Shambhala Mountain Center Wastewater Utility Plan Utility Plan... · Shambhala Mountain Center....
-
Upload
phungxuyen -
Category
Documents
-
view
223 -
download
0
Transcript of Shambhala Mountain Center Wastewater Utility Plan Utility Plan... · Shambhala Mountain Center....
Shambhala Mountain Center
Wastewater Utility Plan
REVISED April 2010REVISED March 2010
REVISED January 2010February 2009081-039.000
Prepared by:
WRIGHT WATER ENGINEERS, INC.Denver, Colorado
Prepared for:
Shambhala Mountain CenterRed Feather Lakes, Colorado
Shambhala Mountain Center Wastewater Utility Plan
Prepared by:
WRIGHT WATER ENGINEERS, INC. Denver, Colorado
REVISED April 2010 081-039.000
i
TABLE OF CONTENTS
Page EXECUTIVE SUMMARY ............................................................................................................ 1 1.0 INTRODUCTION ............................................................................................................. 3
1.1 Facilities Plan Summary ...................................................................................................... 4 1.2 Implementation .................................................................................................................... 5 1.3 Summary of Utility Plan Structure ....................................................................................... 6
2.0 GENERAL PLANNING ................................................................................................... 6 2.1 Feasibility of Consolidation of Facilities Reg. 22 @ 22.8 (1) (b) .......................................... 6 2.2 Wastewater Reuse .............................................................................................................. 7 2.3 Environmental Components ................................................................................................ 7
2.3.1 National Environmental Policy Act (NEPA) Information .................................. 10 3.0 WASTEWATER CHARACTERIZATION ........................................................................ 10
3.1 Service Area Designations ................................................................................................ 11 3.2 Population Datasets & Forecasts ...................................................................................... 11 3.3 Wastewater Flow Projections ............................................................................................ 14
3.3.1 Infiltration/Inflow Analysis ................................................................................ 17 3.3.2 Character of Influent ....................................................................................... 18 3.3.3 Industrial Pretreatment Program ..................................................................... 22
3.4 Treatment Works .............................................................................................................. 22 3.4.1 Process System and Dispersal System .......................................................... 22 3.4.2 Infrastructure Sizing and Staging .................................................................... 32 3.4.3 Location and Siting.......................................................................................... 32 3.4.4 Biosolids Handling........................................................................................... 32 3.4.5 Schematic of Treatment Works ...................................................................... 33 3.4.6 Odor Control Considerations .......................................................................... 33
3.5 Air Quality Permit .............................................................................................................. 33 3.6 Stormwater Management Plan .......................................................................................... 38 3.7 Site Characterization Report ............................................................................................. 38 3.8 Collection System .............................................................................................................. 38
3.8.1 Major Lift Stations ........................................................................................... 39 3.8.2 Interceptor Sewers .......................................................................................... 39 3.8.3 Collection System Plan ................................................................................... 39
3.9 Maps.................................................................................................................................. 43 3.9.1 Treatment Plant Site Envelope ....................................................................... 43 3.9.2 Service Area ................................................................................................... 43 3.9.3 Collection System ........................................................................................... 43
4.0 WATER QUALITY CHARACTERIZATION .................................................................... 47 4.1 Water Quality of the Receiving Water ............................................................................... 47 4.2 TMDLs and/or Waste Load Allocations ............................................................................. 47 4.3 Watershed Issues ............................................................................................................. 48 4.4 Preliminary Effluent Limitations (PELs) ............................................................................. 48 4.5 Maps.................................................................................................................................. 49
4.5.1 Watershed ...................................................................................................... 49 4.5.2 Impaired Waters ............................................................................................. 50
5.0 ALTERNATIVE ANALYSIS ........................................................................................... 50 5.1 Treatment Works .............................................................................................................. 50
5.1.1 Sequencing Batch Reactor (SBR) .................................................................. 51 5.1.2 Extended Aeration Activated Sludge............................................................... 51 5.1.3 Membrane Bioreactor (MBR) .......................................................................... 51
5.2 Level of Treatment ............................................................................................................ 52 5.3 Cost Evaluation ................................................................................................................. 55 5.4 Preferred Alternative ......................................................................................................... 56 5.5 Proposed Implementation Schedule ................................................................................. 58
ii
5.6 Public Participation and Selection Process ....................................................................... 59 6.0 MANAGEMENT AND FINANCIAL PLANS ................................................................... 59
6.1 Management Structure and Agreements .......................................................................... 59 6.2 Wastewater Management Plan ......................................................................................... 60 6.3 Financial Management Plan .............................................................................................. 61
6.3.1 Financial Assistance ....................................................................................... 63 6.3.2 User Charge Summary ................................................................................... 63
7.0 REFERENCES .............................................................................................................. 63
iii
TABLES Table 1 Existing Conditions - Buildings on Central Wastewater System .................................................... 11 Table 2 Existing Conditions - Buildings on Separate OWS ......................................................................... 11 Table 3 Existing Buildings on Central Wastewater System That Have Septic Tanks ................................. 19 Table 4 Existing Buildings Currently on Separate OWS ............................................................................. 19 Table 5 Influent BOD Concentrations to the Existing Wetland Cells (After Presedimentation Tanks) on
Various Dates .......................................................................................................................... 20 Table 6 Character of Wastewater Influent to the Proposed WWTF ........................................................... 22 Table 7 Estimated Capital Costs of Collection System By Phase ............................................................... 43 Table 8 PELs Issued to SMC by CDPHE (October 30, 2009 Letter) .......................................................... 49 Table 9 Comparative Estimated Capital Costs – WWTF ............................................................................ 55 Table 10 Comparative Annual O&M Costs ................................................................................................. 56 Table 11 Ranking of New WWTF Processes ............................................................................................. 58 Table 12 Shambhala WWTF Implementation Schedule ............................................................................. 59 Table 13 Summary of Capital, O&M, Replacement Costs and Total Revenues ......................................... 62
FIGURES Figure 1 Shambhala Mountain Center WWTF, Magic Sky Ranch Girl Scouts Camp and Ben Delatour Boy
Scout Camp Location Map ........................................................................................................ 8 Figure 2 Property Boundary, Service Area, Wastewater Utility Planning Area, and the Ultimate Planning
Area ......................................................................................................................................... 12 Figure 3 Average Daily Water Use for Each Overnight Person by Month - 2007 to 2009 (Based on Total
Metered Water Pumped from Onsite Wells and Number of Overnight Visitors Plus Staff) .... 15 Figure 4 Projected Flow and Peak Population for 20 Year Planning Period Compared to Design Capacity17 Figure 5 Projected BOD Concentration for 20-Year Planning Period Compared to Design Capacity ........ 21 Figure 6 Process Diagram Sequencing Batch Reactor (SBR) .................................................................... 28 Figure 7 Dispersal System Conceptual Design Plan ................................................................................... 29 Figure 8 Dispersal System Conceptual Design Profile................................................................................ 30 Figure 9 Unnamed Drainage Swale Watershed Site Map .......................................................................... 31 Figure 10 Wastewater Treatment Facility Location ..................................................................................... 34 Figure 11 Wastewater Treatment Facility Site Plan .................................................................................... 35 Figure 12 Preliminary Design – Wastewater Treatment Facility Process Plan ........................................... 36 Figure 13 Preliminary Design – Wastewater Treatment Facility Process Profile ........................................ 37 Figure 14 Wastewater Collection System Existing Condition ..................................................................... 44 Figure 15 Wastewater Collection System Master Plan ............................................................................... 45 Figure 16 South Sewer Line Master Plan .................................................................................................... 46 Figure 17 Process Diagram Extended Aeration Activated Sludge .............................................................. 53 Figure 18 Process Diagram Membrane Bioreactor (MBR) ......................................................................... 54
APPENDICES (END OF REPORT)
A Preliminary Effluent Limits Letter (October 30, 2009) B Letter Dated March 2, 2010 to Wayne Lorenz from the NFRWQPA Regarding Shambhala
Mountain Center Utility Plan C Letter Dated September 27, 2001 to Richard A. Swaback from the CDPHE Regarding
Compliance Advisory on Compliance Inspections of Shambhala Mountain Center D Geotechnical Investigation and Phase II Percolation Study for the SMC WWTF performed by CTL
Thompson (December 11, 2009) E Federal Emergency Management Agency (FEMA) Floodplain Map F Watershed Map G Opinion of Capital Costs – Collection System H Opinion of Capital Costs – Treatment Plant Options
iv
I Letter Dated December 14, 2009 to Jon Barbieri from The Sakyong Foundation Regarding Donor Funds
J Site Ownership/Control Documentation K CDPHE Consent Order
081-039.000 Wright Water Engineers, Inc. Page 1 Revised April 2010
SHAMBHALA MOUNTAIN CENTER WASTEWATER UTILITY PLAN
EXECUTIVE SUMMARY
The Shambhala Mountain Center (SMC) currently is served by a wastewater system that consists
of onsite wastewater treatment and a Central Wastewater Treatment Facility (WWTF).
This Wastewater Utility Plan (WUP) presents a phased construction program to address
modifications to the existing wastewater collection system and a new mechanical WWTF.
The preferred alternative for wastewater treatment processes at SMC were based on meeting the
water quality limits received from the Colorado Department of Public Health and Environment
(CDPHE) in Preliminary Effluent Limits (PELs) letters for discharge to groundwater. The
groundwater discharge is proposed via a dispersal system constructed in the meadow to the
northeast of the SMC “downtown” area. A sequencing batch reactor (SBR) is proposed as the
major treatment process to meet the PELs at SMC. The groundwater discharge permit limits will
be met, and monitored, prior to the dispersal system.
The projected wastewater flows from the SMC and required wastewater treatment capacity are
addressed in Table E-1.
Table E-1 SMC Wastewater Treatment Capacity
Population
Wastewater Flows Flow Average Daily
(gpd) Summer Maximum Daily1
(gpd) To Be Constructed 650 Persons 33,000 49,000
Future Expansion 1,250 Persons with Day Visits of 3,000 63,000 94,000
1 Based on 1.5 summer maximum daily flow to average daily flow.
The preferred alternative treatment process system (the SBR system) was sized based on the
projected average daily flow of 33,000 gallons per day (gpd) with a summer maximum daily flow
of 49,000 gpd. This wastewater treatment flow capacity will address up to 650 people of the
Shambhala Mountain Center Wastewater Utility Plan
081-039.000 Wright Water Engineers, Inc. Page 2 Revised April 2010
anticipated growth forecasts. An expansion of the capacity of the proposed SBR treatment
system will be needed for the future visitation wastewater flows.
The wastewater collection system piping needed for the central wastewater treatment system will
be constructed based on the phasing shown in Figure 10 in this report.
An opinion of probable capital costs for the wastewater collection system piping, by phase, is
presented in Appendix G. The wastewater collection system piping costs to most of the onsite
wastewater treatment systems (OWS) into the central facility is $530,000 to $780,000, to be
constructed by the end of Phase II. These costs do not include the future phase development.
The capital cost of the preferred wastewater treatment process (SBR process) is estimated at
$1.46 million to $2.15 million (49,000 gpd). The anticipated annual operations and maintenance
(O&M) cost is $82,000 per year.
Construction of the new mechanical WWTF is proposed to begin in March of 2011.
Shambhala Mountain Center Wastewater Utility Plan
081-039.000 Wright Water Engineers, Inc. Page 3 Revised April 2010
1.0 INTRODUCTION
The Shambhala Mountain Center (SMC) is a mountain retreat center located in the Red Feather
Lakes area in Larimer County, Colorado. It is approximately 30 miles to the north and west of
the City of Fort Collins and is situated on 600 acres. The SMC offers programs on Buddhist
meditation, yoga, and other disciplines. Most of the visitors use the facilities on a short-term
basis. The SMC opened in 1971. SMC is limited to 450 visitors and staff on the main campus,
plus an additional 80 people on the Red Feather Campus during peak months (June to
September), or a total of 530 people during peak months, in accordance with current Larimer
County Land Use requirements. During off-peak months, (October to May) Land Use
requirements limit SMC visitors and staff to 150 people on the main campus plus an additional
50 people on the Red Feather Campus, or a total of 200 people.
Potable water is provided to the SMC by several onsite wells that pump into a water distribution
system. The water system is designated as a community public water system (PWSID No.
CO0235685) under the requirements of the Colorado Department of Public Health and
Environment (CDPHE).
SMC’s current wastewater treatment systems include both a central wastewater collection and
treatment system and onsite wastewater treatment systems (OWSs). A central collection and
treatment system consists of approximately 13 septic tanks followed by presedimentation tanks, a
two-cell constructed wetland system, and a polishing pond. No disinfection is provided. Treated
effluent is discharged from the polishing pond by evaporation and to groundwater via Colorado
Discharge Permit No. COX-630037. Currently, the approved hydraulic capacity of the central
wastewater system is 7,785 gallons per day (gpd).
There are several issues regarding the wastewater system at SMC, based on a recent compliance
inspection by CDPHE. The following is a summary of issues:
1. There is no written record in CDPHE files that Site Approval and Design Approval was
obtained for the as-constructed wastewater treatment processes.
Shambhala Mountain Center Wastewater Utility Plan
081-039.000 Wright Water Engineers, Inc. Page 4 Revised April 2010
2. An inflow metering device is needed.
3. The facultative polishing pond appears to be leaking (based on a CDPHE site visit on
July 25, 2007). The leaking may also be an unpermitted surface discharge to the
unnamed tributary. The facility currently only has a Groundwater Discharge Permit,
which does not include a surface water discharge point.
4. The current General Discharge Permit does not accurately reflect the existing treatment
processes, flows, or discharge locations.
This Wastewater Utility Plan (WUP) was prepared to evaluate the existing wastewater system
and provide planning for new treatment processes that will meet groundwater discharge permit
limits via a groundwater dispersal system.
1.1 Facilities Plan Summary
The wastewater facilities proposed in this WUP represent major modifications to the existing
infrastructure. A new mechanical wastewater treatment facility (WWTF) will be constructed to
take the place of the existing wetland treatment cells. The mechanical WWTF will have
treatment processes that will meet the preliminary effluent limits (PELs). A groundwater
dispersal system will discharge the highly treated effluent to the alluvial groundwater.
Most of the existing OWSs within the service area will be abandoned and included on the central
WWTF. There are also septic tanks that are functioning on sewer lines that go to the existing
wetland treatment cells. It is planned that these septic tanks be phased out so that raw
wastewater will be directed to the new mechanical WWTF.
The abandonment of existing septic tanks and OWSs will be done in a phased approach. Phase I
is proposed as the construction of the mechanical WWTF and phasing out of septic tanks in the
“downtown” area of SMC. Phase II is proposed to abandon the OWSs at Stupa View Staff
Housing, and Red Feather Conference Center and associated buildings and connect on to the
central system. The Stupa Support Building/Visitor’s Center, MPE-Summer Kitchen, Ma
Mason, Mason House, Windhorse Hill, and Teacher’s Residence will be connected as needed
Shambhala Mountain Center Wastewater Utility Plan
081-039.000 Wright Water Engineers, Inc. Page 5 Revised April 2010
(i.e., when there are problems with the OWS). These connections, when needed, are addressed
as a Phase III in this report. The OWSs at these locations will be abandoned and connected to the
central system by construction of a gravity sewer.
In accordance with Larimer County Department of Health and Environment, Individual Sewage
Disposal System Regulations (2004) abandoned septic tanks will be pumped and filled with soil,
or removed (Larimer County, 2004).
Wastewater collection system piping will be designed and constructed according to this WUP.
1.2 Implementation
This present plan for wastewater treatment upgrades at SMC began at the end of 2006 with a
request to CDPHE for determination of PELs for the proposed groundwater discharge. Since this
2006 PEL request, the planning for the wastewater treatment and discharge has evolved and the
PELs have been updated. The most current letter from the CDPHE is for groundwater discharge
and is dated October 30, 2009 (See Appendix A).
Several alternative treatment technologies have been evaluated in this WUP based on the
groundwater PELs. A cost analysis and a schematic design for a mechanical WWTF are
presented with the alternatives analysis.
A previous draft of this WUP was presented to the North Front Range Water Quality Planning
Association (NFRWQPA) originally in February 2009 and then again in January 2010.
Comments from the review of this draft were received from NFRWQPA (letter dated March 2,
2010). This current, revised version of the draft WUP addresses the comments in the March
2010 NFRWQPA letter (See Appendix B).
A Site Application for a new WWTF will be submitted following referral review and acceptance
of this WUP by the NFRWQPA and Larimer County.
The SMC is currently in a funding program for the design and construction of the collection
system and new WWTF. It is anticipated that the funding campaign will take some time for
success. At this time, construction of the new WWTF is anticipated to begin on March 1, 2011.
Shambhala Mountain Center Wastewater Utility Plan
081-039.000 Wright Water Engineers, Inc. Page 6 Revised April 2010
1.3 Summary of Utility Plan Structure
This report is structured according to the NFRWQPA Utility Plan Guidance, approved on
June 22, 2000 and amended on June 28, 2007. Chapter 2 presents the general planning for the
collection system and new WWTF, including the considerations for consolidation, wastewater
reuse, water rights, and environmental components. Chapter 3 provides the details for the
evaluation starting with the service area and population, and continuing with wastewater flow
projections and characterization of water quality. The conceptual design of the preferred
treatment alternative is also presented in Chapter 3 along with the site location. In Chapter 4, the
water quality requirements for discharge to groundwater are addressed. The presentation of the
treatment alternatives evaluation follows in Chapter 5. The details of the management and
financial plans are covered in Chapter 6. The technical support documents are attached as
appendices.
2.0 GENERAL PLANNING
2.1 Feasibility of Consolidation of Facilities Reg. 22 @ 22.8 (1) (b)
The SMC Central WWTF is located in Section 23 Township 9 North, Range 73 West of 6th
Principal Meridian, Larimer County, near County Road 68 C. Other than individual residences,
there are two camp developments in the region of the SMC. These are the Magic Sky Ranch Girl
Scouts Camp and the Ben Delatour Boy Scout Ranch. The Magic Sky Ranch Camp is served by
a WWTF that has a capacity of 0.01 million gallons per day (mgd) which began operation in
2007. The Magic Sky Ranch Camp WWTF is located approximately 4.7 straight line miles from
the existing SMC WWTF, as shown on Figure 1. This distance, plus the fact that the Magic Sky
Ranch Camp WWTF does not have sufficient treatment capacity to serve SMC, makes
consolidation of the two facilities unreasonable.
The Ben Delatour Boy Scout Ranch has been served in the past by a lagoon and individual septic
systems. The camp has been working with the CDPHE to meet the treatment needs of the camp
given the intermittent nature of the operations. The existing wastewater systems are located at a
distance of approximately 1.4 straight line miles from the SMC WWTF, also shown in Figure 1.
Consolidation of the SMC and the Ben Delatour Boy Scout Ranch Camp wastewater treatment
Shambhala Mountain Center Wastewater Utility Plan
081-039.000 Wright Water Engineers, Inc. Page 7 Revised April 2010
was studied. However, the consolidation of these two facilities was not recommended due to
pipeline alignment obstacles, land ownership hoops, water rights considerations, and related
economic impacts of the geologic barriers and distance involved with consolidation.
The Ben Delatour Boy Scout Ranch Camp recently submitted a draft WUP (dated May, 2009) to
the NFRWQPA to address a separate WWTF to serve the Boy Scout Camp.
Finally, the 2007 update of the Areawide Water Quality Management Plan (208 Plan) for
Larimer and Weld Counties identified both SMC WWTF and the Ben Delatour Boy Scout Ranch
wastewater system as “minor sources” and did not envision consolidation of these facilities.
2.2 Wastewater Reuse
SMC currently has no plans for wastewater reuse.
2.3 Environmental Components
The SMC existing WWTF and the existing OWSs are located on the property owned by the
Shambhala International (Vajradhatu). The SMC varies in elevation from about 7,650 feet to
8,360 feet and the property drains directly into Elkhorn Creek. The site of the new WWTF is at
an elevation of approximately 7,725 feet. The soil and subsurface characteristics of a WWTF
site are important for design criteria. Based on soil mapping from the National Resources
Conservation Service’s (NRCS) National Cooperative Soil Survey, the soil in the WWTF area is
characterized as a Wetmore-Boyle-Moen Complex.
A geotechnical investigation was performed on the site in the area of the proposed dispersal
system and the new WWTF in November 2009. The result of the investigation showed soils and
rock consisting of silty sand, clayey sand, moderately to highly weathered granite, and slightly
weathered to fresh granite.
The SMC is a mountain environment with a variety of mountain wildlife including deer, elk,
bears, mountain lions, bobcats, rabbits, squirrels, chipmunks, and many species of birds.
WRIGHT WATER ENGINEERS, INC.2490 W 26TH AVE 100A
DENVER, CO. 80211(303) 480-1700
FIGURE
09/04/08 GIS; Z:\Project Files\08\081-039\081-039.000\CAD-GIS\GIS\girlscouts.mxd
LARIMER COUNTY, COLORADO
LOCATION MAP
RED FEATHER LAKES
Shambhala MountainCenter WWTF
Magic Sky RanchGirl Scouts Camp
APPROXIMATELY 4.7 MI.
Ben DelatourBoy Scout Camp
APPROXIMATELY 1.4 MI.
9N72W9N73W
10N72W
8N72W
10N73W
8N73W
9N71W
10N71W
8N71W
SHAMBHALA MOUNTAIN CENTERWWTF, MAGIC SKY RANCH
GIRL SCOUTS CAMP AND BENDELATOUR BOY SCOUT CAMP
PROJECT NO.
1081-039.000
Base Map: USGS Topographic Map- 24K Series
1 INCH = 8,000 FEET0 8,000 16,0004,000
FEET
Shambhala Mountain Center Wastewater Utility Plan
081-039.000 Wright Water Engineers, Inc. Page 9 Revised April 2010
The climate is characterized as low in precipitation (approximately 17 inches of precipitation per
year), low humidity, abundant sunshine, and usually low winds. Average monthly air
temperatures have wide seasonal variations. Summer temperatures range between 40°F and
95°F, while winter temperatures vary from -20°F to 50°F. Summer weather patterns produce
heavy thunderstorms that contribute a large portion of the annual precipitation.
Vegetation in the area of the existing WWTF and the proposed new WWTF consists of
groundcover that is comprised of native grasses, brush, and pine trees. The prominent trees
growing in the area are Ponderosa pines, Douglas firs, junipers, and aspen.
Wetland plants are present in the “dry swale” and the unnamed tributary. In addition, there are
wetland areas around the banks of Lake Sunyata and the existing wastewater treatment lagoon
(refer to Figure 9 for locations).
The NFRWQPA wetland policy is:
“No net loss of wetland functions should occur within the region, and cost effective use
of wetlands in urban design should be encouraged. Development within a designated or
delineated wetland should occur only when no other alternative exists. Wetland
mitigation should consist of replacement wetlands of similar type and quality, as
determined by appropriate scientific analysis, which results in an equal (at the minimum)
replacement of lost wetland functions. Wetland replacement within the same hydrologic
watershed as defined in the 208 Plan is the preferred compensatory mitigation measure.”
The proposed central WWTF is being planned to avoid existing regulated wetland areas.
However, the sewer lines and the piping to the dispersal system will need to be constructed
through wetland areas. Prior to submittal of the Site Application to the CDPHE, it is planned
that a wetland delineation be performed to assess the extent of impact of new construction.
It is anticipated that a Nationwide 404 Permit will need to be obtained from the U.S. Army Corps
of Engineers (USACE) to address the construction of the piping to the dispersal system and
wastewater collection piping.
Shambhala Mountain Center Wastewater Utility Plan
081-039.000 Wright Water Engineers, Inc. Page 10 Revised April 2010
2.3.1 National Environmental Policy Act (NEPA) Information
The wastewater facilities addressed in this WUP are on private lands and the project will be done
on behalf of a private landowner. The SMC is not intending to apply for construction funds from
the State Revolving Loan Fund for this project. Therefore, the requirements of NEPA may not
specifically apply to the project. It is anticipated that this WUP addresses the EA information
that is needed, including the need for the project, alternatives (when there is an unresolved
conflict concerning alternative uses of available resources), environmental impacts of the
proposed action and alternatives, and a listing of agencies and persons consulted.
3.0 WASTEWATER CHARACTERIZATION
The Utility Plan for the new central wastewater system to serve the SMC is described by a
service area, projected flow rates, required treatment, and the description of the new WWTF site
and system. The service area was established based on the property boundary and the eventual
consolidation of most of the existing septic tank/leach field systems into the central treatment
system. It is anticipated that Hyagriva and a residence at Windhorse Hill may remain on
residential OWS.
The population that will be served by the project has been estimated using past employee and
visitation records and proposed plans by the Owner.
Water demand by the existing residents form the basis for the wastewater flow projections.
The existing central treatment facility consists of a series of pre-sedimentation tanks, submerged
flow wetland cells, and a “polishing” pond. In CDPHE’s Compliance Advisory Letter (dated
September 27, 2007) it was stated that the effluent pond “appeared to be leaking, with a possible
unpermitted discharge to an un-named surface water creek”. This compliance advisory is one of
the reasons for the project. A copy of the Compliance Advisory Letter is included in Appendix
C.
The recommended treatment system was selected based on the Alternatives Analysis presented in
Section 5.0. A description of the proposed new WWTF is presented in Section 3.4.
Shambhala Mountain Center Wastewater Utility Plan
081-039.000 Wright Water Engineers, Inc. Page 11 Revised April 2010
3.1 Service Area Designations
The 2007 update of the 208 Plan for Larimer and Weld Counties has been prepared by the
NFRWQPA as part of the continuing 208 Plan update process. The 208 Plan identifies the SMC
as a “minor source” and recognizes the SMC service area. The service area map presented in
Figure 2 shows the entire property which is the service area. The service area map in Figure 2
defines the ultimate planning area (UPA). This is also the Wastewater Utility Planning Area
(WUSA). As presented in this WUP, the new WWTF will be built in two phases. The new
WWTF will ultimately be sized to treat flows from the WUSA based on full buildout conditions.
3.2 Population Datasets & Forecasts
Within the WUSA, each existing building with wastewater flows has been identified to be
currently either on the central wastewater system or on separate OWS. The buildings that are
currently on the central wastewater system are shown in Table 1 and the buildings that are
currently on OWSs are presented in Table 2.
Table 1 Existing Conditions - Buildings on Central Wastewater System
Vajra Bath House Rigden Lodge Ratna Bath House Padma Toilet House Kitchen Sacred Studies Hall Puspa Bath House-Downtown Shambhala Lodge Shotoku (Tiger-Lion)
TOTAL BUILDINGS 10
Table 2 Existing Conditions - Buildings on Separate OWS
Teachers Residence Stupa View Staff Housing Ma Mason Mason House and Trailer Red Feather-Ranch House, Caretakers House, Lodge Building
Red Feather Bath House
MPE Kitchen Stupa Support Building Windhorse Hill Hyagriva
With the exception of the Padma Bath House, the buildings presented in Tables 1 and 2 have an
associated septic tank (both on central and OWS).
Shambhala Mountain Center Wastewater Utility Plan
081-039.000 Wright Water Engineers, Inc. Page 13 Revised April 2010
It is planned that all of the buildings on the property (and within the WUSA) will eventually be
served by the central wastewater system in the future, with exceptions of Hyagriva (a single
family residence) and Windhorse Hill.
Currently, the SMC population averages approximately 45 employees and during peak
population periods (e.g., training sessions) with visitors there can be a total of up to 450 people
on the SMC site.
SMCs Land Use Plan allows 450 population. Subsequent to this, SMC purchased the adjacent
40 acres (formerly the Amokula Campfire Girls Camp). Larimer County allows this property’s
continued use of an additional 80 population, so the total allowable summertime population for
the SMC is 530.
It is planned that with additional SMC program development, up to a population of 650 will be
supported at the SMC. Therefore, Phase I of the project will be constructed to serve the 650
population even with the consideration that some of the buildings will still be on OWS. Phase I
construction will include new mechanical WWTF. It is also planned that all of the septic tanks in
the downtown area and the Ratna and Vajra Bath Houses will be bypassed and abandoned and
(by County Regulations) connected to the central wastewater system by the end of Phase I.
Phase II collection system construction is proposed to abandon the OWSs at Stupa View Staff
Housing and Red Feather Conference Center and associated buildings and connect on to the
central system.
Phase III is proposed to address collection system construction when there is OWS failure or any
new buildings that are built in the proximity of the Ma Mason, Mason House, Windhorse Hill
(only if mobile home use continues), Stupa Support Building/Visitor’s Center, MPE-Summer
Kitchen, and/or Teacher’s Residence. At this time, none of the OWSs that serve these buildings
are failing. The OWSs at these locations will be abandoned and connected to the central system
at the time of OWS failure (if and when they do fail) or prior to new buildings construction. All
buildings proposed for connection to the treatment facility during Phase III will meet Larimer
County requirements.
Shambhala Mountain Center Wastewater Utility Plan
081-039.000 Wright Water Engineers, Inc. Page 14 Revised April 2010
It is anticipated that a future phase will be developed at the SMC. This future phase would be a
major phase where additional buildings would be developed, up to an overnight population of
1,250 with day long events with up to 3,000 in attendance. The WWTF planning presented in
this WUP addresses the above proposed Phase I, Phase II, and Phase III with expansion area
allocated for the future phase (1,250 people).
The Land Use Plan for this future phase population (i.e., 1,250 overnight) and development must
be reviewed and approved by Larimer County. The currently approved Land Use Plan addresses
a population of 450. Subsequent to this, SMC purchased the adjacent 40 acres (formerly the
Amokula Campfire Girls Camp). Larimer County allows this property’s continued use of an
additional 80 population, so the total allowable summertime population for the SMC is 530.
It is anticipated that the CDPHE will require Larimer County approval of the Land Use Plan that
addresses the greater population (i.e., 650 overnight) and development addressed in this WUP.
Larimer County is a referral agency in the process for the Site Application addressing the
wastewater treatment facilities. A Site Application approval from CDPHE is required prior to
construction of a new wastewater treatment facility.
3.3 Wastewater Flow Projections
For planning purposes, combined historic metered water from four wells over a three year period
(years 2007 to 2009) was used to approximate the amount of wastewater flows to be expected in
the future. On a monthly basis, the SMC records the total amount of water pumped from the
water wells. The SMC also keeps a record of visitors and employees that stay overnight at the
site. (SMC does not track day use of the facility). However, using the total metered water use
includes use by day visitors (and any wastewater flow from day visitors). Also, day use
population is minimal and is not believed to have a significant wastewater contribution to the
SMC WWTF. Therefore, per capita water use is estimated based on overnight users only. The
estimated per person water use on a monthly basis for the past three years is shown in Figure 3.
The historic water use ranged from 28 to 64 gpd per person. This range is probably due to
factors such as varying irrigation amounts, type of program and activity taking place on the site,
number of beds in tent-based housing, etc. In addition, there have been incidents during this
Shambhala Mountain Center Wastewater Utility Plan
081-039.000 Wright Water Engineers, Inc. Page 15 Revised April 2010
0
10
20
30
40
50
60
70
Wat
er
Use
(G
PD
/Cap
ita
Average = 44 GPD/Capita
2007 2008 2009
period that have been reflected in the metered water use that would not have resulted in
wastewater flow. For example, a garden hose was left on overnight that significantly increased
the amount of water metered.
Based on the water use data presented in Figure 3, the overall average daily use is 44 gpd per
capita. For the purposes of this plan, WWE assumed that 50 gpd per person could be used in-
house and result in a wastewater flow. The wastewater flow of 50 gpd per person was compared
to other planning criteria (e.g., Metcalf Eddy, 2003) for this type of development and was
reasonable when compared with these criteria.
The 50 gpd per person was assumed to represent a conservative average daily wastewater flow.
To determine the rated capacity of the new WWTF, WWE used a factor of 1.5 times (including
infiltration/inflow [I/I]) the 50 gpd per capita (or 75 gpd per capita) to estimate a design peak day
flow to the WWTF.
Figure 3 Average Daily Water Use for Each Overnight Person by Month - 2007 to 2009
(Based on Total Metered Water Pumped from Onsite Wells and Number of Overnight Visitors Plus Staff)
Wat
er U
se (G
PD
/Cap
ita)
Shambhala Mountain Center Wastewater Utility Plan
081-039.000 Wright Water Engineers, Inc. Page 16 Revised April 2010
Using the average daily and peak day wastewater flows described above, and the population
projections described in Section 1.0, Figure 4 shows the projected wastewater flows to the
WWTF over a 20 year period. This average daily wastewater flow to peak day peaking factor is
consistent with several references. The Water Environment Federation (WEF) Manual of
Practice No. 8, Design of Municipal Wastewater Plants and the CDPHE Guidelines on Individual
Sewage Disposal Systems suggest average daily to peak day peaking factors of 1.6 and 1.5,
respectively.
Figure 4 shows two proposed increases in peak population over the 20 year planning period. The
first increase is from 450 to 530 total overnight guests and staff and then to to 650, which is
anticipated to occur in 2013. The WWTF will be designed to handle the flow from this increase.
This increase in peak population is contigent on modifications that may be imposed by Larimer
County.
The next population increase would be for up to 1,250 overnight guests and employees and is
projected to occur in 2018. A WWTF expansion will be needed to accommodate this 1,250
population.
Shambhala Mountain Center Wastewater Utility Plan
081-039.000 Wright Water Engineers, Inc. Page 17 Revised April 2010
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
10000
0
10000
20000
30000
40000
50000
60000
70000
80000
90000
100000
Po
pu
lation
Flo
w (
gpd
)
Year
Avg. Day WWTF Capacity Population
Figure 4 Projected Flow and Peak Population for 20 Year Planning Period Compared to
Design Capacity
3.3.1 Infiltration/Inflow Analysis
The collection system is small and inflow from such sources as leaky faucets are generally
controlled though water use monitoring and water conservation measures. Infiltration from
groundwater is limited due to the overall groundwater table, generally lower than the collection
system, and the low precipitation in the region.
The current collection system is comprised of mostly 4-inch diameter pipelines (SDR -35) that
have been buried at shallow depths and are not in the typical groundwater zone. Therefore,
infiltration from groundwater conditions probably does not occur.
There are few manholes on the current system that could otherwise be sources of I/I. There are
numerous septic tanks, and the wetland cell pre-sedimentation tanks that are constructed from
precast concrete. Normally, precast septic tanks have been constructed to be water tight. Also,
Shambhala Mountain Center Wastewater Utility Plan
081-039.000 Wright Water Engineers, Inc. Page 18 Revised April 2010
these septic tanks are installed away from stormwater runoff areas. There is only one location
where a septic tank could possibly receive some storm water runoff, and diversion landscaping is
maintained in that area.
The existing wetland cells are lined with a synthetic membrane (polypropylene 30 mil) that was
constructed by a reputable liner installer (Watersaver Company) and the installation of the liner
was observed by a competent SMC employee.
SMC staff has made observations of the outfall into the existing polishing pond and the inflow
into the manhole ahead of the wetland pre-sedimentation tanks. These observations have been
made early in the morning hours between 4 a.m. and 6 a.m. at various times of the year when
population on the property was at a minimum. Only “pencil thin” flows were observed at these
locations.
In addition, staff and guests are encouraged to report plumbing fixtures that are found to be
leaking, and signs with instructions how to report leaks are posted in many of the public
restrooms.
This plan anticipates that most of the existing sewer piping on the site will be replaced. Future
wastewater collection pipelines (to connect existing buildings that are currently on OWS) will be
designed and constructed to minimize infiltration.
3.3.2 Character of Influent
The inflow wastewater to the existing wetland treatment system is characterized by a domestic
sewage process by septic tanks. Most of the buildings that are currently on the existing central
wastewater system have an installed septic tank. The existing buildings that are known to have
septic tanks and the associated septic tank volumes are presented in Table 3.
Shambhala Mountain Center Wastewater Utility Plan
081-039.000 Wright Water Engineers, Inc. Page 19 Revised April 2010
Table 3 Existing Buildings on Central Wastewater System
That Have Septic Tanks
Building Septic Tank Volume (Gallons) Comments Phase to Connect
to Central System Vajra Bath House 1,500 Summer Use Only Phase I Ratna Bath House 1,500 Summer Use Only Phase I Shambhala Lodge 2,000 & 1,500 Phase I Padma Toilet House 2,0001 Summer Use Only Phase I Sacred Studies Hall 1,500 Phase I Kitchen 500 and 1,500 Grease Trap-500 Gallons Phase I Bath House-Downtown 1,500 Phase I Puspa 1,250 Phase I Shotoku (Tiger-Lion) 1,500 Phase I Rigden Lodge 330 and (3) 1,500 Grease Trap-330 Gallons Phase I
TOTAL NUMBER OF SEPTIC TANKS 13 1 This septic tank receives sewage from Padma Toilet House, Sacred Studies Hall, Kitchen, Puspa, and Shotoku
The existing buildings that are currently on separate OWS are presented in Table 4.
Table 4 Existing Buildings Currently on Separate OWS
Building Served Septic Tank Volume (Gallons) Comments Phase to Connect
to Central System
Teacher’s Residence 1,250 48 Infiltrators; 3-100 Foot trenches Phase III
Stupa View Staff House-Phase I 2,000 Infiltrators-54 Chambers; 827 ft2 Phase II
Ma Mason 1,000 Phase III Mason House & Mason Trailer 750 Phase III Red Feather-Ranch House, Caretaker’s House, Lodge Building
Old Tank = 750 New Tank = 1,000 Grease Trap Phase II
Red Feather Bath House (Men & Women) 2 - 1,500 Phase II
MPE Kitchen 1,250 Summer Only Phase III Stupa Support Building 1,000 Phase III
Haygriva 1 Tank-Volume Unknown
Single Family Residence
To Remain on OWS
Windhorse Hill 2 Tanks-Volume Unknown
Residence-4 Mobile Homes Phase III
TOTAL NUMBER OF SEPTIC TANKS 13
Based on Tables 3 and 4, there are a total of 26 existing septic tanks on the SMC. In addition,
there are three existing grease interceptors. Each grease interceptor is planned to be replaced
Shambhala Mountain Center Wastewater Utility Plan
081-039.000 Wright Water Engineers, Inc. Page 20 Revised April 2010
when the building that it serves joins the central system. Each grease interceptor will be properly
sized, according to codes/regulations.
The wastewater quality data obtained in the influent to the existing wetland cells demonstrate
BOD concentrations, as shown in Table 5 from samples taken at periodic time intervals. The
average of these BOD concentration data is 164 mg/L.
Table 5 Influent BOD Concentrations to the Existing Wetland Cells (After
Presedimentation Tanks) on Various Dates
Sample Date Influent BOD (mg/L)
8/27/2006 143 8/30/2006 137 9/3/2006 152 9/6/2006 111 9/10/2006 148 9/13/2006 169 9/17/2006 100 9/20/2006 134 9/24/2006 234 9/28/2006 150 3/18/2007 158 7/11/2007 331 Average 164 Minimum 100 Maximum 331
The wastewater quality characteristics to the new WWTF are expected to change somewhat as
the existing septic tanks are bypassed and facilities are placed on the collection system and the
OWSs are abandoned and connected to the central system. The existing septic tanks remove a
portion of the suspended solids and BOD in the raw wastewater. Therefore, the concentrations of
these parameters in the raw wastewater to the new WWTF may be lower than will be
experienced when the OWSs are abandoned.
A significant contribution of organic loading to the WWTF will be from kitchen and wash room
sources. A Water Environment Research reference, “Food Service Establishment Wastewater
Shambhala Mountain Center Wastewater Utility Plan
081-039.000 Wright Water Engineers, Inc. Page 21 Revised April 2010
Characterization,” which was provided to WWE by NFRWQPA Board Members, provides a
design value for BOD concentration from restaurants of 1,523 mg/L. Wastewater from kitchens
on the SMC site is expected to account for approximately 15 percent of the total wastewater flow
to the WWTF (Leverenz and Tchobanoglous). The remaining 85 percent of wastewater will be
from other domestic uses and is expected to have a BOD concentration of 240 mg/L (CDPHE
ISDS Regulations). The combined BOD concentration is expected to be 430 mg/L. For the new
WWTF, at average day flow, the BOD loading to the WWTF will be 117 pounds per day and at
peak day the BOD loading will be 175 pounds per day. Figure 5 shows the projected loading to
the WWTF over a 20-year period, assuming this organic loading concentration.
Figure 5 Projected BOD Concentration for 20-Year Planning Period Compared to Design
Capacity
0
50
100
150
200
250
300
350
400
Load
ing
(lb
s./d
ay)
Year
Average Day WWTF Capacity
Shambhala Mountain Center Wastewater Utility Plan
081-039.000 Wright Water Engineers, Inc. Page 22 Revised April 2010
Other wastewater quality characterization parameters and their expected concentrations are
presented in Table 6.
The parameters and concentrations of the parameters shown in Table 6 were used for the
planning of the wastewater treatment processes presented in this WUP. The concentrations of
the parameters shown in Table 6 are based on existing, onsite data, WWE experience, and
criteria in various references (e.g., Metcalf Eddy 2003).
Table 6 Character of Wastewater Influent to the Proposed WWTF
Parameter Concentration Units Carbonaceous BOD5 (Average) 430 Milligrams per Liter (mg/L) Total Suspended Solids (TSS) (Average) 300 mg/L Ammonia Nitrogen (Average) 50 mg/L as Nitrogen Total Alkalinity (Average) 50 mg/L as Calcium Carbonate pH 6.8 to 7.5 Standard Units (SU)
3.3.3 Industrial Pretreatment Program
The SMC is a religious retreat resort with no industries within the WUSA. The property
managers are responsible for maintaining the individual septic tanks.
3.4 Treatment Works
Three treatment process alternatives were evaluated for the wastewater generated at the SMC.
The evaluation was based on conceptual design and resulted in a preferred alternative. The
alternative analysis is presented in Section 5.0.
This section describes the preferred alternative and presents the proposed site location for the
WWTF. A treated effluent dispersal system for discharge to groundwater is also described.
3.4.1 Process System and Dispersal System
The preferred alternative for the treatment processes at SMC were based on meeting the water
quality limits received from the CDPHE in the PELs letter, see Appendix A. The PELs for
groundwater discharge were issued by the CDPHE on October 30, 2009 (PEL No. 200188). The
Shambhala Mountain Center Wastewater Utility Plan
081-039.000 Wright Water Engineers, Inc. Page 23 Revised April 2010
preferred treatment process alternative addresses the PELs for groundwater discharge, see
Section 4.4.
The specific treatment processes proposed for the preferred alternative for the SMC are shown in
Figure 6. The selection of the treatment processes may be further evaluated by the design team
during final design, as further discussed below under specific process system descriptions. Each
process will be designed to treat the design peak day flow of 49,000 gpd. Refinement of sizes
and capacities of each treatment process will be determined during final design. The following
are short descriptions of each process within the preferred alternative.
Manually Cleaned Bar Screen – A bar screen will be provided at the entrance location to
the WWTF to screen out large items that are non-biodegradable. The screen will have
openings of ¼ to ½ inch and will need to be manually raked on a daily basis. During final
design, the design team may further evaluate this treatment process to determine if it is a
CDPHE requirement and an appropriate and necessary treatment process for the SMC
WWTF.
Influent Flow Measurement – An open channel flow Parshall (or Palmer Bowlus) Flume
or a mag meter will be used to measure the influent to the WWTF. This flow
measurement flume will be placed inside of the headworks room of the WWTF building.
Sequencing Batch Reactors (SBRs) – The SBR process is a form of the activated sludge
process in which anoxic zone, aeration, sedimentation, and decant functions are combined
in a single reactor. Two SBRs are proposed in the preferred alternative to address the
redundancy required by the CDPHE. The SBR process employs a five stage cycle: fill,
react, settle, draw, and idle. The SBR will provide nitrification and denitrification for
biological nitrogen removal. Biological reactions begin to take place as the raw
wastewater fills the tank and a period is allowed for the anoxic conditions to develop (for
denitrification). The wastewater is then aerated to provide the major BOD reduction and
nitrification. The next step includes settling and, after the settling period, the supernatant
is decanted (or drawn off from the top) and discharged to the flow equalization basin.
Shambhala Mountain Center Wastewater Utility Plan
081-039.000 Wright Water Engineers, Inc. Page 24 Revised April 2010
During final design, the design team will determine if the SBRs should be placed above
or below grade. The above grade option may be preferred to avoid extensive rock
excavation. In the case that the SBRs are above grade, a raw water pump station will be
required upstream of the SBRs to pump wastewater to them.
Sodium Bicarbonate Addition – The treatment process of nitrification consumes
alkalinity in the wastewater. The background alkalinity concentration in the raw water
supply to the SMC does not have adequate alkalinity for full nitrification (i.e.,
concentrations of alkalinity are less than 200 mg/L as calcium carbonate). Therefore, an
alkalinity supplement is needed in the preferred alternative. This will be provided by a
liquid sodium bicarbonate feed system.
Flow Equalization – Since the SBR process is a batch process, flow equalization will be a
part of the preferred alternative. The flow equalization basin consists of a tank that has
sufficient volume to equalize the flow and allow the effluent to be pumped at a uniform
rate to the subsequent treatment processes. Submersible pumps will be used to provide
the flow equalization to the filtration step.
Filtration – The presence of higher levels of suspended solids will be detrimental to the
disinfection process and the effluent dispersal system. Efficient removal of any biosolids
that could carry over after the decant cycle from the SBR is needed. The preferred
alternative includes a filtration step to remove the remaining biosolids and ensure an
effluent that meets the nitrate limit.
There are two types of filters that would be applicable at the WWTF: fabric filter or
granular media filter. The type of filter to be used at the WWTF will be selected during
the final design phase of the project.
The fabric or granular filters are cleaned by a backflush of the filters that will be recycled
to the treatment process.
During final design, the design team will further evaluate this treatment process to
determine if it is an appropriate and necessary treatment process for the SMC WWTF.
Shambhala Mountain Center Wastewater Utility Plan
081-039.000 Wright Water Engineers, Inc. Page 25 Revised April 2010
Ultraviolet Light (UV) Disinfection – The final treatment step will be to disinfect the
treated effluent for inactivation of microbiological agents by the use of UV light. A
flume or mag meter will measure flow.
During final design, the design team will further evaluate disinfection alternatives and
may consider chlorination as an alternative to UV disinfection.
Effluent Pump Station – The treated effluent will be pumped to the dispersal system
through the effluent pump station. The station will be a wetwell located in the WWTF
building with two submersible effluent pumps. An effluent flow meter will be installed
on the discharge force main pipeline and will be located in the WWTF building.
Emergency Power Generator – Although not a specific treatment process, a key
component to the treatment process will be an emergency, propane powered generator to
provide electrical power to the essential treatment processes during a time of power
outages.
Treated effluent from the WWTF will be discharged to the groundwater through the dispersal
system. The proposed discharge permit point of compliance for the SMC WWTF is in the
Effluent Pump Station wetwell, just prior to pumping to the dispersal system. As such, the
dispersal system is not intended to provide additional treatment. The purpose of the dispersal
system is to maximize the dilution of the effluent wastewater with groundwater and surface water
in the unnamed swale watershed. SMC and WWE met with the CDPHE to discuss the proposed
concept for the dispersal system. CDPHE staff agreed that this concept would be acceptable for
discharge to groundwater.
The dispersal system will include three dispersal beds in series in the unnamed swale thalweg
north of the proposed WWTF building. Treated effluent will enter the dispersal beds through a
force main from the effluent pumps station that will deliver treated effluent to a perforated
manifold inlet pipe at the upstream end of the upstream dispersal bed. The dispersal beds will be
designed to provide a total of three days of hydraulic residence time at peak day flow. The
dispersal beds will be installed in the alluvium and weathered granite of the unnamed swale.
Shambhala Mountain Center Wastewater Utility Plan
081-039.000 Wright Water Engineers, Inc. Page 26 Revised April 2010
The dispersal beds will be configured in a step down arrangement down the unnamed swale and
will be separated by native material. The native material is comprised of silty sand and
weathered granite and has a hydraulic conductivity of 5 x 10-4 cm/s (10.6 gpd/sf).
The dispersal beds are currently envisioned to be approximately 50 feet long parallel with the
unnamed swale thalweg, 10 feet wide, and 5 feet deep. The dispersal beds will be composed of
¾ inch to 1-inch washed gravel wrapped in geotextile fabric. This material will have a hydraulic
conductivity of approximately 280 cm/s (250,000 gpd/sf). The porosity of the gravel will be
approximately 0.4 and will provide a total storage volume of approximately 49,000 gallons.
The native material has a much lower hydraulic conductivity than the proposed dispersal bed
material and will act as a semi-impervious barrier between each dispersal bed. (Travel velocity
in the swale through the native material is approximately 0.06 ft/d.) The Geotechnical
Investigation and Phase II Percolation Study for the SMC WWTF performed by CTL Thompson
in included in Appendix D.
Because the native material has a lower hydraulic conductivity, and to minimize the chance of
effluent wastewater surfacing in the unnamed channel during low flow conditions, a subsurface
“overflow” channel will be installed between each dispersal bed to provide a preferential flow
path to the next downstream dispersal bed. The overflow channels will be designed so that the
invert of the overflow channel is near the top of the upstream dispersal bed.
At the end of the downstream dispersal bed, an overflow channel will be designed to run from
the dispersal bed to near the confluence of the unnamed swale with Elkhorn Creek. At the
termination of the overflow channel, the effluent wastewater is expected to join the surface
system. A schematic plan and profile of the conceptual design for the dispersal system are shown
in Figures 7 and 8.
As stated above, the dispersal beds will be sized to each provide storage for one day of effluent
wastewater under peak design flow conditions. Under existing average day flow conditions of
15,000 gpd, the hydraulic residence time through the dispersal system will be approximately 10
days.
Shambhala Mountain Center Wastewater Utility Plan
081-039.000 Wright Water Engineers, Inc. Page 27 Revised April 2010
It should also be noted that, because of the relatively large hydraulic conductivity of the dispersal
bed material, the beds are expected to provide a preferential flow path down the unnamed swale.
This could have the effect of raising the local water table in the thalweg and may increase the
opportunity for mixing of the wastewater effluent with groundwater.
Under typical conditions, the unnamed swale is dry. Surface flow is expected during runoff
events (e.g. snowmelt or rainfall). Design of the dispersal field will be done to minimize
ponding of water on the surface.
Evidence of groundwater that provides contributory flow into the watershed is apparent in
several locations. There are several springs in the watershed, as shown in Figure 9, that indicate
that groundwater is present and joins the surface system. The springs are primarily periodic in
nature and provide surface flow primarily during snowmelt and the wet time of the year. In
addition, during the geotechnical investigation performed in December 2009, groundwater was
present in the test holes at depths ranging between 6 and 15 feet below ground surface. This
groundwater and surface water is available for dilution with the WWTF treated effluent.
To quantify the dilution that could be achieved from the unnamed swale watershed groundwater
and surface water, WWE estimates that the surface and groundwater recharge to the watershed is
approximately 1 to 2 inches over the watershed area. The unnamed swale watershed is
approximately 240 acres, and feeds into Elkhorn Creek west of the SMC. The watershed area is
delineated as shown in Figure 9. The water volume estimated to be available for recharge to the
surface and groundwater system is approximately 20 – 40 acre-feet or 6.5 – 13.0 million gallons
per year. On an annual basis, this implies a dilution ratio of approximately 1:1 to 2:1 of
groundwater and surface water to average day wastewater effluent.
As a contingency plan, in the case that the dispersal system should fail, the existing lagoon east
of the WWTF building can be used to store wastewater until repairs can be made to the dispersal
system.
E l k h o r n C r e e k
R i o R M D C
Marion Spring Box
2/15/10; Z:\Project Files\08\081-039\081-039.000\CAD-GIS\GIS\UnnamedDrainage_Watershed-9.mxd Base Map: USGS 1:24k Topographic
®1 inch = 1,000 feet
0 1,000 2,000500Feet
WRIGHT WATER ENGINEERS, INC.2490 W 26TH AVE 100A
DENVER, CO. 80211(303) 480-1700
FIGURELARIMER COUNTY, COLORADO
SHAMBHALA MOUNTAIN CENTERUNNAMED DRAINAGE SWALE WATERSHED 9
SECTIONS 13, 14, 23, 24, T 9N, R 73W, 6TH P.M.
PROJECT NO.081-039.000Site Map
LegendApproximate Spring LocationUnnamed SwaleApproximate Watershed Area (240 acres)
Shambhala Mountain Center Wastewater Utility Plan
081-039.000 Wright Water Engineers, Inc. Page 32 Revised April 2010
3.4.2 Infrastructure Sizing and Staging
A preferred alternative treatment process system was sized based on the projected average daily
flow of 33,000 gpd with a summer maximum daily flow of 49,000 gpd. These wastewater flows
will address Phase I of the anticipated growth forecasts of up to 650 persons, see Section 3.2.
Additional room for expansion for the future phase population forecasts, up to 1,250 persons,
have been allowed in the site planning for the WWTF.
3.4.3 Location and Siting
An evaluation of site locations for the WWTF was performed. The major considerations for the
WWTF site were the location of the existing collection system, odor considerations, existing site
accessibility, and impact to the Land Use Plan.
The preferred WWTF site is located at the site of the existing SMC maintenance building as
shown in Figures 10 and 11. This site provides adequate space for an access road, treatment
process building (with consideration of future expansion of capacity), location with respect to the
proposed discharge point, and location with respect to the existing SMC maintenance building.
3.4.4 Biosolids Handling
The proposed treatment plant processes produces waste sludge (biosolids) that will require
treatment and periodic removal. Biosolids will be stabilized in an aerobic digester and biosolids
storage basin or in a sludge storage tank. During final design, the design team will determine if a
sludge storage tank or an aerobic digester should be used. The waste sludge will be aerated in
this basin and allowed to settle. Decant from this basin will be drawn off and recycled to the
head of the WWTF. The remaining biosolids will be digested and the concentration of solids
will be increased to the volume capacity of the basin. It is estimated that the basin will require
removal of biosolids on a periodic basis.
The biosolids will be removed and disposed of by a qualified biosolids handling and disposal
contractor.
Shambhala Mountain Center Wastewater Utility Plan
081-039.000 Wright Water Engineers, Inc. Page 33 Revised April 2010
3.4.5 Schematic of Treatment Works
As previously discussed, the process flow schematic for the preferred alternative is presented in
Figure 6. A WWTF site plan and building layout are presented in Figures 11 and 12,
respectively. In addition, a treatment process profile of the preferred alternative is presented in
Figure 13.
3.4.6 Odor Control Considerations
The potential for aesthetic impacts of odors from the wastewater system needs to be addressed
from the perspective of the wastewater collection system and the wastewater treatment processes.
The future wastewater collection system will include the addition of new manholes that will
allow maintenance of the collection system. The manholes will be a potential source for odor
emissions. Therefore, it is proposed that the manholes that are installed at the SMC include a
seal between the manhole lid and the rim frame.
The preferred treatment alternative and the SBR process normally results in good control of odor
emissions since the mixed liquor in the SBR basin immediately mixes with the incoming raw
sewage. However, there will be odors at the WWTF, especially from the Headworks Room.
Therefore, the Headworks Room and the WWTF building air will be vented to an odor control
system. It is anticipated that an organic biofilter or a synthetic media canister type filter will be
used for filtering the air from the Headworks Room and the WWTF building. The specific odor
control system that will be used at the site will be determined in final design. Either of these
odor control processes will reduce the potential for odor release and impact to the population at
SMC or adjacent properties.
3.5 Air Quality Permit
The WWTF is a minor stationary source of biological air contaminants typical of a domestic
wastewater treatment system. A permit is not required by the Colorado Air Quality Commission.
WRIGHT WATER ENGINEERS, INC.2490 W 26TH AVE 100A
DENVER, CO. 80211(303) 480-1700
FIGURE
12/18/08 GIS; Z:\Project Files\08\081-039\081-039.000\CAD-GIS\GIS\Figure_10.mxd
SHAMBHALA MOUNTAIN CENTER
Proposed Wastewater Treatment Facility LocationRigden Lodge
Existing Wetland
LakeSunyata
ExistingPolishing Pond
Shambhala Lodge
KitchenSacred Studies Hall
Dry Swale
Proposed Dispersal System
hUnnamed Tributary
Stupa View Staff Housing
Ma Mason
Mason House
Red FeatherConference Facilities
Ratna Bath House
Vajra Bath House
Shotoku
Padma Toilet HousePuspa
Teacher's Residence
Windhorse Hill
Hyagriva
Stupa
Stupa Support Building
MPE Kitchen
Downtown Bath House
WASTEWATER TREATMENT FACILITYLOCATION
PROJECT NO.
10081-039.000
Photo Source: NAIP 2005 (USGS)
®1 in = 600 feet
0 600 1,200300Feet
LegendBuildings to connect to CentralWastewater System in Phase 1
Shambhala Property Boundary
Buildings to connect to CentralWastewater System in Phase 2Buildings to connect to CentralWastewater System in Phase 3To remain on OWS
Shambhala Mountain Center Wastewater Utility Plan
081-039.000 Wright Water Engineers, Inc. Page 38 Revised April 2010
3.6 Stormwater Management Plan
Stormwater discharges associated with construction disturbances greater than 1 acre require a
Management Plan and Colorado Discharge Permit. A site specific soils assessment was
performed in December, 2009. Based on this assessment, it was determined that construction
dewatering will be anticipated during the installation of the WWTF. The requirements for
permitting construction dewatering and stormwater discharges will be the responsibility of the
construction contractor.
3.7 Site Characterization Report
The site plan for the new WWTF is not within a floodplain. Federal Emergency Management
Agency (FEMA) floodplain maps of the area are included in Appendix E and show the site
within Zone X.
Natural hazards, such as unstable subgrades, are not present on the site. It is anticipated that rock
will be encountered under the site and will need to be excavated for the construction. The extent
of rock excavation will be identified and determined during the final design process.
3.8 Collection System
The existing wastewater handling and treatment within the SMC service area consists of a
portion of buildings on 1) a central wastewater collection and treatment system and 2) some
buildings on OWS. The buildings that are on the centralized and OWS systems are identified in
Tables 1 and 2. The SMC existing central wastewater collection system is shown on Figure 14.
The existing collection system has one manhole located upstream of the existing pre-
sedimentation basins. Furthermore, existing 4-inch diameter pipes are insufficiently sized to
accommodate future flows increased by population growth onsite.
For the existing centralized system, wastewater flows from buildings served by the centralized
system are directed to septic tanks which outlet to the collection system.
Septic tank effluent flows to six presedimentation tanks prior to wetland cell treatment.
Following the wetland cells, water is piped to the existing polishing pond. The effluent is then
evaporated or infiltrated to the groundwater under the pond.
Shambhala Mountain Center Wastewater Utility Plan
081-039.000 Wright Water Engineers, Inc. Page 39 Revised April 2010
3.8.1 Major Lift Stations
Currently, there is one small lift station in the existing SMC collection system located just to the
southwest of the existing polishing pond (see Figure 14). This existing lift station receives raw
wastewater from Ratna and Vajra bath houses and pumps back to the existing wetland cell
treatment system through a force main that extends from the lift station to a manhole just
upstream of the presedimentation basins.
When the new WWTF is constructed, it is proposed that the wastewater from the Ratna and
Vajra bath houses be conveyed by gravity to the new site. The new gravity sewer (alignment
shown in Figure 10) will result in abandoning the existing lift station and force main.
Therefore, there are no proposed lift stations in the wastewater collection system.
3.8.2 Interceptor Sewers
No interceptor sewers are located in the existing SMC collection system.
3.8.3 Collection System Plan
The Phase I, Phase II, and Phase III collection system plan is shown in Figures 15 and 16 along
with the location of existing SMC buildings, the existing septic tanks and OWSs, new and
replaced/abandoned piping, and the new WWTF. The collection system to serve the future phase
(1,250 persons) is not shown since building planning is forthcoming.
The existing septic tanks and OWSs will be abandoned in a phased approach. Manholes near
buildings will be sealed with a flexible and reusable sealant to help control wastewater odor.
Sewer lines will be designed to limit rock tunneling or trenching. The anticipated design depth
from the manhole rim to the top of the pipe is 5 feet. The overall average pipe slope was
calculated by considering topographic elevations of the starting and ending points of the pipe.
The average slope is anticipated to be approximately 5 percent.
Shambhala Mountain Center Wastewater Utility Plan
081-039.000 Wright Water Engineers, Inc. Page 40 Revised April 2010
Phase I
The main objective of the Phase I wastewater system plan is to transfer existing central wetland
wastewater treatment to the new WWTF. Phase I flows transferred will be:
Sacred Studies Hall
Downtown Bath House
Downtown Kitchen
Shotoku (Tiger-Lion)
Puspa
Padma Toilet House
Shambhala Lodge
Rigden Lodge
Ratna and Vajra Bath Houses
An 8-inch diameter line will be used to bypass the existing six presedimentation tanks that
currently outlet to wetland treatment as shown in Figure 14. A new manhole will be constructed
directly to the west of the existing presedimentation tanks and a new 8-inch PVC line will
connect this junction carrying centralized wastewater flows to the new WWTF. The six
presedimentation tanks and wetland cells will be abandoned as treatment processes after
conclusion of Phase I construction.
A new 8-inch diameter sewer line will also be constructed in Phase I to collect wastewater from
the “downtown” area of SMC. New sewer lines and service lines will be installed to bypass
existing septic tanks and allow the abandonment of existing septic tanks (as shown in Table 3).
A new gravity section of 8-inch sewer line will be installed to convey the wastewater from the
existing Ratna and Vajra Bath Houses. The existing lift station and force main will be
abandoned. It is also planned that the septic tanks serving Ratna and Vajra will be bypassed and
abandoned in Phase I.
Shambhala Mountain Center Wastewater Utility Plan
081-039.000 Wright Water Engineers, Inc. Page 41 Revised April 2010
The construction of the Phase I sewer line segments will coincide with the construction of the
new WWTF, also planned for Phase I and will be completed between September 1 and
December 31, 2011.
Phase II
Several new segments of 8-inch diameter sewer line will be constructed in Phase II, as shown on
Figure 15. Major pipeline segments will collect wastewater from:
Stupa View Staff Housing
Facilities in the Red Feather Conference Center area
The OWSs that currently serve these areas will be abandoned as a result of the Phase II
construction. In accordance with CDPHE guidance and expectation, connection of these
buildings to the central wastewater system will occur within one year following the new WWTF
completion and start-up.
The existing 4-inch sewer line that currently serves the Shotoku (Tiger-Lion) facility will be
abandoned in Phase II. The Shotoku will be connected to the new Phase II segments of sewer
line as shown on Figure 15. The septic tank currently serving Shotoku will be bypassed and
abandoned in this phase.
Phase II collection system will be completed between September 1 and December 31, 2012.
Phase III
There are several facilities in the SMC service area that are currently on OWSs that are in rather
remote locations with respect to the new WWTF. These facilities are:
Stupa Support Building/Visitor’s Center
Ma Mason
Mason House
MPE-Summer Kitchen
Shambhala Mountain Center Wastewater Utility Plan
081-039.000 Wright Water Engineers, Inc. Page 42 Revised April 2010
Teacher’s Residence
Windhorse Hill (only if mobile home use continues)
Discussions between the SMC and the Larimer County Health Department staff have resulted in
the approach that the OWSs that serve these facilities currently appear to be functioning properly
and that these facilities should be put on the central collection system when failure of these
existing OWSs occurs. Therefore, construction is on an as needed basis and there is no specific
timeline.
A Phase III category is presented in this WUP to address the collection system improvements that
will be needed when these existing OWSs fail. A new 8-inch south sewer line will be
constructed to the Stupa area to pick up the Support Building/Visitor’s Center and the MPE-
Summer Kitchen, as shown on Figure 16.
Also, a new sewer line will be constructed to serve, by gravity, the Teacher’s Residence.
The Windhorse Hill (a.k.a. Monroe Property) area will be served by a gravity sewer line if it is
determined by the SMC people that the existing mobile home use will continue. This sewer line
segment will be an extension of the sewer line that will be serving the Mason House and Trailer,
as shown on Figure 16.
Long Term Future Phase
A future phase of additional SMC program facilities to accommodate up to 1,250 persons is in
concept development planning. The new WWTF has been planned for the expansion of
treatment to address this future phase population at a maximum daily capacity of 94,000 gpd.
Since the locations of building facilities for this future phase has not been determined, the
specific sewer line alignments are not known. Therefore, this WUP will need to be amended to
address the collection system planning for this future phase. Planning criteria for this future
phase would include locating future buildings in the proximity of the proposed sewer lines as
presented in this WUP, maintaining the use of the downtown center sewer line, keeping the
Shambhala Mountain Center Wastewater Utility Plan
081-039.000 Wright Water Engineers, Inc. Page 43 Revised April 2010
required separation distance between sewer and potable water lines, and aligning the future sewer
lines in roads, as possible, for ease of access and maintenance.
Collection System Costs
An opinion of probable capital costs (hereinafter referred to as “estimated capital costs”) was
developed for each phase of the collection system (Phases I, II, and III). The estimated capital
costs presented in this study are considered to be conceptual. A summary of the estimated capital
costs by phase of development is presented in Table 7. More detailed estimated capital costs are
presented in Appendix G.
Table 7 Estimated Capital Costs of Collection System By Phase
Phase Estimated Capital Costs Phase I $210,000 to $310,000 Phase II $320,000 to $470,000 Phase III $530,000 to $780,000
3.9 Maps
Topography for the entire SMC site was used to develop the maps for this WUP.
3.9.1 Treatment Plant Site Envelope
The proposed site plan for the WWTF is shown in Figures 10 and 11.
3.9.2 Service Area
The service area (and proposed WUSA boundary) is shown in Figure 2.
3.9.3 Collection System
The existing collection system and collection system plan are shown on Figure 14, 15, and 16.
Shambhala Mountain Center Wastewater Utility Plan
081-039.000 Wright Water Engineers, Inc. Page 47 Revised April 2010
4.0 WATER QUALITY CHARACTERIZATION
Existing buildings on separate OWSs within the service area are presented in Table 2. Each of
these systems are small systems that have leach fields that discharge to the soil. As discussed in
this WUP, these OWSs with the exception of Hyagriva (to remain a single family residence) and
Windhorse Hill (if it remains only as a single family residence) will eventually be connected into
the central wastewater system.
The existing central wastewater system includes septic tanks, a series of pre-sedimentation tanks,
submerged flow wetland cells, and a non-discharging effluent pond. In CDPHE’s Compliance
Advisory Letter (dated September 27, 2007) it was stated that the effluent pond “appeared to be
leaking, with a possible unpermitted discharge to an un-named surface water creek”. This
Compliance Advisory is addressed by the recommendations in this WUP.
PELs have been obtained from the CDPHE to address a groundwater discharge.
This section presents the receiving water quality issues pertaining to the design of the new
WWTF.
4.1 Water Quality of the Receiving Water
The receiving water is an undesignated groundwater basin underlying the site within the Cache
La Poudre River watershed. The permit point of compliance will be prior to discharge of the
treated effluent into the dispersal system. The PELs for the groundwater discharge are provided
by the CDPHE in Appendix A.
4.2 TMDLs and/or Waste Load Allocations
There are no approved or projected waste load allocations or total maximum daily load
requirements associated with the effluent discharge.
Shambhala Mountain Center Wastewater Utility Plan
081-039.000 Wright Water Engineers, Inc. Page 48 Revised April 2010
4.3 Watershed Issues
The NFRWQPA, in the 2007 update of the 208 Plan for Larimer and Weld Counties have
identified the SMC WWTF as a minor source. There are no known water quality issues within
the watershed.
4.4 Preliminary Effluent Limitations (PELs)
Planning for wastewater treatment and discharge at the SMC has evolved over the last several
years. Initially, SMC requested PELs for groundwater discharge for the facility on September 5,
2006. In response, CDPHE issued PELs on October 23, 2006.
SMC sent a letter to the CDPHE on June 16, 2008 requesting PELs for surface water discharge.
The request letter asked that the PELs for groundwater discharge be modified from the original
0.018 mgd to 0.05 mgd. In addition, the request was for effluent discharge to surface water of an
unnamed tributary to Elk Horn Creek at a flow of 0.05 mgd. The request letter also stated that
irrigation use of the treated effluent would be practiced for onsite landscaping during the growing
season.
In response to the June 16, 2008 request, PELs were received from the CDPHE on July 24, 2008
stating PELs for surface water discharge to a tributary to Elk Horn Creek. Just as the first draft
Wastewater Utility Plan (dated February 2009) was being submitted to the NFRWQA last year,
the CDPHE revised the surface water discharge PELs. In a February 25, 2009 letter, the CDPHE
stated that they had obtained new information about the location of the Ben Delatour Scout
Ranch drinking water intake. These newer surface water discharge PELs had much more
stringent limits for nitrate, chloride, and sulfate when compared to the previous surface water
PELs (in the July 24, 2008 letter). The result was that reverse osmosis or ion exchange treatment
was needed to meet these newer surface water discharge PELs. WWE was of the opinion that
this treatment level, although possible, was infeasible for application at SMC.
Therefore, the planning was modified and a groundwater discharge approach was planned. The
CDPHE was requested to update the groundwater discharge PELs (from the October 23, 2006
Shambhala Mountain Center Wastewater Utility Plan
081-039.000 Wright Water Engineers, Inc. Page 49 Revised April 2010
letter). In response, the CDPHE issued updated groundwater PELs in a letter dated October 30,
2009. These PELs are summarized in Table 8.
Table 8 PELs Issued to SMC by CDPHE (October 30, 2009 Letter)
Parameter Limits Applied at Point of Discharge from WWTF
Prior to Ground Water Discharge (Compliance Point 001A1)
BOD5 (mg/l) 45 (7-day average), 30 (30-day average) BOD5 (% removal) 85 (30-day average) Oil and Grease (mg/l) 10 (maximum) Total Suspended Solids (mg/l) 45 (7-day average), 30 (30-day average) TSS (% removal) 85 (30-day average)
Parameter Limits Applied at Downgradient Monitoring Wells/Lysimeters MW050B and MW050C2,
or at Compliance Point 001A1
Total Inorganic Nitrogen as N (mg/l)1 10 (daily maximum) Nitrate plus Nitrite as N (mg/l)2 10 (daily maximum) pH (s.u.) 6.5-8.5 (minimum-maximum) Sulfate (mg/l) 250 (30-day average) Chloride (mg/l) 250 (30-day average) Total Dissolved Solids, mg/l Monitor (30-day average) Total Coliform, # of colonies per 100 ml Membrane Filter Technique 1.0 (average of all samples taken within a year) Multiple-Tube Fermentation Technique 2.2 (average of all samples taken within a year) 1 - Compliance Point 001A is the monitoring/compliance location subsequent to treatment, prior to ground water discharge. 2 - If the facility decides to utilize a downgradient monitoring wells to establish compliance with a permit limit the facility must first perform an upgradient groundwater monitoring study. This will be used to determine ambient groundwater quality, and what if any assimilative capacity exists.
4.5 Maps
The maps shown in Figures 10 and 11 indicate the surface area and includes the major drainages,
watersheds, sanitary sewer pipelines, and proposed WWTF site.
4.5.1 Watershed
The proposed WWTF site is near an unnamed tributary to Elk Horn Creek which is located in the
Cache La Poudre watershed. A watershed map is included in Appendix F.
Shambhala Mountain Center Wastewater Utility Plan
081-039.000 Wright Water Engineers, Inc. Page 50 Revised April 2010
4.5.2 Impaired Waters
The Environmental Protection Agency (EPA) completes a report of watershed assessments that
are performed on watersheds throughout the U.S. A watershed assessment of the Cache La
Poudre was completed in 2002. The report indicates that most tributaries within the watershed
were not impaired. The specific tributaries in the location of the SMC were not assessed in 2002.
However, the report indicated that the watershed surrounding and downstream of SMC were in
good condition.
5.0 ALTERNATIVE ANALYSIS
5.1 Treatment Works
Three potential treatment process alternatives regarding modifications of the activated sludge
process were evaluated for a new WWTF:
Sequencing Batch Reactor (SBR)
Extended Aeration
Membrane Bioreactor (MBR)
Each of these alternatives would include a new treatment building with an open channel flume
for inflow measurement. Each alternative would also include filtration of effluent and an
emergency power generator. The final disinfection of treated effluent for each alternative would
be accomplished by ultraviolet light in an open channel configuration. Each alternative would
include an effluent pump station and a groundwater dispersal system for discharge.
The solids handling approach for all options would be to provide aerobic digestion, solids
thickening in the digester, and solids removal by contract hauler.
Each of these alternatives use a modification of the aeration activated sludge process with
capabilities for biological nutrient removal. Nitrification of ammonia is achieved with longer
retention times in the aeration cycle. Denitrification would be included in each of these
Shambhala Mountain Center Wastewater Utility Plan
081-039.000 Wright Water Engineers, Inc. Page 51 Revised April 2010
alternatives to remove nitrate and for other advantages (e.g., solids, volume, and alkalinity
addition). Denitrification is achieved through anoxic zones with a recycle of activated sludge.
5.1.1 Sequencing Batch Reactor (SBR)
The SBR process is a form of the activated sludge process in which anoxic conditions, aeration,
sedimentation, and decant functions are combined in a single reactor. Most SBR facilities
consist of two or more parallel tanks. The process would employ a five-stage cycle: fill, react,
settle, draw, and idle. SBRs are capable of biological nitrogen removal which would be
accomplished by proper reactor sizing and selection of stage links in aeration times. Blowers for
the aeration cycle would be located in the treatment building. The treatment process schematic
for the SBR alternative is shown in Figure 6.
The reactor tanks would be open, deep concrete basins set into the foundation of the site so that
gravity flow is used to convey the raw wastewater to the SBR tanks. As options, either a package
plant using steel reactors or concrete reactor basins that are constructed at the floor elevation of
the building will be considered in final design. These options provide the advantage of less rock
excavation but will need a raw wastewater influent pump station.
5.1.2 Extended Aeration Activated Sludge
This approach is shown in the process diagram in Figure 17 and includes an anoxic and aeration
basin for each of two process trains. Open, concrete basins would be used with mechanical
mixers in the anoxic zones and submerged diffused aeration in the aerobic zones. Air to the
basins would be provided by new blowers located in the treatment building. Two, round
concrete clarifiers would be used. UV light disinfection would be installed.
5.1.3 Membrane Bioreactor (MBR)
A process diagram for a MBR process is shown in Figure 18. The MBR would utilize an
activated sludge bioreactor for organic removal and use membranes to achieve biomass and
solids separation (rather than a secondary clarifier). The primary advantages of the MBR are that
aeration basins can be reduced in size because they can be operated at mixed liquor
concentrations of 10,000 to 15,000 mg/L (compared to 2,500 to 3,000 mg/L for other systems)
Shambhala Mountain Center Wastewater Utility Plan
081-039.000 Wright Water Engineers, Inc. Page 52 Revised April 2010
and they do not need secondary clarifiers for solids settling. High effluent quality, including
nitrate removal, can be obtained in a relatively small footprint. The cost of MBR’s can be high
due to both capital costs and operational costs and there would be a need to replace membranes
every seven to ten years.
5.2 Level of Treatment
The treatment alternatives that were selected by WWE for consideration in this study all have the
capability of meeting the PELs (PELs addressed in Section 4.4). Each of the treatment
alternatives include an advance level of treatment processes to reliably and constantly meet the
PELs. As previously discussed, there are treatment processes that are common to each
alternative. The common treatment processes and discharge method are: sodium bicarbonate
addition, activated sludge effluent filtration, UV light disinfection, and discharge to groundwater
via a dispersal system. The solids handling approach for all options would be to provide aerobic
digestion, solids thickening in the digester, and solids removal by contract hauler.
Each of the alternatives presented in this report use a different modification of the aeration
activated sludge process with a biological nutrient removal approach. Although each of these
alternatives will meet the PELs, there may be a slight advantage of effluent quality for the MBR
alternative. However, this slight advantage is only one factor for selecting a preferred alternative.
WWE assessed the treatment process alternatives based on a number of other factors as
addressed in Section 5.4.
Shambhala Mountain Center Wastewater Utility Plan
081-039.000 Wright Water Engineers, Inc. Page 55 Revised April 2010
5.3 Cost Evaluation
Estimated capital costs were developed for each alternative. The estimated capital costs were
developed to provide a WWTF capacity of 49,000 gpd, which is through Phase III as shown in
Table 9. Additional capital costs will be incurred to expand the treatment capacity of the WWTF
to meet the future phase flows.
Estimated capital costs are often prepared at several points during the project planning and
design. The expected level of accuracy is directly proportional to 1) the level of engineering
effort applied and 2) known details. The estimated capital costs presented in this study are
considered to be conceptual. A summary of the estimated capital costs for each treatment
process alternative is presented in Table 9. More detailed estimated capital costs for each
alternative are presented in Appendix H.
Table 9 Comparative Estimated Capital Costs – WWTF
Item SBR Extended Aeration MBR Treatment Facility Building $178,000 $208,000 $193,000 Headworks $5,000 $5,000 $5,000 Pretreatment $20,000 $20,000 $20,000 Activated Sludge Process $380,000 $607,000 $508,000 Odor Control $20,000 $20,000 $20,000 Ballast Concrete $25,000 $25,000 $25,000 Equalization Basin $75,000 $75,000 $75,000 Filtration $120,000 $120,000 $120,000 UV Disinfection $65,000 $65,000 $65,000 Effluent Pump Station $34,000 $34,000 $34,000 Dispersal System and Force Main $54,000 $54,000 $54,000 Digester $66,000 $84,000 $84,000 Back-Up Power $65,000 $65,000 $65,000 Site Work $25,000 $25,000 $25,000 Subtotal $1,132,000 $1,407,000 $1,293,000 Electrical and Instrumentation $170,000 $211,000 $194,000 Subtotal $1,302,000 $1,618,000 $1,487,000 Contingency $195,000 $243,000 $223,000 Subtotal $1,497,000 $1,861,000 $1,710,000 Engineering $224,000 $279,000 $256,000 TOTAL $1,721,000 $2,140,000 $1,966,000
Shambhala Mountain Center Wastewater Utility Plan
081-039.000 Wright Water Engineers, Inc. Page 56 Revised April 2010
An estimate of the operation and maintenance (O&M) for each of the alternatives was developed.
The annual O&M costs are presented in Table 10.
Table 10 Comparative Annual O&M Costs
Item SBR Extended Air MBR Operation & Labor $15,000 $20,000 $15,000 Power $13,000 $16,000 $20,000 Chemicals $2,000 $2,500 $2,000 Lab Equipment $1,000 $1,000 $1,000 Sludge Disposal1 $20,000 $20,000 $18,000 Lab Fees $12,000 $12,000 $12,000 Subtotal $63,000 $72,000 $68,000 Contingency (30%) $19,000 $22,000 $20,000 TOTAL $82,000 $94,000 $88,000 1Cost per year at buildout.
5.4 Preferred Alternative
The selection of the most appropriate treatment process in considering a new WWTF was based
on many different factors. To assist in the determination of the recommended process, the three
process options were compared on the basis of several factors. These factors include:
Capital Cost.
Power and Maintenance Cost.
Effluent Quality – For this study, BOD5, suspended solids, ammonia, and nitrate were
considered the critical parameters for designing the treatment facility. Each alternative
can meet PELs. However, there can be a difference between the alternatives for treatment
efficiency of other parameters (phosphorus, dissolved solids, etc.).
Treatment Process Phasing – The three treatment processes were considered with respect
to the phasing.
Waste Biosolids Production – The management cost for waste biosolids can be significant
and there are differences in the quality of solids produced with the options considered.
Shambhala Mountain Center Wastewater Utility Plan
081-039.000 Wright Water Engineers, Inc. Page 57 Revised April 2010
Reliability of Operation – The reliability of the treatment process can be evaluated against
the systems susceptibility to process failure. Treatment consistency is affected by influent
wastewater characteristics, abrupt changes in influent quality, abrupt changes in
temperature, treatment technology used, and operation and maintenance of the system.
Ability to Upgrade – The ability of the processes to be upgraded to achieve improved
effluent qualities is a consideration.
Ability to Expand – Most of the treatment processes can be expanded by using modular
unit construction. However, there are differences between the three.
Future Discharge Limitations – The ability to meet more stringent discharge limits in the
future is also a consideration.
Land Area – Each of the processes will require from two to three acres of land to be
dedicated for the treatment facility. This factor addresses minimizing the area for the
treatment facility.
Aesthetics – The construction of wastewater treatment processes generally tends to be
intrusive and alters the visual character of the area. Visually, however, it is anticipated
that all of the processes will have equal impact. Odors and noise are other aesthetic
issues to be considered.
Each of the above evaluation factors was considered with respect to the three treatment
processes. A weighted numerical ranking approach was used to identify the preferred process.
The weighted numerical weighting was arrived at as follows: each evaluation factor is assigned a
weight factor that is an index of the relative impact between the different factors, from 1 to 10.
Each process was assigned a score that is an index of the relative impact to that process for the
factor under consideration. If two or more processes have an equal impact for a particular factor,
then each is assigned an identical number. The lower the number, the less is the impact
associated with that treatment process for the particular factor.
Shambhala Mountain Center Wastewater Utility Plan
081-039.000 Wright Water Engineers, Inc. Page 58 Revised April 2010
When the weighted numerical rankings for each factor are added, the lowest total score indicates
the preferred process. This method uses judgment considerations on the part of WWE as the
basis for numerical assignments. The results of this numerical evaluation are shown in Table 11.
The results of the ranking in Table 11 indicate that the SBR activated sludge process should be
the preferred alternative.
A schematic site layout of the SBR activated sludge process for the 49,000 gpd capacity is shown
in Figure 6.
Table 11 Ranking of New WWTF Processes
Evaluation Factor Weight Factor
SBR Extended Aeration MBR S* R* S* R* S* R*
Capital Costs 10 1 10 3 30 2 20 Power Costs 5 1 5 3 15 2 10 Effluent Quality 8 2 16 3 24 1 8 Maintenance Costs 5 1 5 2 10 3 15 Treatment Process Phasing 8 1 8 3 24 2 16 Waste Biosolids Production 8 2 16 2 16 1 8 Reliability of Operation 8 2 16 1 8 3 24 Ability to Upgrade 5 1 2 1 2 2 4 Ability to Expand 5 1 5 2 10 1 5 Future Discharge Limits 5 2 10 2 10 1 5 Land Area 5 2 10 3 15 1 5 Aesthetics 7 2 14 3 21 1 7 TOTAL 117 185 127 * S = Score on a scale of 1 (best) through 3 (worst). * R = Weighted Rank = score x weight factor.
5.5 Proposed Implementation Schedule
The proposed implementation schedule for the new SMC WWTF is presented in Table 12. The
schedule assumes a reasonable time for agency approvals that are needed prior to construction.
Although not shown in the schedule, the schedule allows for the fundraising activities that will
need to be performed to address the overall costs of the WWTF.
Shambhala Mountain Center Wastewater Utility Plan
081-039.000 Wright Water Engineers, Inc. Page 59 Revised April 2010
Table 12 Shambhala WWTF Implementation Schedule
Start Date End Date Task January 2010 February 2010 Submit WUP to NFRWQPA March 2010 April 2010 Submit Site Application and WUP to CDPHE April 2010 October 2010 Prepare Final Design of WWTF October 2010 December 2010 Submit Final Design of WWTF to CDPHE January 2011 March 2011 Contract Bidding Phase March 2011 November 2011 Construction of WWTF
5.6 Public Participation and Selection Process
Since the SMC WWTF will be a privately owned facility, there has been no public participation
during the planning and selection process for the SMC WWTF.
6.0 MANAGEMENT AND FINANCIAL PLANS
Management and financial planning are very important aspects in the construction and operation
of a new WWTF. The management and financial planning addressed below are needed to ensure
final construction and proper operations of the WWTF to meet State requirements.
6.1 Management Structure and Agreements
The SMC property is owned by Shambhala International (Vajradhatu) and the property is
managed by the SMC. SMC has a 99 year lease on the property. SMC is a 501 (c) 3
incorporated in the State of Colorado. Shambhala International (Vajradhatu) is also incorporated
in the State of Colorado. Site Ownership/Control Documentation for the SMC property is
included in Appendix J.
The SMC offers year round programming focusing on mind and body disciplines which present
and encourage increased mindfulness and awareness in one’s life utilizing a variety of wisdom
traditions including major spiritual traditions; Christian, Buddhist, Jewish, Native American and
Shaman. Over 3,000 people a year attend programs on site with guest night totals ranging from
19,300 - 28,000 a year.
Shambhala Mountain Center Wastewater Utility Plan
081-039.000 Wright Water Engineers, Inc. Page 60 Revised April 2010
The management structure includes an Executive Director and five senior managers: Finance,
Development (fund raising), Programming, Marketing and Operations. The Expansion
Department (land development including infrastructure), reports directly to the Executive
Director. This management structure is overseen by a Board of Directors.
The wastewater system is overseen by the Expansion Department with assistance from the
Operations Director. An Advisory Team consists of friends of the SMC that have been helping
with the internal planning and development of approaches to the wastewater system in
conjunction with WWE.
The SMC is part of the NFRWQPA which assists in planning facilitation and review of activities
that relate to present and future waste water needs in order to uphold a proper high standard of
water quality protection. The NFRWQPA provides assistance in creating Utility Management
Plans that guide communities and organizations through the wastewater planning process and
will be involved in the review of this report.
6.2 Wastewater Management Plan
The SMC Management Team will be responsible for the wastewater treatment system with daily
supervision by the Expansion Department. The Expansion Department staff will be responsible
for the day to day activities including inspections, regular maintenance, collecting samples, and
normal operations. SMC currently has one Class “C” Operator and one Small Systems Operator
on staff. SMC does not have a staff person with a wastewater treatment Operator “B” License.
SMC will contract with an Operator in Responsible Charge (ORC) to oversee the operation of
the treatment plant. The ORC will make regular visits to the plant and be available as needed for
required process control changes or emergencies.
The Expansion Department oversees the wastewater system management with assistance from
the Operations Director. The ORC will report to the Operations Director.
Shambhala Mountain Center Wastewater Utility Plan
081-039.000 Wright Water Engineers, Inc. Page 61 Revised April 2010
6.3 Financial Management Plan
In order to provide the funds to implement a new wastewater treatment system, SMC is
launching a Capital Fund Campaign in the spring of 2010. Over the past five years SMC has
averaged raising $1,200,000 per year.
SMC plans on raising a minimum of 75 percent of the costs for construction of the plant and
collection system through its fund raising efforts and capital campaign. If necessary, additional
funds will be borrowed either through a conventional lender or through a friend of the
organization. SMC has been successful in borrowing when needed, loans up to $500,000 from
friends and board members.
Shambhala Mountain Center has received restricted grants in support of infrastructure
development for over $270,000 including a recent grant of $133,000 for design and legal fees for
work of preparing the WUP up through the site location application.
In addition, the SMC has $500,000 in a restricted donation being held by a local Foundation set
aside towards the design and construction of the WWTF, see letter in Appendix I.
Table 13 provides a summary of capital, O&M, and replacement costs and the total revenues that
will be used to finance the expenses for construction and operation of the SMC WWTF.
Shambhala Mountain Center Wastewater Utility Plan
081-039.000 Wright Water Engineers, Inc. Page 62 Revised April 2010
Tabl
e 13
Su
mm
ary
of C
apita
l, O
&M
, Rep
lace
men
t Cos
ts a
nd T
otal
Rev
enue
s
Shambhala Mountain Center Wastewater Utility Plan
081-039.000 Wright Water Engineers, Inc. Page 63 Revised April 2010
6.3.1 Financial Assistance
Besides donations, SMC is not eligible for financial assistance like many public sector entities.
We will continue to seek grants from private foundations.
6.3.2 User Charge Summary
Annual O&M costs for the SBR system and other related facilities are estimated at approximately
$100,000. For the past three years the Center has not raised its program and lodging prices. In
2011 prices will be raised in part to provide funds for the system operation which is expected to
start around 2012.
Replacement costs will be supported by adding, when necessary, to the existing capital
expenditure budget which SMC prepares on an annual basis.
7.0 REFERENCES
Larimer County Department of Health and Environment, Individual Sewage Disposal System
Regulations (2004)
Water Environment Federation (WEF) Manual of Practice No. 8, Design of Municipal
Wastewater Plants and the CDPHE Guidelines on Individual Sewage Disposal Systems
Water Environment Research reference, “Food Service Establishment Wastewater
Characterization
Z:\Project Files\08\081-039\081-039.000\Deliverables\Wastewater\WUP\Text.doc
DENVER2490 W. 26th Avenue Suite 100A
Denver, Colorado 80211Phone: 303.480.1700
Fax: 303.480.1020
GLENWOOD SPRINGS818 Colorado Avenue
P.O. Box 219Glenwood Springs, Colorado 81602
Phone: 970.945.7755Fax: 970.945.9210
DURANGO1666 N. Main Avenue Suite C
Durango, Colorado 81301Phone: 970.259.7411
Fax: 970.259.8758
www.wrightwater.com
Wright Water Engineers, Inc.