Table of Contents
PRELIMINARY SITE WORKS..............................................................................................1Factors Affecting the Choice of a Site .....................................................................................1
Reasons for Stripping and Clearing a site ................................................................................4
Purpose of Hoarding................................................................................................................5
Laying Out of a Small Building ...............................................................................................7Purposes of Temporary Shelter .............................................................................................. 11
The Building Site .............................................................................................................. 11Reasons for Temporary Services ........................................................................................... 14
THE MANUFACTURING OF PORTLAND CEMENT...................................................... 16Portland Cement .................................................................................................................... 16
Characteristics of different Types of Cement ......................................................................... 16
The five common types of cement ..................................................................................... 16
Notable Behaviour of Concrete ............................................................................................. 17Characteristics of Aggregates ................................................................................................ 18
Requirements of Aggregates .............................................................................................. 18
Types of Aggregates .......................................................................................................... 18Importance of Proportioning or Batching ............................................................................... 19
The total weight of water in the concrete ............................................................................... 20Some common mixes ............................................................................................................ 20
PROPERTIES OF PLASTICS .............................................................................................. 21
TIMBER AND TIMBER PRODUCTS.................................................................................. 23
Softwood and Hardwood Trees ............................................................................................. 24Softwoods ............................................................................................................................. 24
Hardwoods ............................................................................................................................ 25Conversion of Timber ........................................................................................................... 26
Seasoning of Timber ............................................................................................................. 27Moisture content ................................................................................................................... 28
Timber Defects ...................................................................................................................... 29Wood Preservation ................................................................................................................ 32
Production of Manufactured Boards ...................................................................................... 33Lumber Classification ........................................................................................................... 35
FOUNDATIONS..................................................................................................................... 37Types of Foundations ............................................................................................................ 37
Excavation and Timbering ..................................................................................................... 44Types of excavations ......................................................................................................... 44
Reduced Level Excavation...................................................................................................... 44
Trench and Pit Excavations.................................................................................................... 44Types of Excavation Machines .......................................................................................... 45
Timbering to Excavation........................................................................................................ 47
Precautions.............................................................................................................................. 51WALLS.................................................................................................................................... 52
Definition .............................................................................................................................. 52Categories of Walls ............................................................................................................... 52
Functional Requirements for Walls ....................................................................................... 52
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
2/107
Types of Walls: ................................................................................................................. 52
Definition of a Scaffold ......................................................................................................... 59Two Main Systems of Shoring .............................................................................................. 63
Functional Requirements ....................................................................................................... 65Categories of Floors .............................................................................................................. 65
Floor members ...................................................................................................................... 68
Important Steps in Constructing a Timber Floor .................................................................... 73
ROOFS.................................................................................................................................... 74Definition: ............................................................................................................................. 74
Functional Requirements ....................................................................................................... 74Factors Determining Roof Shape & Design ........................................................................... 74
Roof Classifications .............................................................................................................. 74Types of Roofs ...................................................................................................................... 74
Advantages of using Roof Trusses ......................................................................................... 78Parts of a Roof ...................................................................................................................... 79
Technical Words for Parts of a Roof ...................................................................................... 79Truss Types............................................................................................................................. 80
DOORS.................................................................................................................................... 80
Types of Doors ...................................................................................................................... 81
Door Ironmongery ................................................................................................................. 84
Door Dimensions .................................................................................................................. 85
WINDOWS.............................................................................................................................. 86Functions of Windows ........................................................................................................... 86
Building Regulations for Windows ........................................................................................ 86Technical Terms for parts of a window and frame: ................................................................ 86
Types of Windows ................................................................................................................ 87Some common terms associated with Stairs ........................................................................... 90
Building Regulations regarding Stairs ................................................................................... 90
FINISHES................................................................................................................................ 92
Rendering .............................................................................................................................. 92Plastering .............................................................................................................................. 92
Types of paints ...................................................................................................................... 93Properties of Paints and Varnishes ......................................................................................... 94
Methods of Application ......................................................................................................... 94The Purpose of Solvents ........................................................................................................ 94
RELATED SERVICES........................................................................................................... 97The Principles of Plumbing Pipes .......................................................................................... 97
Methods of Jointing and Fittings ........................................................................................... 97The Combine System of Drainage ......................................................................................... 99
The Separate System of Drainage .......................................................................................... 99
The Principles of Drain Runs............................................................................................... 100
THE BUILDING TEAM AND BUILDING TRADES........................................................ 103The Building Team ............................................................................................................. 103
Various Building Trades ...................................................................................................... 104HISTORY OF BUILDINGS................................................................................................. 105
Factors Influencing Building Designs .................................................................................. 105
Influence of Other Culture on Local Building Styles ........................................................... 105
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
3/107
1
PRELIMINARY SITE WORKS
Factors Affecting the Choice of a Site
ZoningZoning is the legal identification of land for a specific use. The general categories of
zoning are:
1. Residential2. Commercial
3. Industrial4. Agricultural
Zoning helps to assist land developers or owners in recognizing land for use as well asprovide information about the character of the neighbourhood. Lands within a zone may carry
different unit cost.
Land useThe owner or client must be sure that the land can be used for the intended purpose.
Although an area might be appropriately zoned, specific plots of lands may have certainrestrictions placed on them as a result of buried services or proposed development, e.g. roads,
gas lines etc.
OwnershipThis is certified by a deed (legal document) which must be established before any final
decision is taken regarding any purchasing of land. Ownership transfer can only be madebetween the rightful owner and the purchaser.
BoundariesBoundaries must be established and supported by a survey drawing before the actual size
of the property can be ascertained. This task is usually carried out by a legal chartered surveyor.
Boundaries are normally marked in such a way that they can be easily identified or re-established. References for markers are called Datum- Points.
Topography
Topography is the shape of the surface of the land. This shape is sometimes referred toas contour and can be classified as follows:
- flat-
undulating
-
gently sloped- steeply sloped
Access
All lands not immediately adjoining a street or public pathway requires some means ofaccess. This access influences movement on and off site during the construction stages as well
as during normal occupancy. Where the possibility of trespass exists, access should be legallyestablished and be adequate.
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
4/107
2
ShapeWhen purchasing a piece of land, the shape of the land should reflect the proposed shape
of the structure within the framework of the legal restrictions. Examples of problems commonlyencountered with lands are:
1. Too narrow
2.
Corners may be too acute or there may be too many corners.
reinforcing steel
street possible buildinglimiting
position
(a) Narrow Lot
legal limits
(b) High unusable Land Space owing to anumber of and sharpness of corners
Size
Minimum sizes of building lots are usually specified in order that:- Legal requirements of setback and off set distances are satisfied
- The building should occupy the maximum percentage of the total land area as specifiedby the authorities for the prescribed zone.
- A reasonable sized building is produced.
HistoryHistory is the study of past events associated with the use of the site. Historical issues
that should be of concern to the purchaser are:1. Water- whether a natural water course, springs or flooding are associated with the s ite.
2. Dump- whether the site was ever used as a dump.3. Original topography- whether the land was ever filled.
4. Other problems e.g.
o Whether trees were recently removed to accommodate development or
o Underground lines such as electric, gas or telephone.5. Development- This is a measure of clearing and preparation activities associated with a
site. It may also indicate the availability of services to the site.
Unit Cost
Unit cost is the price per metre or foot of the land. Unit cost is normally associated with:1. Level of development
2. Available amenities3. Available Services
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
5/107
3
4. Location5. Zone
6. Demand7. Topography
Amenities refer to the degree of comfort associated with the location, and are related to theavailable utilities, health and educational facilities as well as other features such as publictransport, shopping centres and recreation facilities.
Location may influence the unit cost by providing certain advantages such as prevailing winds,scenic views and general neighbourhood.
Sloping sites
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
6/107
4
Reasons for Str ipping and Clearing a site
Stripping
This is the removal of the topsoil from the construction area. This area is usually strippedto a depth of 150 mm, using a bulldozer.
Stripping helps to provide a sound level platform as well as the removal of vegetablematter as well as the removal of termitesnests.
Soils containing high levels of vegetable matter tend to:1. Support plant life
2. Be very unstable3. Affects some building materials
Clearing
Clearing is not necessarily part of stripping but for undeveloped sites, clearing isessential. Trees which sometimes obstruct the building process, those found to be in the way and
at a time obstruct the flow of traffic and must also be removed. The roots that would pose a
problem to the building process or even affect the foundation must be removed as well.Other obstacles like derelict buildings should be removed, because they too hinder the
building process and can cause problems with the foundation.
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
7/107
5
Purpose of Hoarding
Hoarding is a part of the temporary facility installed on a construction site. Its primary
function is the enclosure of the construction area to serve as a form of protection to passers by.This enclosure has other purposes and is developed accordingly.
Public Protection
The local authority has the responsibility for the protection of the public against injuryduring any construction work. As such, there are laws requiring the installation of hoarding,
particularly where pedestrian traffic is common. Hoarding should provide protection from thevertical side and overhead as well as permit or provide adequate lighting and ventilation if
required.
SecurityThe construction site must be secured, especially during evenings, on weekends and
public holidays.
Material ProtectionHoarding is an ideal way of ensuring some degree of protection against theft and
vandalism of materials and installations.
Control
The control of the movement of workers and avoidance of unwanted interruptions anddistractions assist in increasing productivity. All activities should be carried out with
minimum inconvenience. The movement of supply vehicles and receipt of goods shouldbe planned and controlled at all times.
To keep out stray animals
It is important that stray animals be kept off of the construction site since they can causedisruptions to the building works as well as harm to the workers.
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
8/107
6
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
9/107
7
Laying Out of a Small Building
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
10/107
8
Building LayoutThe Setting out of a building can be divided into two specific operations:
Establishing a datum peg and transferring required levels to various positions
Establishing the position of the building and setting up profiles (batter boards)
Establishing the position of the building and setting up profilesThe basic requirements for establishing the position of a building are linear measurement
(length), the setting out of right angles and the setting out of curves.
Linear MeasurementA 30m steel tape is most often used for setting out; linen or plastic tape should be
avoided as they are likely to stretch, and this could result in serious errors. If steel tapes are notfully stretched out they can give inaccurate readings. Wherever linear measurements are made
the tape should be held horizontal. For sloping sites the possibility of error is far greater. Forslightly sloping grounds pegs of different lengths may be used. For steeper slopes the tape is held
horizontally and the measurement is plumbed down to the peg.
Setting out AnglesRight angles can be set out using any one of the following methods:
1. Using a builders Square2. Using Pythagorass3:4:5 rule
3. Using Site square
Setting out CurvesThe methods used to set out a curve will depend on its size and whether its centre point is
accessible or not.
The four main methods are:1. Timber template
2. The radius Rod3. Triangular frame
4. Calculated ordinates
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
11/107
9
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
12/107
10
Layout Procedures for a Small BuildingIt is essential to obtain a working drawing of the proposed building before any work is
started. After careful study of this, the builder can then proceed with the layout of the building.
The procedures for setting out a small building are as follows:
1. The building line is established with reference to the setback distance from the centre lineof the road. The line is established by driving in 50mm x 50mm softwood pegs A and B
on or near the side boundaries. Position a nail in the top of the pegs to represent the exactposition of the building line. Strain a line between these two nails.
2. Drive two pegs C and D along the building line to indicate the front corners of thebuilding and with reference to the side setbacks as indicated on the Working drawing.
Drive nails into the top of the pegs to indicate the exact position of the corners on thebuilding line.
3.
Set out lines at right angles to pegs Cand Dand establish pegs E and F. Drive nails into
the tops of pegs E and F to indicate the exact positions and strain lines between the four
pegs.4.
Measure along lines CE and DF to establish pegs Gand H, the remaining corners of the
building.Check lines should be used at this point to determine the accuracy of the layout and adjustments
made where required.
Profile boards can now be set up just clear of the trench runs at all corners and wall intersectionsof the building. Ensure that there is adequate clearance space between the position of the trench
and profiles to prevent obstruction to profiles due to excavation procedures. Transfer positionsfrom the setting-out lines on the pegs to the profile boards. Step-off all trenches and block wall
widths and drive nails in these positions. Saw cuts can be used as an alternative to nailing.Lines can be strained on the nails to indicate trench width and block wall width when
excavation and blocks are to be layed.
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
13/107
11
Purposes of Temporary Shelter
The Building Site
Site Preparations
Before any preparation work can commence the Building regulation/code should bechecked. This is necessary to ensure that the building (commercial or residential) to be erected
complies with the standards laid out in the code. There are zoning laws to be adhered to as theyrelate to:
1. The building line
2.
Distance Separation3. Lot line4. Premise
5. Property Line6. Setback
7. Do a check on the Site Deed8. Obtain a Building Permit
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
14/107
12
The Building Line-This is a legally determined boundary that no part of the building can cross.
Distance Separation-This describes the amount of open space between buildings. Open spacehelps to keep fire from spreading from one structure to another and enable good ventilation.
Lot/Property Line- A surveyed and recorded boundary (or monument) that separates one pieceof property from another. In essence, it is the legal boundary that marks a lot or parcel ofproperty.
Premise-A term used to describe collectively a piece of property as well as any buildings or
structure on it.
Setback-This is the open space required between a building line and the street centre line. Itcould also be used to describe the distance between the sides of a building the lot or rear
boundary lines of a property.
Site InvestigationThe purpose of a Site Investigation is to determine beforehand:
Existing trees and buildings on the property or adjacent property
Details such as full data of existing services or the lack of it
Contour lines- natural grade elevations
Details of above ground obstruction such as transmission lines
Topography of the site and existing fording (water running underground)
Sewer system availability or the lack of it
The geographic location (with respect to the orientation)
Required Security and Staffing
Layout(General site conditions such as soil nature, height of water table, flooding risks, andneighbouring properties, among others).
These factors will to a large extent help the builder in the design and construction processesof the proposed work.
Soil Investigations
Determines the suitability of the site for the proposed project
Determine an adequate and economical foundation design.
Determine the difficulties that may arise during the construction process and period.
Determine the occurrence and /or causes of all changes in subsoil conditions
Site Preparation Principles
In Site Preparation the builder will require operatives, materials and plant, which must becarefully controlled so that the operatives have the right machines in the most advantageous
positions, the materials stored in such a way that will allow for easy access and little or nointerference with site circulation, and adequate storage space and site accommodation.
When Planning the Site Layout the following must be taken into consideration:
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
15/107
13
1. Site activities;2. Efficiency;
3. Movement;4. Control ;
5. Facilities for health, safety and welfare provision, and
6.
Accommodation for staff and storage of materials.
Usually before the proposed site is planned and drawn the prevailing conditions should
be considered these are; the condition and positions of existing roads and the setting out of anytemporary roads considered necessary should be noted and planned. Information regarding the
soil conditions, height of water table and local weather patterns should be obtained preferablyfrom the meteorological office or from the local authority.
Temporary Shelters
These are required on a building site for the housing of personnel, services, processes and
materials for the expediting and control of building works, and to cater for illness and accidents
among workers. Consideration should be given to the following:
Statutory RequirementsThe construction site is under the control of the factory inspectorate and as such should
carry provisions for amenities to workers. Amenities usually include a change room, a lunchroom and sanitary facilities.
Activity Areas
Offices: Normally for large projects site offices and briefing rooms are provided to assist in thedaily administration of the project.
Workshops:Carpenters, steel benders and some other tradesmen require workshop facilities to
assist in their work. Workshops should be so located as to ensure good control and effectivehandling of materials.
StorageWarehousing: Warehouses are normally required for storage of delicate components and
fittings. Items normally stored in a warehouse include doors, windows, ceramic receptacles,light fittings, electrical and plumbing appliances etc.
Tools and Equipments Stores: Tradesmen are usually required to carry and secure their own
tools. The main contractor, for special processes may find it necessary to carry a supply ofspecial tools and equipment which would be available to workmen. The store may also carry
other items that can only be had on special issue. Some of these items are paints, locks and smalltools. Such stores are controlled by a storekeeper or a timekeeper.
Material Stores:Material stores may be provided to protect materials from theft or damage. The
material stores are usually close to the appropriate workshop or activity area. Such stores wouldcarry materials such as reinforcing steel, rough lumber and cement. Special provisions must be
made to ensure that materials are not spoiled or damaged during storage and handling. Inaddition, brittle materials such as tiles require provisions.
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
16/107
14
Reasons for Temporary Servi ces
Temporary services relate to the provision of utilities for the purpose of facilitating
construction activities as well as providing conveniences for workers. The supplies normallyinclude gas, water, compressed air, electricity and telephone.
Conveniences
These include conveniences for personnel and work process.
Personnel: Provision under the factories act allows for provision of certain conveniences forworkers. Temporary services assist in the provision of drinking water, adequate lighting andtoilet facilities. Drinking water and toilet facilities should be positioned for quick access thus
reducing idle time.
Work processes:Utilities supplied to the site can be used to drive (power) plant and equipmentor provide ingredients for preparing certain materials.
Examples of supplies used for driving plant and equipment are:A. Air- Pneumatic tools and equipment
B. Oil and Gas- Turbine and hydraulic tools and equipmentC. Electricity- electric tools and equipment
Heat, water and air are used in the following processes:1. Heat- asphaltic processes
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
17/107
15
2. Water- making concrete3. Air- Spray painting, excavating, compacting
Communication
Communication includes physical and verbal contact between the agencies and processes
during the life of the project. Factors to be considered in communication are temporary roads foraccess to the site and storage areas, as well as possible telephone or two way radio contacts forplacing orders and dealing with routing administration and contingencies which are important.
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
18/107
16
THE MANUFACTURING OF PORTLAND CEMENT
Cement is a substance that binds aggregates together into a very dense material that possessesgreat compressive strength.
Portl and Cement
Portland cement is used in the manufacturing of concrete and mortar. It may also be used
as a bed for clay and cement tiles. Ordinary Portland Cement is made by mixing ground chalk orlimestone and clay with water to form a semi-liquid mixture, or slurry. Local materials such as
shale may be used instead of clay in the manufacturing of Portland Cement. The slurry isscreened and is passed into a storage tank where it is kept agitated in preparation for passage into
a kiln, which is a rotating cylinder, approx. 90 meters long, inclined at an angle and fired bypulverized coal or oil.
The slurry is fed into the upper end of the kiln and flows down to the direction of theheat. As the kiln revolves, it dries the slurry. Water evaporates under this intense temperature
heat (raised to about 1500 Celsius) fusing the materials into a clinker or cement noodles. Theclinker is cooled and ground to a fine powder. A small amount of gypsum is added to retard thesetting time of the cement.
Characteristics of different Types of Cement
Portland Cement is the most commonly used cement since it hardens rapidly. There areseveral other cements that can be used for special purposes.
The ratio of Portland Cement to aggregates varies with the strength requirements for theconcrete. Additives may be put into the mixture or cement to enhance the strength or provides
additional qualities such as quicker drying, waterproofing, resistance to sulphate corrosion etc.During the manufacturing of cement, various chemical components are produced. This
compound which influences the properties and behaviour of the cement includes:(1)Strength Development:
(2)Setting Time and Heat ProductionBy varying the components, the properties can be modified. These properties can
influence the ability of the cement to resist sulphate attack, which is the rate at which cementssets and heat is produced.
Some types of cements are low heat (used for concreting large masses) and some high heat (forcold weather conditions).
The five common types of cement used in construction are Types 1, 2, 3, 4, 5
Type 1- NormalThis type is ordinary Portland Cement. It has normal qualities, a reasonable setting time
and is used for general concrete work, when conditions are normal. Such example include:
masonry work, filling of pockets, and ordinary strip foundation.
Type 2ModerateThis type of cement gives off less heat than type 1, and has a moderate resistance to
sulphate. It is suitable for use in foundations where there are low levels of sulphate but
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
19/107
17
offers good resistance to soils with high sulphate level such as those adjacent to chemicalplants.
Type 3 - Low Heat
This type is ideal for use in mass concrete work, such as large foundations or dam
retaining walls. It develops strength slowly and generates less heat, thus reducingcracking.
Type 4 - High Early Strength/Rapid HardeningThis type is used when the weather is bad (rainy season), or when formwork has to be
removed early. It develops strength earlier than types 1 and 2.
Type 5AluminiumThis type contains aluminium ore. It is darker in colour than Normal Portland Cement. It
hardens very rapidly and has great strength.
Notable Behaviour of Concrete
Climatic conditions can influence the setting time of concrete and its used. For
maximum strength development, concrete should be wetted down for 28 days.
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
20/107
18
Characteri stics of Aggregates
Aggregates generally make up the bulk of the concrete. These are available in fine and
coarse grades. For mortar the size of aggregates is very small ranging from 0-4mm, and forgeneral concrete work the size varies from 5-20mm.
Requirements of Aggregates
All aggregates should be:
clean
free from sediments
sound
strongnot easily crushed
well graded
well shaped
Types of Aggregates
Coarse Aggregate
GravelThis consist of small pieces of stone which are somewhat rounded in shape. It makes
good coarse aggregate because it is hard and closed textured. When using gravel as a coarseaggregate the pebbles should be graded in size. (Source= gravel banks, river beds).
Crushed Stones Trap rock is the hardest and most durable stone that can be crushed and usedfor making concrete. This stone is dark, heavy and close-grained, and is of igneous origin.
Granite makes good crushed stone and is less expensive than trap rock. The stone should begraded in sizes 6mm-20mm.
Fine AggregatesFor concrete work these are sand, crushed stones or gravel screening. The most important
of these is sand. Sand is a fine divided material of rock which will pass through a standard 5mm
sieve. Sand is not subjected to disintegration, decay or expansion.
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
21/107
19
Importance of Proporti oning or Batching
Proportioning aids in determining the strength, durability, permeability, workability and
economy of the concrete. Proportioning is essential to ensure a good mix.
Batching is the determination of the exact amount of each ingredient that is placed into aspecific concrete mix.
The following are some results of Batching.
Strength In order to obtain maximum strength, the aggregates must produce little or no
voids in the concrete. This increases the density of the concrete thus increase its strength.Economy Cost is a major factor in concrete work. Cost is influenced by careless use of
ingredients. The most costly ingredient is cement. A poor mix often increases the cost of thejob or reduces the strength of the concrete.
WorkabilityThis is the ability of the wet concrete to be placed and worked with ease. Thisproperty is enhanced by the correct proportioning of the cement and aggregates and water-
cement ratio.
Volume Batching
This is generally used but it is a less accurate method of mixing concrete. A measuringbox is used to determine the amount of cement and aggregates. A change in the moisture
content will impact upon the volume of the materials and affect the quality of the concrete.
Figure 2 showing a diagram of a Gauge or Measuring Box
Batching by Weight
In this method the materials are measured by weight. This is a more reliable system ofbatching than that of volume. Variation in volumes owing to compacting is eliminated when
using this method.
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
22/107
20
Water
The water used in the making of concrete must be clean and free from impurities which
could affect the quality of the concrete. A proportion of water will set up a chemical reaction thatwill harden the cement. The rest is required to give the mix workability and will evaporate from
the mix while it is curing. An excess amount of water will give a porous concrete or reduceddurability and strength.
The water/cement ratio is the amount of water used in the mix and is expressed as:
The total weight of water in the concrete
Weight of cement
For most mixes, the ratio is between 0.4 and 0.7. Concrete mixes can be expressed as volume
ratios, thus:1:2:4= 1 part cement 2 parts fine aggregates and 4 parts coarse aggregates
1:5 = 1 part cement and 5 parts all in aggregates
Some common mixes
1: 10= not a strong mix but it is suitable for filling weak pockets in excavation and for binding
layers1:8 = slightly bettersuitable for paths and paving
1:6 = a strong mix suitable for mass concrete
1:3:6= the weakest mix
1:2:4= the strongest mix suitable for reinforced concrete
Concrete is a mixture of fine aggregates, coarse aggregates, cement and water that possessesgreat compressive strength.
Mortaris a mixture of cement, sand and water in definite proportion.
Slump test
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
23/107
21
PROPERTIES OF PLASTICS
Plastic is one of the new building Materials being widely used in the Building Industryand for Domestic Purposes. Such purposes include: - plumbing, electrical fittings and sanitary
appliances. Plastics are usually by products of Petro-Chemicals.
Plastics are usually:-
light weight
easily handled
durable
strong for their weight
readily adapted to various situations
Properties of Plastics which make them suitable for usage in Construction Work are:
1. strong2. light weight
3.
durable4. pliable/flexible
5. easily joined6. glazable
7. elastic8. water proof
9. rust proof10. cheap/economical11. soft
Some disadvantages of plastics and precautions to be observed in their use are they:
Can be easily damaged if not properly protected
Have a low melting point
Are easy to crushed under weight
Must be supported when suspended
Have poor chemical resistance to thinners and solvents
Becomes brittle under continuous exposure to variations of weather
Types of Plastics Application
1. Thermo-Plastics Conduits, pressure and non-pressure pipes
2. Polyvinyl Tiles, mouldings
3. Polythene Sheeting, bags
4. Nylon Ropes, coverings, garments
5. Thermo-setting Resins
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
24/107
22
Uses of Plastics in the Building Construction Industry are:1. Electrical Installation; Conduits, fittings
2. Plumbing3. Guttering
4. Tiles/Floor Finishes
5.
Waterproofing; Damp Proof Membrane, drains6. Roofing
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
25/107
23
TIMBER AND TIMBER PRODUCTS
Bark - Every species of tree has its own bark which is a means of identification. Thebark is the outer layer of a tree that protects it. Without it the tree cannot survive.
Cambium layer - This is the growing part of the trunk. Here new cells are constantly
developing. Some becoming bark while others become wood.
Medullar Rays- Food is distributed to all parts of the tree by means of these small cells. Thesewood cells grow in length radially and can be easily seen in oak, beech, and mahogany.
Annual Rings - The age of the tree can be determined by the counting of these rings, as each
ring represents one year of growth.
Pith or Medulla- This is the core of the tree. It may be sound or solid, but in many cases it isfilled with a cork like substance. It has a dark, brown colour.
Sapwood - Light coloured outer concentric rings of woody tissue that is found next to the
cambium. It contains only a few living cells and functions mainly in the storage of plant food.
Its thickness varies from 13mm to as much 150mm in some species.
Heart wood - The inner concentric rings of woody tissue which consists of inactive cells.
These cells of heartwood may contain many minerals which contribute to its darker colour, greatbeauty and resistance.
Bast-The channel that is found between the cambium layer and bark which transport food from
the root to the leaf.
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
26/107
24
The tree can be regarded as one of natures gift to man. It provides food, shelter and fuel.The tree is a living organism, the components parts performing specific life functions.
Timber is the oldest building material. The growth process of certain species encouragesthe production of various by-products.
To those studying botany a tree is just another plant. To the carpenter and the joiner it is
the plant which produces the material with which he is mainly concerned namely wood or(timber). The growth of a tree is affected by the soil and by the climate in which it grows.
Softwood and Hardwood Tr ees
Commercial timbers are classified into soft woods and hard woods. The most common
method of identifying them is by their leaf. Soft woods have narrow needle like leaves where ashard woods have a broad leaf.
Sof twoods
Soft woods (gymnosperms) are not all soft; some soft woods are very hard e.g. Yew,
pitch pine strong and durable. Soft woods are all for practical purposes, derived from a group oftrees called conifers. Coniferous trees are mainly evergreen and grow chiefly in the northern
cold to temperate zone. Soft woods comprise about 75% of the timber used in the U.K.Soft woods are non- flowering and have needle shaped leaves and naked seeds contained in
cones, their branches normally arises in whorls with more than two at the same level. Even afterthe tree is converted, most lumber can be easily identified as hard wood or soft wood. Conifers
are simpler and more uniformed in structure than broad leaved trees. They have mainly one typeof cell, the tracheid. These cells appear as regular rows of holes, with the cells formed during
spring and summer (wet seasons) having thin walls and those formed during autumn and winter
(dry seasons) have thick walls. It is this difference in the formation of cells that indicates ayears growth or annual rings.Soft woods main features include:
1. They have an open grain texture, which is easier to work on than hard wood.2. They have a lighter colour than hard wood.
3. They do not shed their leaves seasonally.4. Their leaves are usually needle or cone shaped.
5. They grow quite quickly.6. The timber produced needs to be protected from the weather by applying paint, varnish or
preservatives.7. They need to be protected from insect attack.
Examples of soft woods are:
Douglas firWestern red cedar
Pitch pineWhite pine
Red woodRed pine
Sugar pineSouthern pine
Yellow pineCaribbean Pine
Alaska cedarHonduras cedar
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
27/107
25
Hardwoods
Hard woods (angiosperms) are not all hard, some hard woods are very soft e.g. balsa.Most hardwoods are deciduous or broad-leaved trees. Hard woods include densest, strongest,
and most durable timbers. Some hard woods contain resins and oil which interfere with thehardening of paint such as teak. The cheapest hard woods approximate in cost to the more costly
soft woods.Hard woods can be recognized by their broad leaves on their branches which usually
grow out at different levels, at the most two at the same level. These trees produce flowers fromwhich their seeds come enclosed in a fruit. These trees grow in cool to tropical climates and may
be deciduous or evergreen.Hard woods unlike soft woods have a more complex structure with mainly two distinct
cells. One type is fibrous and similar to the tracheid and the other type is known as vessel orpore cells. The latter appears as pores or holes in the end grain, and as vessel lines on
longitudinal surfaces.Cell structure in both soft woods and hard woods affect the grain, texture, density and
figure in these woods. The grain in soft wood is generally straight, the texture is fine and the
figure is plain to pleasing. In hard woods, the grain may be straight, sloping or interlocked. Thetexture is fine to coarse because of the size and arrangement of the pores and the figure plain tohighly figured. These are dense hard boards and more difficult to work with tools.
Hard woods main features include:
1. They are harder to work with hand tools than soft wood trees.2. They are darker in colour or have distinctive colours.
3. They shed their leaves seasonally.4. They are slow growing and cannot be cultivated.
5. They are more expensive to use for timber.6. They are selected for decorative appearance.
Examples of hard woods are:
MahoganyTamarind
TeakMora
Green heartBullet wood
Satin woodMahoe
Crab wood
WallabaCedarOak
BirchBeech
Balsa
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
28/107
26
Conversion of T imber
Conversion is the process of cutting up timber in marketable sizes. It is a commonfeature that decorative cuts are made during conversion. The two general methods of selling
lumber are plain sawing, (flat or slash sawing) and quarter sawing.
Plain Sawing
The log is slabbed on either two or four sides to form a cant from which other plainsawed lumber is cut. Plain sawed lumber has several advantages over quarter sawed:
1. More lumber is produced when grain figures are not considered.
2. It dries more rapidly.3. It is cheaper to cut.
4. It has lower unit cost.
Plain sawing (1,2,3,4) and quarter sawing (5,6)
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
29/107
27
Quarter Sawing
Quarter sawing can be done any of four methods: radial, tangential, combined radialtangential and quarter tangential.
Quarter sawing has the following advantages:1. Fewer tendencies to warp or twist.
2. Fewer tendencies to cut or twist.3. Less shrinkage.
4.
More durability strength.5. More attractive grain pattern.
6.
More rapid kiln drying.
It is used in the manufacture of high class joinery, furniture and quality work. It wears moreevenly when used as flooring.
DisadvantageThe method of conversion is time consuming and produces much waste.
Seasoning of Timber
Timber cannot be used for carpentry and joinery immediately after it is converted, since
there is a lot of moisture present in the wood. A large portion of this sap must be removed, ifdistortion resulting from shrinkage is to be avoided. The process of moisture removal from thewood is called seasoning. This can be done in either one of two ways: natural or artificial terms
known also as curing or conditioning. It is realized that, the lower the moisture content in thewood the greater its strength.
Natural Seasoning
After conversion, the wet timber is stacked with strips of wood, usually of the same kind,or stickers separating each layer. This allows proper circulation of air which removes the
moisture. A suitable roof is needed to protect the timber from sun and rain. Air seasoningreduced the moisture content to about 17% under ideal conditions and even takes up to two
years. The moisture content must be in equilibrium with that of the atmosphere. The weatherand thickness of the material will vary the length of time required for seasoning. End splits may
be controlled by tacking on straps or metal or wood, or by putting paint wax or oil on the ends ofthe boards.
Advantages
- High quality of lumber.
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
30/107
28
Disadvantages
- Length of time, limited availability of large quantities.- May be more costly
- Needs more space for drying- No control over drying process.
Artificial Seasoning
Artificial seasoning has improved greatly and the kiln which is the storage house for itcan now be completely computerized to control the drying process even without attendance or
human inspection. Accurate moisture content readings are readily available at any time. Thematerials are stacked in a similar manner of that of the natural.
Advantages
-
Relatively short time- Early use of material
- May result in greater availability and reduced cost.- Some wood worms are destroyed by the heat
- Moisture content can be controlled to as low as 12%
Disadvantages- Case Hardening
- Rapid drying can cause it to check or become honey combed.
Moisture content
When a tree is felled it contains a great deal of moisture. The timber will need to havesome moisture content, whatever its commercial use is to be. The purpose of drying the timberis to minimize the subsequent movement when it is used; which means, different uses demands
different moisture content levels. The timber for internal use should have lower moisture contentthan timber which is used externally. This is because internal timber would be reduced by the
warmth of the atmosphere. This can cause excessive shrinkage and possibly other more seriousdefects.
Moisture content is always expressed as a percentage of the dry weight of the timber.The formula used to calculate this formula is:
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
31/107
29
Wet weight- Dry weight x 100
Dry weight= moisture content (%)
A sample of timber is cut and weighed. This is the wet weight. It is placed in a kiln 100C andtaken out at intervals until no further weight is loss. This is the dry weight. A piece of timber
weighs 132.5gIts dry weight is 108.7g
Moisture content weighs 23.8g% of moisture (23.8/108.7) x 100= 21.9%
Example:
132.5- 108.723.8 x100
108.7= 21.9%
Timber Defects
A defect is a fault in the timber that will result in some reduction in strength, appearancewhich is usually cause by natural elements during growth or during conversion and seasoning
which could and should be avoided.
Natural defectsKnots are caused by branches growing out of the tree in which case the grain in the tree
trunk becomes twisted. Forest grown tree usually have less knot because of lack of sunlight.The branches always start at the centre of the tree at the pith.
Sound Knots
They will not fall out of the position they occupy but they tend to crack. This allows theinlet of fungus to attack the wood. Provided that they are not too large or close to the edge they
dont posed a problem.
Dead KnotsThese are a source of real weakness, whatever is the size. They are produced when a
branch is broken off before the tree is finish growing. The tree starved this broken off part of thetrunk causing it to die. It is identified by a very dark colour around the decayed knot, making it
liable to fall out eventually leaving a knot hole. Such a timber is classified as low grade and isunsuitable for structural use.
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
32/107
30
Shakes- Take the form of splits in the wood and detracts from its strength quite considerably.
Heart Shake- These occur in the heart wood of a tree when it is left too long after it has maturedbefore being felled for use. It is due to lack of food.
Checks-These are separation of the wood fibres along the grain. They usually occur along the
ends of lumber. In artificial seasoning checks are caused by rapid drying.
Ring Shake- These follow the contour of the growth ring. They usually result fromexcessive
swaying of the tree in high winds bringing about separation of the fibres.
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
33/107
31
Cup Shake- These are brought about by similar conditions as ring shakes, but without results.
They also position themselves in the growth rings.
Star Shake-These are fine cracks in the appearance of a star as a result of the sun drying up thecellular tissue, when the bark has been damaged or when the timber has been season too quickly.
Dry Rot-This is caused by a fungus (merious lacrymans) a growth which lives in the wood and
destroys it. It thrives on wood in dark, damp unventilated conditions causing it to dry up anddisintegrate into dust.
Wet Rot- Wet rot (cellar) fungus attacks only wet timber, and is found in damp, poorlyventilated cellars. The disintegration of timber is due to exposure to alternate wet and dry
weather which is favourable conditions for growth of fungus.
Up Sets- This is a form of shake, the cause of which is uncertain. The effect of it is in a zigzagcrack across the grain, where the affected boards are likely to snap very easily under little
pressure. Probable causes are:1.
The tree being struck by lightning during growth.
2.
The tree falling awkwardly when felled causing a fracture to run through the log.
Bowing- This often results when the boards are stacked with too much distance between the
sticks.
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
34/107
32
Warp- This is any distortion from the true form and may include any one or a combination of thefollowing: cup, bow, twist. This is caused by the exposure to the elements and poor stacking in
the process of seasoning and usage.
Cupping
Spring Twist
Wood Preservation
Timber for construction work should be treated in order to increase its ability to resistfungal and insect attack. Insects break down the cellular structure of the wood and destroy its
strength and appearance. Timber being exposed needs to be protected.Timber preservation is costly, extending to the life of the timber. Preservation is cheaper in long
term.Some preservatives, such as creosote are used exclusively underground or in roofs where
the material will not be visible. Other types have pleasing effects, example: Cuprinol, Atlas Awhich change the colour of the wood to a light green.
Application requires some care since preservatives are highly toxic and others may attack theskin.
There are three groups of preservatives:
1.
Tar- oil type2. Water solution type
3. Organic solvent type
Tar-oilThese preservatives are distilled from coal tar. Creosote is probably the best know. They
are very efficient but have a strong odour. This can be done by steeping or can be brushedon,where the lumber becomes saturated after a period of time. It becomes resistant to insect attack
and moisture penetration.
Water Solution
Water is used as a vehicle to take the chemical into the timber and afterwards it evaporateleaving the chemical to fight off attack from sodium fluoride, zinc chloride and copper sulphatesolutions which are commonly used as preservatives but are odourless and can be painted over
quite easily.
Organic SolventsThis can be done as non-pressure and pressure impregnation.
Pressure Treatment
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
35/107
33
This is done by forcing liquid Wolman Salt under pressure into the timber- this ensures
better penetration.
Non-PressureBrushing- A suitable material is brushed on the lumber. This is a simple process but slow to
allow the liquid to soak in.
Spraying- This is used in areas difficult to get into, such as roof spaces. It is much quicker andeffective than brushing while using a spray gun.
Dipping- The timbers are submerged in a bath of preserving liquid for 5-15 minutes. Excess
preservatives are allowed to drain into the bath which can produce fairly good results.
Steeping- Similar to dipping, however, the timbers are left submerged for at least (2) weeksespecially with solution types of preservatives.
Production of M anufactured Boards
Ranges of sheet material are widely used in woodworking and building industries. Some
are made from solid timber while others are made from low-grade timber. Standard size forbuilding boards is 1220 x 2440 mm. Thickness varies according to use.
1 laminboard
2 core3 blockboard
4 battenboard5 cellular board, cellular plywood
6 composite board7 hardwood plywood
8 mixed plywood9 softwood plywood
10 multi-ply11 crossbanding
12 star formation13 parallel-grain plies
14 single layer chipboard, standard grade chipboard15 multilayer chipboard
16 peg board, perforated hardboard
17 hardboard
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
36/107
34
PlywoodPlywood is one the most extensively used boards which is made up of an unequal number
of sheets and veneers called plies. Three- ply plywood consists of three veneer of equalthickness glued together with the centre or core veneer, having its grain running at right angles to
the outer veneers. This gives it considerable strength. It has extensive uses which may includepanelling and lining as well as other forms of covering. The grade is usually stamped on the
board by the manufacturer and these must be recognized when deciding the usage of the board.
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
37/107
35
Int - Denotes for internal use only and indicates that is has been glued together with glue having
low moisture resistance. If such timber is exposed to moist conditions there would a separationof the veneers.
MR - Fair resistance to moisture.
BR- High resistance in exposed conditions because it is boil resistant.
WBP- Indicates that it is weather and boil condition and also in the boat building industry.
Laminated Panels
These panels are constructed of thin layers of material glued together to form specialeffects. These panels will resist warping and shrinkage.
Hard Boards
This is yet another of the wood waste product. Hard board are made from wood chipsand logs. The wood is pulped by machine, and bonded with adhesive and finally pressed to a
thickness of 3mm- 6mm. With such a thickness they usually have a width of 1.2m. With lengths
of 2.43 m. Their usage includes panelling, wall and floor covering.
Bagasse BoardBagasse is the residue left after milling cane during the manufacture of sugar. The
material is crushed to a pulp, mixed with adhesive and compressed with a heat treatment. Thisresults in a hard durable board suitable for interior work.
Chip Board
This board makes use of machine chips of wood, glued and compressed into large sheets.The core section consists of larger chips than the surface. A disadvantage is that it is unable to
take a screw. It is used for cheaper range of furniture as well as wall coverings.
Lumber Classif ication
Lumber is sold by standard cubic measurement, board measure.Any size over 30mm and 100mm is boards. (31mm thick and 100mm wide)
37mm thick is planks
Measurement in length is called linear.Measurement in length and breadth is called square measure.
Measurement in length, breadth and thickness is called cube measure.
N- Number of pieces in stock.T- Thickness in mm.
L- Length in metre.
Note:- 1 inch=25.44mm
- 1 foot = 304.8mm- 1 metre = 3.281ft
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
38/107
36
Formula to calculate board in m is:
Foot board measure 10 pieces of 2 x 6 x 120
= 10 x 2 x 6 x 12 012
= 120 FBM
L (M) x W mm x T mm = m31000 1000
If L = 5m W = 175mm T= 5mm
Then volume of board or lumber =
5 x 175 x 251000 1000
= 0.02m3
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
39/107
37
FOUNDATIONS
The purpose of the foundations is to adequately transfer the load of a structure to suitableground and to spread building loads over a sufficient area of soil to avoid undue settlement,
particularly unequal settlement.
Foundations should meet the following requirements;
(1) Building loads must be supported and transmitted to the ground,
(a) safely; transmit and sustain to the ground the total dead and imposed loads so asnot to cause any settlement or(b) without causing deflection or deformation of the building;
(c) without affecting adjacent buildings.(2) They must be of such depth or be so constructed as to avoid damage by shrinkage of the
subsoil.(3) They must be capable of resisting chemicals in the sub-soil.
The explanation of common terms associated with soils in foundation work is given below:
Settlement: Ground movement, which may be caused by:
(a) deformation of the soil due to imposed loads.(b) volume changes of the soil as a result of seasonal conditions.
(c) mass movement of the ground unstable areas.
Made Ground: Refuse, excavated rock or soil deposited for the purpose of filling in adepression or for raising the site above its natural level.
Bearing Pressure:The pressure produced on the ground by the loads.
Bearing Capacity:Safe load per unit area which the ground can carry.
Back Fill: Lateral excavated from site and if suitable used to fill in around the walls andfoundations.
Sub-Soil:Sub-soil lies below the topsoil to a depth about 300 mm.
Types of Foundations
The types of foundations normally used in construction include strip, raft, short bore pileand pad. Various types of foundations are used in domestic buildings. The type of foundationsselected depends main~ on two factors:
(1) The total load of the building ("liveand "dead" loads).
(2) The nature and bearing capacity of the subsoil.(3) The design of the building.
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
40/107
38
Strip Foundation:
The majority of domestic structures have a strip foundation in which a continuous strip ofconcrete provides a continuous support under load-bearing walls. This type of foundation is
composed of plain concrete usually to a mix 1: 3: 6 volumes (1 part cement, 3 parts sand 6 partscoarse aggregate). The thickness of the foundation must not be less than the projection (P) and in
no case less than 150 mm. Reinforcement bars are sometimes used in small domestic building.These bars strengthen the structure, and make it less vulnerable to earth tremors.
Strip Foundation
Wide Strip Foundation
Where the load bearing capacity of the ground is low, as for example marshy ground, softclay and made-up ground, wide strip foundations may be used to spread the load over a large
area of soil. It is usual to provide transverse reinforcement in the base of the footing to withstand
tensions that will arise. This is usually placed near the bottom of the footing. The depth belowground level should be the same as for normal strip foundations. All reinforcements should belapped at the corners and junctions.
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
41/107
39
Deep-strip Foundations
These foundations are used in shrinkable clay soils (to reduce the cost of normal stripfoundation) in depths of 900 mm or more, and to counteract the variable soil conditions in
different seasons. In reducing the width of the foundation trench, the quantity of excavation,backfill and surplus, soil-.removal is also reduced. The deeper foundation also provides greater
resistance to fracture from unequal settlement (by increasing the load bearing strength of thesection).
Deep Strip Foundation
Raft FoundationRaft foundations cover the entire area of the building and usually extend beyond it. They
consist primarily of a reinforced concrete slab up to 330 mm thick, which is often thickenedunder load bearing walls. The level of the base of the raft is usually within 300 mm of the surface
of the ground and the reinforcement is often in the form of two layers of fabric reinforcement,one being near the top and one near the bottom of the slab.
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
42/107
40
The reinforcement helps to spread the loads and resist tensile stress, which could cause
cracking of the raft.Raft foundations are best suited for use on soft natural ground or fill, or on ground that is
liable to subsidence as in mining areas. The ground at the edge of the raft should be protectedfrom weather, which can cause erosion or slippage. This can be overcome by:
(1) Laying concrete paving around the building(2) Deepening the edge beam
(3) Laying a field drain in a trench filled with suitable fill as shown
Raft foundation
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
43/107
41
Stepped Foundation
On a sloping site the most economic procedure is to use a stepped foundation thusreducing the amount of excavation, back fill, surplus soil removal and trench timbering. The
foundation is stepped to follow the line of the ground and the depth of each step is usually 150 or225 mm (multiple of brick courses).
The lap of concrete at the step should not be less than 300 mm. The damp proof coursemay also be stepped in a similar manner. Where the slope exceeds one in tenth it is desirab1e to
use short bored pile to overcome the sliding tendency.
Stepped foundation
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
44/107
42
Short Bored Pile
Short bored piles were devised to provide economical and satisfactory foundations' forhouses built on shrinkable clay. They consist of a series of short concrete pile cast in holes bored
in the ground and joined or connected (for load bearing walls) by light beams usually ofreinforced concrete. They have several, advantages over strip foundations:
i. speed of constructionii. reduced quantity of surplus excavated soil
iii.
ability to proceed with construction in bad weatherProblems do, however, arise on stony sites or where there are many tree roots.
Holes are normally bored to a depth of 2.5 - 3.5 metres by hand or mechanically operatedauger keeping the holes vertical and on the centre 1ine of the beams. The depth will be
determined by the stability and bearing capacity of the clay.The piles, generally about 300-350 mm in diameter, should be cast immediately after the
holes have been bored. A mixture of 1:2:4 concrete is generally used. Short lengths 20 mmdiameter reinforcing bars should be set in the top of each corner pile and bent over to cast in with
the beams. The reinforced concrete beams often 300 x 150 mm' in section, are usually cast informwork, but in some cases are cast in trenches.
The placement of piles is influenced by the shape of the building, the load to be carried
and the load-bearing capacity of the piles. With load bearing walls, piles should be provided atcorners and junctions of walls, with intervening piles placed to give uniform loading and, as faras possible, to keep ground floor door and window openings mid-way between piles.
Short bored pile foundation
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
45/107
43
Pad Foundation
Pad foundations are isolated foundations designed to support columns. The area offoundation is determined by dividing the column load plus the weight of the foundation by the
allowable bearing capacity of the ground. The thickness of the foundation must not be less thanthe projection from the column (unless reinforced) and must, in any case I not be less than 150
mm. The size of foundation can be reduced by providing steel reinforcement towards the bottomof the foundation running in both directions.
Pad foundation
The area of the pad for a foundation may be calculated by determining the ratio of the load to the
bearing capacity of the soils under laying the structure.
Terminology
Three terms used regularly with foundation construction are explained.
Footing:offsets at the base of a wall to provide a greater bearing area.
Damp proofing: making waterproof by special materials or processes.
Hardcore:broken bricks block or stone consolidated as a foundation for concrete in solid floors.
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
46/107
44
Excavation and Timbering
Excavation WorksThe excavation for foundations follows after the setting or laying out the building and
fixing of profiles. Excavations take various forms depending upon the type foundation to be laid.Excavation
The term excavation means to hollow out. In building terms it means to remove earth to
form a cavity in the ground.The method of excavation can either be manual or mechanical. Manual excavation is,
used extensively on small domestic structures. The manual process requires hand tools such as
pick axe, shovel, digging bars, forks and wheelbarrows.
Types of excavations
1.
Over-site Excavation that involves the removal of topsoil up to 300mm deep.
2. Reduced Level Excavation which is carried out below the over-site level to form a levelsurface on which to build and can consist of both cutting and filling operations. The
level to which the ground is removed is called the formation level.3. Trench Excavations are narrow excavations that are primarily used for strip foundations
and buried services. Excavation can be carried out by either machine or hand.
Types of Trench Excavations
Battered faced
Vertical or straight faced
Battered Excavation Vertical/Straight Excavation
Reduced Level Excavation
This is necessary because very few sites are level in their natural state.On small sites the process is similar as for Site clearance. Bulldozers are used for cut and fill
operation and a mechanical shovel plus Lorries are used for cut only operations.
Trench and Pit Excavations
On small sites the hand process can be used but if the depth of excavation exceeds1.200m some method of removing spoil (soil) from the excavation will have to be employed. In
this event a trenching machine such as a Back actor could be employed.
Advantage: Advantage:
No temporary support is required to thesides of the excavation
Minimum amount of soil is removed andtherefore minimum of backfill is required
Disadvantage: Disadvantage:
It incurs extra cost for over excavating andextra backfilling
The sides of the excavation may requiresome degree of temporary support
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
47/107
45
Types of Excavation Machines
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
48/107
46
Typical excavation machines include:
1. Bulldozers2. Scrapers
3. Graders4. Tractor Shovel
5. Skimmer6. Face Shovel
7.
Back actor8. Dragline
9.
Multi-Purpose Excavators10.Trenchers
Mechanical- The bulk of major building projects is now performed. The principal machines are:
Dragline: A bucket dragged towards the machine, and it generally excavates below ground
level.
Face Shovel:This digs in deep faces above the level of its wheels or tracks.
Skimmer:This is used for shallow excavation up to 1.5 m deep and is particularly useful forlevelling and roadwork.
Drag Shovel or Back Actor:This digs below its own level and towards itself and is primarily
used for trench excavation.
Drag and Clamshell:This is for moving loose materials.
The Scraper:Operates like an earth plane and carries its scraping with it.
Bulldozer:This is used for, bulk excavation and grading.
Front End Loader and Back Hoe:This is for excavating and moving loose materials.
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
49/107
47
Timbering to Excavation
This is the term used to cover temporary supports to the sides of excavations and is
sometimes called planking and strutting. The sides of some excavations will need support to:
Protect the operatives while working in the excavation
Keep the excavation open by acting as a retaining wall to the sides of the trench.
The type and amount of timbering required will depend upon the depth and nature of thesubsoil, weather conditions, type of soil, and the duration of the operations.
Types1. Timbering in firm soils
2. Timbering in dry loose soils3. Timbering in loose wet soils
4. Timbering in hard soils
Safety
When excavating foundations and. drains in soil that is liable to fall away from the sidesof the trench, timbering should be used to prevent this (the soil from falling into the trench).
The builder must ensure all trenches are safely timbered or pile sheeted. Apart from the
death or injury, it will result in additional cost to the builder to re-excavate and new damagedwork in the trench should the sides collapse. Proper attention should be given to safety at all
times. The construction industry has a very high accident rate and everyone in the industry mustbe more safety conscious.
TimberingTimbering is the temporary support used at sides of trenches to prevent caving in. The
support given to sides of the trench depends upon the depth of the trench and the soil conditions.Weak soils will require more elaborate temporary support.
Terminology
Poling Boards: are vertical members that usually measure 175 mm x 31 mm x 1 m.
Walling Board: Horizontal members placed against the poling boards with cross sectionmeasurement 150 mm x 75 mm. The length varies.
Struts:Horizontal supports placed across the trench to hold the other members in position. They
are spaced at centres between 1.5 m and 2 m along the length of the trench and are usually 100mm x 100 mm in cross-section.
Wedges:Sometimes pairs of folding wedges are used between the walling boards and the strutsto take up slackness.
Types of Timbering
1. Open BoardingThis is used for moderately firm ground such as sandy gravel, soft dry chalk, clayey, gravel.
2. Poles and strutsThese are used for moderately firm ground, such as stiff clay, firm gravel and hard chalk. The
poling boards are spaced 1.829 m apart.
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
50/107
48
3. Close Boarding or Sheeting
This is used for unstable ground such as loose sand, wet soils and made up grounds.
Timbering in hard soils
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
51/107
49
Timbering in loose dry soils
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
52/107
50
Timbering in loose wet soils
Safety
Construction regulations state that:1. Heavy loads or machinery likely to cause the collapse of the sides must not be moved close to
the excavation.2. Open excavations must be fenced off to prevent persons falling into them.
3. Approaches to excavations must have warn1ng lights prominently d1splayed at night.4. No vibration likely to bring about collapse of the sides must be caused close to the excavation
Curing
When concrete is poured it begins to set/cure and as time passes it becomes solid, and atthe same time increases in strength.
The chemical reaction which accompanies the setting of cement and hardening ofconcrete is dependent on the retention of water is known as curing. Exposed concrete should
therefore be sprayed and covered with bubble plastic sheets or quilts of plastic with fibres orstraw or cement bags (sandbags), until it attains maximum strength (cures). To develop
maximum strength concrete requires the correct conditions and a certain minimum time,
depending on the temperature. Time ranges from 7 - 28 days for normal Portland cement.
PlacingAll form work should be checked, cleaned and oiled before concrete is placed against it.
Concrete should not be permitted to fall freely more than one metre. When transported by abarrow over rough ground segregation of the materials may occur as larger particles settle to the
bottom of the barrow. This will result in weakened concrete. To prevent or reduce this, usepneumatic wheels to help cushion the shock.
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
53/107
51
Precautions
1. The area of concreting should be free from all debris.2. The area of concreting should be washed.
3. The mixing bed should be as near as possible to concreting area.4. The approach of the concreting should be free from all obstruction.
5.
Oil the form work to allow ease of striking.6. Do not allow concrete to fall freely more than one metre.
7.
Use barrows with pneumatic wheels to reduce segregation of materials.
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
54/107
52
WALLS
Definition
This termrefers to a unit that is used to sub-divide or partition space.
It is also considered to be a unit that encloses a space thus giving it a degree of protection fromthe elements.
Categori es of Wall s
There are essentially two categories of walls namely:
Load bearing walls and Non-load bearing walls.
Load bearing Walls
These are walls that are designed to transmit imposed and super-imposed loads inaddition to their own weight to a suitable foundation. They can either be external or internal
walls.
Non-load bearing WallsThese walls are designed to accommodate their own weight in addition to fixings placed
on them. Most often these are used internally.
Functional Requirements for WallsA wall should be:
Fire Resistant;sound insulated;
weather resistant;thermally insulated;
design to accommodate fixings such as doors and windows or openings, anddesigned to safely transmit all loads encountered to a suitable foundation.
Types of Walls:
Rubble walls
Brick wallsParapet walls
Party wallsBlock walls
Cavity wallsTimber Framed walls
Dwarf wallsConcrete walls (In-situ and Prefabricated)
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
55/107
53
Brick walls
The materials used in the manufacture of bricks is clay or it may be from sand or limeand are available in a wide variety of strength, types, textures, colors, and special shaped bricks.
In the manufacturing process, the raw material (usually clay) is dug and then preparedeither by weathering or grinding before being mixed with water to the right plastic condition. It
is then formed into the required brick shape using a mould / form before being dried and fired ina kiln.
Bricks are generally manufactured to a length of 337.5mm, a width of 225mm and a height of112.5 mm.
However, the usual size of bricks for common use is 215 mm in length, width 102.5 mm and aheight of 65 mm where 10 mm of mortar joint thickness is added to 3 faces.
Bonding
This is an arrangement of bricks in a wall, column or pier laid to a set pattern to maintainan adequate lap. The bond is set along the length of the wall working from each end to ensure
that no vertical joint is above another in consecutive courses.
Purpose of Bonding
Bonding is required:To ensure that maximum strength is obtain whilst the load to be transmitted through thewall, column or pier is being distributed.
To ensure that there is lateral stability and resistance to side thrusts.To create an aesthetic (acceptable) appearance.
Types of BondsEnglish Bond
This bond is formed by laying alternate courses of stretchers and headers. It is one of the
strongest forms of bonding pattern used.
English bond details
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
56/107
54
Flemish Bond
This bond is formed by laying headers and stretchers consecutively in each course. It isnot as strong as English bond but is considered to be aesthetically superior.
Stretcher Bond
This bond consists of alternate courses of stretchers and is used extensively for block wallconstruction.
Stretcher bond details
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
57/107
55
Parapet Walls
This is a low wall projecting above the level of a roof, bridge or balcony forming a guardor barrier at the edge. Parapets may be exposed to the elements on three faces namely front, rear
and top and will therefore need careful design and construction if they are to be durable andreliable.
Party Walls
Party wall is an interior lot line used or adapted for joint service between two buildings.
Cavity Walls
These consist of an outer brick or block leaf or skin separated from an inner brick orblock leaf or skin by an air space called the cavity. These walls provide better thermal insulation
and weather resistant than block or brick wall. The two leaves of a cavity are tied together withwall ties at not less than 900mm width and vertical heights of 450mm.
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
58/107
56
Cavity wall details
Timber Constructed WallsTypes: -
Balloon FramedPlatformFramed
Members:-Foundation Footing, sill plate, sole plate, studs, Noggins, Top plate, wall plate, trimmer
stud, cripple stud, header, window sill.
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
59/107
57
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
60/107
58
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
61/107
59
Block walls
These are walling units exceeding in length, width or height the dimensions specified forbricks. They are made from a mixture of cement, sand and marl/crushed stone to specific
proportions.The size of blocks varies depending on their use, but the standard length is given as length 400
mm, width from 75 mm up to 215 mm and a height of 200 mm.Blocks suitable for external solid walls are classified as load bearing and are required to have a
minimum average crushing strength of 2.8N/mm2.
Block walls
CharacteristicsAdequate strength
Good insulationLow cost
Good load bearing capabilities
Block wallsThe core of blocks assumes more than 25% of its total area/volume. According to the
American Society for Testing and Materials (ASTM), blocks are graded based on compressivestrength and range from:
600 psi to be used above grade800 psi used for all exterior walls
Defin iti on of a Scaff old
These are three definitions of a scaffold:
1. A temporary platform either supported from below or suspended from above, on
which workers sit or stand when performing tasks at heights above the ground.2. A raised wooden framework or platform.3. A temporary structure of timber, boards, etc., for various purposes, as for
supporting workmen and materials in building.
Suspended Scaffolds
Supporting outrigger beams must be able to support 4 times the intended load. To keep ascaffoldfrom falling to the ground, it must be attached to the roof, tied to a secure anchorage, or
secured with counterweights. The suspension ropes and rigging must support at least 6 times theintended load.
1. Counterweights must be attached to secure and strong places on a building so they
wont move.2. Do not use bags of sand or gravel, masonry blocks, or roofing materials that canflow or move.
3. Do not use gas-powered equipment or hoists. A hoist must have an automaticbrake for emergencies.
4. A 1-point or 2-point suspended scaffold must be tied or secured to preventswaying.
-
7/25/2019 Building Technology Notes Form 4 2012-2013 New Edition
62/107
60
Independent Tied Scaffolds
An independent scaffold consists of a platform resting on horizontal tubes, usually calledtransoms, which are fixed at 90 to the face of the building and which are secured at both ends to
a row of uprights, or standards, and to horizontal tubes, often called ledgers, running parallel tothe face of the building. An independent scaffold, although it must be tied to the building or
structure, does not rely on it for its strength.
Working platforms and gangwaysThe scaffold boards which make up a working platform should rest squarely and evenly on
transoms to prevent the risk of tripping. Where the ends of boards meet, transoms must bedoubled and so spaced that no board overhangs by more than four times its thickness. Too much
overhang will cause the board to tip if you step on it, while too little less than 50 mm willmean that it is easily dislodged. Normally, each board should have three supports to prevent it
bending or sagging. The space between the edge of the working platform and the face of t