February2015_Maccaferri_MacNews

download February2015_Maccaferri_MacNews

of 15

Transcript of February2015_Maccaferri_MacNews

  • 7/26/2019 February2015_Maccaferri_MacNews

    1/15

    Welcome to the next February 2015 edition of the Maccaferri MacNews.

    This month we will be focusing on two of our design software programs. One is used for Fluid Drainageand the other for Flexible Pavement design. Our software is always free and available our website foreasy downloading. Just register on our website (www.maccaferri-usa.com) to gain access to ourdocuments and software library.

    MacRead Studio for Pavement Design

    Maccaferri developed the MacRead Studio 1.0 Pavement DesignSuite to help engineers and designerscreate models for the proper strength and position of geogrids for road base/sub base stabilization

    Geosynthetics are extensively used for the improvement of soil mechanical properties with the target to

    obtain a pavement sections able to carry higher/more loads; such effect is the results of the positive effectinduced by the geosynthetic presence due to the following stabilizing mechanisms:

    Base course lateral restraint mechanism for horizontal stresses generated by the soil self-weight

    Base course lateral restraint mechanism for horizontal stresses generated by wheels loading

    Tensioned membrane mechanism at the base or sub base - subgrade interface

    The tensile stresses due to the soil self-weight and the tensioned membrane mechanism at the base orsub base - subgrade interface are static, while the tensile stresses induced by traffic load aredynamic/cyclic. However in each instance both static and dynamic stresses coexist.

    The design methods presently available provide no/or insufficient indications about the number ofrequired geogrids layers and the mechanical characteristics thereof. Hence a new design method hasbeen developed which accounts the design of geogrids for road base/sub base stabilization, based on a 4layers model: asphalt layers (binder and wearing course), in case of paved roads; base, sub base,subgrade.

    Once the base and/or sub base thickness has been defined with one of the available methods in literature(AASHTO method, GiroudHan method, Leng - Gabr method, etc.) it is already appropriate for providingthe structural capacity of the road to resist the design number of wheel passages for the whole design lifeof the road. Given this thickness, by considering separately the effect of the static loads (soil self-weightand tensioned membrane mechanism) and the instant effect of wheel load, it is then possible to calculatethe distribution of the horizontal tensile forces in the whole road structure and the overall tensile forcesgenerated in each layer of geosynthetic, and then to select the appropriate geosynthetic for each layerbased on a limit state criterion.

    The proposed design method allows to set the number and the mechanical characteristics ofgeosynthetics layers required for absorbing the horizontal forces generated by self-weight, wheel loadand membrane effect. Obviously, more important is the road structure we are designing and lower the

    design geosynthetic strain shall be: hence for important structures the geosynthetic strain may be limitedto 2%, while for less important structures (or when the design conditions afford slightly largerdeformations) 3%, 4% or5% geosynthetic strain may be acceptable.

    Below is a Case History in South Africa where this method was used successfully.

  • 7/26/2019 February2015_Maccaferri_MacNews

    2/15

    Special Supplement for Geosynthetics 2015 February 2015 MacNews

    CASE HISTORY: Unpaved Road Secunda Mpumalanga (Republic of South Africa)

    Design by Leng -Gabr + Geogrid Design

    A Reconstruction and Development Programme taking place near Secunda in Mpumalanga (Republic ofSouth Africa) required the improvement of the road infrastructure, from gravel to paving block surfaceroad. In a particular stretch about 600m long, soft soil was encountered at 0.5m deep from natural groundlevel. The original design reported in Figure 3 required a rock pioneer layer of 350mm which would havecaused major construction issue and most important, it would have impacted on the budget which mostsurely would have brought the project to a standing still.

    Figure. 3Original cross section

  • 7/26/2019 February2015_Maccaferri_MacNews

    3/15

    Special Supplement for Geosynthetics 2015 February 2015 MacNews

    The Leng-Gabr method was used to calculate the reduction in pavement thickness of the rock layer. Backanalyzing the model in order to match the layer thickness, an overall CBR for the whole pavement wasconsidered as follows:

    Input data:

    (a slit film polypropylene woven geotextile with 70-70 kN/m ultimate tensile strength was considered)

    Output:

  • 7/26/2019 February2015_Maccaferri_MacNews

    4/15

    Special Supplement for Geosynthetics 2015 February 2015 MacNews

    The pavement thickness using the geotextile reinforcement reduces from 730mm to 530mm.

    The Leng-Gabr method yielded the following result: the rock layer thickness with the woven geotextilereinforcement can be reduced from 350 mm to 150mm.

    Therefore the total thickness of the pavement has reduced from 730 mm to 530 mm.

    Since the reduced total thickness is still very large for a single geotextile reinforcement, the above

    outlined Geogrid Design method was used to check the effective reinforcement requirement: the selectedinput data are reported below Table 2:

  • 7/26/2019 February2015_Maccaferri_MacNews

    5/15

    Special Supplement for Geosynthetics 2015 February 2015 MacNews

    Table 2 Input data selected for Example 1

    The geogrid design model resulted in the following section as shown in Table 3.

    Table 3 Results of calculation for Example 1

    The woven geotextile at the sub basesubgrade interface has to work at 3 % strain, rather than 2 %considered in the Leng-Gabr method, producing 9.63kN/m tensile strength for the tensioned membraneeffect Tm, which is not considered in the Leng-Gabr method; moreover an extruded biaxial Polypropylenegeogrid, with 20-20 kN/m ultimate tensile strength is required to reinforce the 300 mm thick base layer:

    MacGrid EG 20S (Extruded Geogrid 20 kN/m);MacTex W1 7S (Woven Geotextile 70 kN/m)

    This geogrid will work at 3 % strain as well. Considering that the pavement is made up of articulatedconcrete blocks, that is a very flexible pavement; such strain level is considered to be appropriate. Notethat for the geogrid in the base course the prevailing tensile forces is the T pforce due to the dynamic loadproduced by wheels, while the tensile force Tzproduced by soil self-weight corresponds to5 % of theultimate tensile strength of the geogrid; at this tensile level the long term creep deformation of the geogridcan be assumed to be negligible.

  • 7/26/2019 February2015_Maccaferri_MacNews

    6/15

    Special Supplement for Geosynthetics 2015 February 2015 MacNews

    For the woven geotextile in the sub base the prevailing tensile force is the Tm force due to the tensionedmembrane mechanism which, as above said, is developed during construction, without furtherdevelopment in time; the tensile force Tzproduced by soil self-weight corresponds to 0.8 % of its ultimatetensile strength; at this tensile level the long term creep deformation of the geotextile can be assumed tobe negligible.

    MacFlow Studio for Drainage

    Maccaferri has developed the MacFlow Studio software to facilitate the design of MacDraingeocomposites. MacFlow Studio software has been engineered as an expert system, able toautomatically select the appropriate geocomposites for any given project, and is presently the mostadvanced software for geocomposite design available on the market.

    Used with our MacDrain geocomposite, the fluids drain underground from one place to another and arecomposed by a draining core bonded - on one or both side - to filtering geotextiles. MacDraingeocomposites are designed to replace traditional drainage materials such as gravels and sands.

    MacFlow Studio software has been engineered as an expert system, able to automatically select theappropriate geocomposites for any given project, and is presently the most advanced software forgeocomposite design available on the market.

    MacFlow Suite is composed of 6 different modules:

    MacFlow H: for the design of MacDrain geocomposites in sub-horizontal applications

    MacFlow S: for the design of MacDrain geocomposites in sloping applications

    MacFlow V: for the design of MacDrain geocomposites in sub-vertical applications

  • 7/26/2019 February2015_Maccaferri_MacNews

    7/15

    Special Supplement for Geosynthetics 2015 February 2015 MacNews

    MacFlow EH: for the design of MacDrain geocomposites as an equivalent to a given granular

    layer in sub-horizontal applications

    MacFlow ES: for the design of MacDrain geocomposites as an equivalent to a given granular

    layer in sloping applications

    MacFlow EV: for the design of MacDrain geocomposites as an equivalent to a given granular

    layer in sub-vertical applications

    Examples of use of MacDraingeocomposites in horizontal, sloping and vertical applications

    MacFlow software affords to calculate the design input flow QDin MacDraingeocomposites by taking

    into account:

    The length and inclination of the geocomposite The coefficient of infiltration of rainfall into the soil or material placed on the geocomposite

    The types of contacts on the two faces of the geocomposites: Hard / Hard, Hard / Soft or Soft /

    Soft

    The unit weight and thickness of soil or material placed on the geocomposite, and the distributed

    surcharge

    The average water temperature, hence its dynamic viscosity, or a given viscosity

    The rainfall characteristics: parameter a and exponent n of the pluviometric curve in the region

    of the project, or a given rain height, and the design duration of the rainfall

    Any additional surficial flow entering the geocomposite

    Then MacFlow software affords to calculate the available long term flow rate Qaof MacDrain

    geocomposites, based on the results of short term flow rate laboratory tests according to ASTM D471608 (2013) test standard and the application of Reduction Factors (for the intrusion of filter geotextiles intothe draining core, for the compressive creep of the geocomposite, for chemical and biological clogging ofthe draining core) to account for long term reduction of flow rate.

    The appropriate values of the Reduction Factors can be selected according to the suggested valuesreported in the Drainage Manual issued by Maccaferri.

    MacFlow software compares the design input flow with the available long term flow rate of all MacDrain

    geocomposites, and shows the products for which the available flowrate exceed the requested flowrateand calculate also the related factor of Safety.

    Hereafter we report a case study where the MacFlow S design package was used

  • 7/26/2019 February2015_Maccaferri_MacNews

    8/15

    Special Supplement for Geosynthetics 2015 February 2015 MacNews

    Example of MacFlow S input and output:

    CASE HISTORY: Remediation of Blanchard Landfill - Le Moule, GuadalupeCOMPLEX WATERPROOFING AND DRAINAGE PROJECT FOR LANDFILL COVERThe Blanchard landfill, IN THE TOWN OF Moule, French Guadaluope, Caribbean, was opened in 1982for receiving collected domestic and assimilated-to-domestic waste, but without specific measures for the

    protection of the environment.

    Moreover, the passage of Hurricane Hugo in 1989 resulted in the landfilling of other waste types, likemetallic scrap, out of use vehicles, etc.

    Two options were then available: close the landfill or go through a remediation program. Finally theoption of remediation was selected by the municipality.

    This remediation was carried out in several stages:

  • 7/26/2019 February2015_Maccaferri_MacNews

    9/15

    Special Supplement for Geosynthetics 2015 February 2015 MacNews

    1. Removal of cars, metallic scraps and all non-domestic wastes to be sent to adequate treatment

    processes

    2. Re-profiling of the landfill to ensure stability

    3. Capping the landfill by: Sealing with a Geocomposite Clay Liner (GCL) to prevent water

    penetrating into the waste, percolating to the soil and causing contamination; installation of

    geocomposite drains to capture biogas and rain water; and placement of topsoil on the capping to

    allow revegetation.

    After 6 months of work and nearly 1.5 million invested, the Blanchard landfill in the town of Moule is nowfully rehabilitated. Between July 2012 and January 2013 Contractor CSD Ingenieurs and Project managerRHEA Environnement Antilles completed the works, including: profile remodeling, waterproofing of thecapping, biogas management by biofiltration.

    The remediation project allowed putting the site in safe conditions and the successful environmentalintegration of the landfill.Waterproofing was provided by Maccaferri GCL MacLine W11 (10,000 m

    2), while drainage was provided

    by Maccaferri geocomposite MACDRAIN W1061 (16,000 m2).

    The Maccaferri products used for the remediation of the Blanchard landfill

    Detail of the landfill capping

    Cross-section showing the re-profiling and final capping of the landfill

  • 7/26/2019 February2015_Maccaferri_MacNews

    10/15

    Special Supplement for Geosynthetics 2015 February 2015 MacNews

    Plan view of the landfill remediation

    Installation of MacDrain W1061 geocomposite

    Installation of MacLine W11 GCL

    The landfill capping near completion

    DESIGN OF MACDRAIN W GEOCOMPOSITE FOR RAIN DRAINAGE OF CAPPING. DESIGN BYMACFLOW-S SOFTWARE

    Cross-section A-A was selected for the design of the rain water drainage system:

    The total slope length is equal to 45 m;

    Considering the two berms the average slope length is equal to 1V : 2H, that is the slope angle is

    equal to 26;

    Considering that Guadaloupe is in tropical area, the design rainfall intensity is very high: it was

    set at 150 mm/hour with a critical duration of 1.0 hour;

  • 7/26/2019 February2015_Maccaferri_MacNews

    11/15

    Special Supplement for Geosynthetics 2015 February 2015 MacNews

    The Reduction Factors for evaluating the available long term flow rate of MacDrain

    geocomposites were selected according to the indications provided in the MacFlow Drainage

    Manual issued by Maccaferri, for the following conditions:

    o Surcharge on MacDrain = 1.0 m thick cover soil

    o Contacts = Soft / Soft

    o Design life = 30 years

    Since the drainage system is on slope, MacFlow-S software was used.

    Input and output pages from the MacFlow software for the design of Blanchard landfill:

    FAQ's: Soil Reinforcement/GeosyntheticsIs the use of a biaxial geogrid economical compared to two uniaxial geogrids installed in crossdirection?

    It's common assumption that, using one biaxial geogrid is more economical than using two uniaxialgeogrids in cross direction. The main reason behind this assumption is the cost of additional layer ofgeogrid and its installation. This assumption is correct. However, some hidden costs have to be evaluatedif biaxial geogrid is chosen and this impacts not only the economical aspect but also the goodEngineering practice.

    To answer this question properly, we have to evaluate two potential scenarios related to differentapplications. Most importantly, we need to distinguish between soil stabilization application and soilreinforcement application.

    In case of soil stabilization applications, the low strength geogrids (e.g. 30/30, 40/40, --- up to 100/100kN/m) are used as reinforcement material. The typical applications are road base / sub-basereinforcement and parking area sub-base reinforcement aimed at improving the bearing capacity of thesub-soil by spreading the loads on to much larger surface area.

    In case of soil reinforcement applications, the required tensile strength is typically much higher and it isnot same in both directions (e.g. Piled embankment, Embankments on voids or on soft soils and similarapplications).

    In any case, the design tensile strength must be guaranteed in both working directions. This can beachieved by overlapping geogrids. The length of required overlap is based on passive friction and

  • 7/26/2019 February2015_Maccaferri_MacNews

    12/15

    Special Supplement for Geosynthetics 2015 February 2015 MacNews

    bonding. The connection strength at the overlap is calculated using the surcharge load and frictioncoefficient between soil and geogrid. The length of overlap or the connection strength shall be greaterthan the required structural strength. Having said that, geogrid strength is governed by the connectionstrength and the design connection strength is not the strength of geogrid.

    The length of geogrid overlap (Le) is calculated using below formula:

    (1tan(1)

    +

    2tan(2)

    )

    WhereTdesign Design tensile load in the reinforcement per meter runfp The partial factor for reinforcement pullout resistance Unit weight of embankment fillh The average height of embankment fill above the reinforcement length

    a'1 The interaction coefficient relating the soil / reinforcement bond angle to tan(1)onone side of the reinforcement

    a'2 The interaction coefficient relating the soil / reinforcement bond angle to tan(2)onother side of the reinforcement

    1 The large stain angle of friction of embankment fill under effective stress

    condition on one side of the reinforcement2 The large stain angle of friction of embankment fill under effective stresscondition on other side of the reinforcementfms The partial material factor applied to tan()

    In case of soil stabilization applications, the calculated length of overlap coincides with standard range ofoverlap (20 to 40cm). It is evident that, in case of soil stabilization the standard geogrid overlap ensuresthe structural continuity in both main and cross direction because the forces mobilized are very limitedand minimum length of overlap is sufficient to fulfill the structural continuity.

    The overlap length requirement is completely different when the required design tensile strength is notlimited. For example, if we have to provide 50 kN/m of connection strength, the required overlap is 6.6 mwith 1.0m of soil cover. The length of overlap is inversely proportional to overburden pressure. As

    overburden (depth of soil) increases, required overlap length decreases.Lets analyze two different design cases:

    1. Standard road/parking area with 70 cm of base and sub base and 15 cm of asphalt layer; fullwidth approximately 8 meters where a 30/30 kN/m geogrids has to be installed at the base inorder to provide a tensile strength of 10 kN/m at 2%. Using above formula to calculate length ofgeogrid overlap, the required overlap length to guarantee the continuity is 30 cm so the standardoverlap length satisfy the requirement; the below sketch shows geogrid installation layout.

  • 7/26/2019 February2015_Maccaferri_MacNews

    13/15

    Special Supplement for Geosynthetics 2015 February 2015 MacNews

    Fig 1.0 Soil Stabilization: Road / Parking area base / sub-base reinforcement using biaxial geogrids

    2. 3.0m high embankment supported using group of piles spaced at 2 m having a cap size of 80 cm:In this case a geogrid of 300 kN/m is required (Tdesign= 140 kN/m approx.) in the transversedirection and geogrid with 140 kN/m is required (Tdesign= 64 kN/m approx.) in the longitudinaldirection.

    If we use two different geogrids, 300 kN/m in one direction and 150 kN/m in the other, we do notneed an overlap in transverse direction. However, overlap is required in the longitudinal directionif the length of the geogrid roll is shorter than the length of the embankment. In this case thewastage will be equal to the required overlap 1.6 m divided by the length of the roll. If we assumelength of roll as 80 m, the approximate waste would be 2%. Under such circumstances, there will

    be minimum wastage however we have to take into consideration two geogrids installationoperation instead of one. To be noted that, even if, we have a geogrid with a strength of 300/30kN/m and 110/30 kN/m we cannot add the tensile strength of the cross direction of the firstgeogrid to the tensile strength of longitudinal direction of the second geogrid (30 kN/m + 110kN/m) to achieve the design strength (140 kN/m) because the stress-strain curve of the twomaterials are not comparable and have quite different modulus.

  • 7/26/2019 February2015_Maccaferri_MacNews

    14/15

    Special Supplement for Geosynthetics 2015 February 2015 MacNews

    Fig 2.0 Soil Reinforcement: Piled Embankment Reinforcement using two layers of uniaxial geogrids

    In case of using one biaxial geogrid with tensile strength of 300/150 kN/m, we can install it in one passbut the grid will have to be overlapped minimum 1.60 m at each sheet. It is important to note that themaximum width of a geogrid is never more than 5.3 m (typically between 4 and 5); we will have awastage ranging from 30 to 40%. In these projects even if, use of biaxial geogrid is correct, It is notadvisable because it will require an overlap connection every few meters and this is something that is nota good practice. Also from the cost point of view such overlapping makes this installation / solutionuneconomical.

    Fig 3.0 Soil Reinforcement: Pilled Embankment Reinforcement using Biaxial geogrid

  • 7/26/2019 February2015_Maccaferri_MacNews

    15/15

    Special Supplement for Geosynthetics 2015 February 2015 MacNews

    From the above examples, in most applications it is not suitable to use biaxial geogrids and it is evidentwhy most of the geogrid manufacturers try to produce materials with limited strength in the crossdirection. The knitting or the woven technology has a limitation on minimum numbers of filaments in thewarp direction. Because ofsuch limitation on number of filaments, cross machine direction strengthcannot be lower than 20-30 kN/m. Extruded geogrids or strip bonded geogrids does not have suchstructural limitation so the extruded geogrid are considered fully uniaxial and the strip bonded have aminimum strength of 5 kN/m in the cross machine direction.

    To recap, it is evident that to make an appropriate cost comparison, we will have to apply the followingformulas keeping in mind good installation practice to analyze which design case is cost effective.

    Cost of solution with two geogrids = Cost of geogrid (longitudinal) + Cost of geogrid (transversal) + Costof longitudinal geogrid installation + Cost of transversal geogrid installation + Cost of geogrid overlappingin longitudinal direction.

    Cost of solution with one geogrid = Cost of geogrid + Cost of geogrid installation + Cost of structuraloverlapping

    Upcoming Events:

    Meet our people and learn about our products and solutions at:

    Booth #1917 at theSME/CMA, Annual Conferencein Denver, CO, Feb. 15-18, 2015Booth #831 atGeosynthetics 2015in Portland, OR, Feb. 15-18, 2015The outdoor section, booth #9024,IFCEE 2015Conference in San Antonio, TX Mar. 17-21, 201560th New Mexico Transportation Engineering Conferencein Las Cruces, NM, Apr. 22-24, 2015New Mexico Floodplain Managers Association,TBD, April 2015

    And many more throughout the year!

    10303 Governor Lane Blvd.

    Williamsport, Maryland 21795800-638-7744www.maccaferri-usa.com

    http://r20.rs6.net/tn.jsp?e=001biN1cbvjCVInVluH8TV_F1o8SEPUNxSt1IupMhrXXvQiAZo4-8v01J0QUT2BtdnHyZNV1sXntZuBHZV46LpQJhA2ELUUY6vaIUJBRaO1oZxIhoTBvKpaXP2PbrO-uaekhttp://r20.rs6.net/tn.jsp?e=001biN1cbvjCVInVluH8TV_F1o8SEPUNxSt1IupMhrXXvQiAZo4-8v01J0QUT2BtdnHyZNV1sXntZuBHZV46LpQJhA2ELUUY6vaIUJBRaO1oZxIhoTBvKpaXP2PbrO-uaekhttp://r20.rs6.net/tn.jsp?e=001biN1cbvjCVInVluH8TV_F1o8SEPUNxSt1IupMhrXXvQiAZo4-8v01J0QUT2BtdnHyZNV1sXntZuBHZV46LpQJhA2ELUUY6vaIUJBRaO1oZxIhoTBvKpaXP2PbrO-uaekhttp://r20.rs6.net/tn.jsp?e=001biN1cbvjCVInVluH8TV_F1o8SEPUNxSt1IupMhrXXvQiAZo4-8v01J0QUT2BtdnHyZNV1sXntZsJBwWNqizKmMilifvJUfjQaGAiTYst2kczqJ7-YCw7NZwsnwNTep03http://r20.rs6.net/tn.jsp?e=001biN1cbvjCVInVluH8TV_F1o8SEPUNxSt1IupMhrXXvQiAZo4-8v01J0QUT2BtdnHyZNV1sXntZsJBwWNqizKmMilifvJUfjQaGAiTYst2kczqJ7-YCw7NZwsnwNTep03http://r20.rs6.net/tn.jsp?e=001biN1cbvjCVInVluH8TV_F1o8SEPUNxSt1IupMhrXXvQiAZo4-8v01J0QUT2BtdnHyZNV1sXntZsJBwWNqizKmMilifvJUfjQaGAiTYst2kczqJ7-YCw7NZwsnwNTep03http://r20.rs6.net/tn.jsp?e=001biN1cbvjCVInVluH8TV_F1o8SEPUNxSt1IupMhrXXvQiAZo4-8v01J0QUT2BtdnHyZNV1sXntZuL0GtTKDhc7nQd_9Ozp1eRhqoIrYcH0IM=http://r20.rs6.net/tn.jsp?e=001biN1cbvjCVInVluH8TV_F1o8SEPUNxSt1IupMhrXXvQiAZo4-8v01J0QUT2BtdnHyZNV1sXntZuL0GtTKDhc7nQd_9Ozp1eRhqoIrYcH0IM=http://r20.rs6.net/tn.jsp?e=001biN1cbvjCVInVluH8TV_F1o8SEPUNxSt1IupMhrXXvQiAZo4-8v01J0QUT2BtdnHyZNV1sXntZuL0GtTKDhc7nQd_9Ozp1eRhqoIrYcH0IM=http://r20.rs6.net/tn.jsp?e=001biN1cbvjCVInVluH8TV_F1o8SEPUNxSt1IupMhrXXvQiAZo4-8v01J0QUT2BtdnHyZNV1sXntZuHxG7xTt6hlACW7HtvsLvfQSv5gwfI0TUzxayktaxte5GQpaA2UhbcjIJvVw--bQY3k0-sdn-iAEEDnqrahI_DnxxhtlGb6J9eq3_oITFE6N6iMkqbEHXf2ptmf2X4Xt1ZUSB1xWbylZOFMI0uEylVX-dwHtXSJHiPHNfnpHGoNLh6xsDPVuIL6S68q3RFDZAAKAFD5WTsQU9s08Z1-WaYwP7nqhnvaVh7l8mcObOEml4PbeJgQ5OfJ16mareif2w=http://r20.rs6.net/tn.jsp?e=001biN1cbvjCVInVluH8TV_F1o8SEPUNxSt1IupMhrXXvQiAZo4-8v01J0QUT2BtdnHyZNV1sXntZuHxG7xTt6hlACW7HtvsLvfQSv5gwfI0TUzxayktaxte5GQpaA2UhbcjIJvVw--bQY3k0-sdn-iAEEDnqrahI_DnxxhtlGb6J9eq3_oITFE6N6iMkqbEHXf2ptmf2X4Xt1ZUSB1xWbylZOFMI0uEylVX-dwHtXSJHiPHNfnpHGoNLh6xsDPVuIL6S68q3RFDZAAKAFD5WTsQU9s08Z1-WaYwP7nqhnvaVh7l8mcObOEml4PbeJgQ5OfJ16mareif2w=http://r20.rs6.net/tn.jsp?e=001biN1cbvjCVInVluH8TV_F1o8SEPUNxSt1IupMhrXXvQiAZo4-8v01J0QUT2BtdnHyZNV1sXntZvhZnSvhe5PuYrRTS5phVSGSE6vrDpTkcU=http://r20.rs6.net/tn.jsp?e=001biN1cbvjCVInVluH8TV_F1o8SEPUNxSt1IupMhrXXvQiAZo4-8v01J0QUT2BtdnHyZNV1sXntZvhZnSvhe5PuYrRTS5phVSGSE6vrDpTkcU=http://r20.rs6.net/tn.jsp?e=001biN1cbvjCVInVluH8TV_F1o8SEPUNxSt1IupMhrXXvQiAZo4-8v01J0QUT2BtdnHyZNV1sXntZt6GguzvLBLXX16uUw9T1hGDjQxoC1BiFe3VzW2h_5oSw==http://r20.rs6.net/tn.jsp?e=001biN1cbvjCVInVluH8TV_F1o8SEPUNxSt1IupMhrXXvQiAZo4-8v01J0QUT2BtdnHyZNV1sXntZt6GguzvLBLXX16uUw9T1hGDjQxoC1BiFe3VzW2h_5oSw==http://r20.rs6.net/tn.jsp?e=001biN1cbvjCVInVluH8TV_F1o8SEPUNxSt1IupMhrXXvQiAZo4-8v01J0QUT2BtdnHyZNV1sXntZt6GguzvLBLXX16uUw9T1hGDjQxoC1BiFe3VzW2h_5oSw==http://r20.rs6.net/tn.jsp?e=001biN1cbvjCVInVluH8TV_F1o8SEPUNxSt1IupMhrXXvQiAZo4-8v01J0QUT2BtdnHyZNV1sXntZvhZnSvhe5PuYrRTS5phVSGSE6vrDpTkcU=http://r20.rs6.net/tn.jsp?e=001biN1cbvjCVInVluH8TV_F1o8SEPUNxSt1IupMhrXXvQiAZo4-8v01J0QUT2BtdnHyZNV1sXntZuHxG7xTt6hlACW7HtvsLvfQSv5gwfI0TUzxayktaxte5GQpaA2UhbcjIJvVw--bQY3k0-sdn-iAEEDnqrahI_DnxxhtlGb6J9eq3_oITFE6N6iMkqbEHXf2ptmf2X4Xt1ZUSB1xWbylZOFMI0uEylVX-dwHtXSJHiPHNfnpHGoNLh6xsDPVuIL6S68q3RFDZAAKAFD5WTsQU9s08Z1-WaYwP7nqhnvaVh7l8mcObOEml4PbeJgQ5OfJ16mareif2w=http://r20.rs6.net/tn.jsp?e=001biN1cbvjCVInVluH8TV_F1o8SEPUNxSt1IupMhrXXvQiAZo4-8v01J0QUT2BtdnHyZNV1sXntZuL0GtTKDhc7nQd_9Ozp1eRhqoIrYcH0IM=http://r20.rs6.net/tn.jsp?e=001biN1cbvjCVInVluH8TV_F1o8SEPUNxSt1IupMhrXXvQiAZo4-8v01J0QUT2BtdnHyZNV1sXntZsJBwWNqizKmMilifvJUfjQaGAiTYst2kczqJ7-YCw7NZwsnwNTep03http://r20.rs6.net/tn.jsp?e=001biN1cbvjCVInVluH8TV_F1o8SEPUNxSt1IupMhrXXvQiAZo4-8v01J0QUT2BtdnHyZNV1sXntZuBHZV46LpQJhA2ELUUY6vaIUJBRaO1oZxIhoTBvKpaXP2PbrO-uaek