refining gas processing petrochemicals - Honeywell · PDF filerefining gas processing...

5
SPECIAL FEATURES GAS PROCESSING DEVELOPMENTS MASS TRANSFER REFINING GAS PROCESSING PETROCHEMICALS PETROLEUM TECHNOLOGY QUARTERLY ptq Q4 2014

Transcript of refining gas processing petrochemicals - Honeywell · PDF filerefining gas processing...

Page 1: refining gas processing petrochemicals - Honeywell · PDF filerefining gas processing petrochemicals ... unit operation models (pipes, vessels, ... predefined scenarios as part of

special features

gas processing developments

mass transfer

refininggas processingpetrochemicals

petroleum technology quarterly

ptqQ4 2014

cover and spine copy 22.indd 1 15/09/2014 10:32

Page 2: refining gas processing petrochemicals - Honeywell · PDF filerefining gas processing petrochemicals ... unit operation models (pipes, vessels, ... predefined scenarios as part of

Override control of fuel gas

MiRO oil refinery in Germany has expanded its fuel gas system using natural gas as

an additional energy source. The new natural gas system, which includes a complex override control structure, had to be integrated in the historically evolved fuel gas system outside of a shutdown. Therefore, a detailed dynamic simulation study (DSS) of the new and integrated overall fuel gas system was carried out using UniSim Design. The objectives of the DSS include ensuring stable and safe operation of the new system as well as shortening the start-up time.

This article gives an overview of the project and shows initial results after successful start-up of the new fuel gas system.

Refinery and natural gas import project MiRO (Mineraloelraffinerie Oberrhein) is one of the largest oil refineries in Germany. The refinery is located in Karlsruhe and consists of two sites which are intercon-nected in multiple ways (feeds, products and utilities). In the past, the fuel gas system of the refinery was based on liquefied petroleum gas (LPG) and fuel oil as the exter-nal make-up energy source. Price changes have made natural gas financially attractive as an addi-tional energy source, and thus MiRO decided to include natural gas as an alternative make-up gas.

A simplified structure of the new integrated fuel gas system with the energy sources – refinery off-gas, FCC gas, coker gas, LPG and natu-ral gas – is shown in Figure 1.

When natural gas was to be added to a refinery’s fuel gas system, detailed dynamic simulation of the new system ensured stable operation and a shorter start-up period

RAINER SCHEURING Cologne University of Applied SciencesALBRECHT MINGES and SIMON GRIESBAUM MiRO Mineraloelraffinerie OberrheinMICHAEL BRODKORB Honeywell Process Solutions

In order to meet the varying requirements of the refinery, MiRO has developed a complex override control structure. In addition, piping and control of the new natu-

ral gas system had to be integrated in the historically evolved fuel gas system outside of a shutdown. Therefore a dynamic simulation study of the overall fuel gas system was carried out with the following main objectives:

• Ensuring the integrated fuel gas system is stable in all operating conditions and transition phases• Ensuring there are no oscillations or other dynamic problems• Testing the control configuration and pre-tuning the controllers prior to installation• Ensuring additional control objec-tives (min/max flow rates, and so on) are met• Testing that transitions from LPG to natural gas and back, as primary fuel, are easy to handle• Safe commissioning• Reducing commissioning time.

Dynamic simulation of fuel gas system Dynamic Process Simulators such as Honeywell UniSim Design, Invensys Dynsym, or AspenTech Aspen Hysys Dynamics are based on first principle process modelling engines that allow realistic model-ling of the transient behaviour of processes typically found in the oil, gas and chemical industries. In order to create a process model, the user selects readily available components and thermodynamic packages to define physical proper-ties and phase equilibria for the system and then creates a flow-sheet by adding and linking generic unit operation models (pipes, vessels, pumps, distillation columns, for instance) and control equipment (valves, PIDs, and so on). The resulting model can be initialised to a specific initial condi-tion and run through different predefined scenarios as part of a dynamic simulation study.

Dynamic simulation studies are a standard tool in the process indus-

www.eptq.com PTQ Q4 2014 81

Ref

iner

y o

ff g

as 1

LPG

Ref

iner

y o

ff g

as 2

LPG

Co

ker

gas

FC

C g

as

Nat

ural

gas

New

Pressure: 8.5 barg

Pressure: 3.8 barg

Plant 1 Plant 2

Figure 1 Structure of MiRO fuel gas system (simplified)

Price changes have made natural gas financially attractive as an additional energy source

Page 3: refining gas processing petrochemicals - Honeywell · PDF filerefining gas processing petrochemicals ... unit operation models (pipes, vessels, ... predefined scenarios as part of

82 PTQ Q4 2014 www.eptq.com

back, which prevents windup and ensures that the outputs of all controllers are equal.5 Figure 3 shows a possible realisation of an over-ride controller with two controllers (C1 and C2), two controlled variables (PV1 and PV2), a low selector, external reset feed-back (ERF), and one manipulated variable (OP).

The override control system of MiRO’s fuel gas system is far more complex and has to manage:• A large number of controlled variables and controllers• An elaborate structure• Various requirements (safety limits, optimal operating point, and so on).

As an example, a part of the override control scheme is shown in Figure 4.

Simulation analysis of many scenariosIn order to ensure that the objec-tives shown above are fulfilled, extensive simulation analyses of a wide range of realistic scenarios were performed. For instance, in the case of a sudden shutdown of a 100 MW fired heater at five minutes simulation time the fuel gas system pressure stayed in the stipulated range as shown in Figure 5. The red curve represents the pressure. The

tries for analysing and optimising transient process behaviour. Application examples for operabil-ity or safety studies include dynamic flare load estimation in refineries1 or onshore gas fields,2 and compressor studies.3 For the DSS carried out at MiRO refinery, the authors selected UniSim Design for its modelling speed, stability and its capability to model complex control systems.

The new natural gas system had to be integrated into the fuel gas system using existing piping and vessels as it was not possible to add new equipment outside of a shutdown (as explained above). This existing equipment is not optimised with respect to capacity and pressure drop, and could lead to problems in the tran-sient behaviour of the integrated system. Figure 2 shows a small section of the overall UniSim model, where piping of the real plant is modelled with great accuracy.

Override controlOverride control is a control strat-egy where one manipulated variable is adjusted by two or more controlled variables.4 Override control typically uses a PI/PID algorithm for each controlled varia-

ble. A low or high selector (LS or HS) chooses between the PI/PID outputs at a given time. Integral parts of the PI/PID controllers

which are not selected are at risk of integral windup, therefore an anti-windup strategy is required. One option is external reset feed-

Figure 2 Small section of the UniSim model

SP1 SP2

OP1PV1 OP2 PV2

ERF ERF

OP

Plant

LSC1 C2

Figure 3 Override control with external reset feedback

Override control is a control strategy where one manipulated variable is adjusted by two or more controlled variables

Page 4: refining gas processing petrochemicals - Honeywell · PDF filerefining gas processing petrochemicals ... unit operation models (pipes, vessels, ... predefined scenarios as part of

pressure set point is 8.5 bar(g), and the pressure rises up to 9.1 bar(g). The blue curve shows the active OP, which directly controls the valve connected to HGP 260 P4 in Figure 4.

84 PTQ Q4 2014 www.eptq.com

Because many PID controllers are involved, which may interact and cause oscillations, PID parameter tuning was a central point of the simulation analysis.

As a result of the investigations, a

number of issues were adjusted such as:• Pressure limits for flare gas relief• Valve sizing• Control parameters.

On the whole, simulation analysis has verified that the design of the fuel gas system, including the natu-ral gas system, and the complex override control system is fully functional and error free.

Commissioning of natural gas systemIn December 2013, the natural gas system was integrated into the existing fuel gas system. Standard control engineering tasks, such as linearisation of non-linear valve curves, were pursued where neces-sary. The control parameters which had been designed in the simula-tion study provided good starting points for detailed parameter

LOSEL

LOSEL

MINMAXTARGET

MID OF THREE

HISEL

Ps=19.5 bar

13.8 bar

8.50 bar 8.75 bar 8.70 bar

12 bar

8.30 bar

10 bar 10 bar

7.7 bar

205PC001

205PI

061

205PC260

205PC061

205PC034

205PC60C

205FC259

205HC061

205PC60A

205PC60B

205PC02A

205PI

034

205PI

035

205PC01B

HGP061P6

HGP260P3

HGP061P3

HGP061P2

HGP061P4

HGF241P1

HGP061P1 HGP

002I1

HGP260P1

HGP260P2

HGF259P1

HGF259I1

GDR2

PC

205PI

001

205PI

259

205TI

259

241PI

257

HGP260P4

Flare

205PC002

HGP034P1

Vessel105m3

Vessel

EvaporatorEvaporator

52m3

LOSEL HISEL

HISEL

SV=17.5 bar

205PI

060

Figure 4 Part of override control scheme of MiRO refinery

9.0

10.0

9.5

8.5

8.0

PC

10

1-P

V, b

arg

84

70

56

42

28

PC

10

1-O

P, %

00 4 8 12 16 20 24 28 302 6 10 14 18 22 26

Time, minutes

PC101-OPPC101-PV

Figure 5 Trend of fuel gas system pressure in the case of a 100 MW oven shutdown

Page 5: refining gas processing petrochemicals - Honeywell · PDF filerefining gas processing petrochemicals ... unit operation models (pipes, vessels, ... predefined scenarios as part of

www.eptq.com PTQ Q4 2014 85

Rainer Scheuring is Professor of Automation Technology and Control Theory at Cologne University of Applied Sciences. He holds a master’s in technical cybernetics and a PhD from Stuttgart University, Germany.Email: [email protected]

Albrecht Minges is a Senior Process Control Engineer in the department for process automation at the MiRO-Refinery in Karlsruhe, Germany. He holds a BS degree in process engineering from University of Applied Sciences, Mannheim.Email: [email protected]

Simon Griesbaum is a Process Control Engineer in the department for process automation at the MiRO-Refinery in Karlsruhe, Germany. He holds a master’s in chemical engineering from University of Applied Sciences, Mannheim.Email: [email protected]

Michael Brodkorb is Software Sales Support Leader EMEA at Honeywell Process Solutions in Tarragona, Spain. He has a degree in chemical engineering from University of Dortmund, Germany, and a PhD from Bradford University, UK.Email: [email protected]

tion study helped to develop a fully functional and error free system. As a consequence, commissioning and start-up of the expanded fuel gas system went smoothly without any significant problems.

UniSim Design is a mark of Honeywell Inc.

References1 Gruber D, Leipnitz D-U, Sethuraman P, Alos M A, Nogues J M, Brodkorb M, Are there alternatives to an expensive overhaul of a bottlenecked flare system?, PTQ, Q1 2010, 93-95.2 Panigrahy P, Balmer J, Alos M A, Brodkorb M, Marshall B, Dynamics break the bottleneck, Hydrocarbon Engineering, Sept 2011, 93-96.3 Nugues J M, Brodkorb M, Feliu J A, How can dynamic process simulation be used for centrifugal compressor systems, Hydrocarbon Engineering, Aug 2012, 92-98.4 Luyben M L, Essentials of Process Control, McGraw-Hill, New York, 1997, 122-125.5 Smith C A, Automated Continuous Process Control, John Wiley & Sons, Hoboken NJ, 2002, 88-92.

tuning. In many cases, the control parameters of the dynamic simula-tion could be used without any changes.

As a result of the careful prepara-tion, commissioning went smoothly without any significant problems. It is noteworthy to emphasise the short period of time that was required for commissioning and startup of the expanded fuel gas system.

ConclusionMiRO refinery had to expand its fuel gas system for the usage of natural gas as an additional alterna-tive energy source. A new natural gas system, which includes a complex override control structure, was integrated into the historically evolved fuel gas system outside of a shutdown. In order to ensure safe and stable operation of the new system, as well as a smooth startup, a dynamic simulation study of the fuel gas system was carried out using UniSim Design. The simula-