Earned Value
-
Upload
katie-benson -
Category
Documents
-
view
2 -
download
0
description
Transcript of Earned Value
Page 2
SCHEDULE & COST VARIANCE
PROJECT NAME JIMMA UNIVERSITY UNIVERSITY KITTO FURDISSA .
SITE/BLOCK Site All
1. SCHEDULE VARIANCE
SITE Cost Variance (BCWP-ACWP) Cost-Schedule Index (CSI)=(CPI)x(SPI)
1 Site 01 932,909.00 834,578.67 796,992.49 (98,330.33) 37,586.18 1.05 0.89 0.94
2 Site 02 813,631.00 505,770.28 490,999.88 (307,860.72) 14,770.40 1.03 0.62 0.64
3 Site 03 1,103,205.98 169,308.00 203,531.11 (933,897.98) (34,223.11) 0.83 0.15 0.13
Machinery cost - - 182,379.42 - (182,379.42)
Total 2,849,745.98 1,509,656.95 1,673,902.90 (1,340,089.03) (164,245.94) 0.90 0.53 0.48
REPORTING PERIOD: FROM YEKATIT 19.2004 TO YEKATIT 25.2004
Item No.
Budgeted Cost of Works Scheduled (BCWS)
Budgeted Cost of Works Performed (BCWP)
Actual Cost of Works Performed (ACWP)
Schedule Variance (BCWP-BCWS)
Cost Performance Index (CPI)(CPI)=(BCWP)/(ACWP)
Schedule Performance Index (SPI) (SPI)=(BCWP)/(BCWS)