MARKET PROCESS DESIGN
MPD 06 – New QH Metered Demand Connection
MPD 06 New QH Metered Demand Connection Market Design Version 10.4
Page 2 of 12
TABLE OF CONTENTS
1. INTRODUCTION .................................................................................................................................................................................................................................... 3
1.1 SCOPE ..................................................................................................................................................................................................................................................... 3
1.2 HISTORY OF CHANGES ........................................................................................................................................................................................................................... 3
2. PROCESS MAP ..................................................................................................................................................................................................................................... 5
2.1 PROCESS DESCRIPTION ......................................................................................................................................................................................................................... 8
MPD 06 New QH Metered Demand Connection Market Design Version 10.4
Page 3 of 12
1. Introduction
1.1 Scope
This Procedure describes the process for New QH Metered Demand Connection.
This process applies to
1.2 History of Changes
This Procedure includes the following changes:
Version in which Implemented
Source of Change Description of Change
Draft 235 Changes to provisional acceptance criteria for change of legal entity
Draft B037 Message 010 is used for all Registrations
Draft Removal of 103 flow to New Supplier to inform of delay in processing due to need for additional
information
Further Changes since version 3.1
Draft MIG September 3rd Standardisation on use of QH/NQH terminology
Updates arising from Supplier clarification
Draft Written Supplier
Clarifications 2
Text in box 15 updated to include ‘provisional’
Draft Written Supplier
Clarifications 5
Updated text on page 6, 7 to Provisionally accepted rather than Registration
Draft Written Supplier
Clarifications 3
Updated section on MPRN assignment (Page 4)
Changes applied after version 4.1
MPD 06 New QH Metered Demand Connection Market Design Version 10.4
Page 4 of 12
Version in which Implemented
Source of Change Description of Change
Version 4.2 MCR 0010 Update to include business rules re: provision of EAI code. The validation of EAI on 010 Message is
included
Changes applied after version 4.2
Version 4.3 MCR 0046 ESB National Grid Requirements communicating New QH metered Connection
Version 6.0 MCR 0095 Amendments to MDP6 to satisfy new requirements of SEM implementation regarding the Supplier
Unit ID and additional validation rules and processing required surrounding Trading Sites
This will necessitate changes to :-
ARIS Process Flow Diagram (ARIS screenshot)
ARIS Process Flow Diagram – Supporting Text
Market Messages
Web-Form
Version 8.0 RMDS QA No business changes applied. MPD clean-up: objects enlarged to make text readable, swimlane
actors shifted left, swimlanes tightened.
Version 8.0a MCR 0161 Updated to reflect implementation of "MCR 0161 - Increasing the threshold for connection agreement
return". Changed references of threshold from "100 kVA" to "MV (Medium Voltage)" the following
steps:
* Get Connection agreement where required
* Set MPRN Status to Assigned
* Set Registration status to provisional
Version 10.4 MCR 1155 – Conversion of
MPDs from ARIS to
document format.
ARIS Process flow converted to Visio format and Step Table included.
Changed SMO to SEMO
MPD 06 New QH Metered Demand Connection Market Design Version 10.4
Page 5 of 12
2. Process Map
MPD 06 – New QH Metered Demand ConnectionC
us
tom
er
ES
B N
etw
ork
sS
up
plie
rT
SO
SE
MO
Post
x
3
Prepare quote, get
terms accepted
MPRN available
for Registration /publication
7
Receive
Registration
010MM
6
Registers MPRN
with MRSO
4
Set MPRN status to
Assigned
Contact with
Supplier
10
Validate
Registration
Registration
invalid
Agreed Procedure 1
8
Inform MRSO of
Update Trading
Site Registration
9
Receive Trading
Site Registration
Registration
valid
101RMM
13
Receive notice of
Registration
Rejection
2
Receive Application
Form
1
Customer sends New
Connection Form and
Application Form &
Site Details
Customer
Require New
Connection
5
Customer
contacts Supplier
11
Update QH
Registration record
with rejection
12
Inform Supplier
of Registration
Rejection
14
Set Registration
status to
Provisional
15
Send Provisional
Acceptance to
Supplier
101PMM
16
Receive Provisional
Acceptance
V
Next step 17
MPD 06 New QH Metered Demand Connection Market Design Version 10.4
Page 6 of 12
MPD 06 – New QH Metered Demand Connection
Cu
sto
me
rE
SB
Ne
two
rks
Su
pp
lie
rT
SO
SE
MO
17
Get Connection
agreement where
required
V
19
Receive ETCI cert
and/or DoF and
Duct Ready cert
x
22
Complete Meter
installation &
Energisation
V
24
Receive QH
Meter Details
25
Confirm
Communications
From step 14
To step 29
18
Send ETCI cert and/
or DoF & Duct Ready
cert
20
Update Customer
details
21
Check if ready for
Energisation
Ready for
energisation
Not ready for
energisation
23
Confirm QH details
to Data Collector
27
Details Made
available to MRSO
26
Receive
confirmation of
communications
28
All data available to
complete
Registration
MPD 06 New QH Metered Demand Connection Market Design Version 10.4
Page 7 of 12
MPD 06 – New QH Metered Demand Connection
Cu
sto
me
rE
SB
Ne
two
rks
Su
pp
lie
rT
SO
SE
MO
29
Set Registration
Acceptance status
30
Determine if
Trading Sitex
Not Trading site
Trading site
V
33
Send Registration
acceptance to
Supplier
101MM
34
Receive
Registration
Acceptance
35
Send Meter Details
to Supplier
331MM
36
Receive Meter
Details
37
Send Meter Details
to TSO
331MM
38
Receive Meter
Details
39
Send Registration
acceptance to TSO
101MM
40
Receive
Confirmation of
Registration
31
Advise SMO of
Registration
acceptance
32
Receive
confirmation of
Registration
From step 28
MPD 06 New QH Metered Demand Connection Market Design Version 10.4
Page 8 of 12
2.1 Process Description
Process Step Role Process Step Description Interface
1 Customer sends New Connection Application & Site Details
Customer The Customer sends application form and site details to ESBN. Post
2 Receive Application Form
ESBN ESBN receives an application form & site details from a Customer.
3 Prepare quote, get terms accepted
ESBN On receipt of an application from the Customer, ESBN will prepare and issue a quotation to the Customer. The MPRN for the new meter point will be issued to the Customer with the quotation. In the case of multi-site developments, the Developer will be issued with a list of the MPRNs.
4 Set MPRN status to Assigned
ESBN The status of the MPRN will be set to assigned once the following criteria have been met:
The quotation must have been accepted and Capital Contribution paid
The Customer must have accepted the terms of connection and returned a signed Connection Agreement (over MV (Medium voltage))/Acceptance of Offer (Under MV(Medium Voltage))
As soon as the MPRN has reached the status of ‘Assigned’, Registrations will be accepted by Meter Registration System Operator (MRSO) for that MPRN
5 Customer contacts Supplier
Customer The Customer contacts a Supplier to register the MPRN.
6 Registers MPRN with MRSO
Supplier The Supplier provides a Registration application, completed in accordance with the applicable Rules to Meter Registration Service Operator (MRSO). The Supplier is responsible for the validity of all information provided for the purposes of registering a Meter Point. A Registration request from a Supplier will be taken as a request for energisation by ESBN.
010 MM
7 Receive Registration ESBN ESBN receives Registration request from a supplier - next step 10
8 Inform MRSO of Update Trading Site Registration
SEMO Single Market Operator (SEMO) will advise MRSO of Update Trading Site Registration. See Wholesale Market Agreed Procedure1.
9 Receive Trading Site Registration
ESBN MRSO receive update Trading Site Registration.
MPD 06 New QH Metered Demand Connection Market Design Version 10.4
Page 9 of 12
Process Step Role Process Step Description Interface
10 Validate Registration ESBN MRSO will validate the Registration in accordance with the applicable validation rules and advise the Supplier of the outcome.
Failure of the following validations will cause the Registration to be rejected.
The Supplier must have provided all mandatory information.
The MPRN must have been assigned and is not terminated.
The Supplier Id is a valid one and the Supplier has a DUoS agreement.
The Supplier must be entitled to register a Meter Point under the legislation and in accordance with the Trading and Settlement Code.
The Supplier warrants that a supply agreement exists with the Customer at the Meter Point being registered.
The Supplier must provide a Supplier Unit that is valid for the Supplier
The Supplier Unit must not be a Trading Site Supplier Unit.
The Supplier must provide a sub-aggregation code (SSAC) that is valid for the Supplier Unit and for the Settlement Class.
EAI must be valid and not blank for sites over 30 kVA. Failure of the following validation will cause the Registration to be rejected unless ESBN approves the new information. Meter Point Address advised by Supplier is materially inconsistent with Meter Point Address known to MRSO. ESBN may accept or reject the new address submitted by the Supplier.
Registration invalid - next step 11
Registration valid - next step 14
11 Update QH Registration record with rejection
ESBN MRSO will update the Registration record with the rejection.
12 Inform Supplier of Registration Rejection
ESBN If Registration is rejected the Supplier is informed of the rejection with the reasons. A Registration received prior to energisation that is provisionally accepted will supersede any previous Registration. The Supplier of any previously accepted Registration will be informed.
101R MM
13 Receive notice of Registration rejection
Supplier The Supplier receives notification of the Registration rejection.
MPD 06 New QH Metered Demand Connection Market Design Version 10.4
Page 10 of 12
14 Set Registration status to Provisional
ESBN Where the Registration is valid, ESBN will determine if provisional acceptance is required. Failure of the following validations will cause the Registration to be provisionally accepted.
The Meter Point is not energised. The Registration will become effective when the Meter Point is energised.
The connection voltage is equal to or exceeds “MV (Medium Voltage)"and there is no Connection Agreement in place or there is a change of Customer name or registered company number or Change of Tenancy. In this case ESBN must confirm the existence of a Connection Agreement before the Registration is accepted.
15 Send Provisional Acceptance to Supplier
ESBN If the Registration is provisionally accepted the Supplier will be informed of the provisional acceptance, with reasons, together with Meter Point status and characteristics known to MRSO at the time.
101P MM
16 Receive Provisional Acceptance
Supplier The supplier will receive notification of Provisional Acceptance of Registration.
17 Get Connection Agreement where required
ESBN Where a Registration has been provisionally accepted pending receipt of a Connection Agreement (in cases where Connection Voltage is equal to or exceeds MV (Medium Voltage)), DSO will signal the existence of a Connection Agreement to MRSO.
18 Send ETCI cert and/or DoF & Duct Ready cert
Customer The Customer will be responsible for the provision of a Wiring Certificate, Declaration of Fitness (DoF) for MV & above and a Duct Ready Certificate to ESBN where required.
19 Receive ETCI cert and/or DoF & Duct Ready cert
ESBN ESBN receives the Wiring Certificate, Declaration of Fitness (DoF) for MV & above and a Duct Ready Certificate.
20 Update Customer details
ESBN On receipt of Connection Agreement the new Customer details are updated.
MPD 06 New QH Metered Demand Connection Market Design Version 10.4
Page 11 of 12
21 Check if ready for Energisation
ESBN ESBN will check if all the criteria are met for energisation. DSO will arrange for the energisation of the Meter Point in accordance with the metering requirements specified and applicable metering codes, practices and standards. This will occur when the following conditions are true:
All payments required have been received.
A Connection Agreement must be in place.
All certificates required (wiring certificate/ Declaration of fitness etc.) have been received.
A Provisionally Accepted Supplier Registration must be in place for Customer s with MIC greater than or equal to 30 kVA.
If all criteria are met - next step 22
If all criteria are not met - back to step 21
22 Complete Meter installation & Energisation
ESBN Distribution System Operator (DSO) will arrange for the Energisation of the Meter Point in accordance with the metering requirements specified and applicable metering codes, practices and standards.
23 Pass QH Meter details to Data Collector
ESBN On completion of Energisation of the Meter Point, DSO will confirm QH details to Data Collection.
24 Receive QH Meter Details
ESBN Data Collection receives QH meter details.
25 Confirm Communications
ESBN Upon receipt of the meter details Data Collection will be responsible for confirming the existence and operation of communications at the new QH metered site to the DSO.
26 Receive confirmation of communications
ESBN Data Collection will confirm communication with the QH metered site to DSO.
27 Make details available to MRSO
ESBN At Energisation, and once communications have been verified, DSO will make meter details and the Meter Point status available to MRSO and completes the Meter Point characteristics.
28 All data available to complete Registration
ESBN MRSO will confirm that all data required for Registration is available.
29 Set Registration Acceptance status
ESBN Registration status changed to acceptance.
MPD 06 New QH Metered Demand Connection Market Design Version 10.4
Page 12 of 12
30 Determine if Trading Site
ESBN MRSO will determine if the Registration is for a Trading Site.
If Trading Site - next step 31 and steps 33 - 39
If not Trading Site - next steps 33 - 39
31 Advise SEMO of Registration acceptance
ESBN MRSO will advise SEMO of Registration for the Trading Site. Email
32 Receive confirmation of Registration
SEMO SEMO receives details via email of the Registration of the Trading Site.
33 Send Registration acceptance to Supplier
ESBN Where a Meter Point has been energised and there is a Registration for which all
other conditions for final acceptance are met, the Registration is confirmed and the
Supplier will be informed of the final acceptance. Where energisation is not notified
to MRSO within five days of the energisation date, then, when energisation is
identified: - a Registration acceptance, backdated to the energisation date, will be
sent to the provisionally accepted Supplier. Should a Meter Point have a
provisionally accepted Supplier Registration for sixty working days, and that Meter
Point has not been energised, MRSO will issue a report to the Supplier and the
DSO.
101 MM
34 Receive Registration acceptance
Supplier The Supplier receives confirmation of the Registration.
35 Send Meter Details to Supplier
ESBN ESBN send Meter Details to the Supplier. 331 MM
36 Receive Meter Details Supplier The Supplier receives Meter Details.
37 Send Meter Details to TSO
ESBN ESBN send Meter Details to the TSO. 331 MM
38 Receive Meter Details TSO TSO receive Meter Details.
39 Send Registration acceptance to TSO
ESBN ESBN send confirmation of the Registration to the TSO. 101 MM
40 Receive confirmation of Registration
TSO TSO receive confirmation of Registration.