PROJECT MGT. PRESENTATION
-
Upload
maheshvkat1972 -
Category
Documents
-
view
187 -
download
0
Transcript of PROJECT MGT. PRESENTATION
PROJECT MANAGEMENT
CAPTIVE POWER
PLANT PROJECT
Presentation by
Mahesh V. KulkarniVth Term - OperationsManipal University
A Power plant
PROJECT – Turnkey in Nature 2 x 2.5 MW Captive Power Plant spread over 4 acres of
land (free field)
2 x G3612, 11 KV, 1500 RPM Natural Gas Gensets
Customer: Southern Energy Development Corporation Ltd. (SEDCO) – a Carborandum Universal Group
Location: Nallur, Mannargudi (near Tanjavur), Tamilnadu
Consultant: Aquatherm Consulting Engineers, Chennai
Guarantees- Fuel Consumption, Lube oil Consumption, Genset output power
NEED FOR PROJECT MGMT.- WHY DID OUR COMPANY FORM A PROJECT MGT. DEPARTMENT?
• Too many projects running over time and overbudget
Project scope creep Project management
responsibility not clear Too much emphasis on outputs
rather thanoutcomes
Insufficient emphasis on risks
Saves company TIME….MONEY
Triple constraint
Quality
Scope
Time
Cost
Project department - Sandwich
Takeover from Sales
Handover to Service department
Sales Service
Project
Five Phases of Project Management Phases
Developing the Plan
Scoping the Project
Launching thePlan
Monitoring &ControllingClosing Out the
Project
Scoping the project- Primarily it is the definition and control of what IS & IS NOT included in the project
Project Scoping FormProject Name – SEDCO
Project Manager – Mahesh Kulkarni
Team Members – 05 nos.
Opportunity (Why do this project?): To earn profitProject Goal: Smooth executionObjectives: Timely completion within a allotted costsSuccess Criteria (Outcomes): Effective commissioning of all equipment by suppliersAssumptions, Risks, Obstacles: Technological,Environmental, Interpersonal, Cultural, Political
SCOPE Imported supply from USA – Value USD 1.5 Mn
Indigenous supply (Balance of plant) – INR 2.62 Crores
Erection of all supplied items
Time frame – 6 months
Imported scope by Letter of Credit
Indigenous supply payment terms – 50 % advance, 30 % against supply and 20 % after commissioning.
33 KV Substation supply and erection by Bharat Bijlee
Govt. approvals from 1. TNEB, 2. GAIL, 3. CEIG, 4. Pollution control board
Total vendors in the project – 11 nos. (EPC Contractor – mechanical & electrical, manufacturers of air compressors, air receivers, Radiator, NGR Panel, Circuit breaker panel, MCC panel, main and auxiliary transformer, LAVT panel, Control & Relay panel, etc.)
Developing The Plan
Construct/AnalyzeProject Network
Prepare theProject Proposal
Identify ProjectTasks (WBS)
Estimate Task Duration
Determine Resource Requirements
Project Planning Activity• Create a work break
down structure (WBS) for the project you identified in the scoping document. Identify and sequence tasks.
WBS - A WBS is the functional decomposition of a system, it breaks the project into chunks of work at a level of detail that meets planning and scheduling needs
WBS:SEDCO PROJECT
3. CONSTRUCTION2. PROCUREMENT1. DESIGN & ENGINEERING
1.1 Sizing of equipment
1.1.1 Foundation
1.1.2 Piping layout
1.2 Drawings
1.3 Consultant approvals
2.1 Order placement
2.1.1 Long delivery items
2.1.2 Short delivery items
2.2 Inspection
2.3 Clearance & Transportation to site
3.1 Unloading at site & Erection
3.1.1 Erection of equipment on foundation
3.1.2 Piping and cabling
3.2 Pre-commissioning checks
3.3 Plant trial run and handover
Advance
Project Planning: Resources
1. People - skills and value
2. Facilities – Office, AutoCAD, computers and softwares, Vehicles, etc.
3. Equipment – like Crane – hired
General Manager …
DRAFTSMAN …..
ELECTRICAL ENGR.…….
Manager Projects ……..
SITE MANAGER …….
Manager Projects (S. Sridhar)Project Manager ……
Commissioning Engr. …..
Finance Manager ….
Principal …..
Suppliers for indigenous supplies(11 vendors)
Service Manager (Singuttuvan)
Customer - SEDCO(Project Mgr.)
Consultant–Aquatherm ….
4. Time – Six months starting 1st March
Role of a Project Manager Role:
Process Responsibilities
People Responsibilities
• Project issues • Disseminating project information• Mitigating project risk • Quality • Managing scope • Metrics • Managing the overall work plan
• Implementing standard processes• Establishing leadership skills• Setting expectations• Team building• Communicator skills
Duties & Responsibilities of PMI. PLANNING: Breaking down Project into independent
activities or events with the help of Bar Chart.
Providing progress reporting at regular intervals to the Customer, Consultant and Caterpillar with a copy to Service department.
Reallocation / rearranging money/resources to improve schedule.
III. INSPECTIONS & DESPATCHES: Witnessing the equipment inspection at
suppliers place. coordinating with Customer for allotting safe
equipment unloading and storage area at site.
IV. SITE CO-ORDINATION : Visiting site for checking Civil developments. Guiding mechanical contractor and Customer
at site for flushing of piping, welding & surface preparation, pre-commissioning checks to suit Caterpillar standards.
II. TECHNICAL ACTIVITIES: Preparation of Specification of material for
mechanical bought out items like Pipes, Elbows, Valves, Flexible hoses required for Cooling system, Starting air system.
Preparation of Material specification for fabricated items like Chimney, Exhaust & Intake duct, etc.
Preparation of Mechanical Drawings – As built P & I drawings and Isometric drawings for Natural Gas system, Air start system, Cooling Water system, etc
V. COMMERCIAL: Evaluation of the offers from vendors techno–
commercially. Negotiating with suppliers effectively to avoid
cost over run & make maximum profit margins. Planning cash flow (in & out) with the help of
Finance department for smooth project operation.
Coordinating with Finance Department for releasing the payment to suppliers after checking proper attached documents.
Collecting payment for additional supply of material other than Purchase order.
Calculating the profit earned in the project
Gantt Chart (Microsoft Office Project Professional 2003)
Visual scheduling tool Graphical representation
of information in WBS
Show dependencies between tasks, personnel, and other resources allocations
Track progress towards completion
Gantt Chart – Example
Estimated time to complete a task
Task
s
Bars indicate time requirement
Arrows indicate task dependencies: Predecessor task Successor task
Look Out for the Creepers! Scope Creep - Change is constant – must be
accommodated (Comes from the customer)
Civil design – due to change in civil structure by Customer
Power plant logic - Frequent changes in the electrical logic by Customer’s site manager
Accommodated and completed the project on time
Project communication - Absolutely critical to the success of projects!
Project meetings with suppliers - Meets weekly to resolve short-term conflicts, look ahead to the remaining development cycle. Attended by project manager, project engineers, projects manager (if required).
Planning meetings – Inter-organizational - review progress on goals, resolution of cross division functional conflicts, perform mid-course corrections, review cash flow, etc. Attended by division heads, project manager, GM (if reqd.)
Fortnight coordination meetings with Customer and Consultants – Meets for reviewing the progress, approvals, set milestones for future weeks, commissioning schedule, etc. Attended by project manager, project engineers, projects manager (if required).
Quality Management Quality Management is the process that
insure the project will meet the needs via: Quality Planning, Quality Assurance, and Quality
Control. Quality is ensured by Clearly Defined Quality Performance Standards Stage inspection of equipment to verify
conformity / adherence to specifications, Testing and Quality Assurance Processes will
ensure standards are satisfied Continuous ongoing quality control
Project Financial Management Divide and conquer
To make a better estimate, divided the project into individual subsystems.
Then divided each subsystem further into the activities that will be required to develop it.
Next, made a series of detailed estimates for each individual activity.
And sum the results to arrive at the grand total estimate for the project.
Tight control of costs by supervising any changes in the scope.
Preparation of cash inflow and outflow statement
Budget
SUCCESSES
Customer Requirements satisfied
Completed within allocated time frame +
2 extra months with prior notification (out of 2 months, 1 month
recorded as Force majeure)
Completed within allocated budget
Accepted by the customer
Difficulties and Risks in Project Management Road Transport strike lasted for 2 weeks,
Difficulty in transporting the heavy equipment to the rural area due to lots of curves,
Communist area – additional amount to Comrades for each truck,
Language barrier – interior people speaks Tamil only,
Slowing of erection activities due to heavy Monsoon,
Erection contractor – Inexperienced junior engr. appointed at site,
Delays due to short fall of material at site,
Finance Manager transferring the project funds to other projects or emergency without the consent of project manager. Thereby, delay the payment to the Suppliers
Food at site
LESSONS
Planning and Engineering – most important, Contingency in Time need to be considered, PESTEL Analysis (Environment scanning) shall be done, Project management Training to the individuals, Getting the scale of the project management in
proportion to the size and impact of the project, Better monitoring of milestones (and remedial action
when milestones are not being met) Project team shall be micro-managing
Rewards – Direct & Indirect SEDCO admired our team efforts and gifted
a Silver Peacock Monument in a ceremony
Our company announced a bonus of INR 30,000 to project team,
Recognition in the company,
New doors of opportunities opened.