Earned Value

45
Create WBS Work Package Scope Decompositio n 100 %

description

Earned Value in PMP

Transcript of Earned Value

Page 1: Earned Value

Create WBS

Work Package

ScopeDecomposition

100 %

Page 2: Earned Value

Create WBS

Work Package

ScopeDecomposition

100 %100 %

Page 3: Earned Value

Initiating the Project•Conduct project selection methods•Define scope•Document project risks, assumptions, and constraints•Identify and perform stakeholder analysis    

•Develop project charter•Obtain project charter approval

Planning the Project•Define and record requirements, constraints, and assumptions•Identify project team and define roles and responsibilities•Create the WBS•Create Activity List , Attributes and Network Diagram •Estimate activity resources and duration •Estimate activity Costs •Iterations, go back to make changes or updates to Project management Plan •Develop change management plan•Identify risks and define risk strategies•Determine quality standards, processes and metrics•Determine roles and responsibilities•Determine communication requirements •Obtain plan approval•Conduct kick-off meeting

Page 4: Earned Value

Executing the Project•Execute tasks defined in project plan•Ensure common understanding and set expectations•Implement the procurement of project resources•Manage resource allocation•Implement quality management plan•Implement approved changes•Implement approved actions and workarounds•Improve team performance

Monitoring and Controlling the Project•Measure project performance•Verify and manage changes to the project•Ensure project deliverables conform to quality standards•Monitor all risks

Page 5: Earned Value

0 4 10 11 15

SCOPE 100%

Page 6: Earned Value

WP 1 WP 2 WP 3 WP 4

0 4 10 11 15

SCOPE 100 $

Page 7: Earned Value

WP 1 WP 2 WP 3 WP 4

0 4 10 11 15

Page 8: Earned Value

20 $ 60 $ 10 $ 10 $

0 4 10 11 15

BAC

Page 9: Earned Value

20 $ 60 $ 10 $ 10 $

0 4 10 12 15

BAC

Page 10: Earned Value

20 $ 60 $ 10 $ 10 $

0 4 10 11 15

BAC

80 $ Planned Value = 80 $

Page 11: Earned Value

20 $ 60 $ 10 $ 10 $

0 4 10 11 15

BAC

Only Package 1 complete

20 $Planned Value = 80 $

Page 12: Earned Value

20 $ 60 $ 10 $ 10 $

0 4 10 11 15

BAC

Planned Value = 80 $

20 $ Earned Value = 20 $

Schedule Variance = EV – PV = -60 $

Page 13: Earned Value

20 $ 60 $ 10 $ 10 $

0 4 10 11 15

BAC

Planned Value = 80 $

20 $ Earned Value = 20 $

Schedule Variance = EV – PV = -60 $

Behind Schedule

Page 14: Earned Value

20 $ 60 $ 10 $ 10 $

0 4 10 11 15

BAC

Planned Value = 80 $

20 $Schedule Variance = EV – PV = -60 $

Behind Schedule

Earned Value = 20 $

Page 15: Earned Value

20 $ 60 $ 10 $ 10 $

0 4 10 11 15

BAC

Planned Value = 80 $

20 $

30 $

Earned Value = 80 $

What did we spend for completing package 1

Page 16: Earned Value

20 $ 60 $ 10 $ 10 $

0 4 10 11 15

BAC

Planned Value = 80 $

20 $Actual Cost = 30 $

30 $

Earned Value = 80 $

What did we spend for completing package 1

Page 17: Earned Value

20 $ 60 $ 10 $ 10 $

0 4 10 11 15

BAC

Planned Value = 80 $

20 $Actual Cost = 30 $

Cost Variance = EV – AV = -10 $30 $

Earned Value = 80 $

What did we spend for completing package 1

Page 18: Earned Value

20 $ 60 $ 10 $ 10 $

0 4 10 11 15

BAC

Planned Value = 80 $

20 $Actual Cost = 30 $

Cost Variance = EV – AV = -10 $30 $

Earned Value = 20 $

Over Budget

Page 19: Earned Value

20 $ 60 $ 10 $ 10 $

0 4 10 11 15

BAC

Planned Value = 80 $

20 $Actual Cost = 30 $

Cost Performance Index = EV AV = 0.6730 $

Earned Value = 20 $

Over Budget

÷

Page 20: Earned Value

20 $ 60 $ 10 $ 10 $

0 4 10 11 15

BAC

Planned Value = 80 $

20 $ Earned Value = 20 $

Behind Schedule

Schedule Performance Index = EV PV 0.25 ÷

Page 21: Earned Value

20 $ 60 $ 10 $ 10 $

0 4 10 12 15

BAC

20 $ 60 $ 50%

80 $

Page 22: Earned Value

0 4 10 11 15

Page 23: Earned Value

Earned Value

Time

Cost

Page 24: Earned Value

Planned Value

Earned Value

Time

Cost

Page 25: Earned Value

Planned Value

Actual

Cost

Earned Value

Time

Cost

Page 26: Earned Value

Planned Value

Actual

Cost

Earned Value

Time

Cost

Page 27: Earned Value

Planned Value

Actual

Cost

Earned Value

Time

Cost

Schedule Variance

Page 28: Earned Value

Planned Value

Actual

Cost

Earned Value

Time

Cost

Cost Variance

Schedule Variance

Page 29: Earned Value

Planned Value

Actual

Cost

Earned Value

Time

Cost

Cost Variance

Schedule Variance

Both relative to earned value

Page 30: Earned Value

Planned Value

Actual

Cost

Earned Value

Time

Cost

Cost Variance

Schedule Variance

Both relative to earned value

Positive Variances are good ( under spent or ahead of schedule) Negative Variances are bad ( Over spent or Behind schedule)

Page 31: Earned Value

Planned Value

Actual

Cost

Earned Value

Time

Cost

Page 32: Earned Value

Planned Value

Actual

Cost

Earned Value

Time

Cost Late

Over spent

Page 33: Earned Value

Planned Value

Actual

Cost

Earned Value

Time

Cost

Planned Value

Actual Cost

Earned Valu

e

Time

Cost

Late Over spent

Page 34: Earned Value

Planned Value

Actual

Cost

Earned Value

Time

Cost

Planned Value

Actual Cost

Earned Valu

e

Time

Cost

Late Over spent

early under spent

Page 35: Earned Value

Planned Value

Actual

Cost

Earned Value

Time

Cost

Planned Value

Actual Cost

Earned Valu

e

Time

Cost

Planned Value

Actual

Cost

Earned Value

Time

Cost

Late Over spent

Page 36: Earned Value

Planned Value

Actual

Cost

Earned Value

Time

Cost

Planned Value

Actual Cost

Earned Valu

e

Time

Cost

Planned Value

Actual

Cost

Earned Value

Time

Cost

Late Over spent

earlyOver spent

Page 37: Earned Value

Planned Value

Actual

Cost

Earned Value

Time

Cost

Planned Value

Actual Cost

Earned Valu

e

Time

Cost

Planned Value

Actual

Cost

Earned Value

Time

Cost

Planned Valu

e

Actual Cost

Earned Value

Time

Cost

Late Over spent

early under spent

earlyOver spent

Page 38: Earned Value

Planned Value

Actual

Cost

Earned Value

Time

Cost

Planned Value

Actual Cost

Earned Valu

e

Time

Cost

Planned Value

Actual

Cost

Earned Value

Time

Cost

Planned Valu

e

Actual Cost

Earned Value

Time

Cost

Late Over spent

early under spent

earlyOver spent

Late Under spent

Page 39: Earned Value

Performances Indices

Cost Performance Index

Schedule Performance Index

Page 40: Earned Value

Cost Performance Index

Schedule Performance Index Earned Value

Earned Value

Performances Indices

Page 41: Earned Value

Cost Performance Index

Schedule Performance Index Earned Value

Earned Value

Actual Cost

Performances Indices

Page 42: Earned Value

Cost Performance Index

Schedule Performance Index Earned Value

Earned Value

Actual Cost

Planned Cost

Calculates efficiency

Calculates effectiveness

Ratios greater than 1 are good

Performances Indices

Page 43: Earned Value

Cost Performance Index

Schedule Performance Index

Calculates efficiency

Calculates effectiveness

Ratios greater than 1 are good

Final Cost BAC

CPIFinal Project duration

Planned Project Duration

SPI

Earned Value

Earned Value

Actual Cost

Planned Cost

Performances Indices

Page 44: Earned Value

Worked Example 1

A project has a budget of $ 1.5 million and a planned duration of 20 months

After 8 months the reported figures are given below:

Cost Type AmountPlanned Cost $ 720k

Actual Cost $ 600k

Earned Value $ 680k

Calculate CPI , CV , SPI , SV , Final Cost , Final Planned Duration ?

Page 45: Earned Value

Worked Example 1

A project has a budget of $ 1.5 million and a planned duration of 20 months

After 8 months the reported figures are given below:

Cost Type AmountPlanned Cost $ 720k

Actual Cost $ 600k

Earned Value $ 680k

Calculate CPI , CV , SPI , SV , Final Cost , Final Planned Duration & % complete ?

CPI = EV / AC = 680 / 600 = 1.13CV = EV – AC = 680 – 600 = 80

SPI = EV / PV = 680 / 720 = 0.94SV = EV – PV = 680-720 = - 40

Final Cost BAC

CPI

Final Cost 1.5 m / 1.13 132 m

Final Project duration Planned Project Duration

SPIFinal Project duration 20 / 0.94 21.27

Percentage complete EV / BAC * 100 680 / 1500 * 100 45.33 %