Earned Value Techniques

download Earned Value Techniques

of 21

Transcript of Earned Value Techniques

  • 8/22/2019 Earned Value Techniques

    1/21

    Earned Value Techniques

    forProject Cost Control

    Dr. Robert Monson

    University of St. Thomas

  • 8/22/2019 Earned Value Techniques

    2/21

    Copyright 2001 R.J.Monson

    Earned Value Concepts

    Earned Value (EV) is a cost managementtechnique where the value of completed

    work is compared to actual costs and the

    scheduled costsEarned Value is expressed in terms of $s,

    so that completed work can be compared to

    actual costs and spend plans

  • 8/22/2019 Earned Value Techniques

    3/21

    Copyright 2001 R.J.Monson

    Earned Value Calculations

    EV is calculated by multiplying an estimateof the task percent completeby the totalestimated cost for that task

    Example5 week long task costing $10,000Task reported as 37% complete

    Value of work completed =>.37*10,000 = $3,700

  • 8/22/2019 Earned Value Techniques

    4/21

    Copyright 2001 R.J.Monson

    Why use Earned Value?

    Consider a project where you are running at$90,000 or 90% of spend plan. In traditional

    reporting you would consider yourself

    under budgetIf the earned value of that work is $80,000,

    and the spend plan says $90,000, you would

    realize you are over budget as well asbehind schedule

  • 8/22/2019 Earned Value Techniques

    5/21

    Copyright 2001 R.J.Monson

    Example

    Task 1

    Budget of $10,000

    Estimated to be 40% complete

    We have spent $5,000 based on accounting

    We thought we would spend $3,000 by this date

    What is the status of this task?

    Overrun (Because EV is $4,000 vs. $5,000)

    Ahead of Schedule (Because EV is $4,000 vs. $3,000)

  • 8/22/2019 Earned Value Techniques

    6/21

    Copyright 2001 R.J.Monson

    Metrics for Cost Control

    Cost Variance

    CV = BCWP ACWP = EV ACWP

    Difference between work completed and actual costs

    This is where you are on the tasks vs. $s chart

    Schedule Variance

    SV = BCWP BCWS = EV BCWS

    Difference between work completed and work

    scheduled

    This is your monetary burn rate

  • 8/22/2019 Earned Value Techniques

    7/21

    Copyright 2001 R.J.Monson

    Metrics for Cost Control

    Cost Variance IndexCV% = CV/BCWP

    Ratio of work completed to $s spent

    Schedule Variance IndexSV% = SV/BCWS

    Ratio of work completed to work planned

  • 8/22/2019 Earned Value Techniques

    8/21

    Copyright 2001 R.J.Monson

    How do we normally evaluate projects?

    Tasks

    Time

  • 8/22/2019 Earned Value Techniques

    9/21

    Copyright 2001 R.J.Monson

    Evaluating Status

    Tasks

    Time

    37% Complete

  • 8/22/2019 Earned Value Techniques

    10/21

    Copyright 2001 R.J.Monson

    Budget Status

    $

    Time

  • 8/22/2019 Earned Value Techniques

    11/21

    Copyright 2001 R.J.Monson

    Project Evaluation

    We cant really define whether we are onSpecification

    Our Gannt chart doesnt really tell us whether we

    are on ScheduleWe need to know the Budget curve to define if we

    are spending at the correct rate

    Therefore:We typically are considering the wrong variables!

  • 8/22/2019 Earned Value Techniques

    12/21

    Copyright 2001 R.J.Monson

    Project Evaluation

    We have to discover what we are really

    interested in

    Whether the work is getting done close to

    estimateWhether the work is progressing as planned

    Do we think we can finish on Spec, Schedule

    and Budget

  • 8/22/2019 Earned Value Techniques

    13/21

    Copyright 2001 R.J.Monson

    Task Evaluations

    Tasks

    $

  • 8/22/2019 Earned Value Techniques

    14/21

    Copyright 2001 R.J.Monson

    Task Evaluations

    Tasks

    $

  • 8/22/2019 Earned Value Techniques

    15/21

    Copyright 2001 R.J.Monson

    Task Evaluations

    Tasks

    $

  • 8/22/2019 Earned Value Techniques

    16/21

    Copyright 2001 R.J.Monson

    Budget Evaluations

    Time

    $

  • 8/22/2019 Earned Value Techniques

    17/21

    Copyright 2001 R.J.Monson

    Consider some examples

    We must look at both pieces of information

    in conjunction to get the whole picture

    We need to know if we are:

    Getting the work done for the right priceGetting the work done on schedule

    From this information we define status

  • 8/22/2019 Earned Value Techniques

    18/21

    Copyright 2001 R.J.Monson

    Tasks

    $

    Time

    $

  • 8/22/2019 Earned Value Techniques

    19/21

    Copyright 2001 R.J.Monson

    Tasks

    $

    Time

    $

  • 8/22/2019 Earned Value Techniques

    20/21

    Copyright 2001 R.J.Monson

    Tasks

    $

    Time

    $

  • 8/22/2019 Earned Value Techniques

    21/21

    Copyright 2001 R.J.Monson

    Project Evaluation

    Consider the Earned Value of Tasks

    To define if the work is truly getting completed

    Consider the Cost Variance

    Are we getting the work done for the moneyestimated?

    Consider the Schedule Variance

    Are we spending at the appropriate rate to stayon schedule?