1-s2.0-S0263786304000808-main

download 1-s2.0-S0263786304000808-main

of 8

Transcript of 1-s2.0-S0263786304000808-main

  • 7/28/2019 1-s2.0-S0263786304000808-main

    1/8

    Appraisal of value engineering in construction in Southeast Asia

    Charles Y.J. Cheah a,*, Seng Kiong Ting b,1

    a School of Civil and Environmental Engineering, Nanyang Technological University, Block N1, #01b-35, 50 Nanyang Avenue, 639798, Singaporeb School of Civil and Environmental Engineering, Nanyang Technological University, Block N1, CACS-B1b-07, 50 Nanyang Avenue, 639798, Singapore

    Received 31 July 2003; received in revised form 9 January 2004; accepted 27 July 2004

    Abstract

    The concept of value engineering has existed for more than half a century. Its application in construction is credited with some

    success notably in public contracts in the United States. Nevertheless, value engineering is rarely applied in the Southeast Asian

    construction industry. A survey among industrial practitioners has been conducted to identify possible causes for the dire status.

    Generally, there is a lack of understanding in value engineering concepts among industrial practitioners and it is important for

    the government to take the lead in promoting value engineering practices in domestic projects. Moreover, the scope of value engi-

    neering can be broadened to address corporate-level systems and initiatives.

    2004 Elsevier Ltd and IPMA. All rights reserved.

    Keywords: Construction value system; Corporate-level initiatives, Target costing; Value engineering

    1. Introduction

    The origin of value engineering (VE) can be traced

    back to the days of World War II when there was a

    material shortage problem in the manufacturing sector

    due to an increased consumption for war purposes.

    Lawrence D. Miles, an electrical engineer who was then

    assigned to the purchasing department of General Elec-

    tric (GE), started finding ways to alleviate the material

    shortage problem in GEs production. To accommodate

    the constraint, he focused on functions that a product

    was meant to perform and experimented with alterna-

    tives to achieve the same functions without compromises

    in quality. Although the main emphasis was not costreduction, this came as a by-product. Initially named

    as value analysis by Miles himself, the program was de-

    signed to improve value without sacrificing intended

    functions on purpose [1]. This basic premise still under-

    pins todays concepts of value analysis, value engineer-ing and value management.

    The value analysis technique was subsequently intro-

    duced into construction by the US Navy and the Army

    Corps of Engineers circa 1963 through the adoption of

    incentive provisions and sharing clauses in construction

    contracts [2]. Over a short period, other public agencies

    in the US, such as the Department of Transportation

    and the General Services Administration, followed suit.

    Outside the US, value engineering practices and applica-

    tions were introduced in Japan, Italy, Australia and

    Canada all during the 1970s. Construction-oriented

    value engineers were also found in India, South Africa,England, France, Sweden and Germany [3]. Successful

    applications had been reported in many cases of con-

    struction projects [4]. Over time, the subject of VE em-

    braced other tools such as the job plan, the Functional

    Analysis Systems Technique (FAST), and even methods

    to nurture creative thinking (e.g., the Delphi Method).

    The legacy of Miles lives on when he is now widely

    regarded as the inventor of VE. One might also observe

    that VE has been developed and applied in various

    0263-7863/$30.00 2004 Elsevier Ltd and IPMA. All rights reserved.

    doi:10.1016/j.ijproman.2004.07.008

    * Corresponding author. Tel.: +65 6790 5267/4916; fax: +65 6791

    0676.

    E-mail addresses: [email protected] (C.Y.J. Cheah), cskting@

    ntu.edu.sg (S.K. Ting).1 Tel.: +65 6790 4916; fax: +65 6791 0676

    www.elsevier.com/locate/ijproman

    International Journal of Project Management 23 (2005) 151158

    INTERNATIONAL JOURNAL OF

    PROJECTMANAGEMENT

    mailto:[email protected]:cskting@mailto:cskting@mailto:[email protected]
  • 7/28/2019 1-s2.0-S0263786304000808-main

    2/8

    forms to cater for different industrial contexts. The gen-

    eric nature of VE makes it applicable to many types of

    projects ranging from buildings to water treatment

    works. Moreover, it is also suggested (at a later part

    of this paper) that the prospects of implementing VE

    in the corporate and systemic contexts are bright. In

    many ways, the inquiry of key functions furnished bya product or service system and the search for alterna-

    tive solutions beyond mere cost cutting remain central

    to these different forms of implementation. The list of

    advantages often extends beyond functional improve-

    ments, cost reduction and creative solutions, since

    implementation of VE potentially leads to more effective

    teamwork and improved communication among

    stakeholders.

    2. The outlook of VE in Southeast Asia

    While the picture is generally more positive else-

    where, concepts and applications of value engineering

    do not seem to be well embraced by the Southeast Asian

    (SEA) construction industry. In Japan, the birth of VE

    programs was marked by the visit of a Japanese delegate

    to the Society of American Value Engineers (SAVE) in

    1965 [1]. The active presence of large Japanese contrac-

    tors in SEA since the 1970s did not subsequently lead to

    a smooth introduction of VE to the region. One possible

    reason was a lack of knowledge transfer when local SEA

    subcontractors might have been excluded from the VE

    programs. Similarly, despite VEs presence in proximate

    countries such as Hong Kong and Australia, the SEAregion remains devoid of VE knowledge and practices.

    This is also indicated by the worldwide locations of

    the local chapters of SAVE International (formerly

    SAVE), whereby SEA local chapters are nowhere to

    be found. While Hong Kong has set up the Hong Kong

    Institute of Value Management (HKIVM) since 1995 to

    promote awareness and establish standards of value

    management in the city, similar efforts cannot be seen

    in Singapore, for example.

    The objective of the study outlined in this paper is to

    identify causes leading to limited VE application in SEA

    and highlight the real concerns among industrial practi-

    tioners. Findings from the study would help to structure

    future directions and also provide additional insights for

    other countries which are facing similar problems in

    promoting VE practices in their local construction sec-

    tors. It is realized that distinctions do exist between value

    engineering, value analysis and value management

    as defined by the British Standards [5,6]. Rightfully, va-

    lue management is a style of management applied at the

    corporate level while value analysis/engineering con-

    cerns application of tools and methods at the opera-

    tional level (project-oriented activities). Still, the

    context of this paper focuses on more general issues of

    VE application and such distinctions are less critical.

    For the sake of simplicity, only VE is referred through-

    out the paper.

    3. Data collection and research methodology

    A questionnaire survey was conducted among 54

    industrial practitioners who were attending a module

    in value engineering at the Nanyang Technological Uni-

    versity, Singapore. The module was only one component

    of a part-time Masters degree program in international

    construction management catered for working profes-

    sionals. It is important to note that since this was a com-

    pulsory module, participation in the survey did not

    necessarily imply a bias of interest or knowledge in the

    VE topic. In addition, these participants came from a di-

    verse background (see Table 1), with their industrial

    experience ranging from 1 year to over 20 years. Based

    on these facts, it is believed that the sample is reasonably

    random. Effectively, a 100% response rate is gathered.

    The survey is very similar in nature to the one conducted

    by Fong and Shen [7] to study the outlook of VE in

    Hong Kong.

    With the module spanning five sessions, the timing of

    the survey had to be carefully planned in consideration

    of two factors:

    1. From the authors experience, it is expected that some

    participants have either limited knowledge or some

    preliminary misconceptions about VE. Such miscon-

    ceptions need to be clarified before seeking therespondents views about the future prospects of VE.

    2. To preserve the participants independent judgment

    and exclude potential influence by either their peers

    or the course instructor, the survey had to be con-

    ducted prior to the final discussion session.

    In view of these two factors, the survey was con-

    ducted right after the basic concepts and the methodol-

    ogy of VE were introduced. Subsequently, the survey

    results were collated and presented in the final session

    of the module so that further clarifications can be sought

    to explore possible explanations for the findings.

    Table 1

    Respondents background/nature of their employing firms

    Respondents background/nature of employing firms Number

    Contractors 29

    Designers/consultants 11

    Owners/developers/government agencies 5

    Facility operators/managers 3

    Suppliers and others 6

    Total 54

    152 C.Y.J. Cheah, S.K. Ting / International Journal of Project Management 23 (2005) 151158

  • 7/28/2019 1-s2.0-S0263786304000808-main

    3/8

    One additional noteworthy fact is that many of these

    participants came from other Southeast Asian countries

    such as Malaysia and Myanmar. The employing organ-

    izations of some of them have projects and businesses

    not just in Singapore but also in other neighboring

    countries. Furthermore, it is not unreasonable to con-

    sider the nature of the construction industry in this re-gion to be largely homogeneous. In view of all these

    factors, findings gathered from the survey can be consid-

    ered as indicative of the general situation in Southeast

    Asia. The following section discusses the primary results

    of the survey following the outline of the original

    questionnaire.

    4. Details of survey findings

    4.1. Respondents prior knowledge about VE

    To gather a better understanding about the back-

    ground of the respondents, they were asked to comment

    on how knowledgeable they are in VE prior to the

    course. Table 2 effectively shows that 74% of them were

    either lacking in knowledge or completely ignorant

    about VE. Moreover, having now learnt about the var-

    ious aspects of VE, 17% of them came to realize that

    they had previously misconceived VE as just another

    usual cost cutting exercise. Obviously, cost cutting is

    not the entire story of VE, as the basic principle itself

    calls for the provision of functionality in a reliable and

    cost-effective manner [8]. In fact, as the terminology it-

    self implies, the starting point of VE should be value,rather than cost.

    The results did not come as a surprise since they were

    consistent with two previous studies in 1994 and 1997

    [9,10]. In those two studies, a total of five architects

    and 17 engineers were interviewed and 75% of them

    claimed that they had little experience or knowledge

    about VE. Obviously, the outlook has not improved

    over the years. The implications of these findings are

    more than trivial considering the fact that most respond-

    ents are experienced, practicing professionals in the con-

    struction industry with at least a baccalaureate degree.

    Apparently, the lack of knowledge and awareness about

    VE is a major cause for its limited application in this

    region.

    4.2. Respondents opinion on the prospects of VE in

    construction

    This section focuses on both the prospects and limita-

    tions of applying VE in construction.

    First, the respondents were asked to comment on

    whether they believed there is sufficient ground to apply

    VE in construction. The picture portrayed by the

    respondents was an encouraging one. As shown in Table

    3, more than two-thirds of them felt positive about VEs

    prospects in the construction industry. The others had

    chosen to remain neutral, but none had expressed a pes-

    simistic view on this issue.

    Despite a positive belief in VEs prospects, it is also

    important to identify the major impediments that might

    hinder successful VE applications. Six options were

    listed as follows and the respondents were asked to se-

    lect those that they considered as major impediments:

    Divided authority and decision-making process

    among project stakeholders including owners, design-

    ers, contractors, suppliers and others. Conflict of interests among the various parties (VE

    may not create a winwin situation for all parties

    concerned).

    Lack of communication among the different

    stakeholders.

    Lack of time to implement especially when VE is

    applied to a specific project rather than a more per-

    manent production or management system.

    Lack of knowledge/awareness about VE in the

    industry.

    Plain inapplicability of most VE principles in the con-

    text of construction.

    Respondents were also requested to specify any other

    factors which they perceived as major but not listed in

    the above. The findings for this issue are summarized

    in Table 4.

    In Table 4, the lack of time for VE implementation

    factor is ranked as the most serious impediment, garner-

    ing 65% of the respondents votes. This is closely fol-

    lowed by the consensus that the lack of knowledge

    about VE is indeed a main concern. Under the option

    of Other Factors, one respondent commented that

    some contractors are fearful of getting a lower profit

    Table 2

    Respondents prior knowledge about VE

    Respondents prior

    knowledge about VE

    Number

    (Percentage in brackets)

    Quite knowledgeable 5 (9)

    Thought that VE is just

    another normal cost cutting exercise

    9 (17)

    He ard of, but not sure what it is 28 (52)

    Never heard of 12 (22)

    Table 3

    Feedback on prospects and applicability of VE in construction

    Respondents opinion

    (voting for positive outlook)

    Number of responses

    (Percentage in brackets)

    Strongly agree 11 (20)

    Agree 26 (48)

    Neutral 17 (32)

    Somewhat disagree 0Disagree 0

    C.Y.J. Cheah, S.K. Ting / International Journal of Project Management 23 (2005) 151158 153

  • 7/28/2019 1-s2.0-S0263786304000808-main

    4/8

    margin in the event of ineffective VE implementation.

    This risk has discouraged greater commitment to adopt

    VE in their operations. More importantly, most

    respondents (91%) do not subscribe to the belief that

    VE principles are simply inapplicable to the context of

    construction if the responses were to indicate other-

    wise, it would signal a structural concern that is hard

    to overcome. This finding is thus consistent with the ear-

    lier consensus in Table 3 which portrayed an encourag-

    ing prospect of VE application in construction.

    Generally, construction-oriented VE practices are

    more prevalent in the US essentially due to its manda-

    tory inclusions in larger federal projects under the fed-

    eral procurement law. For Environmental Protection

    Agency (EPA) projects, for example, the once voluntary

    VE program was made mandatory in 1976. Similarly,VE has established a strong foothold in other countries

    such as Japan, Canada, Australia and England through-

    out the years. Compared to these countries, it is worth-

    while to examine factors that may have prevented VE

    practices from flourishing in the Southeast Asian region.

    For this, the respondents are asked to select the most

    dominant differentiating factors from the four options

    listed below:

    Cultural and operating factors in SEA are simply too

    different from countries such as the US and Japan.

    Lack of flexibility in contractual provisions to incor-

    porate VE during the procurement process.

    Lack of awareness or knowledge about VE in the

    local/regional construction industry.

    Lack of support from parties who have more author-

    ity and clout, such as the government and the project

    owners.

    Again, respondents wererequested to specify any other

    differentiating factors which are not listed in the above.

    The findings for this issue are summarized in Table 5.

    In Table 5, one of the two most dominant factors is

    the lack of support from parties with more authority

    to call for VEs implementation. The significance of flex-

    ibility in contractual provisions is also evident in Table

    5. This factor should not be overlooked during the ini-

    tial selection of project delivery methods. In a past sur-

    vey conducted by Yuen [11], respondents were asked to

    select their choice of procurement systems, as shown in

    Table 6. Obviously, integrated project delivery methods

    such as Design&Build and Build-Operate-Transfer

    (BOT) provide more flexibility to VE studies designersand contractors effectively belong to the same team un-

    der these procurement methods. Consequently, frequent

    communication and close ties exist between the two par-

    ties. For the case of Hong Kong, Fong and Shen [7] also

    arrived at a similar conclusion that strict distinctions be-

    tween design and construction phases in traditional con-

    tracting methods have caused confrontational attitudes

    between design and construction teams, which are in

    fact major obstacles to apply VE successfully.

    Not surprisingly, the lack of awareness/knowledge

    about VE continues to be a key problem. Table 5 was

    also designed to hypothesize whether construction pro-

    fessionals in SEA are hindered by local cultural and

    operating factors in adapting to the unfamiliar VE

    methodology imported from abroad. This factor does

    not turn out to be a very major concern.

    4.3. Respondents opinion on usefulness of various VE

    concepts

    The VE methodology is underpinned by various key

    concepts and techniques, such as the job plan and the

    Functional Analysis System Technique (FAST) dia-

    gram. Over the years, new concepts have enriched the

    Table 5

    Possible causes for limited application of VE in Southeast Asia

    Factors limiting application of

    VE in Southeast Asia

    Percentage of respondents

    selecting each option

    Lack of support from parties

    with authority

    61

    Lack of flexibility in contractual

    provisions

    61

    Lack of awareness or knowledge

    about VE

    59

    Cultural and operating factors

    differ from other regions

    37

    Table 6

    Choices of procurement system to allow implementation of VE

    Contract procurement system Percentage of respondents

    selecting each choice

    Traditional (De sign-Bid-Build) 9

    Construction management 14

    Design & Build 57

    Build-Operate-Transfer 20

    Source. Yuen [11].

    Table 4

    Major impediments to application of VE in construction

    Impediments to apply VE

    successfully in construction

    Percentage of respondents

    selecting each option

    Lack of time to implement VE in

    a project environment

    65

    Lack of knowledge about VE in

    the construction industry

    56

    Conflict of interests among

    project stakeholders

    48

    Lack of communication among

    project stakeholders

    43

    Divided authority/segmented

    decision making process

    39

    Plain inapplicability of VE

    principles in construction

    9

    154 C.Y.J. Cheah, S.K. Ting / International Journal of Project Management 23 (2005) 151158

  • 7/28/2019 1-s2.0-S0263786304000808-main

    5/8

    knowledge field of VE. As previously mentioned, this

    survey was timed so that the respondents had just been

    exposed to these various concepts and techniques when

    the survey was conducted. It would be interesting to

    examine their fresh opinions on the usefulness of these

    topics, especially for academician and course instructors

    who are providing educational training services in thisarea. The respondents opinions are collated under Ta-

    ble 7. The findings are generally clear, although a couple

    of issues require further elaboration.

    First, in many industries, the scope of VE is broader

    than those applications found within construction which

    focus primarily at project level implementation. For

    example, VE may be applied to management and service

    systems other than product and project systems [12].

    Cooper and Slagmulder [13] related VE to target costing

    and also proposed the combination of the two as a

    bridging technique to increase collaboration with suppli-

    ers. All these can be classified under VE issues in a cor-

    porate context. Unfortunately, strong appreciation of

    this topic was not reflected in this survey. Incidentally,

    the few respondents who had selected this option be-

    longed to senior management level they obviously

    had a better perspective of corporate level issues.

    Second, it is thought that VE could function as an

    indirect tool to pursue other objectives, such as promot-

    ing interdisciplinary teamwork, nurturing an innovative

    culture within a firm, or even serving as a marketing

    tool. This is in fact a grounded presumption a direct

    analogy can be drawn from past research efforts in the

    area of strategic planning. For example, Langley [14]

    found that the process of strategic planning can be as

    important as the outcome itself, whereby other goals

    are achieved along the way when its execution is taking

    place. However, a similar idea for VE was not well re-

    ceived by the respondents in this survey.

    4.4. Respondents opinion on future prospects of VE

    The final group of questions focuses on the perceived

    effectiveness of VE in elevating the status of construc-

    tion in terms of four related aspects: (1) quality of

    works; (2) new innovations; (3) profit margin of firms;

    and (4) long-term competitiveness of firms. Respondents

    were asked to judge with a prior assumption that the VE

    methodology has been properly planned, structured and

    implemented in each case. The findings are summarized

    in Table 8.

    In Table 8, a larger diversity of opinion is observed

    for the first aspect (quality of works) as compared to

    the others. In the post-survey session, when discussions

    were open to the floor, some respondents expressed their

    view that quality, although intrinsically linked to value,

    is not the only concern in VE studies. In fact, other tech-

    niques that specifically address quality issues such as

    Total Quality Management (TQM), would be more

    effective. Some have also commented that the lack of

    time to implement VE in many cases (see Table 4) would

    inevitably lead to a certain level of quality compromise.

    A more uniform agreement was found for the second

    and third aspects in Table 8. Consistent with Table 7,

    which ranks creative thinking techniques as one of themost useful VE concepts, 80% of the respondents thought

    that VE would help to promote new innovations in the

    industry. For the third aspect, 72% sided with the belief

    that VE is effective inimproving the profit margin offirms.

    Overall, the general consensus seems to convey that VE is

    a valuable concept that would help to elevate the status of

    the industry. Responses gathered for the last aspect were

    in line withthis conclusion, with85% statingthat VE helps

    to promote a firms competitiveness in the long-run.

    5. Other insights furnished by non-parametric statistics

    Armed with the survey results, selective non-paramet-

    ric statistical tests can be used to verify or refute

    Table 7

    Feedback on the usefulness of various VE concepts

    Selected VE concepts Percentage of respondents

    selecting each option

    Functional analysis 63

    Creative thinking techniques 59

    Concept of Value 54

    Job plan as a systematic

    approach

    52

    Concept of cost 50

    VE in the corporate context (e.g.,

    target costing)

    24

    FAST diagram 22

    VE as an indirect tool to serve

    other purposes (e.g., marketing)

    19

    Enhancing scope of VE with

    other disciplines (e.g., IT, economics)

    11

    Table 8

    Effectiveness of VE in improving status of selected aspects

    Se lec ted aspe cts Numbe r of re sponses (voting for strong effe ctiveness of VE)

    Strongly agree Agree Neutral Somewhat disagree Disagree

    Quality of works 11 20 20 2 1

    New innovation 18 25 10 1 0

    Profit margin of firms 16 23 14 0 1

    Long-term competitiveness 24 22 6 1 1

    C.Y.J. Cheah, S.K. Ting / International Journal of Project Management 23 (2005) 151158 155

  • 7/28/2019 1-s2.0-S0263786304000808-main

    6/8

    hypothesized relationships among a few factors. The

    technique makes minimal assumptions about the under-

    lying distribution of the sample data, unlike the case of

    parametric studies. Furthermore, non-parametric meas-

    ures of correlation are available for both categorical

    (nominal scale) and ranked data (ordinal scale) [15],

    which suit the characteristics of the data collected in thissurvey.

    Hypothesis 1. Type of firms and frequency of applying

    VE.

    In Table 1, most respondents came from a contract-

    ing background. One might suspect whether the survey

    results would be distorted by the dominance of this

    group of respondents. One way this could be reflected

    is through the association between two parameters:

    type of firms and frequency of VE application. If

    contractors truly take a different stance as a group, this

    could be manifested by their frequency in applying VE.

    Table 9 shows the construction of a 2 2 contingency

    table used to test this hypothesis. The classifications

    along each axis are self-explanatory. Using the data in

    Table 9, the Cramer coefficient C, which is a measure

    of degree of association between two sets of attributes,

    was computed as 0.255. This coefficient is not statisti-

    cally different from zero at a = 0.05 significance level,

    thus one cannot reject the null hypothesis that there is

    indeed no relationship between the two sets of attri-

    butes. It follows that organization types within the con-

    struction value system do not seem to influence the

    likelihood of VE application.

    Hypothesis 2. Firm size and frequency of applying VE.

    A similar test can be done to examine the relationship

    between firm size and frequency of VE application.

    It is logical to assume that larger firms would have more

    resources, project opportunities and larger economies of

    scale to implement VE. The measure of firm size can be

    represented by the number of employees in the organiza-

    tion as reported by the respondents. To ensure consist-

    ency of results for the range of number of employees

    reported, two separate tables were constructed for differ-

    ent cutoff points (100 and 150 employees). The Cramer

    coefficients were computed as 0.316 and 0.324, respec-

    tively, and they are both statistically different from zero

    at a = 0.05 significance level. The results reject the null

    hypothesis and confirm that larger firms seem to be

    more frequently engaged in VE studies. This finding

    concurs with the viewpoint of some respondents that

    smaller jobs undertaken may not benefit from VE possi-

    bly due to a lack of scope. This issue is especially signif-

    icant in the regional context as the market consists of

    many small private firms.

    6. Summary and discussion of survey results

    In summary, the survey findings confirm the belief

    that VE principles are sound and possess strong applica-

    tion prospects in the SEA construction industry. On the

    other hand, many hurdles still stand in the way for VE

    practices to flourish. First, there is a lack of knowledge

    about VE in this region. Specifically, there is a huge

    necessity to educate:

    1. Parties who have the authority and clout to impose

    VE provisions in contracts, such as owners, develop-

    ers and government agencies.

    2. Industrial practitioners in general, especially in pro-

    moting its usefulness and clarifying misconceptions

    about the VE principles.

    It is important to realize that concerns and conflict of

    interests can be largely resolved if all parties have a better

    understanding of the VE principles and appreciate the

    potential benefits derived from VE studies. For example,

    some owners perceive VE proposals submitted by con-

    tractors as an excuse to lower quality and functionality

    (which they assume as forming the basis of the costreduction proposed). Ironically, contractors, who might

    well have a genuine intention to improve on an existing

    design, would eschew the risk of unsuccessful VE studies

    that potentially lead to losses. If only the two parties

    understand each others concern, a winwin situation

    can be structured through proper design of contractual

    provisions in equitable savings and risks sharing. This,

    obviously, can only be realized when the basis and prin-

    ciples of VE are clear to them in the first place.

    Second, governments and building/construction

    authorities should play a lead role in promoting VE.

    Past experience of the US clearly demonstrates the

    importance of this factor [2]. Specifically, incentives to

    apply VE should be built within the provisions of public

    contracts. Over time, this also helps to build up case

    precedence and form a database showing success and

    failure rates of VE applications. By referring to these

    evidence and precedence, private sector owners would

    feel more comfortable in adopting VE for their projects.

    Key lessons can also be learned from past failures so

    that practices are improved over time or customized to

    suit unique circumstances.

    It should be mentioned that the current situation is

    partly a repercussion of the survey conducted by Yuen

    Table 9

    Contingency table: type of firms versus frequency of VE application

    Frequency of VE application T ype of firms Total

    Contractors Non-contractors

    Never/rare 19 10 29

    Sometimes/frequent 10 15 25

    Total 29 25 54

    156 C.Y.J. Cheah, S.K. Ting / International Journal of Project Management 23 (2005) 151158

  • 7/28/2019 1-s2.0-S0263786304000808-main

    7/8

    [11] when respondents in his case also expressed posi-

    tive views on VE but nonetheless commented on various

    factors that have neutralized its popularity growth. Inci-

    dentally, some of these factors coincide with the cur-

    rently identified ones. This implies that nothing much

    has been achieved during the past few years in promot-

    ing VEs adoption in this region.Finally, project delivery methods, design of contrac-

    tual provisions and organizational structure (for both

    projects and companies) are all highly relevant issues of

    concern. Segmented delivery methods such as the tradi-

    tional approach of Design-Bid-Build may not have room

    and time to cater for VE implementations. Moreover,

    since the VE process serves to draw inputs from a multi-

    disciplinary team, engagement of VE consultants should

    be helpful in coordinating VEs implementation and min-

    imize theconflict of interests among different stakeholders

    provided that the consultants are backed by the owner

    [2]. For government agencies that have a more constant

    stream of ongoing projects, it may even be justified to

    form a VE program committee to oversee the implemen-

    tation for various projects andbuild up case precedence to

    facilitate learning and future improvements.

    7. Broadening the scope of VE in construction

    In many cases, implementation of VE within construc-

    tion is largely confined to the project level. Researchers

    such as Akiyama [12] and Cooper and Slagmulder [13]

    have commented on the role of VE in a larger corporate

    context. To utilize VE in shaping long-term competitive-ness of construction firms, its scope has to be broadened.

    Some may refer this to value management. Essentially,

    the key issue lies on the adoption of a broader mindset in

    expanding the basic VE methodology.

    7.1. Value engineering and target costing

    Cooper and Slagmulder [13] linked VE to a concept

    known as target costing, which they defined as a

    structured approach to determine the life-cycle cost at

    which a proposed product with specified functionality

    and quality must be produced to generate the desired le-

    vel of profitability over its life cycle when sold at its

    anticipated selling price. Although this definition is

    more related to the manufacturing sector or the sale of

    a product, much can be learned from the concept and

    applied to the construction business.

    In long-term planning, a firm typically determines

    the type of market segments to compete, the type of

    clients to serve, and any revenue or profit targets to

    achieve all these based on a chosen form of corpo-

    rate strategy. In all cases, the external market condi-

    tions always serve as the backdrop. The process of

    target costing starts with the presumption that market

    conditions and competitive pressure will dictate a cer-

    tain level of targeted profit margin for each type of

    projects (or market segments at large). Given this tar-

    geted profit margin, the allowable cost can usually be

    derived. When the current cost of a working system

    judging from past projects of similar nature or

    attributes, is higher than the allowable cost, a costreduction objective should be set, coupled with a rea-

    sonable time frame to achieve such objective. In this

    way, the initial market-driven effect is transmitted

    down to the project and component levels. Value engi-

    neering then comes in at this point.

    The VE principles and methodology provide a sys-

    tematic approach in searching for alternative solutions

    that preserve the functionality and reliability of con-

    structed facilities a floor value, so to speak. The cost

    is obviously capped by the allowable cost described

    previously. Taken together, the two measures provide

    guidelines for redesigning the working system so as to

    achieve the minimum floor value while being subjected

    to the maximum cost cap. Note that this process is con-

    ceptually different from the usual practice of lowering a

    mark-up or tender price when the market outlook is

    gloomy. The target costing-plus-VE process presets

    a profit margin and work from thereon, whereas lower-

    ing of mark-up implies a reduction in profit margin in

    and of itself. The former effectively calls for more inten-

    sive effort to be devoted by an organization to improve

    on their operational systems rather than simply yielding

    to market conditions and competitive pressure by

    adopting a lower mark-up.

    For the cost reduction objective to be realized then, itis obvious that a firm would have to work closely with

    other parties within the value system who play an influ-

    ential role in project- and component-level costing. In

    construction, these parties are likely to include designers,

    contractors, subcontractors and suppliers. Given the seg-

    mented nature of most contractual systems and delivery

    methods, large firms that possess in-house design and

    construction teams would be in a much better position

    to carry out the above mentioned strategy. Furthermore,

    large firms have more bargaining power in drawing their

    regular suppliers to work with them towards a new pro-

    ject or product system a phenomenon that is exempli-

    fied by the automobile industry (which incidentally has

    a value system that is quite analogous to construction).

    For smaller firms, this strategy can still be explored with-

    in a network of quasi-firms [16]. In this network, stable

    working relationships typically exist within a group of

    contractors, subcontractors and suppliers.

    7.2. Enhancing value engineering with development in

    allied disciplines

    Since its inception, the knowledge field of VE has en-

    joyed valuable contributions from related areas such as

    C.Y.J. Cheah, S.K. Ting / International Journal of Project Management 23 (2005) 151158 157

  • 7/28/2019 1-s2.0-S0263786304000808-main

    8/8

    creative thinking. Today, the trend continues in various

    aspects. Not too long ago, new developments in prefab-

    rication and precast concrete technology have expanded

    the domain of technical solutions. Likewise, large con-

    struction firms, notably the Japanese, have achieved

    admirable advancement in building automation and

    robotics [17]. All these developments have helped to ex-pand the frontier in searching for alternative solutions

    for a project, a product or a system. For example,

    Tabatabai-Gargari and Elzarka [18] illustrated how

    the integration of knowledge-based systems and compu-

    ter-aided design systems could generate design alterna-

    tives and improve the accuracy of cost estimates two

    major steps in a typical VE study.

    The VE methodology also has many softer aspects

    that should not be overlooked. For example, forming a

    VE team and coordinating VE activities require prudent

    observation of group dynamics such as leadership, trust

    building and conflict resolution. Commonly perceived as

    a functional analysis technique, the FAST diagram is

    also an effective communication tool since it is essen-

    tially a roadmap that facilitates discussions among the

    VE team members. Not too long ago, Green [19] re-

    ported on a research project that sought to propagate

    a few soft methodologies within UK value manage-

    ment practice.

    In many ways, these concurrent developments help to

    elevate the application of VE techniques to the macro le-

    vel. Indisputably, the VE process is generic and a broader

    range of available solutions can only enhance its useful-

    ness in solving component-, project-, system- and corpo-

    rate-level issues. Even new developments in finance andeconomics can indirectly affect VE through the aspects

    of life-cycle costing alternative solutions need to be

    evaluated in the light of marginal operating and mainte-

    nance costs, replacement values, decommissioning costs

    and salvage value of the facility. Proper evaluation tech-

    niques are thus required to arrive at a reasonable esti-

    mate in present value terms, so that all alternatives

    can be compared on par.

    8. Conclusions

    This paper presents a survey that is indicative of the

    extent to which value engineering principles and prac-

    tices are being applied in Southeast Asia. Although gen-

    erally there is a strong belief that future prospects of VE

    in the Southeast Asian construction industry are posi-

    tive, a number of impediments still stand in the way.

    In particular, more efforts are required to educate indus-

    trial practitioners and owners on various aspects of VE.

    Governments also have to play a lead role in promoting

    such initiatives.

    In addition, there is substantial ground to broaden the

    scope of VE by: (a) introducing its use at the macro level;

    (b) enhancing its effectiveness by adopting new develop-

    ments in allied disciplines. All these factors imply that

    since its inception, VE has somewhat changed its outlook

    towards a new and promising direction. Construction

    professionals need to keep themselves abreast of theseissues in order to elevate the status of their firms and

    the industry as a whole. Back in Southeast Asia, how-

    ever, there are obviously more concerns of catching up

    with these ongoing developments.

    References

    [1] Younker DL. Value engineering: analysis and methodology. New

    York: Marcel Dekker; 2003.

    [2] Zimmerman LW, Hart GD. Value engineering: a practical

    approach for owners, designers and contractors. New York: Van

    Nostrand Reinhold; 1982.

    [3] DellIsola AJ. Value engineering in the construction indus-try. New York: Van Nostrand Reinhold; 1982.

    [4] US Environmental Protection Agency. Value engineering: case

    studies and formats for proposals and reports; 1977.

    [5] British Standards Institution. BS EN 13251: Value management,

    value analysis, functional analysis vocabulary Part 1 Value

    analysis and functional analysis. London; 1997.

    [6] British Standards Institution. BS EN 12973: Value management.

    London; 2000.

    [7] Fong PSW, Shen Q. Is the Hong Kong construction industry

    ready for value management?. Int J Project Manage

    2000;18(5):31726.

    [8] Mudge AE. Value engineering: a systematic approach. Pitts-

    burgh, PA: J. Pohl Associates; 1990.

    [9] Ong SC, Teo CM. Application of value engineering to building

    projects. Unpublished final year project report, Nanyang Tech-nological University, Singapore; 1994.

    [10] Chong TW. Application of value engineering techniques for cost

    reduction in construction project. Unpublished final year project

    report, Nanyang Technological University, Singapore; 1997.

    [11] Yuen CC. Applications and limitations of value engineering

    concepts in Singapore construction industry. Unpublished Master

    of Science dissertation, Nanyang Technological University, Sin-

    gapore; 2000.

    [12] Akiyama K. Function analysis: systematic improvement of

    quality and performance. Cambridge, MA: Productivity Press;

    1991.

    [13] Cooper R, Slagmulder R. Target costing and value engineer-

    ing. Portland, OR: Productivity Press; 1997.

    [14] Langley A. Formal analysis and strategic decision-making.

    OMEGA 1991;19(213):7999.[15] Siegel S, Castellan Jr NJ. Nonparametric statistics for the

    behavioral sciences. New York: McGraw-Hill; 1988.

    [16] Eccles RG. The quasifirm in the construction industry. J Econ

    Behav Organ 1981;2(4):33557.

    [17] Cousineau L, Miura N. Construction robots: the search for new

    building technology in Japan. Reston, VA: ASCE Press; 1998.

    [18] Tabatabai-Gargari M, Elzarka HM. Integrated CAD/KBS

    approach for automating preconstruction activities. J Construct

    Eng Manage 1998;124(4):25762.

    [19] Green SD. A participative research strategy for propagating soft

    methodologies in value management practice. Construct Manage

    Econ 1999;17(3):32940

    158 C.Y.J. Cheah, S.K. Ting / International Journal of Project Management 23 (2005) 151158