Spalding Gymnastics Scoreboard

Post on 23-Feb-2016

51 views 0 download

Tags:

description

Spalding Gymnastics Scoreboard. Advisor: Zhao Zhang Team Members: Chris Chambers Christopher Reis Alex Dean Luke Breuer. Client: Spalding Advisor: Zhao Zhang Team: May 13-01. Problem statements:. Client needs a more sufficient way to display multiple event scores. - PowerPoint PPT Presentation

Transcript of Spalding Gymnastics Scoreboard

Advisor:

Zhao Zhang

Team Members:

Chris Chambers

Christopher Reis

Alex Dean

Luke Breuer

SPALDINGGYMNASTICS SCOREBOARD

Client: Spalding Advisor: Zhao Zhang Team: May 13-01

PROBLEM STATEMENTS:

• Client needs a more sufficient way to display multiple event scores.

• The target consumers are athletic venues who hold gymnastic events.

• Adaptable to other indoor events.

FUNCTIONAL REQUIREMENTS• Able to be read from 100’- 200’ away

• Easy transportation (Size matters)

• Powered by external 120 VAC source (General wall outlet)

• Controlled by computer

• Wireless communication from computer to message board (WiFi)

• Message board relatively insulated from elements in indoor facilities (Humidity)

CONCEPT SKETCHMain Ideas• Small enough to transport

• Displays four different event names on the left

• Scrolls through athlete names and scores for each event on the right

CONCEPT OF OPERATION

SYSTEM DESCRIPTION

USER INTERFACEHTML WebsiteReasons:1. The IC we are using will include a

USB port for a WiFi dongle

2. Allows score reports to be accessed via handheld device (If you can connect to the internet)

3. Allows user to use any computer to program the scoreboard

MICRO-CONTROLLER UNITBeagle BoneReasons:1. Embedded Linux (Angstrom Distro)

2. Interfaces with LED Drivers

3. Acts as Ad-Hoc router/HTML Server

4. Enables complex code to be abstracted (USB, TCP/IP, etc)

LED CIRCUIT MATRIXReasons:

1. Reduction of GPI/O pins

2. Persistence of vision

3. Matrix operation

4. Reduction of power consumption

5. Reduction of discrete components

PCB SCHEMATIC

PCB LAYOUT

LED OPTIONS• Four options

• Three Red options

• One RG option

• Vary in luminosity from 54-220 milli-candela

• 1206 Surface Mount packaging (606 for RG LED)

POWER SYSTEMBuck converterReasons:1. Allows 120 VAC Input

2. Convert Down to 12 VDC to power LED’s

3. Use Linear Dropout Regulator to convert to 5 VDC to operate BeagleBone and Driver logic.

FUNCTIONAL BREAKDOWN

NON-FUNCTIONAL REQUIREMENTS

• Powered by a battery source

• Built to withstand outdoor weather conditions

• Ability to be mounted on stands

• Ability to be integrated with other boards

WORK PLANPhase 1 – Small scale testing and proof of concept design – Power consumption analysis

Phase 2 – Large scale hardware layout and design

– Drafting of external components

Phase 3 – Prototyping and assembly of components

Phase 4 – Extensive testing and analysis of prototype

Phase 5 – Report on final results and correction of errors

POSSIBLE DEVELOPMENT ISSUES

Problem 1 – Programming in HTML

– Setting up router

Problem 2 – Code to interface with LED Drivers

Problem 3 – Developing the mounting system

Problem 4 – Time constraint on adding in non-functional requirements

Problem 5 – Network Security

MITIGATION PLAN

HTML/Router – Work with advisor (Dr. Zhang)

LED Drivers – Prototype early in January

Mounting – Develop plan with customer to provide mounting system

Time Constraint–Set realistic time goals, invest in early development work

FACILITY VISIT• Spalding/AAI Manufacturing Facility

(Jefferson, IA)

• Point of Contact: Norm Robbins

• Onsite visit with client’s team

• Tour of assembly lines

• Gained familiarity with Spaldings manufacturing capability

• Discussion of rotary forming capability

BUDGET AND ORDERING

OVERALL IDEA OF PROJECT

Allow athletes and fans to receive live updates of scores either via scoreboard or on the web.

QUESTIONS?

Chris Chambers Alex DeanLuke Breuer Christopher Reis