Grounds DepartmentOff Season Review

February 27, 2013

New forward tee boxes on # 2

Deep tine aeration alleviating soil compactions of the fairway.

4 green – reclaimed putting areas

5 green – reclaimed putting areas

6 green 7 greenReclaimed putting areas

8 green – reclaimed putting areas

Original design for # 8 green

Logs from hole # 8

Left side of 8 green – Brush clearing and grade tweaks

Tree roots growing through bunker drainage gravel

Tree roots compromising drainage pipe and gravel of our bunkers

Old bunker drainage lines

Green side bunker work # 10

Worn bridge decking on # 4 bridge

Gary Derickson and Garrett Lewis installing new decking on # 4 bridge

New decking for # 4 bridge

Tree removals for new 50 ft netting along one tee

Storm Damage left of 15 fairway

Storm damage to left of 15 fairway

Storm Damage to left of 15 fairway

Storm Damage behind 3 tee

Storm damage 12 tee

New drain basin on # 9 rough

Toro Golf Decoder Control System(GDC)Update

Continuing education opportunities