National Status and Activity Report

Republic of Serbia

Zoran Lukic / Plovput

DISC 12, Vukovar, 13/12/2012

Notices to Skippers

http://nts.risserbia.rs/

Electronic Reporting

Eri DGW - https://eridgw.risserbia.rs

Hull Database

http://hull.risserbia.rs

European Ship Identification Number - ENI

ENCs

Complete coverage of Serbian International Waterway Network– Danube River– Sava River– Tisa River

AIS Network in Serbia

18 AIS basestations, full coverage of the Danube and Sava River

AIS Tracking and Tracing

AIS Tracking and Tracing - WEB

Lock Management System

Installed at two locks on the Serbian Danube

IALA Beacon nearby Belgrade

RIS Centre in Belgrade

Additional features

dGPS correction over AIS D4D webportal RIS index Integrity monitoring system Trouble ticketing and alarming system … One WLAN hotspot installed at Iron Gate lock

within NEWADA Project

Ship equipment programme

AIS Transponder + ECDIS in information mode

Governmental vessels– 47 vessels equipped

Commercial vessels– 117 vessels equipped, out of 180 applied

Future Agenda?

RIS operations and deployment AtoNs

– Pilot (NEWADA Duo)– Full implementation

Second WLAN hotspot installation (NEWADA Duo)

NEWADA Duo - Remote AtoNs

Boys to be equipped Broadcasting information thru AIS msg. 21

– Visible to the skipper on the ECDIS screen– Visible to the Waterway administration in the

operator room via AIS network

NEWADA Duo - Remote AtoNs

Serbia

Belgrade Centre Giurgiu Centre

Ruse Centre

AIS

WEB INTERFACE

WEB INTERFACE

PILOT

NEWADA Duo - Virtual AtoNs

NEWADA Duo -Virtual AtoNs

Serbia

Belgrade Centre Giurgiu Centre

Ruse Centre

AIS

WEB INTERFACE

WEB INTERFACE

PILOT

National - AtoNs Roll-out

Project proposal for full roll-out of AtoNs on the Danube (Remote AtoNs and Virtual AtoNs)

Timeframe 2014-2016 Budget approx. 3MEur, IPA funds Three projects

– Supplies of equipment– System integration– Supervision

WLAN installation Iron Gate 2 lock

Questions and Discussion