PEL Report(Submitted to Engr. Hasnain Raza)
date post
18-Jan-2017Category
Documents
view
49download
5
Embed Size (px)
Transcript of PEL Report(Submitted to Engr. Hasnain Raza)
Internship & Project Report
Project Title
Energy Efficient Production Hall
Internship Department
Energy Meter Production (EMP) Department
Duration
03rd-28th August 2015
Submitted To:
Engr. Hasnain Raza
Submitted By:
Hafiz Qasim Ali (UET Taxila)
Faisal Sattar (UET Lahore)
Khubaib ur Rehman (UOL Lahore)
Muhammad Yasir (UOS Sargodha)
Zain ul Abdeen (NUML College Mianwali)
Pak Electron Limited
Page 1
Contents
Dedication4
Acknowledgement.5
Executive Summery..6
History & background of PEL.7
Appliances Division..7
Power Division...7
Structure of EMP Departmen .......8
Energy Meters...9
Single Phase Energy Meters.9
SMT (Surface Mounting Technology) ..9
Terminal Block Assembly..10
Final Assembly.10
Testing & Calibration..11
Parameter Setup..13
OPEN Enable...13
SPDP (Security Packing & Dispatching) ..13
Quality Control.14
Dispatch packing...14
Sample Testing...14
Pak Electron Limited
Page 2
Contents
PEL INTERNSHIP PROJECT.15
Project title.15
Objective.15
Components required....15
LED Light Specifications...16
Designing of Lightening Scheme maintaining 100Lux at table surface.17
Room Dimensions...17
Calculating No. of Luminaries...17
Mounting Scheme..18
Circuit Diagram...19
Block Diagram....20
PCB Layout.20
Pak Electron Limited
Page 3
Table of Figures
Figure 1: Structure of EMP Department.8
Figure 2: 1 Watt DIY LED..16
Figure 3: Lightening Scheme.18
Figure4: Circuit Diagram.19
Figure 5: Block Diagram..20
Figure6: PCB Layout20
Pak Electron Limited
Page 4
DEDICATION
Dedicated to our respected coordinators at PEL and all those who helped us out to make our
Internship full of learning
Pak Electron Limited
Page 5
Acknowledgement
We are really pleased here to acknowledge the sheer efforts of many people those who have provided us
their relentless services in the completion of our Internship and our internship report. We would like to thank
personally to all EMP department Engineers Mr. Hasnain Raza & Mr. Hassan Ali who from their very busy
schedule helped us a lot in my learning program. Also we would like to thank to Mr. Hasnain Abid (HR) &
Miss Fatima (HR) who cooperated and guided us very well throughout this period.
May Allah Bless you all!
Pak Electron Limited
Page 6
Executive summary
We started our internship at PEL on 3rd August 2015. We were expecting a huge learning from this experience as this was first time we stepped into real world of manufacturing products. We were enthusiastic and full of energy to learn and explore the facility. We thank whole heartedly to those who made this internship possible. We cannot express our gratitude for our supervisor and engineers at EMP department who showed by example how to be professional and work toward the success of the company. Despite all the short comings experience at PEL was a fruitful one and we learned a lot. We would also like to thank those who took out time form their busy schedule to explain the working and assembling of Energy meter. No company is perfect, every company lacks in one area or the other but the thing is only those companies remain in competition who by all means keep on improving on their already perfect systems. We wish PEL and all its employees a very best of luck for their future and may PEL become a flag bearer of the manufacturing industry in Pakistan.
Pak Electron Limited
Page 7
History and Background of PEL
Pak Elektron Limited (PEL) is the pioneer manufacturer of electrical goods in Pakistan. It was established in 1956 in technical collaboration with M/s AEG of Germany. In October 1978, the company was taken over by Saigol Group of Companies. Since its inception, the company has always been contributing towards the advancement and development of the engineering sector in Pakistan by introducing a range of quality electrical equipment and home appliances and by producing hundreds of engineers, skilled workers and technicians through its apprenticeship schemes and training programs. The company comprises of two divisions:
Appliances Division Power Division
APPLIANCES DIVISION
This Division of PEL consists of appliances manufacturing. Following appliances are being manufactured at PEL:
PEL Air Conditioners
PEL Refrigerators
PEL Deep Freezers
PEL Microwave Ovens
PEL Water Dispensers (Research)
POWER DIVISION
PEL was founded in 1956 and has since been serving the Power utilities, industries, individual customers, housing and commercial projects by providing reliable, customized and cost effective solutions. Following power utilities are manufactured at PEL at the moment:
Power Transformers
Switchgears
Energy Meters
Distribution Transformers Since I have done my internship in Energy Meter Production department, so here I shall explain it in detail.
Pak Electron Limited
Page 8
Structure of EMP Department:
Energy meter is assembled here and have to pass through various sections and processes to
come to final form. Here is given the flow layout of various sections of Energy meter
department (EMP).
Figure 1: Structure of EMP Department
Pak Electron Limited
Page 9
Energy Meters
Following type of Energy meters are being manufactured and assembled at PEL at the moment:
Single Phase Energy meters
Three Phase Energy meters
LT & HT meters
Single Phase Energy meters Each energy meter is assembled and passes through various processes in different blocks of the EMP department. Following are the main working blocks in EMP department:
SMT (Surface Mount Technology)
Terminal Block
Final Assembly
Calibration & Accuracy
SPDP (Security Packing & Dispatching)
Quality Control
SMT (Surface Mounting Technology) PCB with few minor components like capacitors, resistors and pre-programmed microcontroller already installed is provided here. Following components are being installed/ assembled over here:
Battery Placement
Battery soldering
LCD pinned
1 LED fixed
Complete Soldering
Micro switch
Remaining 2 LEDs fixed
Micro switch soldering
Transmitter receiver are connected
Unnecessary extended legs are cut down
Visual inspection of front and back of PCB
Visual inspection is performed to check whether all the components are connected properly. If yes, then PCB is sent to final assembly section where it is assembled in base. CT & PT are already assembled in base and are connected with PCBs appropriate points.
Pak Electron Limited
Page 10
Terminal Block Assembly
In this section, copper wire is cut. Also Resistance metallic sheets are manufactured and finally all these are sent to be soldered with CT & PT in the base. Following steps are being performed over here:
Cu wire is covered with PVC insulation sleeve
Resistance metallic sheet is soldered with pressure plate
Solder three wires
Glass sleeve
Current coil sleeve/shrinkable sleeve
All sleeves are compressed by hot air
Cu rope wire (Neutral) is connected with CT
Phase rope wire is connected with PT
CT & PT are coupled and combined
Both CT & PT are fixed in base
Screw block is connected with base
Base is visually checked
Small errors are removed by hand
Final Assembly Terminal block base with CT & PT and PCB from SMT are sent in final assembly section. Both are coupled here. Following stages are involved in doing so:
Cable tie
PCB soldered with base here
Error check Following errors are monitored and checked here. Minor errors are removed here while for serious sort of errors, the defected part is sent to the concerned section
Cable Tie checked
Wires are checked if they are properly connected or not
Wire placement check
Switch checking
Terminal block check
LCD is checked and it is supposed to give zero, if not, then error is removed
If everything is OK and no fault or error is found anywhere in meter, then meter is sent to calibration and verification section.
Pak Electron Limited
Page 11
Testing & Calibration
Following procedures are performed on meter in this section to check and remove any sort of error in meter:
Calibration (9 steps)
Accuracy
Parameters
Calibration
Following 9 steps of calibration are performed on meter:
Step No.1 Assign Meter No. First of all, meter no is given to each meter.
Step No. 2 Temperature Calibration Temperature is maintained and calibrated at 23 Degree Celsius
Step No. 03 Live Percentage Error In this step, meter is tested with following conditions applied PF=1 Current=10A Voltage=ON (Phase) Range is -0.29 to 0.29
Step No. 04 Live Percentage Error with Induction Load Following conditions are maintained in this step: Current=10A PF=0.5L
Step No. 05 Resistive Load Live Percentage Error Meter is tested and cali