BTS Site Installation

24
BTS Site Installation (Training Material) Prepare By:-Neeraj Kumar Sharma Date:- 31-August-2010

Transcript of BTS Site Installation

Page 1: BTS Site Installation

BTS Site Installation (Training Material)

Prepare By:-Neeraj Kumar Sharma

Date:- 31-August-2010

Page 2: BTS Site Installation

Types Of Installation:

Contents:

Types Of Installation

Indoor Installation

Outdoor Installation

Page 3: BTS Site Installation

Indoor Installation:

Indoor Cable Tray

Grounding Bar

Battery Bank Installation

SMPS Installation

BTS Installation

Connection of Power Cable

Page 4: BTS Site Installation

Installation Of Indoor Cable Tray:

Indoor Cable tray types-

Wall mounted

Roof Mounted

Page 5: BTS Site Installation

Some Basic Things for the cable tray installation:

Grounding of cable tray with IGB (Internal Grounding Bus Bar).

Distance between cable tray & roof of shelter is Depends on the dimension of Hatch plate.

Cable tray should right below the hatch Plate.

Drills are made on the shelter walls or roof to provide support for Horizontal Cable Tray.

After marking the drilling holes, the ladder is fixed using supporting clamps.

Cable Tray forms a major part of installation work since all the Grounding,Power,E1,IF & RF Cable routing is done over this Cable tray.

Page 6: BTS Site Installation

Cable Tray forms a major part of installation work since all the Grounding,Power,E1,IF & RF Cable routing is done over this Cable tray.

Page 7: BTS Site Installation

Grounding Bar Installation:

There are two types of grounding bars-

External Grounding Bar (EGB)

Internal Grounding Bar (IGB)

Page 8: BTS Site Installation

Some Basic Things for Grounding Bar installation:

EGB and IGB both are installed right below the hatch plate, and both are connected to each other by double connection of 35 mm square grounding cable.

EGB (External Grounding Bar) is directly connected by the Earth Pit by the GI strip.

IGB (Internal Grounding Bar) which is installed inside the shelter room, this is made up of GI strip.

EGB (External Grounding Bar) which is installed on the out side of shelter, This is totally made of Copper strip.

Every indoor equipment should be grounded through IGB.

Then crimp and fix the Lugs at both ends of above these three types of cables & wrap with insulating tape with same color of cable.

Grounding resistance of working ground, Protection ground and lightening arrester should be not more than 5 Ω. (Recommended range 0.5 Ω to 5Ω for working ground &1-5 Ω for protection ground).

Page 9: BTS Site Installation

Battery Bank Installation:

In Telecom BTS site 48 volt DC battery bank installed. there are 24 cells in each Battery Bank each is having the 2 volt DC. These battery bank are installed on stand and grouted in the shelter properly.

These battery bank have certain distance from the SMPS and we should try to keep O/P of each terminal is in opposite direction of SMPS.

Grounding of Battery bank is done with the IGB by the 35 mm square grounding cable & connected to EGB (Internal Grounding Bar).

Page 10: BTS Site Installation

SMPS INSTALLATION:

SMPS is installed nearby the Shelter Door.

Battery bank directly connected with the SMPS.

SMPS is the DC supply source by which all the equipment inside the shelter is connected like BTS and MW Rack.

It charges the battery bank by the AC supply, There are modules which converts AC supply to DC supply.

In absence of AC supply it gives the supply by Battery Bank to equipments.

It Should be grounded on two points One is on positive bus bar and one is with the body of SMPS with the 35 mm square grounding cable.

Page 11: BTS Site Installation

SMPS GROUNDING:

Positive Bus bar grounding Body grounding

Page 12: BTS Site Installation

BTS Installation:

The BTS installation position should be consistent and must be as per shelter layout design.

Now mark the position of BTS base bolts position at ground & do the grouting of Bolts.

Then fix base of BTS into grouted bolts also check the leveling.

BTS, Microwave rack, DDF box and all the equipment except power equipment are installed on the same side right in front the power equipments.

BTS should be grouted properly.

Page 13: BTS Site Installation

SURGE ARRESTER INSTALLATION:

Surge arrester are high frequency protector, these surge arrester protects the BTS from the lightning. These surge arrester fix on the surge arrester stand and this surge arrester stand grounded with EGB.

Surge Arrester StandSurge Arrester Stand Surge ArresterSurge Arrester

Page 14: BTS Site Installation

JUMPER CABLE CONNECTION ON BTS:

Jumper cable connects on the BTS top.

All feeder of three sector connects by the jumper cable.

Feeder connects by the jumper via Surge Arrester.

Page 15: BTS Site Installation

Power cable connection On BTS:

BTS power cable blue one connects with the negative bar which is right in front the SMPS via the particular rating of fuses. And positive bus bar connect with black wire of BTS terminal. This negative blue cable connects with the negative terminal of BTS and black one connects with the Gnd of BTS.

Page 16: BTS Site Installation

Out Door Installation:

GSM Antenna Installation on the Tower.

Feeder cable Installation and routing.

Earthing of Feeder cable.

Connection of Jumper cable to Feeder on GSM antenna end.

Connection of Jumper cable to Feeder on BTS end.

Page 17: BTS Site Installation

GSM Antenna Installation on the Tower:

GSM Antenna installed on the tower according to the RF plan.

The orientation (Azimuth) of the GSM antenna should be according to network plan.

GSM antenna also have the tilt by which the coverage area can be increased or decreased, it is also according to plan.

Tilt may be zero, two, three or four degree.

GSM antenna clamp should be tightened on the tower properly, it should be not loose.

Page 18: BTS Site Installation

Feeder cable Installation and routing:

Feeder cable ( 7/8”) connects with the BTS and GSM antenna. It is connected with BTS and GSM antenna via the Jumper cable. Feeder cable should be routed on the tower by Dummy clamp. In feeder cable installation feeder cable should not be bend more then 90 degree at

certain point.

Feeder cable routingFeeder cable routing Bending is not more then 90 degreeBending is not more then 90 degree

Page 19: BTS Site Installation

Feeder cable comes in the shelter and before entering in the shelter it takes a “U” drop. Due to this U drop the water do not go inside the shelter. So we must take care about this U drop just before the entrance in shelter.

U drop of FeederU drop of Feeder

Page 20: BTS Site Installation

GROUNDING OF FEEDER CABLE:

• Feeder cable should be grounded on three points. Two on the tower and one with the EGB.

• Grounding is very necessary and it must be on three points.

• Grounding is done by the Grounding kit and it should be properly shield with weather proof.

Page 21: BTS Site Installation

Connection of Jumper cable to Feeder on GSM antenna end:

.

Weather proofing on GSM Weather proofing on GSM and jumper cable on Towerand jumper cable on Tower

• Feeder cable connects with GSM antenna by the jumper cable .

• Connection should be very tight and shield with weather proof.

• Weather proof should be properly done, if it is not proper then this may be on of the reason of VSWR.

Page 22: BTS Site Installation

Connection of Jumper cable to Feeder on BTS end:

Feeder cable connect with BTS by the jumper cable.

Between jumper and feeder surge arrester should be connected

Feeder CableFeeder Cable

Surge Arrester StandSurge Arrester Stand

Jumper cableJumper cable

Page 23: BTS Site Installation

Precaution:

Connection of each power cable should be proper.

Before switching on the BTS we should check the Input voltage on the BTS terminal by the Multimeter, If it is ok then we should switch on the BTS.

We should visually check the Grounding connection of each equipment.

All equipments inside the shelter must be grouted.

At the time of connection of power cable to Battery Bank we must take care about the safety.

Page 24: BTS Site Installation