disposal of material south of
the project site would require the use of North Avenue, County LS, and South Cleveland
Road.
7.1.7.4 Traffic
During the floodplain excavation port ion of the project, approximately 1200 truckloads of
sediment will travel haul roads near the project. Depending on the number of trucks used, this
trucking could take between 20 and 30 days of constant hauling. Proper signage will be
required and detours may be suggested for through-traffic, restrict ing traffic near the project
site to local residents only.
22
7.1.7.5 Erosion control
With proper dewatering techniques, loss of sediment into the stream and into Lake Michigan
can be minimized. Silt fencing will be used to contain runoff events and a combination of
erosion control fabric and cover crop seed will be used to stabilize bare areas.
7.1.8 Additional data needs
To complete a Final Design for the Centerville Creek project, addit ional survey data will be
required. The Wisconsin State Historical Society has determined that there are no
archeological or architectural properties within the area of potential effect of the restoration
work. In accordance with Section 106 of the National Historic Preservation Act and 36 CFR
Part 800, any sediment disposal sites will need to be surveyed and approved by a qualified
archeologist.
The following addit ional survey data will be collected as part of the Final Design phase of the
project and can be t ied into the exist ing base map:
o Roads
o Utilit ies
o Disposal site
o Project limits (define ownership)
o Staking
o As-built survey
o Boring locations
Soil borings will be required to determine parameters such as compaction, cohesion and the
potential for seepage and slope failure due to soil composit ion. Borings taken with a hollow
stem auger will be analyzed using standard ASTM methods including:
o In-situ standard penetration test (ASTM D 1586)
o Grain size (ASTM D422)
o USCS Classification of Soils (ASTM D2487)
o Water content (ASTM D2216)
o Moisture / Density relationship (ASTM D1557)
o Atterburg limits (ASTM D4318)
23
7.2 Cost
The total cost for this project is broken down in Appendix D, and is summarized here. The
total cost for the project including design and construction is $800,700. This estimate
includes addit ional surveying, data collection, staking, permitt ing, design, plans and
specifications and construction supervision. Oversight of the construction process is crit ical
in river restoration, where complex biological habitat features are often changed in the field
during installat ion. This estimate also includes floodplain excavation, dewatering and stream
restoration. See Appendix D for further details.
Several assumptions are necessary during this stage of design, and these assumptions can
greatly effect project cost. First among these is the assumption of a nearby disposal site for
excavated materials. Any hauling of excavated sediment beyond 0.5 miles from the project
site will increase the cost of construction. Other assumptions include:
o Project will be let as one bid package.
o Construction will occur in 2002.
o No special requirements for material handling or disposal due to contaminants.
o No historical or archeological investigations or associated design considerations.
o Disposal site is within Village of Cleveland city limits.
o Excavation and stream restoration occur simultaneously.
o No rock or muck excavation required.
o No easement acquisit ion costs associated with design or construction.
o No off-road construction vehicles such as scrapers may be used. Large, mult i-axle dump trucks will be used for sediment hauling.
o A haul road will be not be necessary for trucking material off-site.
o No topsoil dressing of the site prior to seeding. It should be verified that the material will have adequate organic content and nutrients to support plant growth.
7.3 Permitting issues
This project will require a Wisconsin DNR “Chapter 30” permit for the relocation and
restoration of a navigable waterway. As part of this permitt ing process, the Wisconsin DNR
will forward the permit application to the U.S. Army Corps of Engineers for consideration
under the Section 404. As part of this process, it may be determined that an Environmental
Assessment will be necessary. Removal and disposal of impoundment sediments requires a
non-hazardous waste permit as detailed in Section 5.1.2.1. Because the stream is within
Village of Cleveland city limits, Manitowoc County does not require any zoning or permits.
Questions regarding zoning can be directed to the Manitowoc County Code Administrator.
24
Once a disposal plan is in place, the Manitowoc County Highway Department should be
contacted regarding any transportation permits or restrict ions. Questions regarding
permitt ing, weight restrict ions and routing should be directed to Manitowoc County Highway
Commissioner.
7.4 Construction limitations
Ownership of the impoundment area should be resolved before construction begins.
Construction easements can be acquired, but landowners should be made aware of the
eventual result of restoration and of the importance of keeping the area wild. If the Village of
Cleveland acquires land, this area should be designated as parkland, eliminating the potential
problems associated with development and active recreational use.
If public ownership is not an option, landowners may consider Conservation Easements.
These easements are written into the t it le specifying the restrict ions for development, building
and vegetation management. A landowner may assist in writ ing the easement language,
thereby affording some flexibility with regard to personal management of the property. Most
land trusts that manage easements, however, require perpetual easements that contain
restrict ive clauses limit ing any cutt ing or trimming of vegetation. In most cases it is
recommended that no addit ional buildings be allowed on the property. Landowners need not
place the entire property in an easement, but can designate certain port ions, such as the
impoundment area and surrounding slopes, as protected. Conservation Easements are legal
t it le documents and help protect wild lands well into the future. More information can be
obtained by calling the University of Wisconsin Extension Basin Educator at 920-388-4313.
Donating or selling land to a group such as the Northeast Wisconsin Land Trust also ensures
proper management and protection of wild lands. The Northeast Wisconsin Land Trust can be
contacted at 920-738-7265.
8.0 Additional Funding See the attatched file for links to grant information.
9.0 Schedule (see attached)
25
10.0 Glossary The following fluvial geomorphology terms are commonly used in this document:
Aggradation – the vert ical buildup of channel bed elevation due to excessive sediment
deposit ion.
Bankfull capacity – the amount of flow contained by banks during a bankfull event. The
bankfull channel must be appropriately sized to accommodate anticipated flows. Undersized
channels can result in degradation and frequent flooding, while undersized channels can
aggrade (Rosgen 1996).
Belt width - describes the maximum boundary within which a stream meanders back and
forth across its floodplain. The belt width of a stream often completely confines the
floodplain.
Degradation – the lowering of channel bed elevation due to excessive erosion of bottom
sediment.
Lateral stability – the resistance of a channel to excessive bank erosion or deposit ion
Meander wavelength – the distance between the apexes of two meanders.
Radius of curvature (Rc) - describes the degree of curvature of a meander, and is equivalent
to the radius of a circle that matches the meander curvature when superimposed on the
meander.
Shear stress – the force of moving acting on channel bed and banks that can entrain and
move substrate part icles. Shear stress is commonly measured in pounds per square foot, and
is dependent on channel slope and water depth.
Sinuosity – the degree of meandering or lateral channel migration typically seen in natural
stream channels. Sinuosity aids in the dissipation of energy in the stream system, as increased
sinuosity decreases channel slope.
Vertical stability – the resistance of a channel to both downcutt ing or degradation of the bed
and aggradation or sediment accumulation.
Width to depth ratio – equal to the bankfull width divided by the mean depth of the
bankfull channel.