ZEM-EHERHOBUD · 2019. 10. 25. · • 6 oil switches of МКП-110 kV type with foundation have...

22
ZEM-EHERHOBUD

Transcript of ZEM-EHERHOBUD · 2019. 10. 25. · • 6 oil switches of МКП-110 kV type with foundation have...

Page 1: ZEM-EHERHOBUD · 2019. 10. 25. · • 6 oil switches of МКП-110 kV type with foundation have been dismantled; • 6 SF 6 circuit -breaker of 110kV of 120-SFM-32B type have been

ZEM-EHERHOBUD

Page 2: ZEM-EHERHOBUD · 2019. 10. 25. · • 6 oil switches of МКП-110 kV type with foundation have been dismantled; • 6 SF 6 circuit -breaker of 110kV of 120-SFM-32B type have been

• Conducts activity since 2006

• Two main activities:

Construction of engineering

and energy facilities

Supply of power

equipment

Page 3: ZEM-EHERHOBUD · 2019. 10. 25. · • 6 oil switches of МКП-110 kV type with foundation have been dismantled; • 6 SF 6 circuit -breaker of 110kV of 120-SFM-32B type have been

More than 40 successfully completed EPCI-contracts

Page 4: ZEM-EHERHOBUD · 2019. 10. 25. · • 6 oil switches of МКП-110 kV type with foundation have been dismantled; • 6 SF 6 circuit -breaker of 110kV of 120-SFM-32B type have been

And more than 50 projects for energy construction supply

Page 5: ZEM-EHERHOBUD · 2019. 10. 25. · • 6 oil switches of МКП-110 kV type with foundation have been dismantled; • 6 SF 6 circuit -breaker of 110kV of 120-SFM-32B type have been

ENGINEERING FACILITY CONSTRUCTION

BOILER EQUIPMENT AND TURBINE LINING PRODUCTION PLANT

PK «Power Engineering Plant» urban village Malynivka Reconstruction of existing industrial building

2009-2011

Page 6: ZEM-EHERHOBUD · 2019. 10. 25. · • 6 oil switches of МКП-110 kV type with foundation have been dismantled; • 6 SF 6 circuit -breaker of 110kV of 120-SFM-32B type have been

ENGINEERING FACILITY CONSTRUCTION

EXECUTED:

• Complex of construction and installation works on reconstruction of existing industrial plants and additional buildings with

the total area of 35000 sq.m. and building area 20 ha and putting into operation the object built along with the works:

• Reconstruction of building part of industrial and administration and amenity rooms.

• Supply and installation of all technological equipment in full.

• Supply and installation of 6 two transformer ТП 10/0,4 kV.

• Reconstruction of cubicles10 kV , delivery of equipment for ПС 110/10 kV«Malynivka».

• Filler piece КЛ-10 and 0,4 kV.

• Installation of networks, outside lighting, water delivery, canalization, showerly and faecal in-site utility networks a full scale.

• Construction and installation of pumping system with the water tower.

• Supply and installation of boiling room including 2 boilers ДКВР and the complex of gas engine generator.

• Execution of land improvements, including in-site asphaltic roads;

• Putting the object into operation.

Page 7: ZEM-EHERHOBUD · 2019. 10. 25. · • 6 oil switches of МКП-110 kV type with foundation have been dismantled; • 6 SF 6 circuit -breaker of 110kV of 120-SFM-32B type have been

HEAT POWER ENGINEERING OBJECT CONSTRUCTION

Second construction stage of the station «Pozniaky» Kyiv

November 2016 - November 2017

Page 8: ZEM-EHERHOBUD · 2019. 10. 25. · • 6 oil switches of МКП-110 kV type with foundation have been dismantled; • 6 SF 6 circuit -breaker of 110kV of 120-SFM-32B type have been

HEAT POWER ENGINEERING OBJECT CONSTRUCTION

EXECUTED: • Installation of foundations of boiler room, pumproom, smoke-induced room and foundations of two gas boilers;

• Delivery and installation of metal constructions frame, boiler room, pumproom, smoke-induced room , enclosure structures made from sandwich panels, membrane roof construction;

• Delivery and installation of heating conduit, diameter up to 1020 mm included as well as pipes of auxiliary equipment of the substation;

• Delivery and installation of water boiler КВ-Г-116,3-150 with a capacity of 100 Hkal/hour, blower ВДН-18 with frequency regulated and complex of technical process auto control (АСУ ТП);

• Delivery and installation of smoke flue elements with the hookup point into exsting reinforced concrete smoke pipe 80 m high;

• Delivery and installation of complex station-service switchboard 6 kV (КРУСН-6kV), complex switchboard 0,4 kV (КРУ-0,4kV), two dry type transformers 6/0,4 kV 1000 kVA, with cabal lines 6 kV made from crossed linked polyethylene;

• Delivery and installation of two cubicles 6 kV for ПС 110/6 kV «Yuzhnaya» with the complex of installation and pre-commissioning works;

• Delivery and installation and adjusting of technical process auto control АСУ ТП realized at Honeywell construction;

• Pre-commissioning works of all thermotechnical and electrical equipment of АСУ ТП system;

• Delivery and installation of additional ventilation systems and climate control, gas suppression system, clock system, phone line;

• Execution of works on installation of external engineer nets and installation of technological gas pipe of 700mm diameter;

• Execution of land improvements, including in-site asphaltic roads;

• Pre-commissioning works on station equipment with the combined testing;

• Putting the object into operation. Works were executed within the conditions of new construction.

Page 9: ZEM-EHERHOBUD · 2019. 10. 25. · • 6 oil switches of МКП-110 kV type with foundation have been dismantled; • 6 SF 6 circuit -breaker of 110kV of 120-SFM-32B type have been

ENERGY GENERATION

Equipment Supply for the construction of Cherepetska HPP,

units №№ 8&9, 225 MW 2012 – 2013

Page 10: ZEM-EHERHOBUD · 2019. 10. 25. · • 6 oil switches of МКП-110 kV type with foundation have been dismantled; • 6 SF 6 circuit -breaker of 110kV of 120-SFM-32B type have been

ENERGY GENERATION

EXECUTED:

• Boiler equipment supply TPE-223 steam capacity 630 t/h for units №№ 8 & 9;

• Turbine pipelines supply for piping of turbine K-225-12,8-4P for units №№ 8 & 9;

• Procurement of high and middle pressure station pipelines for units №№ 8 & 9 (HPP, CPP, PV etc.).

New Units were constructed within the conditions of operating station

Page 11: ZEM-EHERHOBUD · 2019. 10. 25. · • 6 oil switches of МКП-110 kV type with foundation have been dismantled; • 6 SF 6 circuit -breaker of 110kV of 120-SFM-32B type have been

A HYDRO POWER PLANT CONSTRUCTION

RECONSTRUCTION OF HPP «NOVOSHICHI»

2012

Page 12: ZEM-EHERHOBUD · 2019. 10. 25. · • 6 oil switches of МКП-110 kV type with foundation have been dismantled; • 6 SF 6 circuit -breaker of 110kV of 120-SFM-32B type have been

A HYDRO POWER PLANT CONSTRUCTION

EXECUTED:

• Inspection of reinforced concrete and metal structures of the dam; • Development of a working draft of a hydroelectric power station; • A complex of construction works on clearing the reservoir bed and creating sewn dams; • The complex of construction works on the device downstream drainage; • Production and installation of gates of the culvert dam; • Fabrication and installation of gates and wired grids of the HES water intake device; • The construction of a power plant and a tail drain; • Installation of electro-mechanical equipment; • Installation of a 10 / 0.4 kV power distribution substation; • Supply and installation of auxiliary systems, ventilation, fire extinguishing systems, fire and security alarms,

telephone network; • A set of works on the installation of external engineering networks was completed. Landscaping completed; • Commissioning work was completed on the station equipment with a comprehensive test; • Commissioning of the facility.

Page 13: ZEM-EHERHOBUD · 2019. 10. 25. · • 6 oil switches of МКП-110 kV type with foundation have been dismantled; • 6 SF 6 circuit -breaker of 110kV of 120-SFM-32B type have been

AN ELECTRIC POWER FACILITY RECONSTRUCTION

Reconstruction of substation 110/10/6 kV «Vyshgorod»

Providing power of Кyiv HEP in Ukrainian energy system December 2013 – May 2014

Page 14: ZEM-EHERHOBUD · 2019. 10. 25. · • 6 oil switches of МКП-110 kV type with foundation have been dismantled; • 6 SF 6 circuit -breaker of 110kV of 120-SFM-32B type have been

AN ELECTRIC POWER FACILITY RECONSTRUCTION

EXECUTED: • 6 oil switches of МКП-110 kV type with foundation have been dismantled;

• 6 SF 6 circuit-breaker of 110kV of 120-SFM-32B type have been installed, six sets of current transformer 110kV of ТФЗМ-

110-Б-IVУ1 type, 1 set of voltage transformer 110 kV of НКФ-110-II-У1 type with foundation;

• Installation earthing ring and new cable trays;

• Modification of entrances and bus arrangement 110 kV, re-laying of two ВЛ-110 kV for electric substation;

• Delivery of installed binders of ЯПВ, ЯОВ, ЯЗВ, ЯЗ types, relay boards;

• All commissioning works have been executed;

• Outdated net bar of substation was replaced with reinforced concrete fence

All works were executed within the conditions of operating substation 110 kV

Page 15: ZEM-EHERHOBUD · 2019. 10. 25. · • 6 oil switches of МКП-110 kV type with foundation have been dismantled; • 6 SF 6 circuit -breaker of 110kV of 120-SFM-32B type have been

SCOPE OF WORK

Execution of EPCI-contracts includes:

- project works; - selection and delivery of equipment; - installation and construction works; - startup and commissioning of equipment; - staff training; - placing in operation.

Page 16: ZEM-EHERHOBUD · 2019. 10. 25. · • 6 oil switches of МКП-110 kV type with foundation have been dismantled; • 6 SF 6 circuit -breaker of 110kV of 120-SFM-32B type have been

DESIGN WORK

We cooperate with leading project organizations:

Page 17: ZEM-EHERHOBUD · 2019. 10. 25. · • 6 oil switches of МКП-110 kV type with foundation have been dismantled; • 6 SF 6 circuit -breaker of 110kV of 120-SFM-32B type have been

We supply equipment our own manufactured and our partners:

PARTNERS

Page 18: ZEM-EHERHOBUD · 2019. 10. 25. · • 6 oil switches of МКП-110 kV type with foundation have been dismantled; • 6 SF 6 circuit -breaker of 110kV of 120-SFM-32B type have been

The execution of installation and construction works is conducted in

compliance with all state estimate norms and safety measures

Page 19: ZEM-EHERHOBUD · 2019. 10. 25. · • 6 oil switches of МКП-110 kV type with foundation have been dismantled; • 6 SF 6 circuit -breaker of 110kV of 120-SFM-32B type have been

All supplied equipment is tested, readjusted and approbated

Page 20: ZEM-EHERHOBUD · 2019. 10. 25. · • 6 oil switches of МКП-110 kV type with foundation have been dismantled; • 6 SF 6 circuit -breaker of 110kV of 120-SFM-32B type have been

Project ends up with putting the object into operation

Page 21: ZEM-EHERHOBUD · 2019. 10. 25. · • 6 oil switches of МКП-110 kV type with foundation have been dismantled; • 6 SF 6 circuit -breaker of 110kV of 120-SFM-32B type have been

For 14 years of company existence :

27

19

0 0

19 projects included equipment supply

12

24

9

12 projects made within new construction conditions

Новые объекты Реконструкции Модернизации

New objects

0 0

32

13

32 projects completed in capacity of prime contractor

Reconstructions Modernization

Page 22: ZEM-EHERHOBUD · 2019. 10. 25. · • 6 oil switches of МКП-110 kV type with foundation have been dismantled; • 6 SF 6 circuit -breaker of 110kV of 120-SFM-32B type have been

We highly appreciate partnership and we believe it is the most significant component of company success in terms of achieving goals and follow

its mission:

Creation of modern new level energy objects that correspond to the highest

world standards of effectiveness, ecology, quality and safety.