Tree planting in the London Road public
realm area.
Specimen trees planted around Swales
1, 2 and 3.
Tree planting underway adjacent to the
London Road junction.
Elva Way mini roundabout completely
removed, verge reinstated and noise
barrier installed.
Last section of sub base prepared for
blacktop laying. Elva Way in the
background.
Looking east from Glovers Roundabout
towards Acton’s Bridge.
Topsoiling the side slopes around
Glovers Roundabout.
Glovers Roundabout – Entrance to the
Enterprise Park. Glovers House in the
background.
Glovers Roundabout looking towards
Glovers Bridge.
Planting mature saplings around
Glovers Roundabout.
Railway cutting looking towards Glovers
Bridge. Finishing works underway.
Looking east across Combe Haven
Underbridge towards Acton’s Farm
Overbridge.
Looking east towards Acton’s Farm
Overbridge. Seeded verges are
springing to life.
Acton’s Farm to Watermill greenway –
Surfacing of pedestrian/cycle route
commenced.
Looking across the planted landscape
mounding towards Pond H1.
Looking east across Watermill
Underbridge.
Looking east towards Hillcroft Farm
Overbridge from Watermill Underbridge.
Looking west from Watermill
Underbridge.
Hillcroft Farm Overbridge looking
towards Adam’s Farm Overbridge.
Powdermill Underbridge looking east towards
Adam’s Farm Overbridge. Safety and
environmental barrier finishing works underway.
Powdermill Underbridge – Highway
drainage being installed through steel
ducts slung off the bridge deck.
Looking west through Adam’s cut
towards Adam’s Farm Overbridge.
Looking east across Decoy Pond
Underbridge towards Chapel Wood cut.
Decoy Pond Underbridge – Safety and
environmental barrier works underway.
Pond H6 in operation
near Decoy stream.
Greenway Bridge G05 – Abutment tie-in
and access track crossover slabs
completed.
Looking east along the climbing lane
towards Upper Wilting.
Finishing works underway approaching
Crowhurst Road Underbridge from the
west.
Railway Underbridge looking east
towards Queensway. Safety barrier and
landscape planting underway.
Interface between safety barrier and
environmental barrier at Railway Bridge
– awaiting special bracketry for infill.
Queensway cutting looking east
towards the Queensway Junction.
Landscape planting underway.
Greenway tie-in works at the Upper
Wilting Farm entrance off Crowhurst
Road.