UltraDeck · 18 Railing Installation: Fusion ... Your installation guide for UltraDeck ... on page...

20
UltraDeck ® Decking & Railing Installation Guide www.midwestmanufacturing.com

Transcript of UltraDeck · 18 Railing Installation: Fusion ... Your installation guide for UltraDeck ... on page...

Page 1: UltraDeck · 18 Railing Installation: Fusion ... Your installation guide for UltraDeck ... on page 14 for installation instructions. Fig. 1

UltraDeck® Decking & Railing Installation Guide

www.midwestmanufacturing.com

Page 2: UltraDeck · 18 Railing Installation: Fusion ... Your installation guide for UltraDeck ... on page 14 for installation instructions. Fig. 1

Table of Contents:2 General Guidelines for Deck Installation4 Plank Board Installation6 QuickCap™ Installation8 Cladding & Endcap Installation9 General Guidelines for Rail Installation10 Railing Installation: Method 112 Railing Installation: Method 214 Railing Installation: Method 316 Railing Installation: Pinnacle18 Railing Installation: Fusion®20 Frequently Asked Questions & Warranty

General Guidelines for Deck Installation

• Hidden Fastening System• Available in 8' long stainless

steel or brown powder coated finish.• 3/4" premium screws are

recommended for bracket to joist and plank to bracket connections.

• Hidden Fastening System • Naturally gaps the planks

3/16" apart, saving you measuring time.

• Color-matched composite deck screws.

• Designed to be applied over existing decking

• Naturally gaps the planks 7/32" to 3/8".

DEKMOUNTDesigned for use with UltraDeck®

RusticTM, NaturalTM, & Fusion®; Recommended for radius edge boards

T-CLIP™ & ULTRACLIPDesigned for use with UltraDeck®

RusticTM, NaturalTM, & Fusion®

SURFACE SCREWINGDesigned for use with UltraDeck®

RusticTM & NaturalTM Radius Board

QUICKCAP™Designed only for use with UltraDeck® QuickCapTM

Fastening Systems:

Once you decide which way the deck boards will run, determine the span between the joists. Always adjust the joist span to accommodate the deck pattern and stairs. Be sure the foundation is sound, level, and use a minimum of two fasteners for attachment of deck boards to each joist. Be sure to check local codes for additional requirements and information. Additional framing will be required for all butt joints. See nailer board information in Plank & End Gapping. 12" o.c. maximum

45° Deck Pattern

12" o.c.. maximum

Perpendicular Stair Pattern

16" o.c.. maximum

Perpendicular Deck Pattern

Deck Framing Requirements:

Your installation guide for UltraDeck® decking

2

T-ClipTM UltraClip

UltraDeck® Fading Information

All UltraDeck® products are created from a wood and plastic polymer composition which lets you create a low-maintenace outdoor space without having to worry about cracking, splintering, rot, or insects. The Fusion Decking and Railing products are produced with an added cap layer that provides the most fade resistance.

Fading will occur at different rates depending on sun exposure of the products. Vertical applications such as spindles will fade at a slightly different rate than decking, as the sun exposure is different in these two areas. Over time, all Natural, Rustic, and QuickCap decking and railing will fade to a similar shade.

See the UltraDeck® Decking and Railing book for color charts and fading information.

Page 3: UltraDeck · 18 Railing Installation: Fusion ... Your installation guide for UltraDeck ... on page 14 for installation instructions. Fig. 1

3

When installing UltraDeck® decking, gapping guidelines must be followed to ensure that gaps between decking and end gaps allow for proper expansion/contraction, drainage, and the shrinking of treated wood joists that can happen over time.

3/4"

1/32" to 1/4" GapPer Gapping Chart

Surface Screwing

Nailer BoardsAn additional nailer board will need to be added to the framing material at any butt joint connection to properly end gap UltraDeck® planks. See Figure 2.

Plank & End Gapping:

*For QuickCapTM end gapping, see page 8

!

T-ClipsTM

Install two UltraDeck® T-Clips™ to each board at every end gap. The additional nailer boards must be used to aid in supporting the deck planks and proper T-Clip™ placement. See Figure 2.

Rustic™, Natural™, & Fusion®

For every 16' of plank, allow a 1/16" gap for every 20°F temperature difference between the time of board installation and the maximum expected temperature (refer to the end gapping chart, Figure 1). With all fastening methods, make sure to use two fasteners for attachment of deck boards to each joist.

DekMountInstall DekMount onto each joist by screwing a 3/4" premium screw through side hole in DekMount. Install deck planks one at a time, from the house or walled structure, working your way outward.

Surface ScrewingWhen using screws through the top side of decking, at each end of the plank, pre-drill and sink screws at least 3/4" away from the edge of the plank to prevent splitting. Do not over tighten the fasteners. See Figure 3.

Note: UltraDeck® Post Sleeves are designed to fit over dimensional 4x4 posts. If the 4x4 posts you are using are outside of standard, trimming or shimming of the 4x4 edges may be required. Check fit of the 4x4 post into the Post Sleeve prior to attaching it to your deck structure and make any changes to the 4x4 if needed.

4x4 PostJoist Members

Reinforcement Blocking

Rim Joist(2) 1/2” x 6” Lag Screws

5-1/4” Apart

A deck board installed as a joining board at the seams will minimize the look of end to end contraction by separating the visual gap.

End Gapping Solutions

4x4 Post

Rim Joist

Joist Members

Reinforcement Blocking

(3) 3” Screws

Installing Posts to Deck Substructure:

Step 1: Determine the location and install the 4x4 treated posts to the substructure. The maximum post spacing is 6' between posts. Do not notch 4x4 railing posts unless using Method 3.Step 2: Use blocking that is the same size and dimension as the joist members to reinforce the side of the 4x4 post opposite the rim joist. Step 3: Use three 3" quality deck screws for attaching each end of blocking to joist.Step 4: Secure 4x4 treated post to the rim joist and reinforcement blocking using two 6" lag screws (with a minimum spacing of 5-1/4" apart.) Countersink the lag screws if using UltraDeck® Cladding.

*For deck designs including railing

2

Note: Method 3 railing will require U-Top-It posts. See Method 3 on page 14 for installation instructions.

Fig. 1

Fig. 3Fig. 2

Additional Nailer Boards

Additional Nailer Board

UltraDeck®

T-Clips™

1/32" to 1/4" Gap Per Gapping Chart

T-Clip

Fig. 2

Page 4: UltraDeck · 18 Railing Installation: Fusion ... Your installation guide for UltraDeck ... on page 14 for installation instructions. Fig. 1

When installing decking with a T-Clip, the fasteners will automatically set the side-to-side gapping of the decking. If installing decking using DekMount or surface screwing options (see Fastening Systems on page 2) a minimum of 3/16” gap will need to be left between planks. If the temperature is below 40˚ F at the time of installation, a 3/8” gap is recommended.

3/16” to 3/8” Gap

Side-to-Side Gapping

Plank Board Installation: Your installation guide for Rustic™, Natural™, & Fusion® decking

Side-to-Side Gapping:

Follow the deck framing tips and the plank gapping, end gapping pages to begin your plank installation. These steps are key to ensure your decking is properly installed to last for many years.

Installing Planks that Run Parallel to a HouseBegin by securing UltraDeck® T-ClipsTM to the ledger along the house at every joist. Slide the deck board into place. Slide the UltraDeck® plank into place.

Install a row of UltraDeck® T-ClipsTM at every joist along the deck frame (A). Then, slide the next UltraDeck plank into place (B). Attach the next row of UltraDeck® T-ClipsTM, sliding the next plank into place (C). Continue this process until the deck surface is covered.

Pre-drill the last UltraDeck® plank along the outer lip every 8". Fasten it to the rim joist with 1-5/8" premium deck screws. Do not use UltraDeck® T-ClipsTM to secure the outside edge of the last board.

Installing Planks that Run Perpendicular to a HouseBegin by pre-drilling the first plank along the outer lip every 8". Fasten the plank to the rim joist with 1-5/8" premium deck screws. UltraDeck® T-ClipsTM are not used on the outside edge of the first board.

Install a row of UltraDeck® T-ClipsTM at every joist along the deck frame (A). Then, slide the next UltraDeck plank into place (B). Attach the next row of UltraDeck® T-ClipsTM, sliding the next plank into place (C). Continue this process until the deck surface is covered.

Pre-drill the last UltraDeck® plank along the outer lip every 8". Fasten it to the rim joist with 1-5/8" premium deck screws. Do not use UltraDeck® T-ClipsTM to secure the outside edge of the last board.

T-Clip™ Installation:

!

START

8" Apart

START

A B

C

Parallel Perpendicular

1A

2

3

1B

2

3

Note: T-Clips have arrows on them to show which way of installation. Always have arrows pointing towards last completed deck board. Make sure all arrows are facing the same direction.

4

1A

2

3

1B

Page 5: UltraDeck · 18 Railing Installation: Fusion ... Your installation guide for UltraDeck ... on page 14 for installation instructions. Fig. 1

5

DekMount Installation:

Surface Screwing Installation:

Note: When using this method, use composite deck screws, or 2-1/2" conventional deck screws. Composite deck screws are recommended for this application, as they pull shavings into the screw hole, eliminating the "mushrooming effect". When using conventional deck screws, you must pre-drill and countersink for each screw to avoid the "mushrooming effect".

Begin screwing, keeping screws at least 3/4" away from the edge or end of the plank to prevent splitting. It is necessary to pre-drill and countersink at each end of an UltraDeck® board. Always add additional nailer boards at butt seams (see page 3). Do not over tighten fasteners. When fastening NaturalTM Radius planks, screws must be passed through the interior channel to avoid compression of the planks (2 screws must be placed on each board at every joist).

Install DekMount onto each joist by screwing a 3/4" premium screw through side hole in DekMount. DekMount should be flush on top of the joist and flat against the side of the joist. DekMount is easily cut with snips to fit in any required length. Stagger DekMount butt joints so they don't land in the same location on each joist. 12" is recommended for staggering of butt joints.

Install deck planks one at a time, from the house or walled structure, working your way outward. This allows you to reach the last plank attached from beneath the deck. The deck planks should be located and spaced using side to side and end gapping charts before screwing. Screw from the bottom; for best results, do not screw at the edge. By kneeling on top of the plank and reaching underneath, the screws are driven upwards through the DekMount and into the plank. DekMount is designed to provide for a minimum of 2 holes for each plank. If the deck is elevated and is easier to fasten from below the deck, another person should be on top of the deck, not only to ensure proper spacing, but to provide weight; allowing the screws to securely anchor deck board.

1

2

3/4" Screws

DekMount Hidden Fastening System

DekMount Hidden Fastening System

Joist

1

1

*For all RusticTM boards & NaturalTM radius boards only

1

4

2

Note: Use of clamp to secure board in place prior to fastening will aid in installation.i

Rustic boards

Natural radius edge boards

Note: For radius board installation, follow DekMount or surface screwing installation instructions.

If installing decking planks with T-ClipsTM, follow Step 3 of T-ClipTM installation on final grooved deck (at perpendicular joists only).

For deck framing perimeter applications, additional bridging joists every 16" may be required to support radius edge boards installed in perimeter applications.

Page 6: UltraDeck · 18 Railing Installation: Fusion ... Your installation guide for UltraDeck ... on page 14 for installation instructions. Fig. 1

QuickCap™ Installation: Your installation guide for QuickCap™ decking

If two QuickCapTM boards are spliced, a joining board installed at the seams will minimize the amount of visual end-to-end gap, Figure 3. This is done by separating the end-to-end gapping. If splices are needed and the joining board method is not used, it is recommended to stagger splices by two feet or more and use QuickCapTM Fasteners 3/4" to 2" at each side of the splice, Figure 4. QuickCapTM boards expand and contract with temperature changes. Follow the End Gapping Chart if any splices are needed to cover the surface of your old deck, Figure 5.

!QuickCap™ End Gapping:

QuickCap™ Site Preparation:Check the condition of your current deck to make sure it is sound. If any part of the substructure or the surface is showing decay, make repairs prior to installing the QuickCapTM boards. Any raised or twisted boards should be fastened down with quality 3" premium deck screws, tightened until the deck surface is level, Figure 1. If there are any areas where two deck boards come together end to end on top of a joist, the joist should be in-spected for structural stability (an additional joist should be added if needed). If using additional screws and joists is not successful in smoothing out the deck surface, sand down any raised edges using an abrasive sanding disk attached to an angle grinder, Figure 2. Existing decking must be prop-erly side gapped to provide proper drainage.

!

Fig. 2

Old deck QuickCap™ deck (diagonal installation)

6

Fig. 1 Fig. 3

Fig. 5

UltraDeck® QuickCapTM Fasteners on both ends of the splice

Fig. 4

Page 7: UltraDeck · 18 Railing Installation: Fusion ... Your installation guide for UltraDeck ... on page 14 for installation instructions. Fig. 1

7

QuickCap™ Installation:Snap a chalk line, parallel to the existing surface, at 1-1/2" in from the edge of the deck to act as a reference. Add an additional chalk line every 16" to mark the placement of each QuickCap™ fastener. If the chalk line falls in the gap between the existing deck boards, move the line back until the line is at least 3/4" in from the edge of the existing deck boards. This will decrease the space between this line and the previous line making sure the chalk lines do not exceed the recommended 16" spacing. The 16" spacing for additional lines will continue from this adjusted line.

Color-matched cladding screws may be used to attach the first section of the QuickCap™ boards along the outside edge of the deck. Pre-drill and countersink each screw. These screws should be placed every 16" and go through the first leg that is at least 1-1/4" in from the outside edge.

Install a row of QuickCap™ fasteners on the chalk lines, one every 16". Then slide the QuickCap™ plank into place. Continue this process until the deck surface is covered. Do not over tighten the fasteners; this will not allow the clip head to line up with the groove in the plank.

QuickCap™ boards can be ripped down when less than a full width is needed. Fasten the unaltered edge of the board to the existing deck with a QuickCap™ Fastener. Then fasten the altered edge by pre-drilling and fastening with color matched cladding screws to the cut side of the board.

Color-matched cladding screws may be used to attach the last section of the QuickCap™ boards along the outside edge of the deck. Pre-drill and countersink each screw. These screws should be placed every 16" and go through the first leg that is at least 1-1/4" in from the outside edge.

Cut end ofQuickCap™

Color-matchedcladding screw

QuickCapTM

Fastener

SupportLeg

SupportLeg Support

Leg

SupportLeg

Outside deck edgePre-Drill

16''

1-1/4''

7/32” to 3/8” Gap

16''

Chalk Lines

1

2

3

4

5

16

2

3

45

Perpendicular installation

Page 8: UltraDeck · 18 Railing Installation: Fusion ... Your installation guide for UltraDeck ... on page 14 for installation instructions. Fig. 1

Cladding Dimensions:UltraDeck® NaturalTM and UltraDeck® Fusion®: 3/8" x 4" x 12'UltraDeck® RusticTM: 7/16" x 10-1/2" x 12'

Cladding will provide a professional finished look to your deck. UltraDeck® cladding can be used as skirting to cover; joist members, elevated support posts, outside edges of board profiles, stair stringers, and other exposed lumber products.

When attaching cladding to the deck frame, use color-matched cladding screws. In order to be sure there is enough room for proper expansion and contraction of the UltraDeck® planks, secure cladding only to the deck frame; not the decking planks. When installing cladding be sure to pre-drill and countersink two screws, starting 1-1/2" from the top and bottom edge of the cladding every 12". Screws should be snug but it is important not to over tighten the screws.

For long distances requiring multiple pieces of UltraDeck® cladding, use opposing miter cuts at the seam to reduce visible joints, Figure 1.

UltraDeck® Cladding UltraDeck® Cladding

Outside Joist

Jois

t

Jois

t

Deck Board

Deck Board

45° Miter Cut on Cladding

Endcaps are a great way to protect your UltraDeck® with hollow profiles by helping create a barrier against moisture, dirt, and insect infestation. They can provide a clean, professional look to end cuts made at a 90° angle. Endcaps are not necessary for any butt joints in the deck. If desired, a silicone adhesive caulk may be used to further secure endcaps to the planks.

Cladding & Endcap Installation: Your installation guide for UltraDeck® Cladding

UltraDeck® Cladding:

UltraDeck® Plank Endcaps:*For NaturalTM boards only

8

Fig. 1

Page 9: UltraDeck · 18 Railing Installation: Fusion ... Your installation guide for UltraDeck ... on page 14 for installation instructions. Fig. 1

9

Your installation guide for UltraDeck® Railing

Cut the UltraDeck® post sleeve to the proper length.

Slide the cut UltraDeck® post sleeve over the 4x4 treated post. When using the UltraDeck® NaturalTM sleeves, be conscious of the orientation of the recessed channel so that all posts have the same appearance. With the UltraDeck® RusticTM, Pinnacle, or UltraDeck Fusion® post sleeves, be sure to slide the ring base to the bottom before installing the railing. Post sleeves are secured to the 4x4 post as the first spindle is fastened to the post sleeve. Install the Post Cap by aligning it with the top of the post sleeve and sliding it into position. A silicone adhesive caulk can be used to secure the post cap to the post sleeve, if desired.

Installing UltraDeck® Post Sleeves:

Note: UltraDeck® Post Sleeves are designed to fit over dimensional 4x4 posts. If the 4x4 posts you are using are outside of standard, trimming or shimming of the 4x4 edges may be required. Check fit of the 4x4 post into the Post Sleeve prior to attaching it to your deck structure and make any changes to the 4x4 if needed. Post sleeves are available in both 48” and 96” lengths. Since decking and railing components are extruded products and post cap and ring base components are injection molded, each will fade at a different rate.

12

3

Inserts, railings, and top caps can be marked for cutting by laying the components on the stairs and marking the angle and length using the installed post as a reference.

On the lines that you marked, trim all pieces to the same angle. This angle will also be used to cut the spindles.

Once railing and spindles are cut to necessary angle and length, follow the appropriate railing instructions (listed below).

Spindle & Handrail Preparation for Stair Rails:

General Guidelines for Rail Installation:

1

2

3

Types of Railing Installation:

Method 1: For UltraDeck® Rustic™ & Natural™ (see page 10)Method 2: For UltraDeck® Rustic™ & Natural™ (see page 12)Method 3: For UltraDeck® Rustic™ & Natural™ (see page 14)Pinnacle: For UltraDeck® Pinnacle (see page 16)Fusion: For UltraDeck® Fusion® (see page 20)

*All UltraDeck® Railing methods are recommended for spans of 6' or less

8

1

i Note: It is very important to verify spindles are all the same length. Measure and cut accordingly.

2

Page 10: UltraDeck · 18 Railing Installation: Fusion ... Your installation guide for UltraDeck ... on page 14 for installation instructions. Fig. 1

Method 1 Railing System:

Railing Installation: Your installation guide for Rustic™ & Natural™

!

Method 1 uses spacer blocks between the spindles, and does not require pre-drilling of the metal insert. Method 1 meets ICBO-ESAC174 Code.

Make sure the post sleeve and ring base have been installed. Make sure post is plumb and level. Properly size the top and lower rail, and metal insert by measuring the distance between the two post sleeves, and cut to desired length. Make sure the spindles are all the same length, measure and cut accordingly.

Top Rail (1)

Post Spindles (2)

3" Composite Deck Screws (6)

Lower Rail (1)

Support BlockCheck with local building code

Post Cap (2)

Spindles Traditional 6' section : ~15Check with local building code

Post Sleeve (2)

Spacer Blocks

Spacer BlocksNumber according to spindles

Number according to spindles

Metal Insert (1)

Ring Base (2)

10

i Note: It is very important to verify spindles are all the same length. Measure and cut accordingly.

To apply this method as a stair rail assembly, please see preparation instructions, page 9.

Top Cap

Post Sleeve

Upper Handrail

Spindle

Base Ring

Spacer blockLower HandrailSupport

block

Rail Section:

Metal insertSpacer block

Page 11: UltraDeck · 18 Railing Installation: Fusion ... Your installation guide for UltraDeck ... on page 14 for installation instructions. Fig. 1

11

Starting with the post spindle set even with the end of the insert, continue down the top rail, evenly spacing spindles, making sure to meet local building code for spacing. Keep in mind an additional post spindle is placed even with the opposite end of the insert. Measure the distance between spindles and cut spindle spacer blocks from UltraDeck® spindles for the upper and lower railing.

The two post spindles will need to be pre-drilled to attach the completed rail to the post sleeves. Using a 1/8" drill bit, drill three holes at a 60° angle in the spindle, spacing them 3-1/2" from the top and bottom, and one on center.

All rail spans over 3' require a spindle support block centered under the lower rail assembly. Check with local building codes and cut the support block to the required height from UltraDeck® spindles.

Starting with one of the post spindles, begin sliding the spacer blocks and spindles into the profile of the metal insert. Make sure the post spindles are flush on the ends of the assembly. Slide the upper handrail over the metal insert. This is intended to be a tight fit; please use soap as a lubricant if needed.

Pre-drill and fasten the spacer blocks and spindles to the top rail using 1" corrosion resistant screws.

To install the support block, attach the block to the bottom side of the lower rail by fastening a screw through the lower rail into the support block.

Slide the spindles and spacer blocks into the profile of the lower railing. Pre-drill and fasten the spacer blocks using 1" corrosion resistant screws.

Position the rail assembly between the post sleeves, following local building code height requirements. Secure the post spindles to the post sleeves using six 3" composite deck screws through the pre-drilled holes.

Align the post caps with the top of the post sleeve and slide into place. A silicone adhesive may be used to secure the cap.

Metal Insert

Spindle

Upper Handrail

1

2

3

4

567

8

9

Method 1 Installation:

4x4 Post

8

4

Spindle

Support Block

Lower Handrail

6 Spindle

Spindle spacer block

Handrail

1" corrosion resistant screws

7

10

Pre-drill spindles at a 60° angle

Metal Insert

PostSpindle

1

Page 12: UltraDeck · 18 Railing Installation: Fusion ... Your installation guide for UltraDeck ... on page 14 for installation instructions. Fig. 1

Method 2 Railing System:

Railing Installation: Your installation guide for Rustic™ & Natural™

!Make sure the post sleeve and ring base have been installed. Make sure post is plumb and level. Properly size the top and lower rail, and metal insert by measuring the distance between the two post sleeves, and cut to desired length. Makes sure the spindles are all the same length, measure and cut accordingly. Cut a 6" piece of metal insert for the support block assembly.

Method 2 does not require spacer blocks between spindles, requires pre-drilling of the metal insert, and the top and lower rail profiles are identical.

12

Top Rail (1)

Post Spindles (2)

3" Composite Deck Screws (6)

Lower Rail (1)

Support BlockCheck with local building code

Post Cap (2)

Spindles Traditional 6' section : ~ 15Check with local building code

Post Sleeve (2)

6" Metal Insert

3-1/2" Premium Deck Screws

Metal Insert (1)

Ring Base (2)

i Note: It is very important to verify spindles are all the same length. Measure and cut accordingly.

To apply this method as a stair rail assembly, please see preparation instructions, page 9.

Rail Section:Top Cap

Post Sleeve

Upper Handrail

Spindle

Base RingSupport block

Lower Handrail(See detail 5)

Metal insert

Page 13: UltraDeck · 18 Railing Installation: Fusion ... Your installation guide for UltraDeck ... on page 14 for installation instructions. Fig. 1

13

Starting with the post spindle, set even with the end of the insert, continue down the top rail, evenly spacing spindles, making sure to meet local building code for spacing. Keep in mind an additional post spindle is placed even with the opposite end of the insert. Pre-drill holes on the metal insert with a 1/4" drill bit, aligning the center of the spindles to the center of the metal handrail insert.

On each end of the spindles, pre-drill the center, using a 1/8" drill bit to avoid splitting. The two post spindles will need to be pre-drilled to attach the completed rail to the post sleeves. Using a 1/8" drill bit, drill three holes at a 60° angle in the spindle, spacing them 3-1/2" from the top and bottom, and one on center.

All rail spans over 3' require a spindle support block centered under the lower rail assembly. Check with local building codes and cut the support block to the required height from UltraDeck® spindles.

Taking the metal insert, begin to slide the spindles into place, aligning the pre-drilled holes. Starting with the center spindle, attach metal insert and spindles using 3-1/2" premium deck screws. Attach post spindles flush on the two ends of the assembly. Remember spindles must be cen-tered to ensure ease of assembly when attaching the top rail. Do not use composite deck screws.

Position the lower rail so the spindles will rest on the top side of the rail. Secure the spindles to the rail from the underside using quality 3-1/2" premium deck screws. Do not use composite deck screws. Screws should be snug; do not over tighten.

Slide the top rail onto the metal insert with attached spindles. This is intended to be a tight fit; please use soap as a lubricant if needed.

To install the support block, take the 6" piece of metal insert, slide the support block into the profile of the insert, and secure with a premium deck screw. Slide the insert to the center of the lower rail.

Position the rail assembly between the post sleeves, following local building code height requirements. Secure the post spindles to the post sleeves using six 3" composite deck screws through the pre-drilled holes.

Align the post caps with the top of the post sleeve and slide into place. A silicone adhesive may be used to secure the cap.

Method 2 Installation:

1

2

3

4

5

67

8

9

Spindle

Metal Insert

Upper Handrail

Lower Handrail

Spindle

6" Metal Insert

Support Block

Lower Handrail

Deck Screws

12

4, 6 7

4x4 Post

8

5

Pre-drill spindles at a 60° angle

iNote: Make sure screw is centered. If screw head falls out of groove, sliding rail may be difficult.

i

Page 14: UltraDeck · 18 Railing Installation: Fusion ... Your installation guide for UltraDeck ... on page 14 for installation instructions. Fig. 1

Railing Installation: Your installation guide for Rustic™ & Natural™

Method 3 Railing System:

! If using cladding, it should be installed before railing. Lag bolts must be countersunk to allow for post sleeve. Make sure the notched post sleeves have been installed. Make sure the post is plumb and level. Properly size the top rail and insert by measuring the distance between the two post sleeves, and cut to desired length. Make sure the spindles are all the same length, measure and cut accordingly.

Method 3 uses the U-Top-It posts, requires pre-drilling of the metal insert, and uses field cut beveled spindles to secure to the perimeter deck joists.

Top Rail (1)Metal Insert (1)

Post Spindle (2)

Spindles

Post Cap (2)

Post Sleeve (2)

3" Composite Deck Screws (6)

3-1/2" Premium Deck Screws

3" Premium Deck Screws

Traditional 6’ section: ~ 15Check with local building code

14

i Note: It is very important to verify spindles are all the same length. Measure and cut accordingly.

To apply this method as a stair rail assembly, please see preparation instructions, page 9.

Rail Section:

Post Sleeve

Top Cap

Handrail

Spindle

Cladding (if using cladding, see detail 1). Cladding will need to be trimmed where post sleeves sit.

Deck board(will need to be cut, see detail 6)

Joist

Additional nailer board

Metal insert

Page 15: UltraDeck · 18 Railing Installation: Fusion ... Your installation guide for UltraDeck ... on page 14 for installation instructions. Fig. 1

15

Install cladding (if desired). See page 8 for cladding installation. Install U-Top-It Posts onto joist and flat against cladding with two countersunk lag bolts and additional nailer boards if decking needs to be cut.

Cut post sleeves to match U-Top-It Posts. A small piece of cladding may be used to finish the bottom of the U-Top-It Post.

Evenly space the spindles on the sized metal insert to meet local building code. Pre-drill holes on the metal insert with a 1/4" drill bit, aligning the center of the spindles to the center of the metal handrail insert.

On the top side of all the spindles, pre-drill the center, using a 1/8" drill bit to avoid splitting. Two spindles will need to be pre-drilled to attach the completed rail to the post sleeves. Using a 1/8" drill bit, drill three holes at a 60° angle in the spindle, spacing them 3-1/2" from the top and bottom and one on center.

Taking the metal insert, begin to slide the spindles into place, aligning the pre-drilled holes. Starting with the center spindle, attach the metal insert and spindles using 3-1/2" premium deck screws. Remember spindles must be centered to ensure ease of assembly when attaching the top rail. Do not use composite deck screws.

Slide the top rail onto the metal insert with attached spindles. This is intended to be a tight fit; please use soap as a lubricant if needed.

Position the rail assembly between the post sleeves, following local building code height requirements. Secure the post spindles to the post sleeves using six 3" composite deck screws through the pre-drilled holes.

Once the rail assembly is attached to the post sleeves, align the bottom of the spindles to the deck joist, keeping the same spacing as the top rail. Pre-drill and secure the bottom of the spindles to the joist board using 3" premium deck screws, using two screws on each spindle, evenly spaced.

Align the post caps with the top of the post sleeve and slide into place. A silicone adhesive caulk may be used to secure the cap.

Components for stair rail may need to be cut to match slope.

Method 3 Installation:

Upper Handrail

Metal Insert

42” Beveled Spindle

1

23

4

5

67

8

14

4x4 Post

Pre-drill spindles at a 60° angle

For a more finished look, use cladding on the perimeter joist boards.

42” Beveled Spindle(with pre-drilled

screw holes on each)Post spindle

Post Sleeve

3

6

5

Joist

Decking

U-Top-ItPost

Note: If you are using cladding on your deck, you will have to cut cladding and decking as shown above, so that the post sits atop the joist. Make

sure the post is sitting on the joist, not on the deck boards. Cut post sleeve to fit post.

1

Cladding

Additional nailer board

9

iNote: Make sure screw is centered. If screw head falls out of groove, sliding rail may be difficult.

i

10

Page 16: UltraDeck · 18 Railing Installation: Fusion ... Your installation guide for UltraDeck ... on page 14 for installation instructions. Fig. 1

Railing Installation: Your installation guide for Pinnacle

Pinnacle Railing System:

!Make sure the post sleeve and ring base have been installed. Make sure the post is plumb and level. Properly size the upper and lower rail and the top cap by measuring the distance between the two post sleeves, and cut to desired length. Make sure the spindles are all the same length, measure and cut accordingly.

Post Cap (2)

Post Sleeve(2)

Ring Base (2)Support Block(1)Check with local building code

Upper Handrail (1)

Lower Railing (1)

3-1/2" Premium Deck Screw

SpindlesTraditional 6’ section: ~ 15Check with local building code

16

Top Cap

Rail (Top Position)

Spindle

Rail (Bottom Position)Support Block

Vertical Surface of Rails Face Outward

Rail Section:

i Note: It is very important to verify spindles are all the same length. Measure and cut accordingly.

To apply this method as a stair rail assembly, please see preparation instructions, page 9.

Pinnacle Brackets

Pinnacle Bracket

Pinnacle rail uses brackets for installation and doesn't need post spindles on the outside edges of railings. Vertical wall of rails will allow for multiple spindle styles.

Upper Handrail

Page 17: UltraDeck · 18 Railing Installation: Fusion ... Your installation guide for UltraDeck ... on page 14 for installation instructions. Fig. 1

Evenly space the spindles across the upper and lower railing, leaving space at both ends for brackets, and meeting local building code for spacing. Pre-drill holes with a 1/8" drill bit onto the railings where the spindles will be attached. The vertical sections of both the upper and lower rail will face the outside of the deck or steps.

Working from the center towards the ends, attach the spindles using 3-1/2" premium deck screws. Screws must be flush with the surface of the upper rail to ensure proper fit of the top cap. Do not use composite deck screws.

All rail spans over 3' require a spindle support block centered under the lower rail assembly. Check with local building codes cut the support block to the required height from UltraDeck® spindles. Attach the block on center of the bottom side of the lower rail by pre-drilling and fastening with a quality deck screw.

Place the completed rail section between the posts. At each end of the rail, temporarily support the rail unit on blocks trimmed to length to ensure proper height of the rail assembly. Making sure the rail is plumb, mark the location of the top rail bracket on the post sleeve.

Remove rail section and using screws provided in bracket pack, attach upper rail brackets to each post sleeve where marked. Attach lower rail brackets with screws provided in bracket pack to the lower rail of the assembly.

Hang rail assembly on top brackets. Verify rail assembly is plumb and support block is resting on deck. Attach the top brackets to the underside of the rail assembly and the bottom brackets to the post sleeve on each end.

Using a 1/8" drill bit, pre-drill four holes through the upper rail centered between the spindles. Secure top cap to the upper rail through the pre-drilled holes using 2" premium deck screws. Screws should be snug butnot overtightened.

17

Set rail assembly in place. Using a 1/8" drill bit to hold parts A and B of the hinge together, transfer hole location of the hinge to both post and rail assembly for pre-drilling. Repeat this step for all four corners of the rail assembly. It is important to be accurate when marking holes to brackets line up in the following steps.

Remove rail assembly from stairs and with a 1/8" drill bit pre-drill both the rail assembly and the post at the marked locations.

Attach hinge bracket to both the post sleeve and rail assembly at all four corners with screws supplied with hinge. Leave screws slightly loose, as this will make it easier to line up brackets A and B in the following step.

Set rail assembly in place and line up hinge parts in all four corners. With the hinge aligned, start tapping supplied roll pin into place using a small hammer. Finish tapping pin in with a punch. Tighten screws so they are snug but not overtightened.

Pinnacle Installation:

Pinnacle Stair Bracket Installation:

1

2

3

4

5

6

7

1

2

3

4

16

Secure the Top Cap to Top Rail at locations indicated by arrows.

6

7

Pinnacle Stair Bracket

Bracket

Underside of rail

Top RailBottom Rail

Pinnacle Bracket

Page 18: UltraDeck · 18 Railing Installation: Fusion ... Your installation guide for UltraDeck ... on page 14 for installation instructions. Fig. 1

Railing Installation: Your installation guide for Fusion®

Post Cap (2)

Post Sleeve (2)

3-1/2" Premium Deck Screws

Top Rail (1)

Handrail Insert (1)Post Spindle (2)

Spindles3" Composite Deck Screws (6) Traditional 6’ section: ~ 15

Check with local building code

Support Block(1)Check with local building code

Lower Railing (1)Ring Base (2)

Fusion® Railing System:

!Make sure the post sleeve and ring base have been installed. Make sure the post is plumb and level. Properly size the upper and lower rail and the top cap by measuring the distance between the two post sleeves, and cut to desired length. Make sure the spindles are all the same length, measure and cut accordingly.

18

6" Handrail Insert (1)

i Note: It is very important to verify spindles are all the same length. Measure and cut accordingly.

To apply this method as a stair rail assembly, please see preparation instructions, page 9.

Fusion railing is installed with a composite insert; stair railing assembly will use lower rail for both top and bottom rail.

Rail Section:

Upper handrailHandrail

insert

Lower handrail

Spindle

Support block

Post Sleeve

Top Cap

Page 19: UltraDeck · 18 Railing Installation: Fusion ... Your installation guide for UltraDeck ... on page 14 for installation instructions. Fig. 1

19

Starting with the post spindle set even with the end of the insert, continue down the top rail, evenly spacing spindles, making sure to meet local building code for spacing. Keep in mind an additional post spindle is placed even with the opposite end of the insert.

On each end of the spindles, pre-drill the center, using a 1/8" drill bit to avoid splitting. The two post spindles will need to be pre-drilled to attach the completed rail to the post sleeves. Using a 1/8" drill bit, drill three holes at a 60° angle in the spindle, spacing them 3-1/2" from the top and bottom, and one on center.

All rail spans over 3' require a spindle support block centered under the lower rail assembly. Check with local building codes and cut the support block to the required height from UltraDeck® spindles.

Taking the handrail insert, begin to slide the spindles into place, aligning the pre-drilled holes. Starting with the center spindle, attach handrail insert and spindles using 3-1/2" premium deck screws. Attach post spindles flush on the two ends of the assembly. Remember spindles must be centered to ensure ease of assembly when attaching the top rail. Do not use composite deck screws.

Position the lower rail so the spindles will rest on the top side of the rail. Secure the spindles to the rail from the underside using quality 3-1/2" premium deck screws. (Do not use composite deck screws)

Slide the top rail onto the handrail insert with attached spindles. From the underside of the handrail insert, attach the top rail using eight #4 3/4" screws, equally spacing them along the handrail, using four on each side.

To install the support block, cut a 6" piece of handrail insert and slide the support block into the insert and secure with a premium deck screw. Center handrail insert into the profile of the lower handrail.

Position the rail assembly between the post sleeves, following local building code height requirements. Secure the post spindles to the post sleeves using six 3" composite deck screws through the pre-drilled holes.

Align the post caps with the top of the post sleeve and slide into place. A silicone adhesive may be used to secure the cap.

Deck Screw

6” Handrail Insert(For over support

block only)

Support Block

Fusion® Installation:

1

2

3

4

5

6

7

8

9

18

4x4 Post

Pre-drill spindles at a 60° angle

Lower rail

7

8

Deck Screw

Handrail InsertSpindle

Upper Handrail6

Page 20: UltraDeck · 18 Railing Installation: Fusion ... Your installation guide for UltraDeck ... on page 14 for installation instructions. Fig. 1

What are the dimensions of the deck boards?UltraDeck® Rustic™: 1" H x 5-3/16" W UltraDeck® Natural™: 1-1/16" H x 4" W UltraDeck® Natural™ Radius Edge: 1-1/16" H x 5-3/16" WUltraDeck® Fusion®: 1" H x 5-3/16" W UltraDeck® QuickCap™: 1/2" H x 3-1/2" W

What are the weights of the deck boards?UltraDeck® Rustic™: 2.1 lbs. per lineal ft. UltraDeck® Natural™: 1.1 lbs. per lineal ft. UltraDeck® Natural™ Radius Edge: 1.4 lbs. per lineal ft.UltraDeck® Fusion®: 2.1 lbs. per lineal ft. UltraDeck® QuickCap™: 0.8 lbs. per lineal ft.

How do you clean UltraDeck® decking? UltraDeck® should be periodically cleaned with soap and water or any product made for washing composite decking. Check out the how-to-video for cleaning any UltraDeck® decking and railing products on the Midwest Manufacturing website.

Can color differences occur in UltraDeck® products? UltraDeck® does contain real wood fibers, and like real wood, color differences may occur. When this does occur deck boards should be distributed in a way that creates an appealing, natural looking distribution of boards.

Can I paint or stain my UltraDeck®? Painting or staining is not required for UltraDeck® products to maintain their look. However, if you prefer to stain your deck, the brushed side of the UltraDeck® Natural boards may be stained with a good-quality, composite deck stain after one year of adequate weathering. If a composite deck stain is used, always follow the stain manufacturers recommendations. Keep in mind that staining decking is not a one time application; this will add maintenance to your low maintenance composite decking materials.

Can I put a hot tub on UltraDeck®? The substructure of a deck determines if it can support a hot tub. Since UltraDeck® is not a load-bearing product, the joists of the structure should be used as a support. Any load bearing pillars or legs should be placed directly above a deck joist or sister joist in this application.

Can UltraDeck® be placed over a solid surface? UltraDeck® decking boards can only be installed over a solid surface when using a sleeper system to buffer between the solid surface and the decking. Water must be able to flow through and away from the deck while maintaining an adequate airflow to the underside of the boards. If updating the look of an existing deck is the goal, Quick Cap™ by UltraDeck® is a great and affordable product designed to be installed directly on top of an existing deck in good condition.

Can UltraDeck® be used in docks and waterfront decks? UltraDeck® products have been used in many of these applications. As long as installation instructions are followed, UltraDeck® works well and is aesthetically pleasing in all types of waterfront applications.

Can ice melting products be used on UltraDeck® products? Yes, non-corrosive and non-dyed varieties should be selected for use on UltraDeck® products. Once the ice melting product has melted unwanted ice, the remaining solids should be swept away. As with any surface, prolonged exposure to ice melting products can lead to a residue appearing on the decking. Once warm weather permits, wash the deck of residue left by melted ice and snow.

Where are UltraDeck® products manufactured? All UltraDeck® products are proudly made in the USA!

MIDWEST MANUFACTURING® warrants to the original purchaser of any UltraDeck® decking product, who purchased and installed the product for residential purposes, that such product will not split, rot, warp, or suffer structural damage from fungal decay for a period of ten (10) years, beginning on the date that the product was purchased and continuing until this period of time has elapsed, or until the property on which the UltraDeck® decking product was originally installed has transferred ownership. The warranty only applies to the original purchaser, who must present an original purchase invoice or receipt, and is non-transferable. LIMITATIONS. The warranty does not cover defects that occur through normal wear and tear and weathering of the UltraDeck® decking product (“The Product”), misuse of the product or negligence in the use of the product, improper storage and handling of the product prior to installation, or lack of maintenance of the product in a manner inconsistent with or contrary to the point of sale material provided. Minor surface irregularities and color differences are a natural characteristic of polyethylene and may be slightly visible on the woodgrain surface and will be visible on the underside of the decking. Any such irregularities do not constitute a product defect. MIDWEST MANUFACTURING® will replace, at its own opinion, any UltraDeck® decking product used for residential purposes that is deemed defective within the ten (10) year period for which this warranty applies. The original purchaser must supply MIDWEST MANUFACTURING® with the original purchase invoice indicating the date of purchase and showing sufficient UltraDeck® product was purchased to cover the amount claimed to be defective. If the product must be replaced due to splitting, rotting, warping, or structural damage from fungal decay, according to the sole discretion and judgment of MIDWEST MANUFACTURING®, MIDWEST MANUFACTURING® will send the replacement product to the store where the product was originally purchased. The original retail purchaser(s) to whom this warranty applies must then, at their own expense, pick up the replacement product. The original purchaser(s) must pay all costs of the removal of defective product or installation of the replacement, including labor. No monetary compensation will be paid by MIDWEST MANU-FACTURING®. MIDWEST MANUFACTURING® SHALL NOT BE LIABLE FOR INCIDENTAL OR CONSEQUENTIAL DAMAGES, INCLUDING, BUT NOT LIMITED TO, LOSS OR DAMAGE TO PERSONAL OR REAL PROPERTY, INCONVENIENCE, OR LOSS OF INCOME. This warranty provides you with specific legal rights, and you may have other rights under state law. Some states do not allow for the limitation or exclusion of incidental or consequential damages or limits on the length of an implied warranty, so some of the above limitations or exclusions may not apply to you.www.midwestmanufacturing.com 2009

Frequently Asked Questions:

Limited 10 Year Warranty:

20

2015 edition • 903-0168