Post on 21-May-2015
“Leidinginstallatie met Direct Pipe”
Software days June 16, Colloquium Deltares
Outline
• A-Hak/Drillcon • Direct Pipe principle and total package • Tunnel Boring Machine • Industry perceptions early on and now • Measurement & control • Jobsite setup • Engineering • References & Milestones • Advantages • Video • Conclusion
A.Hak Drillcon part of A.Hak Group Contractor focused on Trenchless installations Services Main or Sub-contractor Project engineering, consultancy, execution
Equipment & tooling HDD technology 16 rigs in total, 8 Maxi rigs Pulling force up to 500 tons
Direct pipe 500 ton unit
Micro tunneling 6 units Up to 3m in diameter
A.Hak Drillcon
Direct pipe principle
Compared to standard HDD & MT Make a pilot bore with a hole size large enough
to accommodate the final product using the product as the drill string.
Microtunneling drillhead technology Inventor Mr Rudi Koegler
Consultant for Drillcon
Total package
Pipe thruster
Powerpack
Steering/control cabin
Tunnel Boring Machine
Pipe Thruster
Pipe clamp Segmented with large contact
surface per segment Hydraulically engaged Vulcanized inserts to increase grip
and protect pipe coating Guide rollers to centralize product
pipe
Thrust/pull frame Anchored to the ground Connected to the pipe clamp frame
with two hydraulic cylinders Angle setting hydraulically
Capacity Pipe OD up to 60”/1524mm Thrust/Pull velocity up to 3m/min Setup angle 0 – 15 degrees
Tunnel Boring Machine
Modified Micro tunnel (TBM) based machine in front of the product pipe Dimensions
Length 19m Machine diameter 1295mm Cutter head diameter 1325mm
Power Pack for main drive
Telescopic Station
Power Pack for Telescopic Station
Conical Interface Ring
Cutting Head Pipeline
Cutting head – adapted to geology
Power pack
Steering cylinder of the active steering joint
Feed line
Slurry line AVN - Machine
AVN1000XB Direct Pipe
Tunnel Boring Machine
19m
Cutting head options
Cobbles
Coarse gravel
Medium gravel
Fine gravel
Coarse sand
Medium sand
Fine sand
Sandy, Silty clay
Silt
Clay
Rock
Cutting Head for Soft Soil
Cutting Head for
Mixed Soil
Rock Cutting Head
Tunnel Boring Machine
10
Mode of operation of the cutting tools and the cone crusher.
Handling of obstacles
Tunnel Boring Machine
Tunnel Boring Machine
• Steering control
• Radius < 600 m
Steering cylinders
Supply lines
FEED AND SLURRY LINE
ATTACHMENT OF CABLES, LUBRICATION AND WATER LEVEL
LINES AND AIR HOSES ON HOOKS.
RUBBER ROLLERS FOR THE EASY ASSEMBLY AND DISASSEMBLY
Industry perceptions
Presumed challenges Risk for pipe coating “shear/peel off” since
the thrust and or pullback forces are transferred through the coating
Technology similar with micro tunneling thus high expected installation forces limiting the length capabilities
Coating possibilities
Coatings successfully tested – Polyethylene (PE)
– Polypropylene (PP)
– Glass reinforced plastic GRP
– Fusion bounded epoxy (FBE)
– Concrete *With and without slippage
Friction & hole stability Stabilized hole
Hole is kept open mechanically Soil properties
Cohesive, non-cohesive Depth diameter ratio (arching effect)
Fluid properties in the annulus Filtercake and fluid pressure
Friction Collapsed/partly collapsed annulus
SKIN FRICTION Contact surface times skin friction coefficient
Stabilized/open annulus FRICTION
Down hole weight times friction coefficient
Control with friction reducing additives
Experience on various projects has proven that the expected installation forces are closer to HDD than to traditional micro
tunneling
(1-3Kpa/m² versus 7.5-10Kpa/m²)
Product
FiltercakeSoil/rock
Return fluidProduct
FiltercakeSoil/rock
Cuttings
Friction reduction
Bentonite lubrication in the annular
1. Lubrication nozzles in the
first machine cans
2. Lubrication ring at the end of the machine
3. Bentonite tank connected with the launch seal / overcut
overcut
Leak prevention
Launch seal Seals up to 1bar pressure
Measurement systems
Measuring wheel
Horizontal orientation: (cm)
via continuous gyro compass
Altitude reference device
Vertical orientation : (mm – cm)
via hydrostatic water leveling system
Water level hose
Altitude sensor I + II
Manual recorded parameters
Monitored parameters
Monitored parameters
Jobsite setup
Equipment spread at launching area
Single pipeline or multiple pipe sections Pipe rollers and overbend construction
Launch Area
Field preparation
Pipe pusher
Launch seal
Pipe string
Pipe support Rollers
Position On surface Overbend Ramp
Pipeline in sections
Insufficient space to lay of the pipeline in one single piece.
Saving of cables, supply lines & pumps.
Target side
Recovery of the direct pipe drilling head – Above ground – Below ground
Engineering • Total or detail and post
engineering – Profile
• Customer requirements • Underground type and
stratigraphy • Product properties
– Construction • Anchoring • Pipe string setup • Seepage avoidance (kwelweg)
– Equipment and tooling selection • Soil investigation • Mud pressure calculations • Thrust force calculation
– Pipe stresses assessment • Pre- and post installation
– Drill technical – As build
• Front pressures • Thrust force • Location
Profile Underground
Construction anchoring
Construction pipe strings
Construction seepage avoidance
Analysis following NEN method
Use of seal and clay box (similar with HDD)
Equipment & tooling Shield pressure calculation
Equipment & tooling Thrust force modeling
Equipment & tooling Thrust force modeling
1. Friction of the pipeline behind the thruster on the rollers.
2. Friction between pipeline and lubricant fluid.
3. Front force at the cutting head of the microtunneling machine
4. Friction between pipeline and the borehole wall.
5. Friction due to buckling of the pipe.
Pipe Stresses
• HDD – Tensile stress
• Pulling > Tension
– Bending stress • Proportional with radius
– Hoop stress • Higher external pressure
due to flow – Hole erosion
• Can be compensated by balancing
• Direct Pipe – Tensile stress
• Pushing > Compression
– Bending stress • Proportional with radius
– Hoop stress • Low external pressure
• No means for full fledge balancing
– Rotational stress • Less than one percent of
total stress
The product stresses considered for Direct Pipe are similar with the ones considered for HDD
Drill technical
TBM
• Cutting wheel selection – Driven by soil
type/conditions
• Shield pressure – Driven by depth, ground
and groundwater pressure
• Thrust force – Soil properties, cutting
wheel velocity and radius
As build shield pressure
As build Thrust force
System measurements
As build profile
– Part of the installation report:
Profile verification by means of gyroscope.
Executed by third party
References Direct Pipe
Direct Pipe®- Projects
No. Project Country Pipe -
Ø
Drilling
Length
(m)
Geologie Coating Construc. Company Cliënt Year
1. Rhine crossing in Worms Germany 48’’ 484 Sand, gravel, clay None Sonntag EWR 2007
2. Brine Outlet in Rysum Germany 48’’ 283 Sand, clay, stones,
wood PE Meyer & John EWR 2009
3. Pipeline Angerlo-Beuningen Netherlands 48’’ 382 Sand, gravel PP A.Hak Drillcon Gasunie 2010
4. Pipeline Angerlo-Beuningen Netherlands 48’’ 435 Sand, gravel, wood PP A.Hak Drillcon Gasunie 2010
5. Expans project Phase VII in Arcada Florida USA 30’’ 224 Sand, clay, coral, shell FBE REM Directional inc. Florida Gas
Transmission 2010
6. Hartelkanaal Crossing in the harbour of
Rotterdam Netherlands 48’’ 545 Sand, clay, wood PP A.Hak Drillcon Gasunie 2010
7. Pipeline Ommen-Angerlo. Crossing of
railline Netherlands 48’’ 518 Sand, gravel, loam PP A.Hak Drillcon Gasunie 2010
8. Pipeline Ommen-Angerlo. Crossing of
railline Netherlands 48’’ 540 Sand, gravel, loam PP A.Hak Drillcon Gasunie 2010/2011
9. Highway 39 keysville Road in Paint City USA 38’’ 119 Sand, clay, coral, Shell FBE REM Directional inc. Florida Gas
Transmission 2011
10. Collier Parkway Crossing in Land O lakes USA 38’’ 228 Sand, clay FBE REM Directional inc. Florida Gas
Transmission 2011
11. Pipeline Ommen- Esveld. Crossing in
Lochem Netherlands 48’’ 1.400 Sand, gravel, loam PP A.Hak Drillcon Gasunie 2011
12. Pipeline Poggio Renatica, Scolo Riolo
Crossing Italy 48’’ 394 Clay, sand PE ICOP spa. SNAM 2011
13. Pipeline Poggio Renatica, Desala Crossing Italy 48’’ 800 Clay PE ICOP spa. SNAM 2011
14. Pipeline Paggio Renatica, Desalo Crossing Italy 48’’ 372 Clay PE ICOP spa. SNAM 2011
15. Tiaga Conutry Extension, state highway
392, Crossing in Carning, New York USA 42’’ 130 Gravel, cobbles None Michael’s Directional inc. Empire pipeline 2011
16. Crossing the River “de Maas” Netherlands 48’’ 1.026 Gravel, clay, sand PP A.Hak Drillcon Gasunie 2012
17. La Somme France 48’’ 1.072 Chalk, Marl, Clay PP A.Hak Drillcon GRT Gaz 2013
References A.Hak Drillcon
Year Client Project Crossed object Length Pipeline material Ground condition
2010 Gasunie Angerlo – Beuningen Road 402m1 Steel 48” w.t.22,7mm Sand / gravel
2010 Gasunie Angerlo – Beuningen Existing gas pipelines 462m1 Steel 48” w.t. 18,7mm Sand / gravel
2010 Gasunie Gasrotonde Europoort Hartelkanaal 536m1 Steel 48” w.t.22,7mm Sand / clay
2010 Gasunie Ommen – Esveld Railroad Zwolle – Almelo Main road N35
546m1 Steel 48” w.t.22,7mm Sand / clay
2010 Gasunie Ommen – Esveld Railroad Deventer - Almelo 570m1 Steel 48” w.t.22,7mm Sand / gravel
2011 Gasunie Ommen – Esveld Agricultural land, roads and existing pipelines
1.400m1 Steel 48” w.t.15,9mm
Sand
2012 Gasunie Odiliapeel – Melick De Maas Railroad Venlo – Roermond Main road N271
1.026m1 Steel 48” w.t.22,7mm
Sand / clay / gravel
2013 GRT Gaz Hauts de France II Agricultural land, road and La Somme
1.072m1 Steel 48” w.t.28,2mm
Gravel / clay / marl
2014 Gasunie Beverwijk - Wijngaarden Main road N201 Parking place Suspicious area of explosives
582m1 Steel 48” w.t.22,7mm
Sand / clay / salty groundwater
Milestones
World record
45
Length: 1.400 m in total
Pipe sections: 3 x 500 m
Construction Company: A.Hak Drillcon.
Client: N.V. Nederlandse Gasunie
(Dutch Gas supplier).
Geology: sand, small gravel and loam.
Gas Pipeline - Ø 48“ (1.220 mm).
Coating: Polypropylene PP.
Double pipe pusher setup
Maximum advance rate:
120 m in single shift of 12 hours
= 10 m/h.
230 m in one day (19.03.2011)
Setup of the second Pipe thruster
Advantages of the Direct Pipe method
• Hole is cased during drilling • Usable for any geological condition (e.g. : gravel)
Pullback option of the whole pipeline & machine Single-phase mode of operation Access from only one side → ideal for outfalls Start and exit point on or below surface No coupling time necessary (drill rods), continuous
process Smaller borehole diameter comparatively to HDD Low bentonite usage & pressures Static pressure in the annulus High velocity fluid isolated from the formation
Awards
Winner of the ISTT NO DIG AWARD 2008 at the NO DIG 2008 in Moscow
Top 5 nominee for the HERMES AWARD 2008 at Hanover Fair.
Winner of the technology award at the 2009 Iploca convention in San Francisco, USA
Winner of the NSTT NO DIG AWARD 2010 in the Netherlands.
Video
Conclusion
• Direct Pipe is globally recognized as the preferred trenchless installation method for:
– Bores in unstable/sensitive (e.g. coarse) formations
– Projects with limited exit space.
• Direct pipe combines the advantages of micro tunneling and HDD with low expected thrust forces
• Products up to 60”/1500mm can be installed over distances up to 1500m
The information contained in the presentation is based on widely accepted theories; calculations and practices, conditions may vary and information in the
presentation is to be used as a guideline only, no liability is assumed through the use of the theories; calculations and practices.