SOCIALIST REPUBLIC OF VIET NAM
ELECTRICITY OF VIET NAM
PECC4 POWER ENGINEERING CONSULTING COMPANY 4SO990012O
RP287Project No.: 14 - 02 VOL. 4
TUY HOA - NHA TRANG 220kV TRANSMISSION LINE
FEASIBILITY STUDY REPORT
RESETTLEMENT ACTION PLAN (RAP)(FIRST REVISION)
Khanh Hoa Province - 2005
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
SOCIALIST REPUBLIC OF VIET NAM
ELECTRICITY OF VIET NAM
PECC4 POWER ENGINEERING CONSULTING COMPANY 4ISO 900 2
PROJECT: 14 - 02
TUY HOA - NHA TRANG 220kV TRANSMISSION LINE
FEASIBILITY STUDY REPORT
RESETTLEMENT ACTION PLAN (RAP)(FIRST REVISION)
Head of Department : Nguyen Kim Dong
Head of Project Design: Le Hoang Thuong -
Khanh Hoa Province, 2005
FOR AND ON BEHALF OF
POWER ENGINEERING CONSULTING COMPANY 4
DEN HUU TAP
DEPUTY DIRECTOR |
Tuy Hoa - Nha Trang 220kV transmission line Feasibility Study
The staffs participating in RAP establishment including of:
No. Full name Content prepared Signature
In charge of presiding RAP1 Tran Van Luyen enestablishment i2 Mai Thi Hop Establishing RAP
Resettlement Action Plan
Tuy Hoa- Nha Trang 220kV transmission line Feasibility Study
CONTENTS
ABREVIATION 4
SUMMARY 5
1. Policy framework 5
2. Project impacts 5
3. Resetlement policy 6
4. Public consultation 6
5. Grievance 7
6. Management organization 7
7. Implemetation schedule 7
8. Cost estimate 8
9. Information dissemination 8
CHAPTER 1: GENERAL INTRODUCTION 9
1.1 The basis of the report 9
1.2 Objectives 9
1.3 Validity of RAP implementation 10
1.4 Description of the project 10
1.4.1 Characteristic of the project 10
1.4.2 Project impacts 13
1.5 Project impacts minimizing measures 13
1.6 Implementation cost estimate 14
CHAPTER 2: IMPLEMENTATION ORGANIZATION AND LEGAL 15
FRAMEWORK FOR COMPENSA TIONAND RESETTLEMENT
2. 1. Institutional arrangements 15
2.2. Organizational'responsibility 15
2.3. Staffing organization and responsibilities 20
2.4 Legal framework 21
CHAPTER 3: ENTITLEMENT POLICY 26
Resettlement Action Plan 1
Tuy Hoa- Nha Trang 220kV transmission line Feasibility Study
3.1 Definition of PAP and limitation to eligibility 26
3.2 Resettlement and compensation principles 26
3.3 Eligibility to get compensation entitlements 27
3.4 Entilement policy 28
3.5 Inpacted categories 31
CHAPTER 4: SOCIO-ECONOMIC SITUATION OFPROJECTAREA 33
AND THE PROJECT IMPACTS
4.1 Survey work, inventory of project impacts 33
4.2 The socio-economic condition of project area 33
4.2.1 Phu Yen Province 33
4.2.2 Khanh Hoa Province 34
4.3 Project impacts 34
CHAPTER 5: PULICPARTICIPATIONAND CONSULTATION 36
5.1 Objectives of information campaign and consultation program 36
5.2 Consultation and inform to people 36
5.3 Information dissemination and PAPs'consultation 37
CHAPTER 6. COMPLAINTSAND GRIEVANCE 40
CHAPTER 7: SUPERVISIONAND MONITORING 42
7.1 Internal supervision 42
7.2 Independent supervision 42
CHAPTER 8: IMPLEMENTATION ORGANIZATION FOR 44
COMPENSA TIONAND RESETTLEMENT PLAN
8.1 Measures for the project implementation 44
8.1.1 Announcement to PAPs 44
8.1.2 Compensation and Resettlement deadlines 44
8.2 RAP implementation process 44
8.3 RAP implementation schedule 46
Resettlement Action Plan 2
Tuy Hoa- Nha Trang 220kV transmission line Feasibility Study
CHAPTER 9: COSTS AND BUDGET 47
9.1 Budget 47
9.2 Compensation price determination 47
9.2.1 Land 47
9.2.2 Impacted trees and crops 47
9.3 Compensation cost estimate 48
9.3.1 Cost for RAP establishment 48
9.3.2 Compensation cost 49
9.3.3 Management cost 49
9.3.4 Supervision cost 49
9.3.5 Reserved cost 49
9.3.6 Total compensation cost for project 49
CHAPTER 10: CONCLUSIONAND PROPOSALS 50
10.1 Conclusion 50
10.1 Proposals 50
APPENDICES 51
Appendix 1: Entitlement Matrix 52
Appendix 2: Table of compensation quantity for Quy Nhon - Tuy Hoa 220kV T/L 59
Appendix 3: Inventory of Project Affected People 62
Appendix 4: Entitlements of Project Affected People 75
Appendix 5: Socio-Economic Household Data Sheet of Project Affected People 87
Appendix 6: Minutes of public consultation 96
Resettlement Action Plan 3
Tuy Hoa- Nha Trang 220kV transmission line Feasibility Study
ABREVIATION
- RAP Resettlement Plan
- PAPs Project Affected Persons
- WB World Bank
- PC People's Committee
- EVN Electricity of Vietnam
- LC Land Clearance
- PMB Project Management Board
- PECC4 Power Engineering Consulting Company 4
- ER Environmental Resource
-GC General Company
- VND Viet Nam Dong
- SC Safe Corridor
- ROW Right-Of-Way
- CPPMB Central Power Projects Management Board
Resettlement Action Plan 4
l
Tuy Hoa- Nha Trang 220kV transmission line Feasibility Study
SUMMARY
Pursuant to the Government policy, the power energy develops in advance of
other sectors to serve as the engine for development with purposes of rich people,
strong country and an equitable, democratic and civilized society. In order to
strengthen the capacity of supplying power source, a vitual infrastructure, Electricity
of Vietnam (EVN) has established the project "Transmission, distribution and
overcoming natural disasters" (3034-VN) financed by World Bank (WB). One of its
component is "Tuy Hoa - Nha Trang 220kV transmission line" project with total route
length of 131,528m going through the territory of Phu Hoa and Tuy Hoa districts, Phu
Yen Province; Van Ninh and Ninh Hoa districts, Nha Trang City of Khanh Hoa
Province.
Tuy Hoa - Nha Trang 220kV transmission line project is constructed in line
with Quy Nhon - Tuy Hoa 220kV transmission line and 220kV Tuy Hoa Substation
projects targeting to combine the local 110kV, 220kV power grid, to receive energy
source from power source of Ha Song Ba hydropower project, etc.. .into power grid
and to upgrade the reliability in supplying power, the quality of power energy of the
local power grid.
1. Policy framework
The plan on project compensation and resettlement is established based on Decree
197/2004/ND-CP dated December 3rd, 2004 of the Government regarding the
compensation, resettlement support when the State takes back the land; Decree
198/2004fND-CP dated November 16th,2004 of the Govermment regarding the method
to determine the land price and the price framework of land kinds; Decree
181/2004/ND-CP of the Government regarding the implementation of Land Law, etc...
and guideline on RAP establishment of WB (the policy framework of unvoluntary
resettlement OD 4.30). According to this policy, PAPs are people, households, entities
with or without juridical personality for their assets on project impacted land and
inventoried before the cut-off-date (September 9th, 2004) are entitled to compensation
and resettlement.
2. Project impacts
The project causes impacts to the followings:
Resettlement Action Plan 5
Tuy Hoa- Nha Trang 220kV transmission line Feasibility Study
- Perpetual land acquisition at tower foundation positions, ect. (the
perpetual acquisition area of 47,345m2).
- Causing damage to trees, crops and other assets at tower foundation
positions and within ROW.
- Temporary land acquisition under project construction
Results of project data collection show that there are 135 households whose houses
and structures are impacted within the safe corridor of the line route, whereas:
+ No household loses over 25% area of agricultural land
+ No affect to cultural relics area, preservation area, pagoda and sensitive areas
+ No ethnic minority household among impacted households.
During public consultation process, impacted households were agreed to select the
compensation procedure on land and assets in cash.
3. Compensation policy
The cut-off-date is September 96, 2004. The price for making compensation on land,
assets and crops is based on the compensation unit price of Phu Yen and Khanh Hoa
Provinces.
All impacted households are entitled according to the policy framework and Vietnam
Decrees such as displacement support, support for production stabilization, etc... Up
till now, the survey result and damage inventory shows that no remarkable impacts to
people, the community and the public assets. As a result, it is unnecessary to have
economical recovery measures.
4. Public consultation
PAPs consultation to get feedback comments will restrict the contradictions and delay
when implementing the project. The resettlement plan will be implemented following
to the reference c