Earned Value fundamentals

78
Earned Value Management Fundamentals Welcome to the course

description

This presentation is from the free online course, which i delivered in February 2013. *If you downloaded before the 8th August, please download again the correct file* -Feel free to download and share. -Denise

Transcript of Earned Value fundamentals

Page 1: Earned Value fundamentals

Earned Value Management Fundamentals

Welcome to the course

Page 2: Earned Value fundamentals

Introduction

Before getting started, please use the comments area below to

introduce yourself (you’re colleagues want to meet you!)

Tell us the business sector/industry you’re coming from,

your company name if you like, your experience with project

management so far and if you have ever been involved with the

challenging world of Earned Value!

What are your expectations from the course?

Page 3: Earned Value fundamentals

Let’s get started!

The ‘Earned Value Fundamentals’ is an introduction course to the

Earned Value Management world (or the Project Controls world!)

We take for granted that you know how to plan a project, develop

the WBS and create activities taking into account the resources

availability. You also know how to distribute the project budget.

Purpose of the course is to understand the Schedule – Cost

integration and learn how Earned Value will help you make

realistic forecasts and get early warning signals that will support

your decision making when planning preventive actions.

Enjoy the course!

Page 4: Earned Value fundamentals

identify

stakeholders

scope

WBS

activities

resources

costs

communications

coordinate

resources

manage

stakeholders

scope

schedule

costs

resources

reporting

lessons learnt

dismiss team

close project

Planning Executing ClosingMonitor & Control

Initiating

The Project Management lifecycle

Page 5: Earned Value fundamentals

Planning ExecutingMonitor & Control

The Project Management lifecycle

WBS

Schedule - Critical Path Method

Distribute Budget – Cost Profile

Allocate Resources

Project Baseline

Record Progress / Actuals

- Dates

- Costs

- Resources

Results & Reporting

Progress

Changes

Variances from the Baseline

Page 6: Earned Value fundamentals

Planning

WBS

Schedule - Critical Path Method

Distribute Budget – Cost Profile

Allocate Resources

Project Baseline

Project Week10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 320804�01�02�03�04 01 02 03 04 05 06 07 09

planned

baseline

Page 7: Earned Value fundamentals

Planning

WBS

Critical Path Method

Distribute Budget – Cost Profile

Allocate Resources

Project Baseline

Executing

Record Progress / Actuals

- Dates

- Costs

- Resources

Project Week10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 320804�01�02�03�04 01 02 03 04 05 06 07 09

planned

baselineactual

status

date

Page 8: Earned Value fundamentals

Planning

WBS

Critical Path Method

Distribute Budget – Cost Profile

Allocate Resources

Project Baseline

Executing

Monitor & Control

Results & Reporting

Progress

Changes

Variances from the Baseline

Project Week10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 320804�01�02�03�04 01 02 03 04 05 06 07 09

planned

baselineactual

status

date

Page 9: Earned Value fundamentals

Earned Value ElementsEarned Value ElementsEarned Value ElementsEarned Value Elements

Page 10: Earned Value fundamentals

Planning Project Week10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 320804�01�02�03�04 01 02 03 04 05 06 07 09

planned

baseline

Project:

Project: Replacement of pits and

ducts along a 200m pavement.

Project Duration: 25w

Budgeted Cost: $250.000

Project Baseline:

Page 11: Earned Value fundamentals

Planning Project Week10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 320804�01�02�03�04 01 02 03 04 05 06 07 09

planned

baseline

Project:

Project: Replacement of pits and

ducts along a 200m pavement.

Project Duration: 25w

Budgeted Cost: $250.000

Project Baseline:

For training purposes, we shall focus on the first project activity that will guide us through the Earned Value Elements.

Page 12: Earned Value fundamentals

Planning Project Week10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 320804�01�02�03�04 01 02 03 04 05 06 07 09

planned

baseline

Project:

Project: Replacement of pits and

ducts along a 200m pavement.

Activity:

Lay 50m of ducts

Baseline Duration: 3weeks – 15days

Baseline Cost: $10.000

Project Duration: 25w

Budgeted Cost: $250.000

Project Baseline:

Cost profile:

Week 1: $3.000

Week 2: $5.000

Week 3: $2.000

$250,000

Page 13: Earned Value fundamentals

Planning Project Week10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 320804�01�02�03�04 01 02 03 04 05 06 07 09

planned

baseline

Activity:

Lay 50m of ducts

Baseline Duration: 3weeks – 15days

Baseline Cost: $10.000

Cost profile:

Week 1: $3.000

Week 2: $5.000

Week 3: $2.000 $3.000

$8.000$10.000

15m40m

50m

The schedule has been developed. The baseline is set.

We have planned to lay 50m of ducts within 15 days.

The budgeted cost is $10.000 and it is cumulatively distributed along the activity duration.

Page 14: Earned Value fundamentals

Planning Project Week10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 320804�01�02�03�04 01 02 03 04 05 06 07 09

planned

baseline

Activity:

Lay 50m of ducts

Baseline Duration: 3weeks – 15days

Baseline Cost: $10.000

Cost profile:

Week 1: $3.000

Week 2: $5.000

Week 3: $2.000 $3.000

$8.000$10.000

15m40m

50m

Budget At Completion

(BAC): $10.000

Distribution over the activity duration

Week 1: $3.000

Week 2: $5.000

Week 3: $2.000

Page 15: Earned Value fundamentals

Project Week10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 320804�01�02�03�04 01 02 03 04 05 06 07 09

planned

baseline$3.000

$8.000$10.000

15m40m

50m

The schedule has been developed. The baseline is set and the BAC has been agreed.

We have planned to lay 50m of ducts within 15 days.

The baseline cost, is $10.000 and it is cumulatively distributed along the activity duration.

The BAC is not standing alone. For each week of the activity a specific amount of work has been planned to be performed.

Budget At Completion (BAC): $10.000

Period Cumulative

$3.000 $3.000

$5.000 $8.000

$2.000 $10.000

Work Planned: 50m of ducts

Period Cumulative

Week 1: 15m 15m

Week 2: 25m 40m

Week 3: 10m 50m

Activity Duration: 15d

Period Cumulative

5d 5d

5d 10d

5d 15d

Page 16: Earned Value fundamentals

Project Week10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 320804�01�02�03�04 01 02 03 04 05 06 07 09

planned

baseline$3.000

$8.000$10.000

15m40m

50m

One week later we update the project progress…

The schedule has been developed. The baseline is set and the BAC has been agreed.

We have planned to lay 50m of ducts within 15 days.

The baseline cost, is $10.000 and it is cumulatively distributed along the activity duration.

The BAC is not standing alone. For each week of the activity a specific amount of work has been planned to be performed.

Page 17: Earned Value fundamentals

Executing Project Week

Activity:

Lay 50m of ducts

Baseline Duration: 3weeks – 15days

Baseline Cost: $10.000

Cost profile:

Week 1: $3.000

Week 2: $5.000

Week 3: $2.000

We planned to lay 15meters within the first five days.

However, one week later when the progress updated, only 10m were completed.

The actual activity cost is so far $3.000.

10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 320804�01�02�03�04 03 0401 02 05 06 07 09

planned

baseline$3.000

$8.000$10.000

15m40m

50m10m

Page 18: Earned Value fundamentals

Executing Project Week

Activity:

Lay 50m of ducts

Baseline Duration: 3weeks – 15days

Baseline Cost: $10.000

Cost profile:

Week 1: $3.000

Week 2: $5.000

Week 3: $2.000

We planned to lay 15meters within the first five days.

However, one week later when the progress updated, only 10m were completed.

The actual activity cost is so far $3.000.

10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 320804�01�02�03�04 03 0401 02 05 06 07 09

planned

baseline$3.000

$8.000$10.000

15m40m

50m10m

Actual Cost (AC) on Week 1: $3.000

Actual Cost is the cost of work

performed by the day the progress

updated. It’s not necessarily the cost

that has been paid to the contractor.

Page 19: Earned Value fundamentals

Executing Project Week

Activity:

Lay 50m of ducts

Baseline Duration: 3weeks – 15days

Baseline Cost: $10.000

Cost profile:

Week 1: $3.000

Week 2: $5.000

Week 3: $2.000

We planned to lay 15meters within the first five days.

However, one week later when the progress updated, only 10m were completed.

The actual activity cost is so far $3.000.

10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 320804�01�02�03�04 03 0401 02 05 06 07 09

planned

baseline$3.000

$8.000$10.000

15m40m

50m10m

Actual Cost (AC) on Week 1: $3.000

Actual Cost is the cost of work

performed by the day the progress

updated. It’s not necessarily the cost

that has been paid to the contractor.

You may also see the AC as Actual Cost of Work Performed (ACWP).

The Actual Cost, or Actual Cost of Work Performed (ACWP) consists of:

Actual [Labor + Non labor (equipment and machinery) + Material (the cost of ducts) + Expenses

(like training, but expenses do not apply to all the project activities)]

Page 20: Earned Value fundamentals

Executing Project Week

Activity:

Lay 50m of ducts

Baseline Duration: 3weeks – 15days

Baseline Cost: $10.000

Cost profile:

Week 1: $3.000

Week 2: $5.000

Week 3: $2.000

10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 320804�01�02�03�04 03 0401 02 05 06 07 09

planned

baseline$3.000

$8.000$10.000

15m40m

50m10m

Actual Cost (AC) on Week 1: $3.000

Actual Cost is the cost of work

performed by the day the progress

updated. It’s not necessarily the cost

that has been paid to the contractor.

Week 1 Planned Actual

Work 15m 10m

Cost $3.000 $3.000

Page 21: Earned Value fundamentals

Project Week

How is the project doing?10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 320804�01�02�03�04 03 0401 02 05 06 07 09

planned

baseline$3.000

$8.000$10.000

15m40m

50m10m

Question:

Page 22: Earned Value fundamentals

Project Week

How is the project doing?10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 320804�01�02�03�04 03 0401 02 05 06 07 09

planned

baseline$3.000

$8.000$10.000

15m40m

50m10m

Question:

Page 23: Earned Value fundamentals

Monitor & Control

Project Week10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 320804�01�02�03�04 03 0401 02 05 06 07 09

planned

baseline$3.000

$8.000$10.000

15m40m

50m10m

How is the project doing?

Question:

How much work should have been done so far?

How much did the work cost?

How much work has been actually done?

Page 24: Earned Value fundamentals

Monitor & Control

Project Week10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 320804�01�02�03�04 03 0401 02 05 06 07 09

planned

baseline$3.000

$8.000$10.000

15m40m

50m10m

How is the project doing?

Question:

Budget At Completion (BAC): $10.000

Period Cumulative

$3.000 $3.000

$5.000 $8.000

$2.000 $10.000

Work Planned: 50m of ducts

Period Cumulative

Week 1: 15m 15m

Week 2: 25m 40m

Week 3: 10m 50m

Activity Duration: 15d

Period Cumulative

5d 5d

5d 10d

5d 15d

Planned Value Cost (PVC) or

Budgeted Cost of Work Scheduled

(BCWS)

How much work should have been

done at the end of week 1?

Planned Value is the target against

which we are measuring the progress

How much work should have been done so far?

How much did the work cost?

How much work has been actually done?

Page 25: Earned Value fundamentals

Monitor & Control

Project Week10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 320804�01�02�03�04 03 0401 02 05 06 07 09

planned

baseline$3.000

$8.000$10.000

15m40m

50m10m

How is the project doing?

Question:

Budget At Completion (BAC): $10.000

Period Cumulative

$3.000 $3.000

$5.000 $8.000

$2.000 $10.000

Work Planned: 50m of ducts

Period Cumulative

Week 1: 15m 15m

Week 2: 25m 40m

Week 3: 10m 50m

Activity Duration: 15d

Period Cumulative

5d 5d

5d 10d

5d 15d

Planned Value Cost (PVC) or

Budgeted Cost of Work Scheduled

(BCWS)

How much work should have been

done at the end of week 1?

Planned Value is the target against

which we are measuring the progress

Planned Value Cost at the end of Week 1

How much work should have been done so far?

How much did the work cost?

How much work has been actually done?

Page 26: Earned Value fundamentals

Monitor & Control

Project Week10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 320804�01�02�03�04 03 0401 02 05 06 07 09

planned

baseline$3.000

$8.000$10.000

15m40m

50m10m

How is the project doing?

Question:

Budget At Completion (BAC): $10.000

Period Cumulative

$3.000 $3.000

$5.000 $8.000

$2.000 $10.000

Work Planned: 50m of ducts

Period Cumulative

Week 1: 15m 15m

Week 2: 25m 40m

Week 3: 10m 50m

Activity Duration: 15d

Period Cumulative

5d 5d

5d 10d

5d 15d

PVC = BAC x Planned % Complete Planned Value Cost at the end of Week 1

We planned to complete 30% of the

Budget At Completion ($10.000) at the

end of the week 1.

PVC = $10.000 x 30% = $3.000

How much work should have been done so far?

How much did the work cost?

How much work has been actually done?

Page 27: Earned Value fundamentals

Monitor & Control

Project Week10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 320804�01�02�03�04 03 0401 02 05 06 07 09

planned

baseline$3.000

$8.000$10.000

15m40m

50m10m

How is the project doing?

Question:

How much work should have been done so far?

How much did the work cost?

How much work has been actually done?

Budget At Completion (BAC): $10.000

Period Cumulative

$3.000 $3.000

$5.000 $8.000

$2.000 $10.000

Work Planned: 50m of ducts

Period Cumulative

Week 1: 15m 15m

Week 2: 25m 40m

Week 3: 10m 50m

Activity Duration: 15d

Period Cumulative

5d 5d

5d 10d

5d 15d

PVC = BAC x Planned % Complete Planned Value Cost at the end of Week 1

We planned to complete 30% of the

Budget At Completion ($10.000) at the

end of the week 1.

PVC = $10.000 x 30% = $3.000

PVC = $10.000 x 30% = $3.000

Page 28: Earned Value fundamentals

Monitor & Control

Project Week10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 320804�01�02�03�04 03 0401 02 05 06 07 09

planned

baseline$3.000

$8.000$10.000

15m40m

50m10m

How is the project doing?

Question:

How much work should have been done so far?

How much did the work cost?

How much work has been actually done?

Actual Cost (AC) is the Actual Cost

of Work Performed until the status

date (you may also see ACWP).

The Actual Cost of the work at the end

of the week1 is $3.000.

PVC = $10.000 x 30% = $3.000

Page 29: Earned Value fundamentals

Monitor & Control

Project Week10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 320804�01�02�03�04 03 0401 02 05 06 07 09

planned

baseline$3.000

$8.000$10.000

15m40m

50m10m

How is the project doing?

Question:

How much work should have been done so far?

How much did the work cost?

How much work has been actually done?

Actual Cost (AC) is the Actual Cost

of Work Performed until the status

date (you may also see ACWP).

The Actual Cost of the work at the end

of the week1 is $3.000.

PVC = $10.000 x 30% = $3.000

AC= $3.000

Page 30: Earned Value fundamentals

Monitor & Control

Project Week10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 320804�01�02�03�04 03 0401 02 05 06 07 09

planned

baseline$3.000

$8.000$10.000

15m40m

50m10m

How is the project doing?

Question:

How much work should have been done so far?

How much did the work cost?

How much work has been actually done?

Actual Cost (AC) is the Actual Cost

of Work Performed until the status

date (you may also see ACWP).

The Actual Cost of the work at the end

of the week1 is $3.000.

PVC = $10.000 x 30% = $3.000

AC= $3.000 It doesn’t look that bad, right?

Page 31: Earned Value fundamentals

Monitor & Control

Project Week10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 320804�01�02�03�04 03 0401 02 05 06 07 09

planned

baseline$3.000

$8.000$10.000

15m40m

50m10m

How is the project doing?

Question:

How much work should have been done so far?

How much did the work cost?

How much work has been actually done?

Earned Value (EV) signifies how

much work has been actually done.

To measure the EV we need to know:

- BAC

- Performance % Complete

EV = BAC x Performance % Complete

PVC = $10.000 x 30% = $3.000

AC= $3.000

Page 32: Earned Value fundamentals

Monitor & Control

Project Week10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 320804�01�02�03�04 03 0401 02 05 06 07 09

planned

baseline$3.000

$8.000$10.000

15m40m

50m10m

How is the project doing?

Question:

How much work should have been done so far?

How much did the work cost?

How much work has been actually done?

Earned Value (EV) signifies how

much work has been actually done.

To measure the EV we need to know:

- BAC

- Performance % Complete

EV = BAC x Performance % Complete

PVC = $10.000 x 30% = $3.000

AC= $3.000

EV = BAC x Performance % Complete

We planned to perform 15m at the end of week 1 which is the 33,33% of the total work.

However, we performed only 10m, which the 20% of the total work.

EV = $10.000 x 20% = $2.000

Page 33: Earned Value fundamentals

Monitor & Control

Project Week10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 320804�01�02�03�04 03 0401 02 05 06 07 09

planned

baseline$3.000

$8.000$10.000

15m40m

50m10m

How is the project doing?

Question:

How much work should have been done so far?

How much did the work cost?

How much work has been actually done?

Earned Value (EV) signifies how

much work has been actually done.

To measure the EV we need to know:

- BAC

- Performance % Complete

EV = BAC x Performance % Complete

PVC = $10.000 x 30% = $3.000

AC= $3.000

EV = BAC x Performance % Complete

We planned to perform 15m at the end of week 1 which is the 33,33% of the total work.

However, we performed only 10m, which the 20% of the total work.

EV = $10.000 x 20% = $2.000

EV = $10.000 x 20% = $2.000

Page 34: Earned Value fundamentals

Monitor & Control

Project Week10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 320804�01�02�03�04 03 0401 02 05 06 07 09

planned

baseline$3.000

$8.000$10.000

15m40m

50m10m

How is the project doing?

Question:

How much work should have been done so far?

How much did the work cost?

How much work has been actually done?

Earned Value (EV) signifies how

much work has been actually done.

To measure the EV we need to know:

- BAC

- Performance % Complete

EV = BAC x Performance % Complete

PVC = $10.000 x 30% = $3.000

AC= $3.000

EV = BAC x Performance % Complete

We planned to perform 15m at the end of week 1 which is the 33,33% of the total work.

However, we performed only 10m, which the 20% of the total work.

EV = $10.000 x 20% = $2.000

EV = $10.000 x 20% = $2.000

Page 35: Earned Value fundamentals

Monitor & Control

Project Week10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 320804�01�02�03�04 03 0401 02 05 06 07 09

planned

baseline$3.000

$8.000$10.000

15m40m

50m10m

How is the project doing?

Question:

How much work should have been done so far?

How much did the work cost?

How much work has been actually done?

Earned Value (EV) signifies how

much work has been actually done.

To measure the EV we need to know:

- BAC

- Performance % Complete

EV = BAC x Performance % Complete

PVC = $10.000 x 30% = $3.000

AC= $3.000

EV = BAC x Performance % Complete

EV = $10.000 x 20% = $2.000

Earned Value explains whether the Actual Cost (AC) has been spent

effectively (Performance % Complete) providing the physical results that

was estimated to (Planned Value).

Page 36: Earned Value fundamentals

How is the project doing?

Question: Project Week10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 320804�01�02�03�04 03 0401 02 05 06 07 09

planned

baseline$3.000

$8.000$10.000

15m40m

50m10m

PVC = $10.000 x 30% = $3.000

AC= $3.000

EV = BAC x Performance % Complete

EV = $10.000 x 20% = $2.000

Earned Value explains whether the Actual Cost (AC) has been spent

effectively (Performance % Complete) delivering the physical results

that was estimated to (Planned Value).

The project is not doing very well…Here are the facts:

Answer:

PVC = $10.000 x 30% = $3.000

AC= $3.000

EV = $10.000 x 20% = $2.000

Page 37: Earned Value fundamentals

Earned Value elements within the Project Management lifecycle

Planning Executing ClosingMonitor & Control

Planned Value Cost

Actual Cost

Earned Value

Initiating

EV = BAC x Performance % CompletePVC = BAC x Planned % Complete

Page 38: Earned Value fundamentals

Earned Value elements within the Project Management lifecycle

Planning Executing ClosingMonitor & Control

Planned Value Cost

Actual Cost

Earned Value

Initiating

BCWP: Budgeted Cost

of Work Performed

BCWS: Budgeted Cost

of Work Scheduled

ACWP: Actual Cost

of Work Performed

Page 39: Earned Value fundamentals

Earned Value elements within the Project Management lifecycle

Planning Executing ClosingMonitor & Control

Planned Value Cost

Actual Cost

Earned Value

Initiating

BCWP: Budgeted Cost

of Work Performed

BCWS: Budgeted Cost

of Work Scheduled

ACWP: Actual Cost

of Work Performed

Why two terms for the same thing?

Page 40: Earned Value fundamentals

Earned Value elements within the Project Management lifecycle

Planning Executing ClosingMonitor & Control

Planned Value Cost

Actual Cost

Earned Value

Initiating

BCWP: Budgeted Cost

of Work Performed

BCWS: Budgeted Cost

of Work Scheduled

ACWP: Actual Cost

of Work Performed

Why two terms for the same thing?

New term !

Page 41: Earned Value fundamentals

Earned Value elements within the Project Management lifecycle

Planning Executing ClosingMonitor & Control

Planned Value Cost

Actual Cost

Earned Value

Initiating

BCWP: Budgeted Cost

of Work Performed

BCWS: Budgeted Cost

of Work Scheduled

ACWP: Actual Cost

of Work Performed

Why two terms for the same thing?

New term !

Old term !

Page 42: Earned Value fundamentals

Earned Value elements within the Project Management lifecycle

Planning Executing ClosingMonitor & Control

Planned Value Cost

Actual Cost

Earned Value

Initiating

BCWP: Budgeted Cost

of Work Performed

BCWS: Budgeted Cost

of Work Scheduled

ACWP: Actual Cost

of Work Performed

Why two terms for the same thing?

New term !

Old term !

Both correct and both in use!

Page 43: Earned Value fundamentals

Measuring the Earned Valuethe Performance % Complete type

EV = BAC x Performance % Complete

Page 44: Earned Value fundamentals

Project Week10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 320804�01�02�03�04 03 0401 02 05 06 07 09

planned

baseline$3.000

$8.000$10.000

15m40m

50m10m

Earned value is all about

measuring the work performed.

The Performance % Complete should

provide realistic and tangible

information for the project’s progress.

It is selected during the project

planning and can be different for each

Work Package.

Althouth there are several methods in

this course we focus in three methods,

proven to be best practices.

PVC = $10.000 x 30% = $3.000

AC= $3.000

EV = BAC x Performance % Complete

Performance % Complete

� Percent Complete Estimates

� Weighted Milestones

� Fixed Formula

EV = $10.000 x 20% = $2.000

Performance % Complete

Page 45: Earned Value fundamentals

Project Week10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 320804�01�02�03�04 03 0401 02 05 06 07 09

planned

baseline$3.000

$8.000$10.000

15m40m

50m10m

Percent Complete EstimatesPVC = $10.000 x 30% = $3.000

AC= $3.000

EV = BAC x Performance % Complete

EV = $10.000 x 20% = $2.000

Performance % Complete

It's the most commonly used

measurement method as it's easy to

administer within the already complex

project environment. However it is

subjective and often relies on the

project manger's perspective.

Expert judgment, experience and

comprehensive understanding of the

project scope are the requirements to

maximize the benefits of the %

complete estimates in the project.

Page 46: Earned Value fundamentals

Project Week10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 320804�01�02�03�04 03 0401 02 05 06 07 09

planned

baseline$3.000

$8.000$10.000

15m40m

50m10m

Percent Complete EstimatesPVC = $10.000 x 30% = $3.000

AC= $3.000

EV = BAC x Performance % Complete

EV = $10.000 x 20% = $2.000

Performance % Complete

It's the most commonly used

measurement method as it's easy to

administer within the already complex

project environment. However it is

subjective and often relies on the

project manger's perspective.

Expert judgment, experience and

comprehensive understanding of the

project scope are the requirements to

maximize the benefits of the %

complete estimates in the project.However, it can be less subjective when tangible measurement is involved; like in our example

the meters of the pits and ducts planned to complete per week (or per reporting period).

Page 47: Earned Value fundamentals

Project Week10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 320804�01�02�03�04 03 0401 02 05 06 07 09

planned

baseline

Weighted Milestones PVC = $10.000 x 30% = $3.000

AC= $3.000

EV = BAC x Performance % Complete

EV = $10.000 x 20% = $2.000

Performance % Complete

The planned work is divided into

segments.

Each Weighted Milestone represents

the percent of the work planned to be

achieved within the period.

You can use it for work packages that

exceed one measurement period.

The milestone values should be set

before the work starts.

The challenge is to agree on the

values and make it clear to everyone

involved what the values represent.

25%60%

100%

Page 48: Earned Value fundamentals

Project Week10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 320804�01�02�03�04 03 0401 02 05 06 07 09

planned

baseline

Fixed Formula PVC = $10.000 x 30% = $3.000

AC= $3.000

EV = BAC x Performance % Complete

EV = $10.000 x 20% = $2.000

Performance % Complete

It can be used in short duration

activities.

Once the work starts, the 50% of the

work is considered as completed. At

the end of it the 100% is completed.

Other examples are:

10/90

25/75

0/100

50% 100%

50/50

Page 49: Earned Value fundamentals

Forecasting the project’s future using EVM

Page 50: Earned Value fundamentals

Forecasting the project’s future using EVM

it's time to get some meaningful results from the project

and try to forecast the future of the project realistically

Page 51: Earned Value fundamentals

Forecasting the project’s future using EVM

it's time to get some meaningful results from the project

and try to forecast the future of the project realistically

Estimate To Complete

Page 52: Earned Value fundamentals

How can we estimate the cost left to perform until the completion of the activity?

Question:

Project Week10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 320804�01�02�03�04 03 0401 02 05 06 07 09

planned

baseline$3.000

$8.000$10.000

15m40m

50m10m

AC= $3.000

EV = $10.000 x 20% = $2.000

Estimate To Complete cost ETC:

Answer:

ETC = Remaining cost of work

(40m*$200/m)

ETC = $8.000

PVC = $3.000

AC = $3.000

EV = $2.000

BAC = $10.000

PVC = $10.000 x 30% = $3.000

Page 53: Earned Value fundamentals

How can we estimate the cost left to perform until the completion of the activity?

Question:

Project Week10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 320804�01�02�03�04 03 0401 02 05 06 07 09

planned

baseline$3.000

$8.000$10.000

15m40m

50m10m

AC= $3.000

Why do we Estimate To Complete?

Because the remaining cost of work is not always fixed. It may vary depending on several factors,

like additional changes that may change the budget.

Perhaps we will be able to complete the activity earlier and therefore cost less, or later than

planned, or use more resources which causes increased cost.

EV = $10.000 x 20% = $2.000

Estimate To Complete costETC:

Answer:

PVC = $3.000

AC = $3.000

EV = $2.000

BAC = $10.000

PVC = $10.000 x 30% = $3.000

ETC = Remaining cost of work

(40m*$200/m)

ETC = $8.000

Page 54: Earned Value fundamentals

Forecasting the project’s future using EVM

it's time to get some meaningful results from the project

and try to forecast the future of the project realistically

Estimate At Completion

Page 55: Earned Value fundamentals

So, at the end of the activity how much will it cost?

Question:

Project Week10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 320804�01�02�03�04 03 0401 02 05 06 07 09

planned

baseline$3.000

$8.000$10.000

15m40m

50m10m

AC= $3.000

Why do we Estimate At Completion?

Because the variable used to forecast the cost at the completion of the activity/project is the ETC.

Therefore, is not a fixed figure and can be adjusted in the future.

EV = $10.000 x 20% = $2.000

The Estimate At Completion cost EAC:

Answer:

EAC = ETC + AC

EAC = $8.000 + $3.000 = $11.000

PVC = $3.000

AC = $3.000

EV = $2.000

BAC = $10.000

ETC = $8.000

PVC = $10.000 x 30% = $3.000

Page 56: Earned Value fundamentals

Project Week10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 320804�01�02�03�04 03 0401 02 05 06 07 09

planned

baseline$3.000

$8.000$10.000

15m40m

50m10m

AC= $3.000

EV = $10.000 x 20% = $2.000

EAC = $11.000

PVC = $3.000

AC = $3.000

EV = $2.000

BAC = $10.000

ETC = $8.000

PVC = $10.000 x 30% = $3.000

Page 57: Earned Value fundamentals

Project Week10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 320804�01�02�03�04 03 0401 02 05 06 07 09

planned

baseline$3.000

$8.000$10.000

15m40m

50m10m

AC= $3.000

EV = $10.000 x 20% = $2.000

EAC = $11.000

PVC = $3.000

AC = $3.000

EV = $2.000

BAC = $10.000

ETC = $8.000

PVC = $10.000 x 30% = $3.000

How is Earned Value involved with all this?

Page 58: Earned Value fundamentals

Project Week10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 320804�01�02�03�04 03 0401 02 05 06 07 09

planned

baseline$3.000

$8.000$10.000

15m40m

50m10m

AC= $3.000

EV = $10.000 x 20% = $2.000

EAC = $11.000

PVC = $3.000

AC = $3.000

EV = $2.000

BAC = $10.000

ETC = $8.000

PVC = $10.000 x 30% = $3.000

Earned Value and Cost Performance

Page 59: Earned Value fundamentals

Project Week10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 320804�01�02�03�04 03 0401 02 05 06 07 09

planned

baseline$3.000

$8.000$10.000

15m40m

50m10m

AC= $3.000

EV = $10.000 x 20% = $2.000

EAC = $11.000

PVC = $3.000

AC = $3.000

EV = $2.000

BAC = $10.000

ETC = $8.000

PVC = $10.000 x 30% = $3.000

Don’t forget that our activity is already underperforming.

The ETC and EAC reflect the current status of the activity/project. However, at this point they don’t

include the cost of delay or underperformance.

Identifying the cost variance between the AC and EV enable us a more realistic picture of the

activity performance at the current time period.

Page 60: Earned Value fundamentals

Project Week10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 320804�01�02�03�04 03 0401 02 05 06 07 09

planned

baseline$3.000

$8.000$10.000

15m40m

50m10m

AC= $3.000

EV = $10.000 x 20% = $2.000

EAC = $11.000

PVC = $3.000

AC = $3.000

EV = $2.000

BAC = $10.000

ETC = $8.000

PVC = $10.000 x 30% = $3.000

Cost Variance (CV) = EV - AC

CV = $2.000 - $3.000 = $-1.000

CV = $-1.000

Page 61: Earned Value fundamentals

Project Week10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 320804�01�02�03�04 03 0401 02 05 06 07 09

planned

baseline$3.000

$8.000$10.000

15m40m

50m10m

AC= $3.000

EV = $10.000 x 20% = $2.000

EAC = $10.000

PVC = $3.000

AC = $3.000

EV = $2.000

BAC = $10.000

ETC = $7.000

PVC = $10.000 x 30% = $3.000

CV = $-1.000

Which is the relationship between the AC and the EV?

Cost Performance Index (CPI) = EV / AC

CPI = $2.000 / $3.000 = 0.67

Page 62: Earned Value fundamentals

Project Week10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 320804�01�02�03�04 03 0401 02 05 06 07 09

planned

baseline$3.000

$8.000$10.000

15m40m

50m10m

AC= $3.000

EV = $10.000 x 20% = $2.000

EAC = $10.000

PVC = $3.000

AC = $3.000

EV = $2.000

BAC = $10.000

ETC = $7.000

PVC = $10.000 x 30% = $3.000

CV = $-1.000

Which is the relationship between the AC and the EV?

Cost Performance Index (CPI) = EV / AC

CPI = $2.000 / $3.000 = 0.67

In simple terms, for each dollar spent, only 0.67 worth paying!

CPI = 0.67

Page 63: Earned Value fundamentals

Project Week10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 320804�01�02�03�04 03 0401 02 05 06 07 09

planned

baseline$3.000

$8.000$10.000

15m40m

50m10m

AC= $3.000

EV = $10.000 x 20% = $2.000

EAC = $10.000

PVC = $3.000

AC = $3.000

EV = $2.000

BAC = $10.000

ETC = $7.000

PVC = $10.000 x 30% = $3.000

Earned Value and Schedule Performance

CV = $-1.000 CPI = 0.67

Page 64: Earned Value fundamentals

Project Week10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 320804�01�02�03�04 03 0401 02 05 06 07 09

planned

baseline$3.000

$8.000$10.000

15m40m

50m10m

AC= $3.000

EV = $10.000 x 20% = $2.000

EAC = $10.000

PVC = $3.000

AC = $3.000

EV = $2.000

BAC = $10.000

ETC = $7.000

PVC = $10.000 x 30% = $3.000

CV = $-1.000 CPI = 0.67

As with the CV, we want to identify and compare the work planned to perform within a time period

with the work accomplished.

The Schedule Variance (SV) will provide us with the right information. It is expressed in in

monetary values.

SV = EV – PV

SV = $2.000 - $3.000 = $-1.000

SV = $-1.000

Page 65: Earned Value fundamentals

Project Week10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 320804�01�02�03�04 03 0401 02 05 06 07 09

planned

baseline$3.000

$8.000$10.000

15m40m

50m10m

AC= $3.000

EV = $10.000 x 20% = $2.000

EAC = $10.000

PVC = $3.000

AC = $3.000

EV = $2.000

BAC = $10.000

ETC = $7.000

PVC = $10.000 x 30% = $3.000

CV = $-1.000 CPI = 0.67

SV = $-1.000

How the Planned and the Earned Value are related?

Schedule Performance Index (SPI) = EV / PV

SPI = $2.000 / $3.000 = 0.67

Page 66: Earned Value fundamentals

Project Week10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 320804�01�02�03�04 03 0401 02 05 06 07 09

planned

baseline$3.000

$8.000$10.000

15m40m

50m10m

AC= $3.000

EV = $10.000 x 20% = $2.000

EAC = $10.000

PVC = $3.000

AC = $3.000

EV = $2.000

BAC = $10.000

ETC = $7.000

PVC = $10.000 x 30% = $3.000

CV = $-1.000 CPI = 0.67

SV = $-1.000

How the Planned and the Earned Value are related?

Schedule Performance Index (SPI) = EV / PV

SPI = $2.000 / $3.000 = 0.67

SPI = 0.67

Page 67: Earned Value fundamentals

Project Week10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 320804�01�02�03�04 03 0401 02 05 06 07 09

planned

baseline$3.000

$8.000$10.000

15m40m

50m10m

AC= $3.000

EV = $10.000 x 20% = $2.000

EAC = $10.000

PVC = $3.000

AC = $3.000

EV = $2.000

BAC = $10.000

ETC = $7.000

PVC = $10.000 x 30% = $3.000

CV = $-1.000 CPI = 0.67

SV = $-1.000

CPI, SPI rule:

CPI > 1 more work done than what actually paid for. CPI = 1 you got exactly what you paid for.CPI < 1 less work done than what actually paid for.

SPI > 1 - ahead of schedule. The work accomplished is more that the work planned.SPI = 1 - the work accomplished is exactly the work planned.SPI < 1 - behind schedule. The work accomplished is less than planned.

SPI = 0.67

Page 68: Earned Value fundamentals

Reporting Earned Value

Page 69: Earned Value fundamentals

Reporting Earned Value

Now that we know what Earned Value means, how it’s used and why

it can make a big difference in a project, we need to know how to

present and report data.

Page 70: Earned Value fundamentals

Reporting Earned Value

Now that we know what Earned Value means, how it’s used and why

it can make a big difference in a project, we need to know how to

present and report data.

Tables and diagrams help to communicate the message clearly and

can be used in meetings for decision making.

Page 71: Earned Value fundamentals

Reporting Earned Value

Now that we know what Earned Value means, how it’s used and why

it can make a big difference in a project, we need to know how to

present and report data.

Tables and diagrams help to communicate the message clearly and

can be used in meetings for decision making.

The Earned Value data are reported cumulatively.

The cumulative data represent a comprehensive project picture as they incorporate the overall project performance up to date.

Page 72: Earned Value fundamentals

Project Week10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 320804�01�02�03�04 03 0401 02 05 06 07 09

planned

baseline$3.000

$8.000$10.000

15m40m

50m10m

PVC

AC

EV

BAC:

Activity: Lay 50m of ducts

Week 1

ETC

CV

$10.000

$3.000

$3.000

$2.000

$8.000

$11.000

$-1.000

SV $-1.000

EAC

35m

$9.000

The first reporting period (week 1) we have the following results:

Back to our example

Page 73: Earned Value fundamentals

Project Week10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 320804�01�02�03�04 03 0401 02 05 06 07 09

planned

baseline$3.000

$8.000$10.000

15m40m

50m10m

BAC:

Activity: Lay 50m of ducts

Week 1

$10.000

35m

$9.000

1

0.5

1.5

0.67

0.67

CPI SPIW1

The first reporting period (week 1) we have the following results:

PVC

AC

EV

ETC

CV

$3.000

$3.000

$2.000

$8.000

$11.000

$-1.000

SV $-1.000

EAC

Page 74: Earned Value fundamentals

Project Week10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 320804�01�02�03�04 03 0401 02 05 06 07 09

planned

baseline$3.000

$8.000$10.000

15m40m

50m10m

BAC:

Activity: Lay 50m of ducts

Week 1

$10.000

35m

$9.000

1

0.5

1.5

0.67

0.67

CPI SPIW1

The second reporting period (week 2) the activity performance is:

PVC

AC

EV

ETC

CV

$3.000

$3.000

$2.000

$8.000

$11.000

$-1.000

SV $-1.000

EAC

Page 75: Earned Value fundamentals

Project Week10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 320804�01�02�03�04 03 0401 02 05 06 07 09

planned

baseline$3.000

$8.000$10.000

15m40m

50m10m

PVC

AC

EV

BAC:

Activity: Lay 50m of ducts

Week 1 Week 2

ETC

CV

$10.000

$3.000

$3.000

$2.000

$8.000

$11.000

$-1.000

$8.000

$9.000

$7.000

$3.000

$12.000

$-2.000

SV $-1.000 $-1.000

EAC

35m

$9.000

1

0.5

1.5

0.67

0.67

CPI SPIW1

The second reporting period (week 2) the activity performance is:

Page 76: Earned Value fundamentals

Project Week10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 320804�01�02�03�04 03 0401 02 05 06 07 09

planned

baseline$3.000

$8.000$10.000

15m40m

50m10m

PVC

AC

EV

BAC:

Activity: Lay 50m of ducts

Week 1 Week 2

ETC

CV

$10.000

$3.000

$3.000

$2.000

$8.000

$11.000

$-1.000

$8.000

$9.000

$7.000

$3.000

$12.000

$-2.000

SV $-1.000 $-1.000

EAC

35m

$9.000

1

0.5

1.5

0.670.78

0.67

0.87

CPI SPIW1 W2

The second reporting period (week 2) the activity performance is:

Page 77: Earned Value fundamentals

Reporting Earned Value

When reporting Earned Value, consistency is everything!

Only when the reporting periods are relevant you can get

meaningful reports!

Page 78: Earned Value fundamentals

Thanks for attending

EVM Fundamentals!

Denise Fotopoulou