PETE 450 Introduction to Geothermal Reservoir Engineering Electricity Generation Dr. Mahmut...
-
Upload
emmeline-lawson -
Category
Documents
-
view
242 -
download
0
Transcript of PETE 450 Introduction to Geothermal Reservoir Engineering Electricity Generation Dr. Mahmut...
PETE 450Introduction to Geothermal Reservoir
Engineering
Electricity Generation
Dr. Mahmut Parlaktuna
PETE 450 2ELECTRICITY GENERATION
Most power plants Most power plants need steam to need steam to generate electricitygenerate electricity
The steam rotates a The steam rotates a turbine that activates turbine that activates a generator, which a generator, which produces electricityproduces electricity
Geothermal power Geothermal power plantsplants use steam use steam produced from produced from geothermal geothermal reservoirsreservoirs
PETE 450 3ELECTRICITY GENERATION
There are three types of geothermal power plantsThere are three types of geothermal power plants
DDry steamry steam
FFlash steamlash steam
BBinary cycleinary cycle
PETE 450 4ELECTRICITY GENERATION
Dry steam power plants draw from underground resources of steam. The steam is piped directly from
underground wells to the power plant, where it is directed into a turbine/generator unit.
Dry Steam Power PlantDry Steam Power Plant
PETE 450 5ELECTRICITY GENERATION
Dry Steam Power PlantDry Steam Power Plant The dry steam power plant is suitable where the geothermal steam is not mixed with water. Production
wells are drilled down to the aquifer and the superheated, pressurised steam (180 - 350 C) is brought to the surface at high speeds, and passed through a steam turbine to generate electricity.
Schematic of a Dry Steam Power Plant
PETE 450 6ELECTRICITY GENERATION
The first geothermal power generation plant from dry steam was constructed in 1904 in Larderello, Italy. This had a capacity of 250kW.
Dry Steam Power PlantDry Steam Power Plant
PETE 450 7ELECTRICITY GENERATION
LarderelloLarderello
The first modern geothermal power plants were also built in Larderello, Italy. They were destroyed in World War II and rebuilt. Today after 100 years, the Larderello field is still producing.
PETE 450 8ELECTRICITY GENERATION
LarderelloLarderello
Larderello Landscape
PETE 450 9ELECTRICITY GENERATION
LarderelloLarderello
Cooling Towers
PETE 450 10
ELECTRICITY GENERATION
LarderelloLarderello
Steam vent
PETE 450 11
ELECTRICITY GENERATION
The GeysersThe Geysers
Geysers Power Plant
PETE 450 12
ELECTRICITY GENERATION
The GeysersThe GeysersFull-scale commercial development began by 1955, and the 11-megawatt (MW) Geysers Unit 1 power plant was commissioned in 1960. By 1989, installed generating capacity at The Geysers was 1,967 MW. Since 1987, The Geysers has experienced a decline in steam pressure and electricity production that has coincided with older power plants in the area reaching the end of their useful lives. Initial pressure in most Geysers production wells was above 500 psi, but by the mid-1990s many fell below 200 psi. And because pressure determines production rate, it is no longer practical in most areas of The Geysers to drill new wells to supplement steam supply.
PETE 450 13
ELECTRICITY GENERATION
The GeysersThe Geysers
The Lake County-Southeast Geysers Effluent Pipeline Project begins operations in 1997. The pipeline project is the first wastewater-to-electricity project in the world. The 29-mile underground pipeline delivers eight million gallons of treated reclaimed water to The Geysers everyday to be recycled into the geothermal resource.
PETE 450 14
ELECTRICITY GENERATION
The GeysersThe Geysers
The Santa Rosa Geysers Recharge Project is selected to transport 11 million gallons of treated reclaimed water per day to The Geysers through a 41-mile underground pipeline, 1998. Water is recycled back into the ground, heated, and used at steam to power the plants.
PETE 450 15
ELECTRICITY GENERATION
The GeysersThe Geysers
PETE 450 16
ELECTRICITY GENERATION
The GeysersThe Geysers
PETE 450 17
ELECTRICITY GENERATION
The GeysersThe Geysers
The first geothermal power plants at The Geysers dry steam field were built in 1962.
It is still the largest producing geothermal field in the world.
PETE 450 18
ELECTRICITY GENERATION
The GeysersThe Geysers
20 plants are still operating at The Geysers. Wastewater from nearby cities is injected into the field, providing environmentally safe disposal and increased steam
to power plants.
PETE 450 19
ELECTRICITY GENERATION
They use geothermal reservoirs of water with They use geothermal reservoirs of water with temperatures greater than 360°F (182°C). This very hot temperatures greater than 360°F (182°C). This very hot water flows up through wells in the ground under its water flows up through wells in the ground under its own pressure. As it flows upward, the pressure own pressure. As it flows upward, the pressure decreases and some of the hot water boils into steam. decreases and some of the hot water boils into steam. The steam is then separated from the water and used The steam is then separated from the water and used to power a turbine/generator. Any leftover water and to power a turbine/generator. Any leftover water and condensed steam are injected back into the reservoir, condensed steam are injected back into the reservoir, making this a sustainable resource.making this a sustainable resource.
FlashFlash Steam Power Plant Steam Power Plant
PETE 450 20
ELECTRICITY GENERATION
Flash Steam Power PlantFlash Steam Power Plant Single flash steam technology is used where the hydrothermal resource is in a liquid form. The fluid is
sprayed into a flash tank, which is held at a much lower pressure than the fluid, causing it to vaporise (or flash) rapidly to steam. The steam is then passed through a turbine coupled to a generator as for dry steam plants.
Single Flash Steam Power Plant
PETE 450 21
ELECTRICITY GENERATION
FlashFlash Steam Power Plant Steam Power Plant
Hydrothermal plant in New Zealand
PETE 450 22
ELECTRICITY GENERATION
Wairakei, New ZealandWairakei, New ZealandThe first geothermal power station from flash steam was built in the 1950s at Wairakei, New Zealand.
PETE 450 23
ELECTRICITY GENERATION
Kızıldere Kızıldere Power PlantPower Plant
20.4 MWe installed capacity
Uses steam at 4.5 bar (147 C)
Due to water disposal problems (B), it can produce 12-13 MWe
PETE 450 24
ELECTRICITY GENERATION
Kızıldere Kızıldere Power PlantPower Plant
PETE 450 25
ELECTRICITY GENERATION
Kızıldere Kızıldere Power PlantPower Plant
0
200
400
600
800
1000
1200
1400
14-Kas-84 11-Ağu-87 07-May-90 31-Oca-93 28-Eki-95 24-Tem-98 19-Nis-01 14-Oca-04 10-Eki-06
Tarih
Top
lam
üre
tim (
ton/
saat
)
PETE 450 26
ELECTRICITY GENERATION
Kızıldere Kızıldere Power PlantPower Plant
0
10
20
30
40
50
60
70
14-Kas-84 11-Ağu-87 07-May-90 31-Oca-93 28-Eki-95 24-Tem-98 19-Nis-01 14-Oca-04 10-Eki-06
Tarih
Su
sevi
yesi
(m
)
KD-1A KD-8
PETE 450 27
ELECTRICITY GENERATION
Binary cycle power plants operate on water at lower Binary cycle power plants operate on water at lower temperatures of about 225°–360°F (107°–182°C). temperatures of about 225°–360°F (107°–182°C). These plants use the heat from the hot water to boil a These plants use the heat from the hot water to boil a working fluid, usually an organic compound with a low working fluid, usually an organic compound with a low boiling point. The working fluid is vaporized in a heat boiling point. The working fluid is vaporized in a heat exchanger and used to turn a turbine. The water is then exchanger and used to turn a turbine. The water is then injected back into the ground to be reheated. The water injected back into the ground to be reheated. The water and the working fluid are kept separated during the and the working fluid are kept separated during the whole process, so there are little or no air emissions. whole process, so there are little or no air emissions.
Binary CycleBinary Cycle Power Plant Power Plant
PETE 450 28
ELECTRICITY GENERATION
Binary Cycle Power PlantBinary Cycle Power Plant Binary cycle power plants (Figure 9) are used where the geothermal resource is
insufficiently hot to efficiently produce steam, or where the resource contains too many chemical impurities to allow flashing.
Binary Cycle Power Plant
PETE 450 29
ELECTRICITY GENERATION
Electricity GenerationElectricity Generation
PETE 450 30
ELECTRICITY GENERATION
Electricity GenerationElectricity Generation
There is 8900 MW of installed geothermal electricity generation capacity worldwide. The United States is the largest producer of geothermal electricity (2544 MW), followed by the Philippines (1931 MW) (Bertani, 2005).
PETE 450 31
ELECTRICITY GENERATION
Electricity GenerationElectricity Generation
PETE 450 32
ELECTRICITY GENERATION
High Temperature Geothermal SourcesHigh Temperature Geothermal Sources
Kızıldere-Denizli (242 °C) Germencik-Aydın (232 °C) Tuzla-Çanakkale (174 °C) Salavatlı-Aydın (171 °C) Simav-Kütahya (162 °C) Seferihisar-İzmir (153 °C) Caferbey-Manisa (150 °C) Yılmazköy-Aydın (142 °C) Dikili-İzmir (130 °C)
PETE 450 33
ELECTRICITY GENERATION
Example-1Example-1
Husavik, Iceland Enery DevelopmentHusavik, Iceland Enery Development
PETE 450 34
ELECTRICITY GENERATION
Example-2Example-2
Nesjavellir, Iceland Enery DevelopmentNesjavellir, Iceland Enery Development
PETE 450 35
ELECTRICITY GENERATION
Example-3Example-3
Svartsengi, Iceland Enery DevelopmentSvartsengi, Iceland Enery Development