MINUTES OF THE 8TH MEETING OF TCC OF SRPC HELD AT KUMARAKOM … · to Kumarakom, Kerala also known...
Transcript of MINUTES OF THE 8TH MEETING OF TCC OF SRPC HELD AT KUMARAKOM … · to Kumarakom, Kerala also known...
SOUTHERN REGIONAL POWER COMMITTEE BANGALORE
MINUTES OF THE 8TH MEETING OF TCC OF SRPC
HELD AT KUMARAKOM ON 05.03.2009
1. INTRODUCTION
1.1 The 8th meeting of the Technical Coordination Committee of SRPC was held
at Kumarakom on 05th March 2009. The list of the participants is given at
Annexure-I.
1.2 AGM (Commercial), NTPC extended a hearty welcome to all the participants
to Kumarakom, Kerala also known as God’s Own Country. He thanked
SRPC for giving NTPC the opportunity to host the 8th TCC and 9th SRPC
Meetings.
1.3 Shri A.N. Dave, Regional Executive Director (South), NTPC welcomed the
honourable Members of TCC and participants to the picturesque
surroundings of Kumarakom. He added that this meeting assumed
significance as the peak months were staring at Southern Regional
Constituents. The shortages in SR were at par with the shortages in the rest
of the country. NTPC like all other generators would maximize its generation
during the peak months. Some of the maintenance overhauls of NTPC units
had been deferred in view of the high demand being faced by Southern
Region. He added that it was a privilege for NTPC to host the SRPC/TCC
Meetings. He also expressed hope that fruitful deliberations would take
place in these Meetings.
1.4 Shri Mohan Lal Batra, MS, SRPC welcomed the Members and participants to
the Meeting. He thanked NTPC for making excellent arrangements for
conduct of the Meeting. He also welcomed Shri T. Chatterjee, CE (GM),
CEA and Shri Major Singh, Director, CEA, to the meeting. He requested
Smt. S. Phebe Beryl, CE (Power Management), TNEB to preside over the
meeting in the absence of Member (Generation), TNEB, who is Chairperson,
TCC.
(8th meeting of TCC held on 05.03.2009 at Kumarakom)
2
Agenda items were taken up for discussion.
2. CONFIRMATION OF THE MINUTES OF THE 7TH MEETING OF TCC
2.1 Minutes of the 7th meeting of the Technical Coordination Committee of SRPC
held at Hyderabad on 18th December 2008 were forwarded vide letter
No.SRPC/SE-II/TCC/2009/366-85 dated 16th January 2009.
2.2 The Minutes were confirmed.
3. TRANSMISSION SCHEMES 3.1 Transmission System for evacuation of power from Simhadri-II TPS (2x500 MW) of NTPC 3.1.1 The following transmission system was agreed for evacuation of power
from Simhadri-II TPS of NTPC in the 25th meeting of Standing Committee
on Power System Planning.
- Simhadri STPP-II TPS – Gazuwaka 400 KV D/C line
- Part capacity of APTRANSCO’s existing Vizag-Vemagiri-Narsaraopet 400 KV D/C line transmission corridor to be utilized through applying for long-term open access to APTRANSCO.
- It was also decided that when Vizag TPS generation was firmed up or any new generation came up in that area, APTRANSCO line could be spared and another line could be taken up as a Regional System Strengthening Scheme.
3.1.2 The Committee had noted that Simhadri Expansion was a 11th Plan
Regional project and NTPC had received power requirement from SR
constituents in excess of the installed capacity of 1000 MW and draft
PPA had been circulated. NTPC vide letter dated 08.03.2007 had
intimated details of requirement of power indicated by various
beneficiaries and vide letter dated 10th April 2007 intimated that the units
were tentatively expected to be commissioned during the financial year
(8th meeting of TCC held on 05.03.2009 at Kumarakom)
3
2010-11. It was also noted that formal allocation from the project was yet
to be issued by MOP. APTRANSCO had concurred to accord Open
Access for APTRANSCO’s transmission system for Simhadri STPS
Stage-II and agreed to make all the beneficiaries as Respondents, in the
proposed petition before APERC for fixation of tariff for use of
APTRANSCO asset.
3.1.3 In the 8th meeting of SRPC the Committee had noted the following:
- NTPC informed that a common Open Access application on behalf of the beneficiaries had already been submitted to APTRANSCO. The 1st Unit of the project was expected by November-December 2010.
- APTRANSCO had informed that they would process the Common Open Access application made by NTPC on behalf of all the beneficiaries and approach APERC at the earliest.
3.1.4 In the meeting, ED (GO), APTRANSCO informed that APTRANSCO
would approach APERC shortly since they were presently engaged in
finalization of Tariff Regulations. He added that later all the beneficiaries
would need to individually sign the agreement with APTRANSCO.
4. TRANSFER OF SIRSI-GUTTUR (DAVANAGERE) 400 kV D/C LINK OF KPTCL TO PGCIL AS A REGIONAL TRANSMISSION SCHEME
4.1 Technical Aspects
The Committee had noted that PGCIL & KPTCL had interaction in this regard
and for technical taking over, they were in readiness.
4.2 Financial Aspects
4.2.1 In the 8th meeting of SRPC held on 19th December 2008, KPTCL had
informed that during first week of December 2008, they had received the
auditor’s certificate and the same would be submitted to PGCIL. KPTCL
had also informed that by next month they would approach KERC for
(8th meeting of TCC held on 05.03.2009 at Kumarakom)
4
necessary approval. PGCIL would also approach CERC after the receipt
of the auditor’s certificate, pending KERC approval.
4.2.2 In the meeting, ED, SR-II, PGCIL informed that PGCIL had not received
the auditor’s certificate.
4.2.3 Director (Trans.), KPTCL said that they would furnish the auditor’s
certificate to PGCIL within a week’s time. KPTCL had already
approached KERC in the first week of January 2009.
4.2.4 CE (Trans), NPCIL expressed concern over slow progress on the issue.
4.2.5 MS, SRPC suggested KPTCL and PGCIL may coordinate to expedite the
issue.
5. NEW PROJECTS OF NLC & NTPC
A Statement giving details of power requirements indicated by various
constituents/finalized allocation percentages in new projects of NLC, NTPC
and Joint Venture are at Annexure-II.
5.1 500 MW (2 X 250) Lignite Based Neyveli-II Expansion
5.1.1 In the 8th SRPC meeting, Director (Power), NLC had informed the revised
schedule of commissioning of Unit-I & Unit-II as February 2010 & June
2010 respectively.
5.1.2 In the meeting, CGM, TS-II & II Expn., NLC said that NLC had discussed
the issue with BHEL and there would not be any further slip in TS-II Expn.
Project. He confirmed the dates of commissioning of Unit-I & II as
February 2010 and June 2010.
5.2 2000 MW (4x500) coal based power plant at Orissa (Ib Valley)
5.2.1 The status of progress in respect of the project is as under:
(8th meeting of TCC held on 05.03.2009 at Kumarakom)
5
- Alternate land had been identified at Rengali Village, Jharsuguda District. Finalization of land acquisition formalities pending with Orissa Government.
- SRP Committee had passed a resolution seeking full share to SR constituents from the project as they were the first to give a firm commitment for power take off from the project.
- Chairperson, SRPC had taken up with the Secretary (Power), MOP for allocation of entire power from the 2000 MW Ib Valley Project to the constituents of Southern Region as they were the first to provide a firm commitment for off-take of power from the project.
- NLC had requested Industrial Promotion Investment Corporation of Orissa Limited (IPICOL) to reserve 1135 hectares of land in the new site and an application in the prescribed format along with the fees had been sent to IPICOL for reserving the land.
- NLC had informed that project was expected to come up in 12th Plan.
- Reply from Orissa Government was awaited by NLC.
- General Manager, Project and Business Development, NLC vide letter dated 6th October, 2008 had stated that Orissa State had released policy guidelines for establishment of Thermal Stations in the State and NLC was perusing the policy papers.
5.2.2 In the 8th meeting of SRPC, NLC had informed that the issues raised by
Orissa Government, like signing of new MOU and 5% share of the profit
were under consideration of its management.
5.2.3 In the meeting, CGM, TS-II & II Expn., NLC informed that the policy
guidelines issued by the Orissa Government including signing of new
MoU and 5% share of profit was under circulation with the Board of
Directors. A view would have to be taken in the matter by NLC.
5.3 Alternative site at Narsapur
- NLC had identified a site at Andhra Pradesh (Narsapur) but the viability of coal transport and logistics were yet to be finalized by them.
(8th meeting of TCC held on 05.03.2009 at Kumarakom)
6
- Director (Power), NLC, in the 7th meeting of SRPC had informed that certain issues like rail linkage to Narsapur, Godavari River Crossing, coal transportation for more than 1000 Km etc. were to be addressed.
- CMD, APTRANSCO had nominated SE (Civil), APTRANSCO, Vishakhapatnam as a Liaison Officer on behalf of APTRANSCO and requested NLC to interact with him, for resolution of the problems.
5.3.1 In the 8th meeting of SRPC the Committee had noted the following:
- Director (Power), NLC had informed that the issue regarding transfer of coal over a distance of 950 Km. was being discussed with Railway Authorities.
- Chairperson, SRPC & Chairman, TNEB suggested that possibility of having Railway as a partner in the project may also be explored since Railways had expressed interest in becoming partners. He had also said that NLC may furnish their milestones to M/s.BHEL for both the projects. A meeting with BHEL, NLC etc. could be organized to sort out the issues at the earliest, in which, the good offices of Hon’ble Union Minister of State for Power could also be sought for early resolution of issues.
5.3.2 In the meeting, CGM, TS-II & II Expn., NLC informed that the Narsapur
project could be taken up if the Ib Valley Project did not materialize. NLC
officials along with designated officer of APTRANSCO inspected the site
and had discussion with Railway authorities. Subsequently, SE,
APTRANSCO had collected the details regarding distance and railway
track availability and communicated the same. The issue regarding
willingness to transport is to be further discussed with Railway officials.
Moreover, decision regarding making Railways as partners was yet to be
taken by NLC.
6. LEVY OF SERVICE TAX ON ELECTRICITY TRANSMISSION AND SLDC CHARGES
6.1 The issue regarding levy of service tax on Electricity Transmission and SLDC
charges was discussed in the 2nd SRPC Meeting held on 31st October 2006
(8th meeting of TCC held on 05.03.2009 at Kumarakom)
7
at Hyderabad. CMD, APTRANSCO, at that time, had informed that
APTRANSCO and some other transmission utilities had received notice for
service tax for transmission of electricity. She had added that even
distribution companies could receive notice in this regard. In case service
tax for transmission of electricity are to be paid by Transmission and
Distribution companies the charges may need to be added in the tariff.
APTRANSCO’s tax consultant had opined that electricity could be defined as
‘goods’ and provision of service tax may not apply on transmission of
electricity and hence it may be exempted from service tax. It was agreed
that Chairperson, SRPC would take up the matter with Secretary, Ministry of
Power, Government of India for further taking up with Ministry of Finance.
Chairperson, SRPC vide letters dated 9th November 2006, 11th December
2007 & 19th February 2008 and 30th October 2008 had taken up the matter
with Secretary (Power), Government of India.
6.2 In the 8th meeting of SRPC held on 19th December 2008 the Committee had
noted the following:
- There was an Order of Hon’ble Supreme Court in regard to AP duty issue pertaining to sale of power from RSTPS, wherein the provisions of treatment of electricity had been dealt with. APTRANSCO would seek legal opinion of their tax consultant based on the Supreme Court order and this opinion would be forwarded to the other constituents.
- CMD, APTRANSCO stated that their Tax Consultant had already opined that electricity may be treated as ‘goods’. The Irrigation Department in Andhra Pradesh had also been asked to pay Service Tax. In view of the above, the issue could be taken up with Secretary (Revenue), Government of India. The issue may also need to be taken up with Director General (Service Tax), GoI, Mumbai for clarification.
- MD, KPTCL said that they would revert back on whether KPTCL had taken up the issue with Appellate Tribunal regarding Service Tax.
(8th meeting of TCC held on 05.03.2009 at Kumarakom)
8
- After deliberation, it was decided that Chairperson, SRPC would take up the issue with Director General (Service Tax), GoI, Mumbai and subsequently with the Secretary (Revenue), GoI.
6.3 Chairperson, SRPC had taken up the matter with Director General (Service
Tax), GoI, Mumbai vide letter dated 4.2.2009 (copy at Annexure- III). MOP
had also sought the views of CEA regarding exemption of service tax on
electricity transmission and SLDC charges. CEA had furnished its views to
MOP vide letter dated 28.01.2009 (Annexure- IV).
6.4 In the meeting, MS, SRPC informed that DG (Service Tax), Mumbai had
forwarded the letter to the Chief Commissioner (Central Excise), Chennai
Zone (copy enclosed as Annexure-V) for further examination. He pointed out
that CEA had furnished its opinion to MoP, which was favourable to the
utilities.
6.5 Director (Trans.), KPTCL informed that KPTCL had taken up the issue
regarding Service Tax with the Appellate Tribunal and details in this regard
would be communicated.
7. OPERATION OF TALCHER-KOLAR HVDC TRANSMISSION SYSTEM IN GROUND RETURN MODE
7.1 In the 8th SRPC Meeting, the Committee had noted the following:
- The power transfer needed to be restricted to 150 MW in GRM, as recommended by KPTCL’s Consultants in the interest of the nearby KPTCL transformers which were getting affected.
- As per PGCIL technical inputs, power transfer could be upto 450 MW in GRM.
7.2 In the CERC (Terms and Conditions of Tariff) Regulations, 2009 for
generation and transmission projects for the period 2009 -14, Appendix-IV of
the same details the procedure for calculation of Transmission System
Availability Factor for a month.
(8th meeting of TCC held on 05.03.2009 at Kumarakom)
9
7.3 Transmission capability reduction of the system in MW (TCR) during GRM
operation of Talcher – Kolar HVDC transmission system needed to be
finalized.
7.4 In the meeting, Director (Trans.), KPTCL said that flow upto 150 MW in GRM
only was acceptable to KPTCL as the assets of KPTCL could get affected
with higher flows. The limit of 150 MW in GRM had been finalized after
detailed studies carried out by KPTCL’s Consultant. He added that humming
sound was heard in transformers as far as in Davanagere and KPTCL could
not take a chance of power transformer failure.
7.5 ED, SR-II, PGCIL said that studies of PGCIL had concluded that 450 MW
flow in GRM, was possible.
7.6 CE (GM), CEA said that it was seen that there were two established results.
GRM operation was not very frequent and occurring once in a while only. To
sort out the issue, CEA could therefore be approached in the matter and
requested to give a decision in the matter as early as possible.
7.7 ED, SR-II, PGCIL said that PGCIL was only part of the measurement
process during tests carried out by M/s. PRDC (KPTCL’s Consultant).
PGCIL was however not a party to the recommendations given by M/s.
PRDC. There was no doubt about the measurement, but it was a larger
question of interpretation.
7.8 SE (O), SRPC pointed out that Clause 4.2 (b) of IEGC states
“Any new or modified connections, when established, shall
neither suffer unacceptable effects due to its connections to
ISTS nor impose unacceptable effects on the system of any
other connected agency.”
(8th meeting of TCC held on 05.03.2009 at Kumarakom)
10
In the previous meeting it was noted that the flow of DC current in neutrals
would damp down with the growth of transmission system.
7.9 ED, PGCIL said that as per PGCIL’s technical input 450 MW flow in GRM
was safe. Flow restriction of 150 MW in GRM was however a scheduling
aspect in real time operation. He added that the matter could be referred to
CEA separately.
7.10 Technical Director, KPCL said that this was a technical problem. The
transformers were getting stressed and humming sound was being observed
when flow in GRM was more than 450 MW. The transformer manufacturer
may also have to be consulted also to give a technical solution to the
problem.
7.11 After deliberations, it was agreed that the Transmission
Capability Reduction of the Talcher - Kolar HVDC transmission system
during GRM operation would be 2350 MW (2500 MW-150 MW) till CEA
recommends a technically acceptable value. CEA would be requested to
examine and suggest a technically acceptable value within a period of three
months. KTPCL & PGCIL would forward their reports and associated
documents to CEA/SRPC Secretariat. The availability of Talcher - Kolar
HVDC would be modified, if required, based on the recommended value of
CEA, with effect from April 2009.
8. PROGRESS OF BUS/LINE REACTORS TO BE COMMISSIONED IN SR 8.1 Bus/Line reactors are to be commissioned by the SR constituents as
identified in the 22nd Standing Committee on Power System Planning of
Southern Region, and approved in the 4th SRPC meeting held on 7.6.2007.
8.2 It was noted that these reactors were not coming up in the desired time
schedule. The issue is being regularly followed up in the OCC meetings. In
(8th meeting of TCC held on 05.03.2009 at Kumarakom)
11
the 26th meeting of the Standing Committee on Power System Planning held
on 13.06.2008, Member (PS), CEA had observed that the progress on
implementation of reactors at 400 kV S/S in SR was rather slow. All efforts
needed to be made to expedite the work as the whole scheme was to be
completed by the end of 2008-09 itself.
8.3 It was decided that each agency would provide detailed status of
implementation of reactors in their state/area of jurisdiction. In the 8th SRPC
Meeting, the representatives of KPTCL informed that they were converting
the line reactor at Guttur (Davangere) for using the same as Bus reactor.
Member (PS) pointed out that the requirement of reactors at Raichur,
Talaguppa, Davangere, Nelamangala and Hoody was in addition to the
existing line reactors in operation. Therefore, KPTCL should install new/
additional reactors in operation.
8.4 CGM, TPS-II, NLC vide letter dated 01.12.2008 addressed to ED, SR-II,
PGCIL (copy enclosed at Annexure-VI) had raised certain issues regarding
the installation of bus reactors at NLC.
8.5 Executive Director (OS). PGCIL vide letter dated 19.02.2009 (Annexure-VII)
had informed that POWERGRID was making special efforts to expedite the
commissioning of 7 Bus Reactors and 4 Line Reactors under its scope
before the schedule of November 2010. Beneficiaries had been requested
to concur for preponement of commercial operation of these reactors so that
they could be declared under commercial operation separately as and when
each reactor was commissioned.
8.6 The updated information furnished by the constituents during the 8th TCC
meeting is given in the Table below:
(8th meeting of TCC held on 05.03.2009 at Kumarakom)
12
Bus Reactors
Sl. No. Bus Name Status POWERGRID 1 Hosur
2 Kolar
3 Hiriyur
4 Salem
5 Munirabad
6 Hyderabad (PG)
7 Sriperumbudur
By March 2010
NTPC 8 Ramagundam
9 Simhadri
Before November 2010. Tender activity started
NPCIL 10 Kaiga Before November 2010 (entrusted to
PGCIL). Tree cutting and leveling works were started and site would be handed over to PGCIL.
NLC 11 Neyveli-Expn.
12 Neyveli TS-II
Before November 2010. To start tender activity.
KPTCL 13 Raichur TPS Would be completed by KPCL before
2010. 14 Talaguppa
15 Davanagere
16 Nelamangala
17 Hoody
Before 2010
APTRANSCO 18 Srisailam LBPH APGENCO has informed about space
constraint at Srisailam. Taken up in SCPSPSR.
19 Kurnool
20 Vizag
By March 2010.
(8th meeting of TCC held on 05.03.2009 at Kumarakom)
13
Line Reactors
Sl.No. Name Status
POWERGRID 1 Trichy 2 Madurai 3 Udumalpet 4 Thiruvananthapuram
By March 2010
APTRANSCO 5 Hyderabad By March 2010
8.7 AGM, SRLDC informed that with the commissioning of bus reactors at
Tirunelveli as approved in previous SRPC meeting, the voltage profile at
Tirunelveli had improved significantly. The voltage was not going beyond 410
kV at night hours even with all the lines in service. He requested the
constituents to expedite the commissioning of the other reactors also. He
added that since there was some space constraint to install a reactor at
Srisailam Left Bank, therefore the machines at Srisailam Left Bank could run
in synchronous condenser mode whenever needed since the units had the
necessary capability. He also enquired from KPTCL whether the
commissioning of the bus reactor at Guttur could be preponed since the 400
kV lines had to be opened in that area on a daily basis. During rainy season
upto 40 numbers, 400 kV lines had been opened, to contain the over voltage.
8.8 CE (Trans.), NPCIL enquired whether the 220 kV side voltages had
improved or not as earlier the Kudunkulam transformers were tripping due to
over fluxing as informed in the previous SRPC meeting. He also informed
that PGCIL had set up their office at Kaiga GS and the team had been
mobilised. Tree cutting was on and the site was expected to be handed over
to PGCIL by 15th March 2009 for installation of reactor.
8.9 Director (Trans.), KPTCL said that reactor at Davanagere would be
commissioned within one year i.e, before March 2010.
(8th meeting of TCC held on 05.03.2009 at Kumarakom)
14
8.10 ED, SR-II, PGCIL said that the position had now been reviewed and reactors
to be commissioned by PGCIL were likely to be commissioned before March
2010. He therefore requested the constituents to agree for commercial
operation of the reactors as and when they are connected to the grid, since
the SR Grid was facing high voltage problems. Earlier the utilities had
already requested for commissioning of the reactors as early as possible in
the interest of System Operation.
8.11 ED (GO), APTRANSCO said that as regards running the Srisailam units in
synchronous condenser mode, they would revert back in 10 days time.
8.12 TCC recommended for commercial operation of PGCIL reactors as and
when they were commissioned.
9. EVACUATION SCHEMES FOR NEW CENTRAL GENERATING STATIONS
9.1 The situation of anticipated availability from the three Central Generating
Stations coming up in the 11th Plan was as under:
a) Kudankulam APP
Unit-I : December, 2009 Unit-II : March, 2010
b) Neyveli-II Expansion
Unit-I : February, 2010 Unit-II : June, 2010
c) Kaiga
Unit-IV : May go beyond 2008-09
9.2 In anticipation of the generation availability in the periods as mentioned
above, SRPC Secretariat had been following up with the constituent States
to match their corresponding evacuation transmission system availability in
appropriate time frame to ensure no bottling up of power at the CTU junction
points of the State.
(8th meeting of TCC held on 05.03.2009 at Kumarakom)
15
9.3 The updated information on progress on evacuation schemes is given at
Annexure-VIII.
9.4 In the 8th meeting of SRPC the Committee had noted the following:
- NPCIL had requested the constituents to furnish the requirement of power from Kudankulam II Stage (4000 MW) which was proposed to be commissioned during 2015-2020.
- Regarding 400 kV Mysore-Kozhikode, PGCIL had informed that the Hon’ble Energy Minister, Government of Karnataka had taken a meeting in this regard with Forest Department and District Collector of Coorg District. Forest Department was taking up the issue with GOI and the District Collector was pursuing the matter in regard to the ROW issue.
- ED (SR-II), PGCIL had said that though there were some positive developments, the situation with regard to ROW of 400 kV Mysore-Kozhikode line would be clear by the next SRPC meeting. In respect of the lines in Kerala, he said that PGCIL was getting full support from the State Government & also from KSEB.
- NPCIL had expressed concern over the tripping of transformer being used to avail start up power at Kudankulam as a result of overfluxing. TNEB had assured necessary assistance to address the issue.
9.5 GM (I/c), SRTS-I, Power Grid vide letter dated 9.2.2009 (Annexure-IX) had
requested APTRANSCO to inform about the status of associated 220 kV
system of Andhra Pradesh, with respect to the commissioning of 400 kV S/S
at Warangal. In the 7th SRPC Meeting, the preponement of commissioning
of Warangal S/S had been approved. ED (OS), PGCIL vide letter dated
19.02.2009 (refer Annexure-VII) had also requested confirmation from
SRPC, about the completion of the project, admitting the commercial
operation of the system and payment of full fixed charges on regional pool
basis.
9.6 ED (OS), PGCIL vide letter dated 19.02.2009 (refer Annexure-VII) had stated
that in the 7th SRPC Meeting, the advancement of Hassan and Karaikudi
(8th meeting of TCC held on 05.03.2009 at Kumarakom)
16
substation along with LILOs had been approved from August 2009 to
February 2009. This was with the understanding that with regard to Hassan
assets, it was tentative and subject to review. KPTCL was requested to
please indicate their readiness so that Hassan related assets could be
commissioned.
9.7 In the meeting, CE (Trans.), NPCIL informed that on account of fuel
constraints Unit-4 of Kaiga would be commissioned in the first quarter of
2010. NPCIL would furnish details regarding proposed Kudunkulam Stage-
II, 4000 MW Project to the utilities.
9.8 ED, SR-II, PGCIL said that regarding forest clearance in Karnataka in
respect of 400 kV Mysore- Kozhikode line, Chief Minister of Karnataka had
cleared the file and they would pursue the issue with MoEF. Regarding
coffee plantation, a meeting with DC, Kodagu, local people and PGCIL had
been held. Another meeting would be held with the local people, within two
weeks, after which PGCIL may be able to take up preliminary survey works.
On Kerala side, things were easing out and the issue of compensation was
likely to be resolved.
9.9 APTRANSCO informed that their system would be ready by July 2009 and
Warangal 400 kV S/S could be commissioned accordingly. TNEB informed
that their system was ready and Karaikudi 400 kV S/S along with LILO could
be commissioned accordingly. KPTCL informed that since their system
would be ready by June 2009, Hassan 400 kV S/S along with LILO could be
commissioned accordingly. TCC recommended for approval of the above
elements and sharing of the transmission charges.
9.10 ED, SR-II, PGCIL requested for commissioning of the following transmission
elements of Neyveli TS-II Expansion Evacuation Scheme:
(8th meeting of TCC held on 05.03.2009 at Kumarakom)
17
• Neyveli TS-II Expansion-Neyveli TS-II (2xS/C)
• Neyveli TS-II Expansion-Pugalur D/C
• Pugalur-Madurai D/C
• 400/220 kV, 2x315 MVA S/S at Pugalur
On a request from the constituents for further details, PGCIL agreed to
present the issue to SRPC the next day with relevant study details and
necessity for early commissioning.
9.11 ED, SR-II, PGCIL also requested for commissioning of the third 400 kV
transformer at Thiruvananthapuram.
9.12 KSEB agreed for the above.
9.13 Technical Director, KPCL said that Unit-8 at RTPS and Unit-2 at BTPS were
expected to be commissioned by November 2009 and 2010 respectively
and requested that transmission evacuation system for these units should
be tied up. Gundia (200 MW) project was also likely to come up in 2010-11.
TCC suggested that the issue may be taken up by KPCL with KPTCL and
Standing Committee on PSPSR.
10. GENERATION & COAL STOCK POSITION AT THERMAL STATIONS OF SOUTHERN REGION
10.1 The need for maintaining statutory coal stock position in all the thermal
stations at all times has been deliberated in various forums of SRPC. OCC
has been reviewing the coal stock position at the stations on a monthly basis.
10.2 Generating Companies were requested to apprise the Committee of the
present coal stock position and also the steps taken by them to enhance the
coal stock to levels as per statutory requirements.
10.3 In the meeting, TCC was apprised of the coal stock position in thermal
stations as downloaded from CEA website as on 1st March 2009.
(8th meeting of TCC held on 05.03.2009 at Kumarakom)
18
10.4 CE, APGENCO said that the coal stock at Dr. N. Tata Rao (Vijayawada)
Station and Rayalaseema was for 7 days & 2 days respectively. Singraneni
had promised continuous supply of 12 rakes/day and APGENCO stations
were hence comfortable with respect to coal stock.
10.5 MS, SRPC suggested that any coal supply related issues could also be taken
up with CEA, enabling it to be discussed in the weekly Sub-Committee
meeting in the Ministry of Coal.
10.6 CE (GM), CEA pointed out that it was surprising that Kothagudem station had
reported loss of generation recently, though it had a coal stock of 8 days. He
requested APGENCO to look into this issue.
10.7 CE, APGENCO said that the coal meant for Kothagudem had been diverted
from Singraneni to VTPS & Rayalaseema and the coal was also of poor
quality (45% ash content).
10.8 Technical Director, KPCL said that the coal stock at Raichur and Bellary
Thermal Station was for 24 days (4,76,000T) & 30 days respectively. He
expressed concern over the limited rakes in the railways for the supply of
LSHS to Yelahanka DG Plant. Though 6 rakes were required per month, 2
rakes were being received and with a great difficulty 4 rakes were now being
received. He said that Yelahanka DG plant was important since it catered to
the load centre at Bangalore.
10.9 CE (GM), CEA suggested that KPCL may forward information to CEA for
further needful, though the matter pertained to LSHS supply and not coal.
10.10 Technical Director, KPCL said that the CHP problem had been resolved in
500 MW Bellary unit and the commissioning process of the unit was on (72
hrs. continuous run). He added that Raichur units had achieved PLF of
93.93% in January 2009 and 99.84% in February 2009.
(8th meeting of TCC held on 05.03.2009 at Kumarakom)
19
10.11 Regional Executive Director (South), NTPC informed that though stock at
Talcher Stg-II was for three days it was a pit head station. Talcher had
maintained PLF of 102% for last about two months. NTPC was in touch with
MCL authorities on a daily basis. The generation at Talcher Stg.-II was not
suffering but it would take some time to build up the coal stock. He also
assured that whenever wharf wall were taken up, availability to SR
constituent would not be affected. He informed that NTPC had postponed
the maintenance of some of its units to next financial year, in deference to
the requests received from the states in this regard.
10.12 SE (O), SRPC pointed out that earlier coal stock at Talcher had reached
critical levels and the Talcher units had run on oil support also.
10.13 Generation levels at NLC Stations
10.13.1 In the 8th SRPC Meeting, NLC had informed that land acquisition problem
still persisted and the site owners were refusing to hand over physical
possession of the land. District Collector, Cuddalore had assured actual
handing over of land by 31st December 2008. In case the land was
handed over by December 2008, NLC would be in a position to mine
lignite by April 2009. In case the land was not handed over, NLC would
have to plan for contingency mining which necessitated lot of changes &
efforts compared to the present mining practice. On a query from MD,
KPTCL, NLC had clarified that 2000 MW generation would be maintained
upto June 2009. Chairperson, SRPC assured that TNEB & GoTN would
make all efforts to ensure that the land was handed over to NLC at the
earliest. He had also suggested that NLC be in operational readiness to
implement the contingency plan, if required.
10.13.2 In the 31st meeting of OCC held on 7.1.2009, NLC representative had
informed that Shri A.R. Ansari had assumed charge as CMD, NLC
recently. CMD had assured full generation from NLC stations before
(8th meeting of TCC held on 05.03.2009 at Kumarakom)
20
Pongal. A Piece of land was being excavated to enhance their mining
activities.
10.13.3 NLC had been requested to apprise the Committee about the progress on
land acquisition and about the availability that NLC would maintain in its
stations in the coming months. At present, the generation in NLC stations
has relatively improved.
10.13.4 In the meeting, CGM, TS-II & II Expansion informed that NLC had met
gross generation of 3254 MU against the target of 2887 MU for the
months of January & February 2009. It had achieved average generation
of 2298 MW against the target of 2039 MW during the same period. He
assured that NLC would maintain about 2000 MW till June end as
assured in the earlier meetings. He said that NLC was getting necessary
assistance from the Govt. of TN and TNEB to resolve land acquisition
problems. NLC had been able to get some land which had facilitated the
generation.
10.14 Generation level at NPCIL Units
10.14.1 In the 8th SRPC meeting NPCIL had informed that there were signs of
improvement on the fuel supply front and even the indigenous fuel
supplies were being augmented. Member (Generation), TNEB vide letter
dated 29.1.2009 (Annexure-X) had expressed concern over the low
level of generation in Atomic Power Stations, and requested for
necessary advance action to ensure maximum generation at Atomic
Power Stations.
10.14.2 NPCIL had been requested to apprise the Committee of the generation
levels that would be maintained at NPCIL units in Southern Region in the
coming months.
(8th meeting of TCC held on 05.03.2009 at Kumarakom)
21
10.14.3 In the meeting, CE (Trans.), NPCIL informed that at present two units at
MAPS and two units at Kaiga GS were on bars. The third unit at Kaiga
GS was expected to be back on bars by month end. NPCIL was
constrained to run the units at 50-60% PLF due to fuel mismatch. He
also expressed concern over the protection system in the Karnataka grid.
On one occasion, recently the fault in Karnataka system was cleared
after 4-5 seconds (by PGCIL system) and consequently Kaiga units had
tripped on unbalance. The generation in the Kali complex also got
affected due to delayed clearance of faults in Karnataka system. The
fault had not been cleared for 4-5 seconds which was a serious issue.
10.14.4 Director (Trans.), KPTCL said that due to heavy fog in the Hubli area
insulator decapping had taken place. KPTCL was monitoring the system
and was taking all steps like insulator replacement to keep the system
secure.
10.14.5 AGM, SRLDC said that in the OCC meeting it had been noted that higher
generation was maintained at Nagjhari, though a number of lines in Kali
complex were out. He suggested that the Kali complex generation be
scheduled by KPTCL, SLDC appropriately based on the availability of net
work. Full analysis report on the grid disturbances in Nagjhari area had
not yet been furnished by KPTCL for the recent incidents.
10.14.6 MS, SRPC suggested that the issue could be deliberated in detail in the
Protection Sub-Committee.
11. USING 220 kV CHIKKODI-KOLHAPUR LINE FOR TRANSFER OF POWER
11.1 SRLDC had proposed a methodology to take care of STOA transactions/UI
power between NEW Grid and SR Grid by using 220 kV Kolhapur-Chikkodi
circuit.
(8th meeting of TCC held on 05.03.2009 at Kumarakom)
22
11.2 As decided in the 7th SRPC meeting, the issue was discussed in the 7th
Commercial Sub-Committee meeting held on 22nd July 2008.The following
were the views of the Constituents:
- CM (Commercial), SRTS-II, PGCIL said that since the link was inter-regional and not intra state, usage of this link factoring in added costs of Karnataka & Maharashtra needs to be relooked, as it involved commercial implications.
- EE, KSEB said that if the transaction was for a particular utility, the utility should bear all the cost and if it was used for UI power transfer, it should be shared by the constituents. He added that regulations would not allow split up of UI on inter regional links, as such Karnataka could absorb the UI.
- EE, TNEB said that in principle they agreed for STOA. He requested KPTCL to take up with KERC for waving off transmission charges and losses for using the link. Differential UI may be borne by all the constituents.
- DGM (Commercial), SRLDC said that losses to the State system were allowed by CERC, but no charges were applicable for Maharashtra and Karnataka systems.
- APPCC intimated that they would avail the power through the line from spare capacity of about 25MW to 30MW by paying the STOA charges on day ahead basis but not on certain period i.e., two months to three months because huge financial commitment involved under STOA charges.
11.3 Subsequently, GM, SRLDC vide letter dated 3rd October 2008 had stated
that UI exchange was opportunistic in nature and had to be carried out at
very short notice. GM, SRLDC had also requested KPTCL to cooperate and
radialise Chikkodi feeders on to Maharashtra at short notice.
11.4 In the 8th meeting of SRPC, the Committee had noted the following:
- KPTCL had informed that there were some IPPs located in Chikkodi area and there could be some loss of generation etc. whenever the island had to be shifted to NEW grid and vice versa. This could lead to disputes etc. at a later date. KPTCL
(8th meeting of TCC held on 05.03.2009 at Kumarakom)
23
had always maintained that radicalization should be for at least 15 days, and there could not be frequent changeover since some IPPs in Chikkodi area were injecting power to the grid on STOA. They would conduct a study on the issues involved and revert back.
- SRLDC had pointed out that the lost opportunities of availing UI in previous months due to saturation of available present inter-Regional capacity and non availability of 220 kV Chikkodi-Kolhapur link.
11.5 AGM, SRLDC vide letter dated 17.02.2009 (Annexure-XI) had again
requested KPTCL to look into the matter for radialising Chikkodi load on to
Maharashtra on short notice whenever opportunity arose to achieve
economy.
11.6 In the meeting, CE (LD), KPTCL said that KPTCL, in principle, had agreed to
the proposal if the commercial interest of KPTCL were taken care of. He
said that the Chikkodi - Kolhapur line should be radialised at least for
minimum 15 days.
11.7 AGM, SRLDC said that the power drawn would be regional UI and
requested Karnataka to convey their willingness so that power could be
availed as UI whenever the opportunity arose.
11.8 Director (Trans,), KPTCL said that there were number of NCE projects in
that area and frequent changeovers could not be considered.
12. RIGHT OF WAY OF KUDANKULAM ATS
12.1 ED (OS), PGCIL vide letter dated 5th December 2008 had mentioned that
TNEB and KSEB had sought compensation for surrendering 220kV Edamon-
Kodikuruchi line and 220kV Iddukki-Madakkathara lines. It had also been
mentioned that the compensation amount would be paid by PGCIL and
expenditure booked to the project cost.
(8th meeting of TCC held on 05.03.2009 at Kumarakom)
24
12.2 In the 8th meeting of SRPC, Member (PS), CEA had informed that the
compensation issue had already been envisaged during the planning stage.
PGCIL should be allowed to go ahead with the scheme, to avoid further time
& cost over-run.
12.3 CMD, APTRANSCO had said that AP would get the issue examined at its
end.
12.4 In the meeting, ED, SR-II, PGCIL clarified that the amount payable to TN and
Kerala was towards value of assets appearing in their books and not as
compensation.
12.5 ED (GO), APTRANSCO said that the relevant details could be furnished to
them. PGCIL agreed to furnish the correspondence received from TN &
Kerala in this regard.
13. ULDC AUGMENTATION
13.1 In the 8th SRPC meeting the status of ULDC augmentation was discussed.
APTRANSCO had pointed out that the scheme may need to be reviewed in
the context of the changed scenario in which 2300-2400 MHz frequency
band had to be surrendered for broad band wireless access. TCC had
however noted that the augmentation scheme had already been approved by
SRPC after detailed deliberations. On further deliberations, it was suggested
that the Constituents would communicate concurrence/approval by
respective Head of Organization to PGCIL, by the month end (December
2008).
13.2 MS, SRPC had taken up the issue with the utilities vide letter dated
13.1.2009. Communication dated 22.01.2009 received from TNEB in this
regard is at Annexure-XII.
(8th meeting of TCC held on 05.03.2009 at Kumarakom)
25
13.3 ED (OS), PGCIL vide letter dated 19.02.2009 (refer Annexure-VII) had stated
that the validity of the offer of the agency (revalidated several times) had
lapsed. Hence, POWERGRID had no other option but to abandon the
project. This was for the information of SRPC.
13.4 In the meeting, ED, SR-II, PGCIL said that the validity of contract had lapsed
and hence PGCIL had no other option but to abandon the project.
13.5 MS, SRPC suggested that the scope of ULDC augmentation works could be
planned to be covered in the scope of the works being planned in lieu of
surrender of 2300-2400 MHz frequency band.
14. REFRAMING OF 2300 – 2400 MHz FREQUENCY BAND FOR BROADBAND WIRELESS ACCESS (BWA)
14.1 PGCIL had informed about the Summary Record of the meeting taken by
Wireless Planning Commission (WPC) on 11.08.2008 in Sanchar Bhavan,
New Delhi to discuss reframing of 2.3-2.5 GHz band in accordance with the
mandate given by GoI. The users of this band had attended the meeting
including POWERGRID. WPC intends to use this band for Broadband
Wireless Access based on the recommendations of Wireless Advisor to GOI.
The users were requested to surrender the band within a certain time frame.
14.2 In the Southern Region there are 35 Nos. Micro wave links commissioned
under ULDC scheme and the same frequency spectrum is being used in all
of these links. The constituent wise break up of the links is as follows:
Sl.No. Constituent Links
1 Central Sector 2
2 APTRANSCO 7 3 KSEB 7 4 PED 3 5 TNEB 16
Total 35
(8th meeting of TCC held on 05.03.2009 at Kumarakom)
26
14.3 PGCIL had informed that the issue was discussed in the ULDC Coordination
Meeting held on 22.09.2008. The beneficiaries had agreed for OFC links
subject to the condition that they were compensated for surrender of the
frequencies. Beneficiaries had been requested to intimate about
development of OFC links in their state and concur for sharing charges of
OFC link in Central Sector. It had also been stated that POWERGRID could
take up these works similar to ULDC project.
14.4 In the 8th SRPC meeting, the Committee had noted that TCC had agreed in
principle about the necessity of the work. The cost implications as furnished
by PGCIL are at Annexure-XIII. APTRANSCO had pointed out that its
Communication Wing would like to carry out AP portion of work while they
would share the CGS portion. PGCIL had opined that it would be desirable if
a single agency took over the entire work. It was also agreed that the
constituents would communicate concurrence/approval by respective Head
of the Organizations to PGCIL by December 2008 end.
14.5 MS, SRPC had taken up the issue with the constituents vide letter dated
13.1.2009. TNEB letter dated 06.02.2009 in this regard is enclosed as
Annexure-XIV.
14.6 ED (OS), PGCIL vide letter dated 19.02.2009 (refer Annexure-VII) had stated
that considering the fact that frequency bands have to be handed over within
two years from November 2008, beneficiaries may please intimate urgently
concurrence for works to be taken up by POWERGRID or alternatively
indicate their plan to ensure data flow to SRLDC. Since lead time was
involved in identifying the agency for execution and imports are involved, the
matter was critical.
14.7 In the meeting, ED, PGCIL informed that in other regions, PGCIL had been
entrusted to carry out the work. He suggested that it would be better if one
agency carried out the work.
(8th meeting of TCC held on 05.03.2009 at Kumarakom)
27
14.8 ED (GO), APTRANSCO said that the estimates furnished by PGCIL were at
large variance with the estimates framed by APTRANSCO’s communication
wing. The reasons for the large variation should be studied.
14.9 CE (PM), TNEB said that TNEB may want to do its portion by themselves.
14.10 ED, SR-II, PGCIL said that the estimates were based on the recent orders.
However, when PGCIL goes for actual tendering, the actual could be in
variance with the estimates. He added that if works are carried out by
different agencies then the responsibility of integration of different systems
would be with the constituents. He suggested that a single agency may take
up the work to avoid interfacing problems.
14.11 Member (Trans.), KSEB said that KSEB was in discussion with PGCIL and
most likely their scope of work would be entrusted to by PGCIL.
14.12 AGM, SRLDC said that this scheme as well as ULDC augmentation scheme
were very much essential for data and information availability and security of
the grid. He added that the matter had wider commercial implications (UI
etc.). He earnestly requested that the project may be done by single agency
i.e., PGCIL, so as to have reliability of grid, and availability of data.
14.13 MS, SRPC said that in interest of work, there should be a single
implementing agency so as to avoid two point control.
14.14 GM (LD&C), PGCIL said that in NR tendering activities had already started.
ER & WR had also agreed that the project be completed by PGCIL. He
added that additional works had also been given by the constituents to be
completed by PGCIL. There was only two years time frame to complete the
works and therefore suggested that the works may be entrusted to PGCIL
without further delay.
(8th meeting of TCC held on 05.03.2009 at Kumarakom)
28
14.15 After deliberations, TCC recommended that a single agency i.e., Power Grid
may take up the whole project including the State & the Central Sector
Scope. This would also avoid interfacing problems.
15. INFORMATION ON GRID CONNECTED RENEWABLES
15.1 MNRES/CEA have been seeking information regarding grid connected
renewables on monthly basis. While the operation data is to be furnished by
1st of the following month, the detailed station-wise authenticated data is to
be furnished by 10th of the following month. The formats for furnishing data
are enclosed as Annexure-XV. Constituents were requested to kindly
arrange to streamline the process of furnishing the required information.
15.2 In the meeting, CE (GM), CEA emphasized on the need for the data to be
made available regularly. He said that MNRES was facing difficulty in getting
timely information on grid connected renewables. He requested all the
constituents to furnish the information in a timely manner.
16. GRID OPERATION
16.1 National Awards for meritorious performance in Power Sector for the year 2007-08
NTPC’s Talcher Super Thermal Power Station awarded the Gold Shield in the category of awards for Meritorious performance of thermal power stations.
NTPC’s Ramagundam Super Thermal Power Station awarded the Silver Shield in the category of awards for Meritorious performance of thermal power stations.
KPCL’s Gerusoppa Hydro Power Station awarded Bronze Shield in the category of awards for Meritorious performance of hydro power stations.
Power Grid’s 400 kV Gooty-Raichur D/C line awarded Silver Shield in the category of awards for Meritorious performance for early completion of transmission power projects.
(8th meeting of TCC held on 05.03.2009 at Kumarakom)
29
Andhra Pradesh EPDCL awarded Gold Shield in the category of awards for Meritorious performance in electricity distribution.
Mandal Mahila Samakhya, Kurupam of Andhra Pradesh Discom, and Mandal Mahila Samakhya, Paderu of Andhra Pradesh Discom awarded Gold Shield & Bronze Shield respectively in the category of awards for Meritorious performance for rural distribution franchisees.
16.2 Efforts by Constituents
Good performance by Ramagundam, Simhadri & Vijayawada thermal power stations.
Efforts by TNEB to increase coal stock at thermal stations.
Appreciation for KSEB for making available all the field inputs for ULDC scheme.
High quantum of power imports by AP.
17. HIGH FREQUENCY DURING LOAD CHANGEOVER
17.1 The high frequency phenomena for short duration during the load
changeover periods around 1800 hrs was being observed. Frequency graph
for few days showing such phenomena is enclosed as Annexure-XVI.
Generators and even transmission utilities were facing problems due to this
phenomena. Staggering of loads by the DISCOMs/State utilities is the most
effective way to mitigate the effect of load changeover. Beneficiaries had
been requested to ensure steps to mitigate the problem.
17.2 In the OCC meetings it had been decided that while Tamil Nadu would
complete the change-over before 1800 hours, AP would complete the
change-over between 1800 hrs. to 1830 hrs. Karnataka & Kerala would
stagger the loads during 2200 hrs changeover phenomena. Similar rise in
frequency has also been observed at 2 AM. Sudden release of MVAR
intensive loads, besides leading to high frequency had even led to tripping of
400 kV lines on over voltage.
(8th meeting of TCC held on 05.03.2009 at Kumarakom)
30
17.3 In the meeting, MS, SRPC expressed concern over the sudden frequency
rise during changeovers.
17.4 AGM, SRLDC said that the issue was being deliberated for last two years but
was not being resolved fully. Frequency was rising by more than 1.0 Hz
during the change over. At times in short interval of time, number of 400 kV
lines were getting tripped and the security of the grid was under threat.
17.5 CE (LD), KPTCL said that backing down of generation was also being carried
out by SLDC, to mitigate the frequency rise.
17.6 Director (Trans.), KPTCL informed that load staggering was being done
among the five DISCOMS in Karnataka.
17.7 AP & TN assured that they would following the timings of load changeovers
and stagger the loads.
17.8 MS, SRPC suggested that AP, Karnataka & TN may implement the time
schedules finalized in the OCC forum in coordination with SRLDC in real
time.
18. FORCED OUTAGES OF THERMAL UNITS
18.1 The issue of forced outages in thermal stations was brought to the notice of
SRPC/TCC in the previous meetings. The forced outages of the thermal
units continue to be on the higher side as can be seen in the table below:
Month Minimum Maximum December 2008 2.69% 9.99% January 2009 1.81% 5.31% February 2009 1.27% 5.12%
18.2 MoP vide letter dated 05.02.2009 (Annexure-XVII) had expressed concern
about the low rate of growth of electricity generation. It had also been
emphasized by MoP that a close watch be kept on long duration outages -
(8th meeting of TCC held on 05.03.2009 at Kumarakom)
31
planned as well as forced. RPCs had also been asked to furnish an
Exception Report on a monthly basis.
18.3 In the meeting, MS, SRPC expressed concern over the quantum of forced
outages. He added that the issue had been deliberated in number of OCC
meetings and previous SRPC/TCC Meetings. MoP and CEA had
expressed concern over the high quantum of forced outages. He added that
the planned maintenance should be carried as per the Kukde norms and
efforts should be made to minimize the forced outages, so as to have
maximum availability.
18.4 CE (GM), CEA said that MoP had taken a serious note of the issue of
outages. He said that Planned maintenance should be carried out as per
agreed schedule and only in extreme contingency it should be altered. Unit
should be brought back quickly after forced outages. He said that RPC’s
had been asked to furnish exception reports on a monthly basis.
18.5 AGM, SRLDC also expressed concern over the forced outages and
informed that on certain occasions forced outages of more than 2500 MW
had been experienced.
18.6 TCC noted that the forced outages at times were critically high and the
generators should take concrete steps to minimize the same.
18.7 Low Frequency Operation
18.7.1 The issue regarding low frequency operation and overdrawal at low
frequency has been under consideration of all forums of SRPC. The
issue was further deliberated in the OCC meetings held during December
2008 - February 2009. During the period under review, Type ‘A’, Type ‘B’
& Type ‘C’ messages (copy enclosed as Annexure-XVIII) were issued to
the constituents by SRLDC. During the OCC Meetings SRLDC had
(8th meeting of TCC held on 05.03.2009 at Kumarakom)
32
informed that as per directives of Hon’ble CERC, SRLDC was furnishing
details of over drawals below 49.0 Hz. on a regular basis to them.
Hon’ble CERC was also monitoring instances of simultaneous exports
and overdrawals at frequency less than 49.0 Hz. In view of the above, the
Committee was requested to deliberate on measures for operation of the
grid within the frequency range of 49.0 Hz to 50.5 Hz, as stipulated in the
IEGC. The decision of the Special TCC meeting held in March 2006 to
resort to load shedding at 49.2 Hz itself to avoid the frequency going
below 49.0 Hz at any instant of time was also brought to kind attention.
18.7.2 In the meeting, CE (PM), TNEB requested the Central Generating
Stations to increase the availability, specifically from nuclear stations.
18.7.3 MS, SRPC requested the constituents to maintain grid parameters within
IEGC range, and also operate the grid in a safe and secure manner. The
utilities should not over draw at low frequency he added.
18.7.4 AGM, SRLDC said that Hon’ble CERC was monitoring the over drawals
at frequencies below 49.0 Hz and 49.2 Hz on a weekly basis. He
informed that since last 10 days, the regional frequency profile had
deteriorated considerably. He added that the grid was presently in a
critical condition and SRLDC had accordingly, apprised the constituents
at the highest level. He requested the constituents to operate the grid as
per the stipulated regulations.
18.7.5 All the constituents assured that the grid would be operated in safe and
secure manner and within IEGC range.
18.8 Utilization of Intra-Regional Power
18.8.1 The need for utilizing the intra-regional power within the region has been
highlighted at various forums of SRPC keeping in view the technical and
(8th meeting of TCC held on 05.03.2009 at Kumarakom)
33
commercial advantages accruing to the constituents. The
requirement/surplus information furnished by the constituents is available
on SRPC web site to facilitate intra-regional exchange of power.
18.8.2 In the Special TCC meeting held on 09.08.2008, TCC had suggested that
commercial and administrative arrangements be tied up among states in
Southern Region to avail the surplus IPP/Captive/URS/State Sector
Power available within the region specifically so that it could be utilized by
the needy state in real time avoiding delays on account of any
commercial and administrative reasons.
18.9 Tripping of radial feeders as regulatory measure to maintain frequency
18.9.1 In this context, kind attention of the constituents was drawn to Clause
5.4.2(c) of IEGC in the previous SRPC meetings.
18.9.2 In the 31st & 32nd OCC meetings, SRLDC had again sought revision of
quantum of tripping to be obtained on radial feeders as regulatory
measures (copy enclosed as Annexure-XIX). It was also noted that the
response on the steps taken needed to be furnished to SRLDC on a
regular basis. In case an identified feeder had already been tripped,
action needed to be taken to trip another feeder so that desired relief as
instructed by SRLDC was obtained, lest system security might get
jeopardized. MS, SRPC had requested the constituents to make full use
of ULDC features so as to have centralized control.
18.10 Under Frequency Relay
Special TCC in its meeting on 09.08.2008 had recommended that all UFRs
be strictly in service and available as per the agreed quantum of relief, on
designated feeders and settings. It had also been stressed that the UF
relays be made fully effective by all the utilities so as to give the designated
relief at specified frequency levels.
(8th meeting of TCC held on 05.03.2009 at Kumarakom)
34
18.11 Grid Events (December 2008 –February 2009)
• Frequency remained within IEGC range (49.0 Hz to 50.5 Hz) for 97.29% of time.
• Frequency remained below 49.0 Hz for 2.53% of time and average frequency was 49.34 Hz.
• Southern Region met a maximum demand of 26200 MW on 12.02.2009 which was maximum till date.
• Andhra Pradesh met a maximum per day consumption of 210.59 MU which was maximum till date.
• Andhra Pradesh met a maximum of 10121 MW (Gross) on 28.02.2009 which was maximum till date.
• Karnataka met a maximum demand of 6237 MW on 28.01.2009 which was maximum till date.
• Tamil Nadu & IPPs/CPPs exported 165 MU & 161 MU respectively during the above period by way of bilateral exports to recipients in other regions.
• Andhra Pradesh, Karnataka, Kerala & Tamil Nadu imported 908 MU, 99 MU, 160 MU & 353 MU from other Regions during the above period.
• Andhra Pradesh & Kerala imported 49 MU & 2 MU intra-regionally during the above period.
• Utilities of Andhra Pradesh, Karnataka, Kerala and Tamil Nadu imported 253 MU, 20 MU, 78 MU & 166 MU from Power Exchanges during the above period.
• 1st & 2nd Unit of 115 MW (peaking station) units at Varahi were commissioned on 03.01.2009 and 14.01.2009 by KPCL.
• LILO of Gazuwaka-VSS 220 kV line at Gangavaram Port charged on 11.12.2008 by APTRANSCO.
• 31.5 MVA, 220/33 kV transformer at Gangavaram Port S/S commissioned on 11.12.2008 by APTRANSCO.
• 220 kV line from Peenya-Somanahalli to Vrushabhavathi commissioned on 29.12.2008 by KPTCL.
• 220 kV S/C LILO of Mahalingapur-Kudachi at Athani commissioned on 15.12.2008 by KPTCL.
• 220 kV S/C LILO of B Bagewadi-Indi line at Bijapur charged on 18.12.2008 by KPTCL.
(8th meeting of TCC held on 05.03.2009 at Kumarakom)
35
• 220 kV D/C line to Shiralkoppa in Shimoga commissioned on 19.12.2008 by KPTCL.
• 1x100 MVA, 220/110 kV transformer at Athani commissioned on 15.12.2008 by KPTCL.
• 2x100 MVA, 220/110 kV transformer at Bijapur test charged on 19.12.2008 by KPTCL.
• 1x100 MVA (2nd transformer), 220/66 kV transformer at HAL commissioned on 06.12.2008 by KPTCL.
• 150 MVA, 220/66 kV transformer at Vrushabhavathi commissioned on 29.12.2008 by KPTCL.
• 1x100 MVA, 220/110 kV transformer at Shrialkoppa charged on 19.12.2008 by KPTCL.
• LILO to Neyveli TS-II from Neyveli Zero Unit to transfer Cuddalore SS load energized on 19.12.2008 by TNEB.
• 2x50 MVA, 230/33 kV transformer at Amuthapuram commissioned on 1.12.2008 by TNEB.
• 1x50 MVA (2nd transformer), 230/33 kV transformer at Udayathur commissioned on 27.12.2008 by TNEB.
• Upgradation of transformer from 80 MVA to 100 MVA, 230/110 kV at Kadapperi commissioned on 6.12.2008 by TNEB.
• Upgradation of transformer from 80 MVA to 100 MVA (2x50 MVA), 230/110 kV at Ingur commissioned on 20.12.2008 by TNEB.
18.12 Grid Frequency
The month-wise frequency profile of the region for the months of December
2008 - February 2009 is given in Table – I below:
Table-I
Month Less than
48.5 Hz
48.5 Hz to 49.0 Hz
49.0 Hz to 49.5 Hz
49.5 Hz to
50.0 Hz
50.0Hz to
50.5 Hz
More than
50.5 Hz
Month average
Hz
Within IEGC range49.0 Hz to
50.5 Hz
Dec. 2008 0.00 1.53 71.22 18.04 8.92 0.29 49.34 98.18
Jan. 2009 0.00 1.49 70.90 19.12 8.32 0.17 49.33 98.34
Feb.2009 0.00 4.80 80.72 12.43 1.98 0.07 49.23 95.13
(8th meeting of TCC held on 05.03.2009 at Kumarakom)
36
18.13 Hydro Availability
The storage levels in the major hydel reservoirs in MU as on 28th February
2009 is given in Table - II below:
Table-II
Energy storage in major hydel reservoirs
Inflows during April 2008 - February 2009 (in MU)
Storage as on 28th Feb. 2009
At FRL
(in MU) Anticipated Actuals MU % ANDHRAPRADESH Jalaput Srisailam
495
-
689 2762
541 4129
321
-
65 -
KARNATAKA Linganamakki Supa+B’Halli+T’Halli
4547 3152
5143 2484
4900 3010
1843 1052
41 33
KERALA Idukki Pamba & Kakki Total Kerala
2190 916 4131
2445 1566 6792
1889 1218 5249
827 684 2019
38 75 49
TAMIL NADU Nilgiris Total Tamil Nadu (excluding Mettur)
1504 2182
2116 3915
1978 3525
651 924
43 42
The reservoir position as on 28th February 2009 was about 42% for the
Southern Region.
18.14 Grid Voltages
SR grid had been experiencing sustained over voltage conditions during the
monsoon period and low demand period and there have been resultant
manual/automatic trippings of both Central and State Sector 400 kV lines. It
had been addressed regularly in the OCC that adoption of adequate voltage
management measures by the constituents would improve the situation.
The grid voltages at the selected 400 kV stations in SR are given in Table-III
below:
(8th meeting of TCC held on 05.03.2009 at Kumarakom)
37
Table – III Voltage profile in kV at the selected 400 kV Sub-stations
for the months of December 2008 & February 2009
400 kV Stations December 2008 January 2009 February 2009
Average of Average of Average of Max. Min. Max. Min. Max. Min. Hyderabad 414 398 412 395 407 390 Ramagundam 415 405 413 402 407 398 Nagarjunasagar 418 402 416 400 412 395 Cuddapah 424 404 421 399 417 394 Vijayawada 427 410 427 410 425 409 Gooty 422 404 418 400 415 396 Gazuwaka 425 414 426 416 426 414 Bangalore 413 391 410 389 412 388 Kolar 420 399 415 397 416 396 Narendra 412 397 413 398 412 399 Thiruvanathapuram 421 401 424 407 419 404 Trichur 410 393 407 389 407 389 Chennai 420 399 418 394 416 391 Hosur 414 395 410 393 411 393 Neyveli-II 418 405 416 405 414 404
The Constituents were requested to improve.
18.15 Short term/long-term measures to contain over voltages
The issue of over voltages had also been taken up in the various OCC
meetings and short-term measures like
Switching off of the capacitors
• Putting reactors into service
• Identifying the optimal tap positions
• Opening of parallel lightly loaded lines
• Absorption of VARs by units within their capability limits
• Running of units in synchronous condenser mode
• Export to other regions through bilateral exchanges
• Export to other regions as UI power
(8th meeting of TCC held on 05.03.2009 at Kumarakom)
38
etc. had been discussed. Specific steps taken by constituents to contain
over voltage had been discussed.
18.16 VAR absorption by Generators within capability limits
18.16.1 The issue of VAR absorption was discussed in the OCC meetings. In
view of the high voltage conditions being faced in Southern Region during
low demand period, the MVAR absorption capability of various generators
may be utilized in improving the voltage condition of the grid.
18.16.2 It is for information that in respect of new generating stations, Clause
1(10) under Part-II (Grid Connectivity Standards applicable to the
Generating Units) of Ministry of Power (Central Electricity Authority)
Notification dated 21st February 2007 stipulates that “Hydro generating
units having rated capacity of 50 MW and above shall be capable of
operation in synchronous condenser mode, wherever feasible”.
18.17 Installation of Shunt Capacitors
18.17.1 Installation of new capacitors matching with the demand growth, along
with monitoring the healthiness of existing capacitors in the grid, is a
continuous process for maintaining good voltage profile at main as well as
at far away grid stations.
18.17.2 The progress of installation of capacitors by the constituents during the
year 2008-09 is given in Table -IV below:
Table – IV (Figures in MVAR)
Capacitors as per the assessment of System Studies Sub-Committee
of SRPC Installed during the
year 2008-09$
Andhra Pradesh 55 * 0 Karnataka 155 7.2 Kerala 0 0 Tamil Nadu 101 0 Total 311 7.2
* by relocation $ upto February 2009
(8th meeting of TCC held on 05.03.2009 at Kumarakom)
39
18.18 Pending field inputs under ULDC scheme
SRLDC had informed that for monitoring of grid & running EMS package, the
availability of data at SLDCs/RLDC needed to be improved. In case of some
of the constituents, large number of SCADA inputs continued to remain
pending as per Annexure-XX. This issue had been regularly deliberated in
the OCC meetings also.
19. DEMAND VARIATION (Peak Vs Off-peak)
19.1 The issue regarding large variation between minimum and maximum
demands had been under the consideration of TCC/SRPC. The issue was
being taken up regularly in the OCC meetings, wherein the following was
observed for the months of December 2008 - February 2009:
Minimum to Maximum Demand Variation % Month Andhra
Pradesh Karnataka Kerala Tamil Nadu Puducherry Southern
Region December 2008
Highest 36.47 53.19 50.53 33.50 37.63 32.58 Date 21st 1st 24th 29th 2nd 1st Lowest 21.03 37.79 35.24 20.33 16.30 21.32 Date 31st 27th 3rd 14th 20th 14th Average 24 45 41 27 24 27
January 2009 Highest 33.52 47.27 45.54 34.79 33.99 29.36 Date 5th 15th 5th 17th 16th 14th Lowest 16.02 27.45 36.15 22.95 17.09 16.93 Date 12th 8th 25th 24th 14th 26th Average 23 41 41 28 27 23
February 2009 Highest 26.30 40.32 42.11 30.71 40.19 21.92 Date 8th 2nd 2nd 9th 28th 2nd Lowest 12.36 22.21 28.99 12.74 13.60 10.59 Date 27th 24th 28th 28th 1st 28th Average 21 34 36 23 24 17
Note: Highest & lowest figures for the month have been computed based on the daily values during the month.
19.2 During the deliberations in the OCC meetings, OCC had expressed that
constituents initiate all possible measures to bridge demand-supply gap by
appropriate Demand Side Management, Supply Side Management & Energy
(8th meeting of TCC held on 05.03.2009 at Kumarakom)
40
Efficiency Programmes as there were energy and demand shortages faced
by the constituents of Southern Region.
20. STATUS OF THE NEW GENERATING SCHEME
20.1 SRPC had desired that the status of the Generating Schemes coming up in
Southern Region should also form part of the Agenda. It was noted that this
information would be extremely useful in planning the load generation
balance for future and would also help in identifying possible bottlenecks and
taking necessary corrective action in time.
20.2 The updated information as communicated by the constituents is given at
Annexure-XXI.
21. ESTABLISHMENT OF YELAHANKA SUBSTATION
21.1 ED (OS), PGCIL vide letter dated 19.02.2009 (refer Annexure-VII) had
stated that with regard to acquiring of land for 400 kV substation at
Yelahanka, there were certain problems being experienced. KPTCL had
acquired 35 acres of land and offered to POWERGRID recently. Since the
land was of irregular shape, for establishment of conventional 400 kV
substation, additional land of 2.5 acres would be required. The proposed
land was observed to have some encroachments on the western side. The
additional 2.5 acres of land required was under litigation in the High Court of
Karnataka. Unless the encroachment is removed and additional 2.5 acres of
land was acquired, establishment of conventional substation would not be
possible. It had also been informed that after study, it had been found
feasible to establish the substation with 400 kV as Gas Insulated Substation
(GIS) and 220 kV side as AIS. Beneficiaries had been requested to concur
for establishment of 400 kV GIS pending ratification in the Standing
Committee on Power System Planning.
(8th meeting of TCC held on 05.03.2009 at Kumarakom)
41
21.2 In the meeting, it was noted that the issue had also been recommended for
approval of SRPC by the Standing Committee of PSPSR.
22. COMMISSIONING OF 3rd TRANSFORMER AT UDUMALPET
22.1 ED (OS), PGCIL, vide letter dated 19.02.2009 (refer Annexure-VII) had
stated that the 3rd transformer at Udumalpet and associated bays to be
established under Kudankulam transmission system would be ready for
commissioning shortly. POWERGRID had proposed for preponement of
commissioning of the transformer to enhance reliability at Udumalpet. TNEB
had been requested to concur to enable POWERGRID proceed further.
22.2 In the meeting, ED, SR-II, PGCIL said that the commissioning of Udumalpet
Transformer would increase reliability of the system.
22.3 TNEB representative said that the issue could be discussed in SRPC
meeting.
23. LTOA CONCURRENCE
23.1 ED (OS), PGCIL vide letter dated 19th February 2009 (refer Annexure-VII)
had stated that in the 8th SRPC Meeting, long term open access was
approved with respect to a number of open access applicants which included
amongst others M/s. LANCO, Kondapalli. The target beneficiaries of that
project with installed capacity of 375 MW were 200 MW in WR and 150 MW
in NR. It had been stated that as per the project developer, the project was
likely to be commissioned by June 2009 and that the beneficiaries for the
same also needed to be finalised. It had been proposed that pending
finalisation of beneficiaries by the developer, connectivity of the project to
Vijayawada as approved in the 8th SRPC Meeting may be agreed. It had
also been mentioned that upon commissioning of generation units, the plant
would operate as merchant power plant, by paying applicable transmission
(8th meeting of TCC held on 05.03.2009 at Kumarakom)
42
charges in addition to LTOA charges till finalisation of beneficiaries.
23.2 In the meeting, SE (O), SRPC said that the connectivity of Lanco –
Vijayawada had already been agreed in the previous SRPC meeting.
23.3 GM (Engg.), PGCIL said that the beneficiaries had not been identified by the
developer. The developer wanted connectivity to the Regional Grid and
would be selling power on STOA basis to the beneficiaries. If connectivity
was given, 375 MW additional power would be available from June 2009
onwards. The developer was willing to pay the LTOA charges of SR grid and
all other applicable charges.
23.4 Consultant, TNEB said that the cost of the dedicated line should be borne by
the developer himself.
23.5 PGCIL clarified that as per regulation 33 of new CERC (Terms & Conditions
of Tariff) Regulation, 2009, the developer was to pay for the dedicated
transmission system.
23.6 After deliberations, TCC recommended for approval of the connectivity
(Lanco-Vijayawada) to SR grid. Lanco would pay the LTOA charges of SR
grid and other applicable charges. Lanco-Vijayawada line would be
constructed by the developer.
24. RECONFIGURATION OF 400 kV DIAMETER AT 400/230 kV ALMATHY S/S 24.1 ED (OS), PGCIL vide letter dated 19th February 2009 (refer Annexure-VII )
had mentioned that at 400 kV Almathy substation, Nellore-Almathy D/C line
and Almathy-Sriperumbudur D/C line have been terminated in such a way
that feeders from Sriperumbudur occupy one diameter and feeders from
Nellore occupy another diameter, causing operational exigencies at times.
Since Almathy substation is a vital link, to improve the reliability it had been
suggested to rearrange the line terminations as shown in the Single Line
Diagram.
(8th meeting of TCC held on 05.03.2009 at Kumarakom)
43
24.2 In the meeting, AGM, SRLDC said that due to operation difficulties and also
to improve reliability he requested that the terminations may be rearranged
as given in the Annexure-XXII. He apprised the Committee of the difficulties
faced on 22nd October 2008 when both the lines got tripped due to breaker
problem. He added that as per studies conducted, with the tripping of
Almathy - Sriperumbudur line, the 230 kV system in Tamil Nadu was getting
stressed.
24.3 SE (O), SRPC enquired whether the existing arrangement was a standard
design feature of PGCIL or not.
24.4 ED, SR-II, PGCIL said that the existing arrangement was in place for about 5
years and in the coming 2 years existing line configuration was likely to be
changed. He therefore suggested that the existing arrangement could
continue.
24.5 After deliberations, it was decided that the existing line configuration would
continue, since the configuration was planned to be changed in the coming 2
years.
25. RENOVATION AND MODERNISATION OF SRPC OFFICE COMPLEX
25.1 SRPC office building was constructed sometime in 1976. Since about 30
years have lapsed since building construction, the office complex is in need
of renovation and modernisation (R&M). In addition, there is a need to
update the old computer machines and their peripherals/networking in the
SRPC Secretariat. R&M and strengthening of RPC’s has also been
discussed in a meeting taken by Chairperson, CEA on 02.02.2009
(Annexure-XXIII) wherein it was decided that the respective RPCs would
approach the respective constituents with a proposal and obtain their
approval for R&M Scheme. The tentative cost estimates for the renovation
and modernisation works is given at Annexure-XXIV. It was proposed to
(8th meeting of TCC held on 05.03.2009 at Kumarakom)
44
take up the works in the beginning of financial year 2009-10. In principle
approval was sought for taking up the works as envisaged. It was also
proposed that the renovation works be carried out through the good offices of
POWERGRID. Necessary funds for this proposal would be placed with
POWERGRID. The R&M works are proposed to be carried out on a one
time basis. The budget estimate figures for 2009-10 in respect of SRPC
Secretariat are awaited from CEA, New Delhi. As per SRPC decision, the
reimbursement of BE for 2009-10 would be sought from the Members of
SRPC further subject to any adjustments.
25.2 MS, SRPC apprised the Committee about the need for renovation and
modernization of SRPC complex.
25.3 CE (GM), CEA said that the constituents were already reimbursing the SRPC
expenditure, and requested for concurrence.
25.4 ED, SR-II, PGCIL said that there were two issues involved in this matter –
one relating to concurrence of expenditure and secondly about the executing
agency. While Power Grid was agreeable for the sharing of expenditure, in
case there was a consensus, it had reservations regarding the executing
agency being Power Grid. He added that about 5 years ago, Power Grid had
offered to carry out the renovation works under ULDC but the offer was not
taken then.
25.5 TCC recommended for approval of SRPC the reimbursement of expenditure
for renovation and modernization of SRPC complex. The executing agency
could be finalized later.
26. REVISION OF UNSCHEDULED INTERCHANGE CHARGES 26.1 MS, SRPC informed about the letter 24.02.2009 from PCKL (copy enclosed
as Annexure-XXV) regarding revision of Unscheduled Interchange charges.
(8th meeting of TCC held on 05.03.2009 at Kumarakom)
45
26.2 It was noted that Hon’ble CERC had issued draft regulations on Unscheduled
Interchange charges, in which it was suggested to bring down the maximum
UI charges to Rs. 7.35. Constituents were suggested to furnish their
comments individually to the Commission.
26.3 Director (Trans.), KPTCL said that since the Naptha prices had come down
the UI prices should also be reduced. He added that the UI prices were
influencing the cost of the power in the market to a great extent.
27. TRIPPING OF TUTICORIN GENERATING UNITS IN TAMIL NADU
27.1 MS, SRPC informed about the letter dated 27.02.2009 from AGM, SRLDC
(copy enclosed as Annexure-XXVI) regarding tripping of Tuticorin generating
units in Tamil Nadu.
27.2 AGM, SRLDC expressed concern over the tripping of Tuticorin units on
26.02.2009 when around 850 MW generation was lost. He said that number
of lines had tripped in that area due to fog and TN could have regulated the
generation at Tuticorin. He added that even in Karnataka, fog related
trippings were taking place in Nagjhari area. He requested the constituents to
identify fog affected areas in their respective system for remedial action.
27.3 CE (GM), CEA informed that fog related trippings had occurred in the
Northern Region also. An expert Committee had identified the areas where
insulators could be affected by pollution and fog. In such areas, porcelain
insulators were being replaced by polymer insulators. Hence SR States
should also identify lines which were getting affected by pollution and fog and
initiate necessary remedial actions similarly.
27.4 ED, SR-II, PGCIL informed that PGCIL had already initiated action for
replacement of insulators in lines, as approved in the previous SRPC
meeting.
(8th meeting of TCC held on 05.03.2009 at Kumarakom)
46
28. REVIEW OF PROGRESS OF WORKS ON NEW TRANSMISSION LINES AND SUBSTATIONS
28.1 The progress of works on the new 400 kV/230 kV transmission lines and
substations in the State Sector under construction in the Southern Region
was reviewed. The updated information based on the data furnished by the
constituents is at Annexure-XXVII.
28.2 The progress of works on the new transmission line and substations in the
Central Sector (POWERGRID) under construction in Southern Region was
reviewed. The updated information is at Annexure-XXVIII.
29. DATE & VENUE OF THE NEXT TCC MEETING
It was decided to hold 9th TCC meeting one day prior to the 10th SRPC meeting.
30. VOTE OF THANKS
CE (PM), TNEB thanked the Members and delegates for the cooperation
extended for the conduct of the Meeting.
***