Wendover Renovation Presentation
2011-2012
Presentation Overview
Renovation Stages◦Before◦Now◦After
How you will be affected
Questions/Concerns
Story Behind this School
This school was built in 1970 as a temporary school and was designed to last only twenty years.
So, in 1990 it should have been demolished and rebuilt.
But now, in 2012, it is being renovated.
Let’s get on to the stages…
Renovation Stages - Before
Front Side of Wendover
Water DamageBoarded Windows
Renovation Stages - Before
No Central Air Conditioning◦Over the years, there has been a couple air
conditioners added on to the building that mostly cool down rooms that don’t have windows.
Renovation Stages - Before
Other parts of the building that are damaged.
Renovation Stages - Before
Renovation Stages - Before
Renovation Stages – Before
Renovation Stages - Now
These pictures show a general idea of what is going on now.
The ceiling tiles were removed during Christmas break. Since they are gone, it will be slightly colder in the hallways.
Renovation Stages - Now
During the time period of the renovation, the equipment and trailers are going to be stored on the football field. It is still to be decided whether or not the football teams will be consolidated into one team next year.
Overview
Renovation Stages - Now
PHASE 1 – *Cafeteria* and Band Room (December 2011 – August 2012)
Renovation Stages - Now
PHASE 1 – *Cafeteria* and Band Room (December 2011 – August 2012)
Renovation Stages - After
Renovation Stages - Now
PHASE 1 – Cafeteria and *Band Room* (December 2011 – August 2012)
Renovation Stages - Now
PHASE 1 – Cafeteria and *Band Room* (December 2011 – August 2012)
Renovation Stages - After
Along with the cafeteria and the band room, there will be a server room where the old instrument storage room used to be. Also there will be an electrical room where the old weightroom used to be.
Renovation Stages - After
PHASE 2 – Kitchen and Storage(April 2012 – August 2012)
Renovation Stages - After
PHASE 2 – Kitchen and Storage(April 2012 – August 2012)
Renovation Stages - After
PHASE 3 – 8th Grade Hallway and Courtyard B (May 2012 – August 2012)
The new 8th grade hallway will be where rooms 127 and 128 are now. Also, Courtyard B will be between the 7th grade hallway and the 8th grade hallway. Also, there will be the new TV Studio where room 100 is now.
Renovation Stages - After
PHASE 4 – *6th Grade Hallway, Courtyard A,* Art Rooms, Chorus Room and Music Room
(September 2012-December 2012)
Renovation Stages - After
PHASE 4 – 6th Grade Hallway, Courtyard A, *Art Rooms, Chorus Room and Music Room*
(September 2012-December 2012)
Renovation Stages - After
PHASE 5 – *7th Grade Hallway*, Library, Health Room, Computer Lab
(January 2013 – May 2013)
Renovation Stages - After
PHASE 5 – 7th Grade Hallway, *Library, Health Room, Computer Lab*
(January 2013 – May 2013)
Renovation Stages- After
PHASE 6 – FCS, Computer Lab, Gym(March 2013 – August 2013)
Renovation Stages - After
PHASE 7 – Hallways and Entrance(June 2013 – August 2013)
Renovation Stages - After
PHASE 8 – Admin Offices and Auditorium(June 2013 – November 2013)
By the end of November 2013, this school will be complete.
How You Will Be Affected
On the first week of May, lunches will be moved into the front side of the gym.
Also in May, the classes in the back hallway will be moved into the auditorium.
ANY QUESTIONS?