  • Waterton Lakes National Park Section 00 01 10 Prince of Wales Trail Improvements TABLE OF CONTENTS PCA Project No. 2051C Page 1 of 2

    TABLE OF CONTENTS Pages

    Division 00 - Procurement and Contracting Requirements

    Section 00 01 10 - Table Of Contents .......................................................................................... 2 Section 00 01 15 - Drawing List .................................................................................................. 1

    Division 01 - General Requirements

    Section 01 11 00 - Summary Of Work ......................................................................................... 3 Section 01 27 00 - Measurement and Payment............................................................................. 8 Section 01 28 00 - Site-Specific Work Restrictions...................................................................... 2 Section 01 28 01 - General Work Restrictions ............................................................................. 5 Section 01 29 00 - Alternatives ................................................................................................... 1 Section 01 31 19 - Project Coordination ...................................................................................... 3 Section 01 32 16 - Construction Progress Schedule ..................................................................... 3 Section 01 33 00 - Submittal Procedures ..................................................................................... 2 Section 01 35 29 - Health And Safety Requirements ................................................................... 3 Section 01 35 43 - Environmental Procedures ............................................................................. 8 Section 01 41 00 - Regulatory Requirements ............................................................................... 1 Section 01 45 00 - Quality Control .............................................................................................. 3 Section 01 52 00 - Construction Facilities ................................................................................... 2 Section 01 55 26 - Traffic Accommodation ................................................................................. 2 Section 01 61 00 - Common Product Requirements ..................................................................... 4 Section 01 71 00 - Examination And Preparation ........................................................................ 3 Section 01 74 19 - Waste Management And Disposal .................................................................. 2 Section 01 77 00 - Closeout Procedures ....................................................................................... 2 Section 01 78 00 - Closeout Submittals ....................................................................................... 5

    Division 02 - Existing Conditions

    Section 02 41 13 - Selective Site Demolition ............................................................................... 3 Section 02 41 14 - Asphalt Paving Removal ................................................................................ 2

    Division 03 - Concrete

    Section 03 10 00 - Concrete Forming And Accessories ............................................................... 2 Section 03 20 00 - Concrete Reinforcing ..................................................................................... 2 Section 03 30 00 - Cast-in-Place Concrete ................................................................................... 5

    Division 05 - Metals

    Section 05 12 33 - Structural Steel .............................................................................................. 4 Section 05 50 00 - Metal Fabrications ......................................................................................... 3

    Division 06 - Wood, Plastics and Composites

    Section 06 15 00 - Wood Fabrications ......................................................................................... 2

  • Section 00 01 10 Waterton Lakes National Park TABLE OF CONTENTS Prince of Wales Trail Improvements Page 2 of 2 PCA Project No. 2051C

    Division 31 - Earthwork

    Section 31 05 16 - Aggregate and Rock Materials ....................................................................... 6 Section 31 36 00 - Gabions ......................................................................................................... 2

    Division 32 - Exterior Improvements

    Section 32 00 01 - Subgrade Preparation ..................................................................................... 1 Section 32 00 02 - Granular Base Course .................................................................................... 2 Section 32 00 03 - Asphalt Concrete Pavement ......................................................................... 11 Section 32 12 13 - Asphalt Prime Coat ........................................................................................ 3 Section 32 17 23 - Pavement Markings ....................................................................................... 1 Section 32 33 00 - Site Furnishings ............................................................................................. 4 Section 32 44 00 - Trail Construction .......................................................................................... 4 Section 32 55 00 - Stone Work .................................................................................................... 5 Section 32 91 19 - Sod Placement and Final Grading................................................................... 2 Section 32 91 20 - Seeding .......................................................................................................... 2

    END OF TABLE

  • Waterton Lakes National Park Section 00 01 15 Prince of Wales Trail Improvements DRAWING LIST PCA Project No. 2051C Page 1 of 1

    Part 1 General

    1.1 DRAWING LIST

    Drawing No. Title 1 Cover Sheet 2 Overall Plan 3 Environmental Management Plan 4 Plan 1 of 9 5 Plan 2 of 9 6 Plan 3 of 9 7 Plan 4 of 9 8 Plan 5 of 9 9 Plan 6 of 9 10 Plan 7 of 9 11 Plan 8 of 9 12 Plan 9 of 9 13 Landscape Details 1 of 4 14 Landscape Details 2 of 4 15 Landscape Details 3 of 4 16 Landscape Details 4 of 4 17 Lookout Area Plan 18 Lookout Area Details 19 Signage Plan 1 of 5 20 Signage Wayfinding 2 of 5 21 Signage Details 3 of 5 22 Signage Details 4 of 5 23 Signage Location Map 5 of 5

    END OF SECTION

  • Waterton Lakes National Park Section 01 11 00 Prince of Wales Trail Improvements SUMMARY OF WORK PCA Project No. 2051C Page 1 of 3

    Part 1 General

    1.1 DEFINITIONS .1 ‘PCA’ refers to Parks Canada Agency.

    .2 ‘WLNP’ refers to Waterton Lakes National Park.

    .3 ‘PoW’ or ‘POW’ refers to the Prince of Wales Hotel and surrounding area.

    .4 ‘LL’ refers to Linnet Lake.

    .5 ‘EB’ refers to Emerald Bay.

    .6 ‘Work’ refers to the provision of all labour, services, material and equipment as necessary for the Contractor to complete and perform their obligations in accordance with the Contract.

    .7 ‘Consultant’ refers to Dillon Consulting Limited (Dillon).

    .8 ‘Owner’ or ‘Departmental Representative’ refers to the Parks Canada Agency (PCA) Project Manager or their duly authorized representative.

    .9 ‘ESO’ refers to a PCA Environmental Surveillance Officer.

    .10 ‘BMP’ refers to Best Management Practices. BMP’s are documents prepared by PCA that outline specific measures to be taken when carrying out various activities within WLNP.

    1.2 PROJECT LOCATION .1 The project is located in the province of Alberta within WLNP in the vicinity of the

    Prince of Wales Hotel. It is located along Highway 5 approximately 8 km from the entrance to WLNP.

    1.3 WORK COVERED BY CONTRACT DOCUMENTS .1 Read this section in conjunction with Drawings and other specifications.

    .2 The general scope of work includes, but may not be limited to, the following:

    .1 Mobilization and demobilization

    .2 Traffic accommodation

    .3 Waste management and disposal

    .4 LL parking area improvements

    .5 LL trail improvements

    .6 LL Salamander Crossing Erosion Control

    .7 Construction of new asphalt trails, LL trail and POW

    .8 Resurfacing of existing asphalt trails, LL trail

    .9 Construction of new bench cut trails

    .10 Construction of new crowned trails

    .11 Construction of new gravel aggregate trails

    .12 Construction of trail drainage improvements

  • Section 01 11 00 Waterton Lakes National Park SUMMARY OF WORK Prince of Wales Trail Improvements Page 2 of 3 PCA Project No. 2051C

    .13 Abandoned trail rehabilitation

    .14 Construction of POW lookout

    .15 EB parking area improvements

    .16 EB water access improvements

    .17 Construction of new gabion walls

    .18 New Trail Head Type 1 Signage

    .19 New Trail Head Type 2 Signage

    .20 New Trail Head Type 3 Signage

    .21 New Informational Signage

    1.4 COMPLETE PROJECT .1 Unless specifically stated otherwise, the Contractor shall supply all transportation, labour,

    materials, tools, equipment and all other incidentals required to complete the Work. The intent is that the Contractor provides a complete product.

    .2 Where it is clear from the contract documents that a particular element of Work is required, but payment terms for that element is not explicitly identified in the specifications, that element of the Work shall be considered to be incidental to the overall project. No separate or additio