THE VALUE PROPOSITION OF REGIONAL NATURAL RESOURCE ...€¦ · 0 THE VALUE PROPOSITION OF REGIONAL...
Transcript of THE VALUE PROPOSITION OF REGIONAL NATURAL RESOURCE ...€¦ · 0 THE VALUE PROPOSITION OF REGIONAL...
THE VALUE PROPOSITION OF REGIONAL
NATURAL RESOURCE MANAGEMENT IN
QUEENSLAND
Karen Vella, Rachael Cole-Hawthorne, and Meegan Hardaker
FINAL REPORT
0
THE VALUE PROPOSITION OF REGIONAL
NATURAL RESOURCE MANAGEMENT IN
QUEENSLAND
Final Report
Karen Vella1,2, Rachael Cole-Hawthorne1, and Meegan Hardaker2
1 QUT Institute for Future Environments Brisbane, Queensland, 4000, Australia
2QUT School of Civil Engineering and Built Environment, Brisbane, Queensland, 4000,
Australia
Supported by the Institute for Future Environments, School of Civil Engineering and Built
Environment, NRM Regions Queensland and Queensland Water and Land Carers
Value Proposition of Regional NRM in Queensland Final Report
1
© The Author(s). 2017 This article is distributed under the terms of the Creative Commons Attribution-
NonCommercial 4.0 International License (CC BY-NC 4.0) (https://creativecommons.org/licenses/by-
nc/4.0/).
This report should be cited as: Vella K., Cole-Hawthorne, R. and Hardaker, M. (2017) The Value
Proposition of Regional Natural Resource Management in Queensland Final Report, Queensland
University of Technology, Brisbane.
Published by Queensland University of Technology on behalf of NRM Regions Queensland and
Queensland Water and Land Carers.
This report is available for download from QUT Eprints website: https://eprints.qut.edu.au/114596/
DOI: 10.5204/rep.eprints.114596
This publication is copyright. The Copyright Act 1968 permits fair dealing for study, research,
information or educational purposes subject to inclusion of a sufficient acknowledgement of the source.
The views and opinions expressed in this publication are those of the authors and do not necessarily
reflect those of NRM Regions Queensland and Queensland Water and Land Carers.
Cover Photo: ‘Hinterland’ © Leonard J Matthews 2015 https://www.flickr.com This article is distributed
under the terms of the Creative Commons Attribution-NoDerivs 2.0 Generic International Public
License (CC BY-ND 2.0) (https://creativecommons.org/licenses/by-nc/4.0/).
Value Proposition of Regional NRM in Queensland Final Report
2
Contents
List of Tables........................................................................................................................................ 4
List of Figures ...................................................................................................................................... 5
Acronyms ............................................................................................................................................. 6
Acknowledgements .............................................................................................................................. 7
1. Executive Summary ............................................................................................................................. 8
2. Introduction ........................................................................................................................................ 13
Phase 1 (2002-08) - Natural Heritage Trust (NHT) II (Commonwealth) ...................................... 14
Phase 2 (2008-13) - Caring for Our Country (CFoC)/Q2 (Commonwealth) Coasts and Country
(Q2C&C) (Queensland) ................................................................................................................. 14
Phase 3 (2013-15) - National Landcare Program (NLP) and the Queensland Government
Investment Program. ...................................................................................................................... 15
Aim and Scope of this Report ........................................................................................................ 16
3. Framework Used to Evaluate NRM Outcomes .................................................................................. 18
4. Methods .............................................................................................................................................. 32
Step 1 - Data Appraisal .................................................................................................................. 32
Step 2 - Sampling Frame ................................................................................................................ 33
Step 3 - Regional Summary Reports .............................................................................................. 34
Step 4 - Whole of Queensland Assessment.................................................................................... 35
Step 5 - Expert Workshop .............................................................................................................. 35
Step 6 - Synthesis and Conclusions ............................................................................................... 37
5. Whole of Queensland Consolidated NRM Assessment ..................................................................... 38
Attribute 1: Action for Sustainability Outcomes ............................................................................... 38
Attribute 2: Performance and Accountability and Return on Investment .......................................... 55
Attribute 3: Community Participation and Engagement .................................................................... 73
Attribute 4: Resilient Institutions and Capacity Building .................................................................. 77
Attribute 5: Strategic Partnerships ..................................................................................................... 80
Attribute 6: Strategic and Integrated Regional Planning ................................................................... 85
Attribute 7: Community Awareness and Knowledge Brokerage ....................................................... 89
6. Conclusions and Recommendations .................................................................................................. 93
Question 1 – What is the value-add of regional NRM arrangements? .............................................. 93
Question 2 – How has the value-add changed under the different governance models of NRM
programs? ........................................................................................................................................... 96
Question 3 – How can existing value be maintained and built upon in a new program and regional
arrangements? .................................................................................................................................... 99
Value Proposition of Regional NRM in Queensland Final Report
3
Question 4 – How can these areas of value be monitored, evaluated, and reported on in a future
program? .......................................................................................................................................... 100
7. References ........................................................................................................................................ 105
8. Appendices ....................................................................................................................................... 109
Appendix 1: Summary of all data acquired...................................................................................... 109
Appendix 2: Data used in assessment .............................................................................................. 110
Appendix 3: How sources of data were used to evaluate NRM Attributes ..................................... 111
Appendix 4: Example of the first page of the data assessment table for SEQ region...................... 118
Value Proposition of Regional NRM in Queensland Final Report
4
List of Tables
Table 1. The attributes of regional NRM based on key words in the NRM guidelines, reviews, and
research projects and summarised as key principles .............................................................................. 20
Table 2. Assessment matrix of attributes for evaluating NRM outcomes (after review) ...................... 31
Table 3. Usefulness of evidence provided in the source data to evaluate NRM attributes .................... 32
Table 4. Sampling Frame ....................................................................................................................... 33
Table 5. The index scale used to rate the value proposition .................................................................. 35
Table 6. Summary of the evidence base and conclusions for Attribute Element 1.1 - Projects address
regional NRM assets and key threats ..................................................................................................... 40
Table 7. Summary of the evidence base and conclusions for Attribute Element 1.2- Natural resource
action is regionally coordinated ............................................................................................................. 47
Table 8. Summary of the evidence base and conclusions for attribute Element 1.3 - Investments achieve
natural resource management action ...................................................................................................... 52
Table 9. Summary of the evidence base and conclusions for Attribute Element 2.1 - Organisational
policies and procedures (for finance, HR management, asset management, fraud control, project
management and project delivery) provide evidence that NRM investments are well governed .......... 57
Table 10. Summary of the evidence base and conclusions for Attribute Element 2.2 - Project, output,
and outcome reporting accounts for investments at the sub-regional level ........................................... 61
Table 11. Summary of the evidence base and conclusions for Attribute Element 2.3 - Regional NRM
communication demonstrates accountability to stakeholders and leverages investment....................... 64
Table 12. Summary of the evidence base and conclusions for Attribute Element 2.4 - Monitoring and
continuous improvement programs are in place .................................................................................... 69
Table 13. Summary of the evidence base and conclusions for Attribute Element 3.1 - NRM has a diverse
community membership base, projects engage diverse networks and sectors. Partnerships are responsive
to needs................................................................................................................................................... 74
Table 14. Summary of the evidence base and conclusions for Attribute Element 4.1 - Stable NRM
presence in the region and regional skills retention and development................................................... 78
Table 15. Summary of the evidence base and conclusions for Attribute Element 5.1- Strategic investment
partnerships at local, state, and federal levels, and across diverse sectors (agriculture, indigenous,
conservation) .......................................................................................................................................... 81
Table 16. Summary of the evidence base and conclusions for Attribute Element 6.1 - Collectively
endorsed plans and connectivity within and among key decision making institutions and sectors ....... 86
Table 17. Summary of the evidence base and conclusions for Attribute Element 7.1 - Community
Awareness and Knowledge Brokerage .................................................................................................. 90
Value Proposition of Regional NRM in Queensland Final Report
5
List of Figures
Figure 2. Framework of attributes for evaluating NRM outcomes ........................................................ 19
Figure 3. A comparison of the NRM outcomes measured between 2002-2015 against attributes ........ 97
Figure 4. The value-add of Queensland’s regional arrangements scored against a 1-5 index scale where
1 = least desired and 5 = most desired. .................................................................................................. 98
Value Proposition of Regional NRM in Queensland Final Report
6
Acronyms
BMP…………………...Best Management Practice
CFoC…….………….....Caring for Our Country
DAFF………..………...Department of Agriculture, Fisheries & Forestry
DERM…………….…...Department of Environment and Resource Management
GBR…………….……..Great Barrier Reef
GBRMPA……….…….Great Barrier Reef Marine Park Authority
HR……………………..Human Resources
JCU…………….……...James Cook University
JD……………………...July - December
JJ………………………January - June
JSC………………….....Joint Steering Committee
JSIP……………………Joint Strategic Investment Panel
MAT…………………...Management Action Target
MERI…………...……..Monitoring, Evaluation, Reporting and Improvement
MIP……………………Major Integrated Project
NAPSWQ……….……..National Action Plan for Salinity and Water Quality
NHT…………..…….….Natural Heritage Trust
NLP…………..….…….National Landcare Programme
NRM…………………...Natural Resource Management
PMP…………………...Property Management Plan
QDAFF………………..Queensland Department of Agriculture, Fisheries and Forestry
QLD…………………...Queensland
Q2C&C……….……….Q2 Coasts and Country
RCT…………………...Resource Condition Target
RGC…………………...Queensland Regional Natural Resource Management Groups Collective
RIMRP…………….….Reef Integrated Monitoring and Reporting Program
SEQ………………..…..South East Queensland
SEQC……………..…...SEQ Catchments
SIP……………………..State-level Investment Program
WQIP…………..……...Water Quality Improvement Plan
Value Proposition of Regional NRM in Queensland Final Report
7
Acknowledgements
The funding for this project was provided by the QUT Institute for Future Environments and School
of Civil Engineering and Built Environment, NRM Regions Queensland, and Queensland Water and
Land Carers.
We also acknowledge the additional support received from the Queensland Department of Natural
Resources and Mines for supplying narrative reports, output summaries, final reports, and other
documentation related to past and current regional NRM programs to QUT for this study and for
organising the stakeholder workshop.
Many thanks also go to the expert panel convened as part of this project and the full involvement
of participating stakeholders from the State and Commonwealth Governments, regional NRM bodies,
researchers, and consultants for their critical contributions.
Finally, we thank Rachel Eberhard of Eberhard Consulting and Emeritus Professor Stephen Dovers
of the Fenner School, Australian National University for providing independent reviews of this report.
Value Proposition of Regional NRM in Queensland Final Report
8
1. Executive Summary
In 2002, Queensland introduced a regional delivery model for natural resource management (NRM)
that applied principles of collaboration, subsidiarity, and adaptive management to address sustainability
problems at the regional scale. A paucity of data evaluating sustainability and other NRM outcomes has
been a consistent problem for the adaptive management of the model and NRM arrangements over time.
This gap must be closed to enable review, adjustment, and implementation of natural resource
sustainability programs in the future.
This report develops a framework and methodology and applies it to assess the outcomes and value
proposition of regional NRM in Queensland to address this knowledge gap. It examines evidence
contained within a large dataset of regional body reports submitted to the Queensland Government
between 2002 and 2015 and provides the first state-wide synthesis of reported data since the introduction
of NRM arrangements in Queensland. The dataset of over 1000 individual documents included:
qualitative reports in the form of narrative annual performance reports, quantitative data in the form of
state output summaries and regional group milestone reports, case studies, and workplans. The data
reported on activity over three main policy and investment phases for regional NRM:
Phase 1 - Natural Heritage Trust II (2002-2008)
Phase 2 - Caring for Our Country and the Q2 Coasts and Country Program (2008-2013)
Phase 3 - NLP and the Queensland Government Investment Program (2013-2015)
This evaluation focuses on assessing the outcomes from regional NRM arrangements in the third
phase of NRM in Queensland. Outcomes from Phase 1 and 2 are included for comparative purposes.
The scope of the analysis does not include Natural Heritage Trust I outcomes because data reporting on
regional NRM investments was not available prior to 2002. This was also prior the introduction of
regional delivery model in Queensland.
The dataset was evaluated using a framework of seven key attributes for regional NRM arrangements.
Each attribute was underpinned by a key principle drawn from the literature and finalised at a workshop of
Queensland NRM practitioners (regional body, government, and non-government participants). These
attributes and the underlying principles that represent the desired outcomes of Queensland’s regional model are:
1. Action for sustainability outcomes – regional NRM arrangements should deliver landscape
management actions that maintain and restore the natural resource base and build social,
economic, and institutional capital in regions over time. This is the foundational principle for
NRM.
2. Performance and accountability and return on investment – regional NRM arrangements
are cost effective, well-governed, accountable to all stakeholders, and government investments
are leveraged (aligned or bought together with other resources) to mobilise and grow
sustainability outcomes in regions.
Value Proposition of Regional NRM in Queensland Final Report
9
3. Community participation and engagement – regional NRM arrangements empower
community groups in NRM and NRM programs are responsive to community and government
needs.
4. Resilient institutions and capacity building – regional NRM arrangements are stable,
enduring, and agile. They provide critical regional capacities and networks to deliver
sustainability and are able to adapt to changing policy priorities over time.
5. Strategic partnerships – regional NRM arrangements reflect principles of subsidiarity. They
develop strong and credible partnerships for sustainability action at the regional scale and
provide linkage between organisations, structures, activities, and investment across local, state,
and national levels for collective impact.
6. Strategic and integrated regional planning – regional NRM arrangements include processes
for achieving consensus around regional priorities and strategies, plans reflect community and
government (local, state, and federal) aspirations, and plans are at an appropriate scale for
implementation.
7. Community awareness and knowledge brokerage – regional NRM arrangements include
processes to gather knowledge from multiple diverse sources (e.g., scientific, indigenous,
policy) together and translate this into regional and local sustainability action.
The synthesis and evaluation of regional NRM reporting has identified important outcomes and
emerging trends in outcome delivery since the introduction of regional NRM arrangements in
Queensland in 2002.
First, performance accountability and return on investment and community awareness and
knowledge brokerage were the areas of highest value-add by regional NRM arrangements from 2002-
2015. Other areas of consistent and positive value-add from regional NRM arrangements across all three
phases were strategic partnerships and community participation and engagement. Queensland’s
regional NRM arrangements have proven to be accountable, agile, and able to maintain natural resource
management outcomes in the context of changing government partnerships and NRM funding priorities.
Second, the value of regional NRM arrangements declined over time in achieving action for
sustainability, in developing resilient institutions and capacity building, and in achieving strategic
and integrated regional planning. Though regional arrangements delivered positive actions in these
areas in the first two phases of regional NRM (from 2003-2013), outcomes in these areas declined in
the last phase (2013-2015). There was a substantial decline in strategic and integrated regional planning
between 2002 and 2015. This was one of the best areas of outcome delivery in the first regional NRM
investment phase; however, outcomes fell between 2008-2013 and fell even further between 2013-2015.
Value Proposition of Regional NRM in Queensland Final Report
10
Third, the evaluation found that strategic and integrated planning, and resilient institutions and
regional capacity attributes are potentially useful lead indicators for measuring progress toward
sustainability outcomes from NRM. Integrated planning and the concerted effort to develop regional
NRM capacity in the first phase of regional NRM in Queensland left a positive legacy for NRM into the
second, and to some extent, third phase of NRM. There was a time lag between the initial investment
in planning and regional capacity development in phase one and the achievement of sustainability
outcomes in the second phase. There was also a time lag between declining outcomes in planning,
regional resilience and capacity in phase two and sustainability outcomes which declined in phase three.
The impact of the continued decline of planning and regional capacity outcomes in phase three on
sustainability outcomes in phase four requires further evaluation.
Fourth, the evaluation found that four attributes – performance and accountability and return on
investment; community participation and engagement; strategic partnerships; and community awareness
and knowledge brokerage – are important foundations for regional NRM. The data indicates that
accountability, engaging community, building strategic partnerships, and brokering knowledge are
essential for developing regional NRM capacity, coordinating and integrating NRM action across
federal, state, and local governments, and achieving natural resource management action.
Fifth, the analysis highlighted the limitations of current reporting processes, which do not
capture efforts toward addressing sustainability outcomes across the regional NRM governance
system. Queensland and Australian government funding of NRM is fragmented across a range of
organisations and sustainability programs. The wider governance system for regional NRM in
Queensland includes agricultural industry groups, conservation groups, state agencies, and local
governments traditional owner groups and a plethora of regional planning and partnership processes for
managing assets and threats such as water, pests, biodiversity and vegetation, and climate adaptation.
How do the efforts of organisations across the entire NRM governance system impact on sustainability
outcomes across Queensland? How do these different efforts impact on the efficacy, appropriateness,
and efficiency of the delivery of NRM programs? Understanding the impact of action on NRM outcomes
across the governance system level is critical to improve the efficacy of future regional NRM – and
related programs.
Finally, the review of reporting over fifteen years showed that NRM today is quite different
compared to 2002, when regional NRM arrangements were introduced. The dataset showed a changed
focus on competitive funding, short term contracts, the introduction of MERI frameworks, and a trend
toward metricised reporting. The loss of the bilateral partnership between the Queensland and Australian
governments was evident in the reports from 2010 onwards. The dataset showed that these changes
have impacted on the regional NRM model, and it appears to be significant, however data describing
the regional model and the extent of changes to the regional model is generally lacking. Exactly
how different are the 14 regional NRM models across Queensland? How have they evolved over time?
Do differences in regional models impact on NRM outcomes? How does NRM in Queensland compare
Value Proposition of Regional NRM in Queensland Final Report
11
to other states in Australia or internationally? What can be learnt from other governance models? This
knowledge would help to adaptively improve Queensland’s diverse regional NRM arrangements and
the efficacy of future NRM programs.
This analysis of regional NRM arrangements concludes by identifying several recommendations
for NRM Regions Queensland and the Queensland Water and Land Carers to maintain and build upon
the value of NRM arrangements and for monitoring, evaluation, and reporting, as follows:
Recommendation 1: Strengthen the integrative role of regional NRM plans in promoting strategic
target setting across government and non-government organisations, alignment of government and non-
government activity to improve implementation, and as the basis for collaborative monitoring and
review in the next phase of regional NRM.
Recommendation 2: Grow the human and governance capacity of NRM bodies to provide
leadership and support for achieving regional resilience (in the face of changing institutional and
regional conditions), to improve the longevity of investments in sustainability action for the Queensland
and Australian Governments and regional communities.
Recommendation 3: NRM partners (e.g., regions, the Queensland and Australian Governments,
non-government organisations and the research/consultancy community) should evaluate the different
regional models and approaches underpinning partnerships and NRM delivery across Queensland’s 14
regions and assess the effects of nuances in governance models on NRM outcomes. How the Queensland
models and their NRM outcomes compare to other states in Australia and NRM systems should also be
evaluated.
Recommendation 4: Provide for a higher level of consistency in reporting frameworks over time,
and broaden the scope of relevant data collection, and the scope of the participating organisations
(government and non-government) involved in monitoring and evaluation. Improve reporting on: i)
efforts to build regional capacity and resilience, ii) strategic and integrated regional planning, iii)
regional partnership models, and iv) sustainability action across government and non-government
organisations.
Recommendation 5: NRM regions and reporting partners (e.g., the Queensland and Australian
Governments, industry groups, traditional owner groups, conservation groups) should work together to
develop a consistent language for narrative reporting and decision rules to guide qualitative assessments
of outcomes achieved by programs. This will enable data about investments and outcomes to be better
shared across Queensland, and scaled up for adaptive management.
Recommendation 6: NRM regions, the Queensland and Australian Governments and other non-
government organisations (e.g., industry groups, traditional owner groups, conservation groups) should
work together to develop an integrated long-term program for evaluating Queensland’s regional NRM
system. This should be based on clear evaluation questions about links between activities and outcomes
Value Proposition of Regional NRM in Queensland Final Report
12
and use data harvesting, targeted new data collections and regional synthesis to evaluate efforts across
the NRM governance system toward addressing sustainability outcomes. It needs to be broader than the
regional NRM organisations, include other government and non-government NRM activity, be more
than monitoring, continue beyond the life of individual projects, and be linked to adaptive management.
If addressed, these recommendations would improve NRM capacities and outcomes, or at least
clarify what these outcomes are. Some of these actions are within the ability of regional bodies to
address, or could be with appropriate resources, while some may be more in the domain of State agencies
or others.
Value Proposition of Regional NRM in Queensland Final Report
13
2. Introduction
Regional governance is one of the most important and complex public policy issues confronting
the achievement of sustainable natural resource outcomes in Australia. Multiple decision-making
processes are a challenge for coordinating the management of land use, resource development, and the
implementation of sustainability improvement initiatives. This is a particular challenge in resource-rich
Queensland, where resource use and its management impacts are heavily contested, and these conflicts
are expected to become more acute in a changing climate.
In 2002, Queensland introduced a regional delivery model for natural resource management
(NRM). This model introduced community based regional NRM bodies under the auspices of a
Commonwealth/State bilateral agreement. Regional NRM bodies worked with Commonwealth and
State governments, agricultural organisations, environmental conservation groups, local community
groups, researchers, and others to coordinate and align management activities around priorities within
regions.
The first instalment of the Natural Heritage Trust (NHT-I) laid the foundations for the regional
model for natural resource and environmental management in Australia between 1997 and 2001. Under
NHT-I, small grants to improve land management were provided from Commonwealth funding under a
major program with the states and subsidiary bodies. However, this approach to delivery for landscape-
scale management was criticised for being ad hoc and too scattered to have impact (Dovers, 2013; Curtis
& De Lacy, 1996). This Australian model is now approaching two decades of implementation, and
evaluation is long overdue.
The regional delivery model applied principles of collaboration, subsidiarity, and adaptive
management to address complex, ‘wicked’ NRM sustainability policy problems at the regional scale. It
was a bold governance experiment (Lane, Robinson, & Taylor, 2009; Lockwood & Davidson, 2010;
Robins & Dovers, 2007; Wallington & Lawrence, 2008). Each Australian state introduced different
regional governance models. These ranged from community-based models in Queensland and Western
Australia, to variations of statutory and regulatory models in New South Wales, Victoria, and South
Australia. The institutional basis of the regional NRM models around Australia have evolved since their
introduction. Governments and others were to evaluate the performance and outcomes of regional NRM
arrangements and use this evidence to inform policy and governance reform.
Although the model used the principles of adaptive management, the evidence base used to support
adaptive management has been a consistent problem since the introduction of regional arrangements
(Vella, Sipe, Dale, & Taylor, 2015), and this problem is not isolated to Queensland. Repeated audit
evaluations at the national level have highlighted the paucity of performance data about sustainability
and other outcomes (Vella et al., 2015). The key problems identified were: 1) the absence of
performance measures to evaluate the impact of the regional delivery model (Auditor General, 1997;
Auditor Genreal , 2001; Hassall and Associates, 2005; Keogh, Chant, & Frazer, 2006); 2) a poor data
Value Proposition of Regional NRM in Queensland Final Report
14
baseline and insufficient monitoring of outcomes (Caring for our Country Review Team, 2012; Senate
Standing Committee on Rural and Regional Affairs and Transport 2010); and 3) the ineffective collation
and use of the reporting data that regional bodies have provided to governments (Caring for our Country
Review Team, 2012). Though improvements have been made in monitoring and performance reporting
at a regional level through monitoring, evaluation, review, and improvement (MERI) strategies since
2008, this has not been collated across regions or over time to provide an evaluation of overall
performance.
This report describes an approach developed and applied in a Queensland case study to evaluate
the outcomes from regional NRM arrangements. The approach used ‘multiple lines of evidence’ to
review the outcomes of regional NRM arrangements between 2002 and 2015. During this phase, there
were three main phases of investment:
Phase 1 (2002-08) - Natural Heritage Trust (NHT) II (Commonwealth)
Under NHT II, 56 regional areas were established with regional NRM bodies. This was based on a
“purchaser/provider engagement model” that emphasised contractual governance (Love, 2012, p. 47).
In 2002, funding was provided to regional NRM bodies under NHT II and also under the National Action
Plan for Salinity and Water Quality (NAPSWQ) (in some regions) to develop regional plans that
identified key targets and environmental assets in NRM regions (Curtis et al., 2014). The program
emphasised capacity building and the development of performance measures, while the key objectives
were biodiversity conservation, sustainable use of natural resources, and community capacity and
institutional change (Love, 2012).
The NHT II delivered investment for outcomes at three levels: national, for projects with a broad
national focus or that cut across state or regional boundaries; regional, for regional scale actions and to
implement NRM plans; and local, known as the Envirofund, for small individual grants to address local
scale problems carried out by local community groups (DEH, 2004).
In Queensland, the NHT II invested A$159 million over five years (Queensland Government,
2017). Focuses included the Natural Heritage Trust Extension Wetlands Programme (2003-2008), which
aimed to develop and implement measures to conserve and manage Queensland’s wetlands. The
Wetlands Programme received $7.5 million in funding from both the Commonwealth and Queensland
Governments to implement the relevant provisions of the Natural Heritage Trust Bilateral Agreement
(Environmental Protection Agency, 2008; NHT, 2004)
Phase 2 (2008-13) - Caring for Our Country (CFoC)/Q2 (Commonwealth) Coasts and Country
(Q2C&C) (Queensland)
Established by the incoming federal Labor government in 2008, the goal of the CFoC program was
to deliver “an environment that is healthier, better protected, well managed, resilient, and provides
essential ecosystem services in a changing climate” (Commonwealth of Australia, 2008, p. 2). The
program focused on strategic outcomes across six national priority areas: the National Reserve System;
Value Proposition of Regional NRM in Queensland Final Report
15
biodiversity and natural icons; coastal environments and critical aquatic habitats; sustainable farm
practices; natural resource management in northern and remote Australia; and community skills,
knowledge, and engagement (Commonwealth of Australia, 2008). The program received an investment
of A$2.25 billion, with a third of this allocated as base-level funding for regional body organisations,
and two-thirds distributed through a competitive project-based grant application process (DAFF &
DSEWPaC, 2011; Robins & Kanowski, 2011). The 2009-10 CFoC competitive grants call received
1,300 applications, of which 59 were successful, a success rate of 5% (Robins & Kanowski, 2011).
Queensland’s regional NRM during this phase, Q2C&C, invested A$86 million over five years to
support Queensland’s regional bodies (Queensland Government, 2017). Q2C&C aimed to deliver on a
series of programs including, weeds and pests, water and wetlands, water quality, land and soils, and
core operations of the regional bodies in the Queensland Murray-Darling Basin (Queensland Murray-
Darling Committee [QMDC], 2011). For the SEQ Catchments regional NRM body, the programs
funded under the Q2C&C investment included: improved system management (including community
skills, knowledge, and engagement), community water quality monitoring, improved collaboration
through the ecosystem services framework, regional planning, traditional owner engagement,
implementation of landscape activity for a prioritised ‘Back on Track’ habitat, and flood and disaster
recovery activities (SEQ Catchments, 2012).
Phase 3 (2013-15) - National Landcare Program (NLP) and the Queensland Government
Investment Program.
The NLP was the result of the merging of CFoC and Landcare under the Liberal government of
2013 (Benham, Beavis, & Hussey, 2015). During the first phase of the NLP (2014-15), investments
were made according to four strategic objectives: community management of landscapes to sustain long-
term socio-economic benefits from their environment, improvement of farmer and fisher long-term
returns through better management of the natural resource base, community involvement in caring for
the environment, and community protection of species and natural assets (Australian Government,
2017).
The Queensland NRM Investment Program complemented the Australian Government NRM
funding, by supporting Queensland’s regional NRM projects and state strategic projects (Queensland
Government, 2017). In 2013, the Queensland Investment Program announced an A$80 million
investment over five years (2013-18), which included A$30 million to protect the Great Barrier Reef
(GBR), with A$55 million of the total to be provided to regional bodies in Queensland (Department of
Natural Resources and Mines [DNRM], 2017). The Queensland Investment Program was focused on
activities in seven key theme areas: 1) management of priority and invasive weeds; 2) management of
priority and invasive pests; 3) restoration of soil condition; 4) adoption of best practice landscape
management; 5) restoration of native riparian vegetation along priority waterways; 6) restoration of
native vegetation in priority wetlands; and 7) the development of engaged, knowledgeable, and skilful
communities (DNRM, 2017).
Value Proposition of Regional NRM in Queensland Final Report
16
Aim and Scope of this Report
This report outlines the approach developed to evaluate the value proposition of Queensland’s
regional NRM system by estimating and comparing the outcomes between 2002-2015. The approach
used a framework of attributes and data from multiple government and regional NRM body sources to
establish the value of the regional NRM delivery system. The approach sought to understand the impact
of regional NRM on outcomes and changes in value over time. The aim was to examine and harvest
findings from regional body reporting and regional case study data existing between 2002 and 2015.
Part of the evaluation required understanding whether it was possible to use this existing dataset to
evaluate the regional NRM outcomes and trends over time. The data were limited to regional reporting
that was held by the Queensland Department of Natural Resources and Mines. Regional body reports
provided to the Australian Government under the first phase of NRM that were submitted to the
Queensland Government through the joint steering committee (JSC) processes formed part of the
dataset. Regional body reports provided to the Commonwealth Government outside of the bilateral
processes (e.g., in phase 2 and phase 3) were not included in the analysis. The analysis sought to evaluate
the value of NRM arrangements in the context of Queensland policy priorities over time to inform the
redesign of Queensland programs. The inclusion of regional reporting data from the Commonwealth
provided a more comprehensive analysis of value outcomes of regional NRM over time and is a useful
addition to this analysis. Similarly, the analysis of data from agricultural groups and other regional
partners improved the assessment of outcomes from regional NRM arrangements.
The dataset included 1,000 individual documents collected over the three investment phases of
regional NRM arrangements since the introduction of regional bodies in Queensland under NHT II. The
analysis centred on the most recent investment phase and included earlier investment phases for
comparative purposes. Outcomes from the NHT I (prior to the introduction of regional NRM
arrangements) would have provided a useful comparison but were excluded from the scope of the
analysis because data were not available. The analysis focused on delivery under Queensland programs.
The federal programs are listed as they form an important understanding in the NRM delivery context,
which underpins the dataset and the findings of this analysis. Appendix 1: Summary of all data acquired
provides a summary of the documents acquired for the analysis.
The analysis used a combination of content analysis, evaluation using decision rules, and expert
involvement to identify the outcomes from the regional delivery system.
The specific questions addressed were:
1. What is the value-add of regional NRM arrangements?
2. How did the value-add change under the different governance models of the past programs?
3. How can the existing value be maintained and built upon in a new program and regional
arrangements?
Value Proposition of Regional NRM in Queensland Final Report
17
4. How can these areas of value be monitored, evaluated, and reported on in a future program?
The remainder of this report is structured as follows: Section 3 outlines the framework of attributes used
to evaluate the outcomes from the regional NRM delivery system. Section 4 describes the methods in
detail. Section 5 presents the findings from the assessment of outcomes across Queensland and over
time. It evaluates outcomes in terms of: (1) action for sustainability outcomes, (2) performance and
accountability and return on investment, (3) community participation and engagement, (4) resilient
institutions and capacity building, (5) strategic partnerships, (6) strategic and integrated regional
planning, and (7) community awareness and knowledge brokerage. Based on the analysis and evaluation
of regional NRM, Section 6 presents a summary of trends under changing NRM governance models,
and provides recommendations in terms of consistency in terminology and monitoring, evaluation, and
reporting frameworks.
Value Proposition of Regional NRM in Queensland Final Report
18
3. Framework Used to Evaluate NRM Outcomes
The framework used to structure the evaluation of NRM outcomes was built on the seven attributes
underpinning the regional NRM model identified by Vella and Eberhard (2015)1. These seven attributes
originated from a synthesis of key guidelines and evaluation documents in Queensland and across
Australia that described the aspects that a healthy NRM system ought to deliver. The key documents
consisted of five Queensland guidelines and sixteen national reviews and major research projects. These
seven attributes were then tested/modified against the national documents.
The seven summary attributes, listed in initial priority order based on the number of times key
words and concepts appeared in the reviewed documents, were:
1. Performance and accountability and monitoring return on investment
2. Community participation and engagement
3. Resilient institutions and capacity building
4. Strategic partnerships
5. Strategic and integrated regional planning
6. Community awareness and knowledge brokerage
7. Action for sustainability outcomes (social/economic/environmental).
These attributes were presented and discussed at the Review of outcomes from regional NRM
investment in Queensland workshop hosted by the Queensland Government in August 2016. This
workshop brought together regional bodies, state and federal agency staff, researchers, and consultants
to provide input into the scope of the review project (Value Proposition of Regional NRM in
Queensland). Based on discussion at the workshop, the priority of the attributes was modified to reflect
the importance and centrality of delivering sustainability outcomes (e.g., Attribute 7 became Attribute
1) (Figure 2).
1 This was developed for the Queensland Regional Natural Resource Management Groups Collective (RGC)
review of regional NRM models in 2015
Value Proposition of Regional NRM in Queensland Final Report
19
Figure 2. Framework of attributes for evaluating NRM outcomes
Table 1 outlines the attribute groupings and the key words identified in the reviewed documents.
20
Table 1. The attributes of regional NRM based on key words in the NRM guidelines, reviews, and research projects and summarised as key principles
Attributes Keywords from
Queensland-focused
Guidelines
Source Keywords from National-level
Audits and Evaluations of NRM
Source Keywords from workshop
discussion NRM CEOs,
Program Managers,
Queensland and Australian
Government Officers.
Key Principles
1. Performance,
accountability
and return on
investment
• Efficient and
effective delivery,
• effective NRM
outcomes,
• accountability at
scales,
• accountability and
return on
investment,
• program
improvement and
adaptive
management,
• maximum
efficiency in
achieving results,
• better business and
NRM practices.
1, 2, 3,
4, 5
• Performance information and
reporting processes,
• grant acquittals,
• cash management,
• program monitoring,
• program objectives achieved,
• operations of the board and
executive management,
• statutory and contractual
compliance,
• organisational policies, procedures
and processes,
• financial management,
• HR management,
• IT and systems management,
• information and knowledge
management,
• asset management,
• stakeholder engagement,
• fraud control,
6, 7, 8,
9, 10,
11, 12,
15, 16,
17, 18,
19, 20,
21, 22,
23, 24,
25, 26,
27, 29,
30, 31,
32
• Local accountability,
accountability to the
region for what is
delivered, cheap not
nasty!
• Flexible = cost effective
– institutions without
overheads and salaries,
• multiplying the
investment- guarantee
5:1,
• know what you’re up
to/transparency,
• saving government
admin/planning/prioritisa
tion
• mobilising investment,
• good governance systems
in place,
• Transparency
• legitimacy
and
credibility of
investment
decision,
• culture of
evaluation
and learning,
• efficiency and
effectiveness.
Value Proposition of Regional NRM in Queensland Final Report
21
Attributes Keywords from
Queensland-focused
Guidelines
Source Keywords from National-level
Audits and Evaluations of NRM
Source Keywords from workshop
discussion NRM CEOs,
Program Managers,
Queensland and Australian
Government Officers.
Key Principles
• project management,
• improving delivery,
• the implementation of regional
delivery arrangements,
• governance and financial
management for regional delivery,
• monitoring, evaluation, and
reporting on the programs’
performance,
• legitimacy,
• transparency.
• accountability – lower
risk for government on
investment (assurance),
• value investment, not
cheapness,
• accountable to members,
• coordination and
alignment of investment,
• mobilising/coordinating/l
everaging investment or
alignment of investment,
• lower risk investment for
government – reason for
investing is to reduce risk
to landscape – regional
arrangements manage the
risk of the investment
working,
• lower risk of money
going astray (higher
degree of accountability
than normal grantee) and
• lower risk of getting flak
for actions.
Value Proposition of Regional NRM in Queensland Final Report
22
Attributes Keywords from
Queensland-focused
Guidelines
Source Keywords from National-level
Audits and Evaluations of NRM
Source Keywords from workshop
discussion NRM CEOs,
Program Managers,
Queensland and Australian
Government Officers.
Key Principles
2. Community
participation
and engagement
• Community
engagement and
ownership,
• decision making
subsidiarity,
• empowering and
engaging
communities,
• subsidiarity,
• local decision
making,
• local partnerships,
• community
participation,
• enabling,
• recognises
community
aspirations,
• diversity,
• integration,
• grass roots
involvement.
1, 2, 3,
4, 5
• Participation and engagement
structures,
• capacity to participate,
• inclusiveness.
7, 10,
13, 18,
19, 20,
27, 30,
31, 32
• capacity building,
• accessibility,
• trust,
• information access,
• manage the noise for
government (reduces the
voices),
• solve the problems,
• deliver community
consensus,
• turn problems into
opportunities,
• responsive to
community,
• reflects community
aspirations/knowledge/
capacity,
• frank and robust
conversations that
government can’t have,
• helps policy development
through community
connections –
• Seeks to
understand,
inform and
engage all of
the
community in
decision-
making,
• represents
community
views,
• devolves
decision-
making to
appropriate
levels.
Value Proposition of Regional NRM in Queensland Final Report
23
Attributes Keywords from
Queensland-focused
Guidelines
Source Keywords from National-level
Audits and Evaluations of NRM
Source Keywords from workshop
discussion NRM CEOs,
Program Managers,
Queensland and Australian
Government Officers.
Key Principles
appropriate and relevant
networking, independent,
• extending the reach of
government.
3. Resilient
institutions and
capacity building
• Viability,
• model needs
renewal,
• program
improvement and
adaptive
management,
• flexible, long term
policy framework,
• leadership.
1, 3, 4,
5
• Three-year investment cycles,
• adaptability,
• learn from unintended outcomes,
• adequate regional resourcing,
• adaptive and responsive processes,
• improved social capital of
planners, managers and
participants,
• effective and connected
institutions,
• government commitment to NRM,
• capacity building,
• capacity of NRM bodies,
• capability.
7, 9,
10,14,
15, 19,
20, 21,
22, 23,
24, 25,
26, 29,
30, 31,
32
• NRM a perpetual issue -
needs to be enduring,
smart, agile,
• sustainable,
• the ‘go to’ hub – single
point of contact,
• there when you need
them,
agile/flexible/responsive,
• adapt to changing policy,
governance structure to
enable this,
• understand
regulation/incentives,
• human capacity on the
ground,
• enduring arrangements,
• resilient and sustainable,
• government reach
extended,
Flexible,
adaptable,
learning networks
that seek to build
capacity across all
NRM
stakeholders/
interests.
Value Proposition of Regional NRM in Queensland Final Report
24
Attributes Keywords from
Queensland-focused
Guidelines
Source Keywords from National-level
Audits and Evaluations of NRM
Source Keywords from workshop
discussion NRM CEOs,
Program Managers,
Queensland and Australian
Government Officers.
Key Principles
• testing/revising/learning,
• state agencies don’t
always have
representation in region,
• link to multiple agencies,
• on the spot.
4. Strategic
partnerships
• Decision making
subsidiarity,
• local decision-
making local
partnerships,
• coordination,
• alignment,
• integration,
• collaboration,
• engagement,
• enabling, diversity,
bridging
government and
community
1, 2, 3,
5
• Stakeholder culture and
commitment,
• participation and engagement
structures,
• linking scales and activities,
• partnerships
6,13, 15,
16, 18,
19, 20,
21, 22,
23, 24,
25, 26,
27, 28,
29, 30,
32
Works with other
organisations at a
variety of levels
for collective
impact.
5. Strategic and
integrated
• Precaution,
• alignment,
2, 3, 4,
5
Thinking regionally 6, 7, 10,
13, 14,
• Prioritises
actions based
Value Proposition of Regional NRM in Queensland Final Report
25
Attributes Keywords from
Queensland-focused
Guidelines
Source Keywords from National-level
Audits and Evaluations of NRM
Source Keywords from workshop
discussion NRM CEOs,
Program Managers,
Queensland and Australian
Government Officers.
Key Principles
regional
planning
• integration,
• collaboration,
• strategic planning,
• integrated regional
NRM planning and
action,
• bridging
government and
community,
• long-term policy
framework
16, 18,
19, 20,
30, 31
on asset value
and risks,
incl. spatial
priorities,
med-long
term, to reach
standards and
targets.
6. Community
awareness and
knowledge
brokerage
Enabling, integrating
and aligning knowledge
2, 3, 5 • Recognising regional diversity and
complexity,
• structures for integrating
knowledge,
• Processes for integrating
knowledge and values
7, 10,
13, 14,
19, 20,
27, 30,
31
Engages and
shares diverse
knowledges
including
scientific,
technical, local,
and Indigenous
7. Action for
sustainability
outcomes
No keywords – though
was recognised as an
2, 4 • Environmental protection,
sustainable agriculture and NRM
outcomes achieved,
6, 7, 8,
12, 13,
14, 15,
• Local and regional
ownership of outcomes
and solutions,
Long-term
maintenance and
restoration of the
Value Proposition of Regional NRM in Queensland Final Report
26
Attributes Keywords from
Queensland-focused
Guidelines
Source Keywords from National-level
Audits and Evaluations of NRM
Source Keywords from workshop
discussion NRM CEOs,
Program Managers,
Queensland and Australian
Government Officers.
Key Principles
(environmental,
social, and
economic)
implicit underpinning
principle.
• Indigenous access and equity
issues,
• risk management,
• improved resource conditions
16, 17,
18, 19,
20, 28,
29, 30
• looking after our life
support system,
• saving work (prevention/
precaution),
• brokering outcomes
across multiple parties,
• long term approaches,
• reach across the state to
extend government.
reach through
implementation,
• scope of landscape
management services,
• managing risk to natural
assets and risk to money
and risk to investment
and perception risk,
• catalysing action/
provide impetus for
change,
• invested in outcomes, at
the right scale (regional),
• link between local and
state/federal govt.,
natural resource
base and the
social, economic
and institutional
capital needed to
sustain it.
Value Proposition of Regional NRM in Queensland Final Report
27
Attributes Keywords from
Queensland-focused
Guidelines
Source Keywords from National-level
Audits and Evaluations of NRM
Source Keywords from workshop
discussion NRM CEOs,
Program Managers,
Queensland and Australian
Government Officers.
Key Principles
• full scope of landscape
management,
• manage loosely around
bioregions.
Sources:
1. Regional Groups Collective. (2015). NRM Discussions/Minutes. Regional Groups Collective Toowoomba.
2. Queensland NRM Bodies. (2015). Thursday Island Meeting Minutes. Regional Groups Collective, Toowoomba.
3. Department of Environment and Resource Management. (2011). Queensland Regional Natural Resource Management Framework,
November 2011. The State of Queensland (Department of Environment and Resource Management, Brisbane.
4. Zammit, C., & Vogel N. (2013). Review of regional NRM arrangements in Queensland. Regional Groups Collective, Toowoomba
5. Campbell, A. (2007). Improving regional arrangements for Natural Resource Management in Queensland. Regional Groups Collective
Toowoomba.
6. Auditor General. (1997). Commonwealth Natural Resource Management and Environment Programs: Audit Report No. 36 1996-97. The
Australian National Audit Office, Canberra.
7. Dale, A., & Bellamy, J. (1998). Regional Resource Use Planning in Rangelands: an Australian Review (Occasional Paper No 06-98), Land
and Water Resources Research and Development Corporation, Canberra.
Value Proposition of Regional NRM in Queensland Final Report
28
8. Auditor General. (1998). Commonwealth Management of the Great Barrier Reef: Great Barrier Reef Marine Park Authority, ANAO,
Canberra.
9. Bellamy, J. A., (ed.) (1999). Evaluation of Integrated Catchment Management in a Wet Tropical Environment: Collected Papers of
LWRRDC R&D Project CTC7, 7 vols., CSIRO Tropical Agriculture, Brisbane.
10. Bellamy, J. A., McDonald, G. T., Syme, G. J., & Butterworth, J. E. (1999). Policy Review Evaluating Integrated Resource Management,
Society and Natural Resources, 12(4), 337-53. doi: 10.1080/089419299279632
11. Bellamy, J. A., Walker, D. H., McDonald, G. T.,& Syme, G. J. (2001). A systems approach to the evaluation of natural resource
management initiatives. Journal of Environmental Management, 63, 407-23. doi: 10.1006/jema.2001.0493
12. Auditor General. (2001). Performance Information for Commonwealth Financial Assistance under the Natural Heritage Trust: Audit
Report No.42 2000-2001, Australian National Audit Office, Canberra.
13. Australian Government. (2003). Review of the National Landcare Program. Department of Agriculture Fisheries and Forestry, Canberra.
14. Auditor General. (2004). The Administration of the National Action Plan for Salinity and Water Quality. Audit Report No, 17 2004-05, The
Australian National Audit Office, Canberra, Australia.
15. Hassall and Associates. (2005). Natural Heritage Trust Phase 1 Final Evaluation, Australian Government Department of Agriculture,
Fisheries and Forestry and Department of the Environment and Heritage, Canberra.
16. McDonald, G. T., McAlpine, C. A., Taylor, B. M. & Vagg, A. (2004). Criteria and Methods for Evaluating Regional Natural Resource
Management Plans in Tropical Savanna Regions, Stage 1 Report for Project 3.2.1, Bioregional Planning in the Tropical Savannas, CSIRO,
Brisbane.
17. Dawson, S. (2005). Carbon management and energy use, in G McDonald, B Taylor & C Robinson (eds), Findings from a review of
regional NRM plans, CSIRO and Tropical Savannas Management CRC, Brisbane, pp. 88-94.
18. McDonald, G. T., McAlpine, C. A., Taylor, B. M., & Vagg, A. R. (2003). Evaluating regional plans in Australian tropical savannas: A
guide for planners and reviewers. Tropical Savannas CRC, Darwin.
19. McDonald, G. T., Taylor, B., Bellamy, J. A., Robinson, C., Walker, M., Smith, T., Hoverman, S., McAlpine, C., Peterson, A., & Dawson,
S. (2005). Benchmarking Regional Planning Arrangements for Natural Resource Management 2004–05: Progress, constraints and future
directions for regions, Healthy Savanna Planning Systems Project. Tropical Savanna Management CRC, Brisbane.
Value Proposition of Regional NRM in Queensland Final Report
29
20. Taylor, B., McDonald, G., Heyenga, S., Hovermann, S., Smith, T., & Robinson, C. (2006). Evaluation of Regional Planning Arrangements
for Natural Resource Management 2005-06: Benchmark Report II, Milestone Report 4 Healthy Savanna Planning Systems Project, Tropical
Savannas Management. CSIRO, Brisbane.
21. Fenton, D.M. (2004). Socio-economic indicators for NRM (Project A1.1) Indicators of capacity, performance and change in regional
bodies. National Land and Water Resources Audit, Canberra.
22. Fenton, D. M. (2006). Socio-economic Indicators and Protocols for the National NRM Monitoring and Evaluation Framework: The Social
and Institutional Foundations of NRM. National Land and Water Resources Audit, Canberra.
23. Fenton, D. M., & Rickert, A. (2006a). Monitoring and evaluating the performance of NAPSWQ regional bodies in Queensland (State
Summary Report). Burdekin Dry Tropics NRM and the National Land and Water Resources Audit, Canberra.
24. Fenton, D. M., & Rickert, A. (2006b). Refining indicators for monitoring and evaluating the social and institutional foundations of
regional NRM programs. Department of Environment and Heritage and The Department of Agriculture, Fisheries and Forestry, Canberra.
25. Fenton, D. M., & Rickert, A. (2008a). Monitoring and evaluating the social and institutional foundations of natural resource management
(RECAP): A National Paper. National Land and Water Resources Audit, Canberra.
26. Fenton, D. M., & Rickert, A. (2008b). A national baseline of the social and institutional foundations of natural resource management
programs. National Land and Water Resources Audit, Canberra.
27. Keogh, K., Chant, D., & Frazer, B. (2006). Review of Arrangements for Regional Delivery of Natural Resource Management Programmes:
Report prepared by the Ministerial Reference Group for Future NRM Programme Delivery Final Report. Australian Government, Canberra.
28. Auditor General. (2007). The Conservation and Protection of National Threatened Species and Ecological Communities. Audit Report No.
31 2006-07, Australian National Audit Office, Canberra, Australia.
29. Auditor General. (2008). Regional Delivery Model for the Natural Heritage Trust and the National Action Plan for Salinity and Water
Quality. Audit Report No.21 2007-08. Australian National Audit Office, Canberra, Australia.
30. Senate Standing Committee on Rural and Regional Affairs and Transport. (2010). Rural and Regional Affairs and Transport References
Committee: Natural Resource Management and Conservation Challenges. Commonwealth of Australia, Canberra.
31. Caring for our Country Review Team. (2012). Report on the Review of the Caring for our Country Initiative. Australian Government Land
and Coasts, Canberra, Australia.
Value Proposition of Regional NRM in Queensland Final Report
30
32. Turnbull. W. (2005). Evaluation of Current Governance Arrangements to Support Regional Investment under the NHT and NAP. P.
Canberra: Departments of Environment Water Heritage and the Arts and Agriculture Forestry Fisheries.
31
Following the workshop, the attributes and elements of the summarised principles were used to
develop a draft assessment matrix to evaluate how the regional NRM delivery system had actually
performed relative to this aspirational framework for healthy regional NRM, which was refined and
simplified during the assessment process. Table 2 provides a summary of the matrix.
Table 2. Assessment matrix of attributes for evaluating NRM outcomes (after review)
NRM Attributes and Element(s) Outcomes
1. Action for
sustainability
1.1 Projects address regional NRM assets and key threats.
1.2 Natural resource action is regionally coordinated.
1.3 Investments have achieved sustainability action (e.g., landholders
adopted best land management practices, weeds were managed, feral
animals were controlled).
2. Performance and
accountability and
return on investment
2.1 Organisational policies and procedures (for finance, HR management,
asset management, fraud control, project management, and project
delivery) provide evidence that NRM investments are well governed.
2.2 Project, output, and outcome reporting accounts for investments at the
sub-regional level.
2.3 Regional NRM communication demonstrates accountability to
stakeholders.
2.4 Monitoring and continuous improvement programs are in place.
3. Community
participation and
engagement
3.1 NRM has a diverse community membership base, projects engage
diverse networks and sectors, and partnerships are responsive to needs.
4. Resilient institutions
and capacity building
4.1 Stable NRM presence in the region and regional skills retention and
development.
5. Strategic
Partnerships
5.1 Strategic investment partnerships at local, state, and federal levels, and
across diverse sectors (agriculture, indigenous, and conservation).
6. Strategic and
Integrated Regional
Planning
6.1 Collectively endorsed plans and connectivity within and among key
decision-making institutions and sectors.
7. Community
Awareness and
knowledge brokerage
7.1 Community awareness of NRM and adaptive use of integrated
knowledge sets.
Value Proposition of Regional NRM in Queensland Final Report
32
4. Methods
A series of steps were developed to fulfil the value assessment using the framework described
above.
Step 1 - Data Appraisal
In this step, the dataset was appraised to determine its contribution to the assessment. A random
selection of qualitative data was extracted from the dataset, imported into NVIVO2 software, and coded
against each of the seven attributes identified in Table 2 above. The key words and phrases for each
attribute, listed in Table 1, were used to search for, and identify, relevant information within the dataset.
For example, environmental protection, social equity, risk management and resource conditions were
some of the key phrases used to search for the Action for sustainability outcomes attribute element. The
coded data from multiple sources were then compiled against each of the attribute elements in a multiple
lines-of-evidence approach. This approach highlighted the sources of data relevant for each attribute
element.
The usefulness of the coded data was then evaluated. This evaluation considered whether the data
provided useful evidence to assess attribute elements, or if any additional expert interpretation was
required. Table 3 provides a high-level summary of the usefulness of the evidence against the NRM
attributes. Other information acquired in the data set, such as quantitative Excel spreadsheets (e.g., state
output summaries, regional group milestone reports, funding reports, and detailed workplans), were
manually coded and added due to the difficulty of added these file formats into NVivo. Pictures, visuals,
and spatial maps were also not included in the review.
Table 3. Usefulness of evidence provided in the source data to evaluate NRM attributes
Attribute Usefulness of Evidence in Data
1. Action for sustainability
outcomes
Data easily provides attribute elements.
2. Performance and
accountability and return on
investment
Data provides some attribute elements.
3. Community participation and
engagement
Expert interpretation of attribute elements required.
4. Resilient institutions and
capacity building
Expert interpretation of attribute elements required.
2 NVIVO is qualitative data analysis software designed specifically to work with unstructured data and large
numbers of documents. It supported this research to develop richer insights and research discovery by organising,
storing, and coding the qualitative data in a more efficient way. The qualitative data organised, stored, and coded
in NVivo primarily included qualitative textual information.
Value Proposition of Regional NRM in Queensland Final Report
33
5. Strategic Partnerships Data provides some evidence of attribute elements.
6. Strategic and Integrated
Regional Planning
Data provides some evidence of attribute elements.
7. Community awareness and
knowledge brokerage
Data provides some evidence of attribute elements.
The data provided enough evidence for the review to answer the outlined research questions and
extract useful recommendations for NRM governance.
Step 2 - Sampling Frame
A sampling frame was adopted to manage the volume of data and number of regions. A
representative year was selected for each of the three major investment phases and data were then
extracted from relevant key data sources for each of the 14 NRM regions. The years were chosen
according to the data available for each investment phase. Due to the disjointedness of the data available
from NHT II, two representative years –2007/8 and 2003/4 – were used in the analysis of the first phase
outcomes.
The project originally planned to develop a simple typology of NRM regions and use indicator
regions to streamline the data extraction and analysis; however, developing a reliable typology of
Queensland regions proved too challenging within the timeframe. The differences in governance
structures, regional capacities, foci, and approaches caused difficulties in selecting reliable indicator
regions.
The selected sampling frame is summarised below in Table 4 below and in more detail in Appendix
2: Data used in assessment.
Table 4. Sampling Frame
Phase Program Investment
Phase
Data Extraction
Point(s)
Regions
1 NHT II 2002-2008 2008/9
2003/4
All (14)
All (state-wide
collated summary
only)
2 Caring for Our Country
/Q2 Coasts and Country
(CFoC/Q2C&C)
2008-2013 2011/12 All
Value Proposition of Regional NRM in Queensland Final Report
34
3 NLP and the
Queensland Government
Investment Program
2013-2015 2014/15
All
Step 3 - Regional Summary Reports
Evidence about the value of NRM from the data for each value element was: a) summarised for
each region, b) synthesised into conclusions about the value of NRM in each region, and c) provided
with an assessment score (/5) using the defined index scale in Table 5.
Appendix 3: How sources of data were used to evaluate NRM Attributes describes which data
sources were used and how they informed the assessment of each attribute element in the value
proposition in the regions. The index scale was used to relate the findings about the value of NRM to
the governance structure of the investment phase. The regional summary reports are not included in this
final report.
Value Proposition of Regional NRM in Queensland Final Report
35
Table 5. The index scale used to rate the value proposition
Index
Scale
How well does regional NRM delivery achieve outcomes against each value element?
5 Easily facilitates NRM outcomes for assets and in response to threats, and maintaining or
improving the health of the natural resource base and the social, economic, and
institutional capital for NRM over time.
4 Makes some progress towards achieving NRM outcomes by accommodating management
action for most assets and in response to significant threats and to maintaining the social,
economic, and institutional capital for improved NRM over time.
3 Some setbacks to projects and regional activity to achieve NRM outcomes (for assets
and/or in response to threats) taking time and investment to recover social, economic, and
institutional capital for NRM.
2 Setbacks to projects and regional activity have serious impacts on NRM outcomes (for
assets and/or in response to threats), resulting in the declining health of the natural
resource base and declining social, economic, and institutional capacity for NRM.
1 Setbacks to projects and regional activity have irreversible impacts on NRM outcomes for
assets or in response to key threats, with both the health of the natural resource base and
the social, economic, and institutional capacity for NRM unlikely to recover.
A data table reporting the outcomes of a - c (summarised, synthesised into conclusions, rated
according to the index scale) was produced for each of the 14 NRM regions. Appendix 4: Example of
the first page of the data assessment table for SEQ region provides an example of the first page of the
data table for one region. The analysis focussed on the third phase (2014-2015) and data was added from
2011/12, 2007/08, and 2003/4 to allow for comparisons of outcomes under past programs.
Step 4 - Whole of Queensland Assessment
A consolidated whole of Queensland NRM assessment was developed using the regional data
tables. This table consolidated assessment summarises the evidence base, conclusions, and assessment
across Queensland for each of the investment phases, as well as data on state-wide projects (that may
include more than one regional body). The focus here is on the third phase, with other phases added for
comparative purposes. The consolidated results of the whole of Queensland assessment of NRM value
are provided in Section 5 of this report.
Step 5 - Expert Workshop
An expert workshop was held to review the consolidated assessment, and in particular, the rating
scales and assessment process. The aim of the expert review workshop was to critically review the
ratings and findings of the assessment and provide advice to sharpen findings. The workshop was held
on 21 March 2017 at QUT, Gardens Point. The expert panel members were:
Value Proposition of Regional NRM in Queensland Final Report
36
Andrew Drysdale, NRM Regions Queensland
Darryl Ebernezer, Queensland Water and Land Carers Association
Dr Melanie Cox, Queensland Department of Natural Resources, and Mines and Energy, Natural
Resources Programs
Dr Bruce Taylor, CSIRO Land and Water, Brisbane
Bob Speirs, Consultant NRM Programs.
In summary, the expert panel provided the following critical feedback:
• The assessment process was acknowledged as being thorough. The use of decision rules,
the sampling frame, and the coding and scaling up process allowed findings to be built on
consistent themes observed across regions. The analyst had no prior knowledge of, or
involvement with NRM. The findings were based on the application of the rules and the
analysis framework for the dataset, and bias was ruled out.
• The overall findings revealed no major surprises and were consistent with expert panel
member impressions of performance and delivery through the regional NRM delivery
system.
• The panel noted that regional delivery performance against some attribute elements was
very consistent over time, despite institutional changes to programs.
• The panel noted areas where regional delivery performance had changed and declined over
time. This was compared to the extensive consultations about the NRM framework in 2005
as part of the Green Paper. It was noted that the evaluation had collected evidence that
supported stakeholder views about the key regional capacities necessary to enhance regional
sustainability outcomes.
• No significant changes were suggested by the reviewers. The panel discussed ways of
presenting data. Suggestions included:
▪ Clearly articulating that outcomes and the quality of outcomes were assessed over
time, but that the assessment did not evaluate program arrangements for the regional
delivery model.
▪ Considering the accumulated value and the legacy of the regional delivery system.
▪ Considering a counter-factual scenario – what would have been delivered under a
state-centric NRM system or a local NRM system?
▪ Reflecting on the quality of the reports reviewed in the conclusions.
Value Proposition of Regional NRM in Queensland Final Report
37
Step 6 - Synthesis and Conclusions
Following the workshop, recommendations and conclusions were compiled about:
• How the accumulated value of NRM programs changed under the different governance
models of past programs.
• How the existing value in a new program and regional arrangements could be maintained
and built upon.
• How the value of the regional NRM delivery model could be monitored, evaluated, and
reported in the future.
Detailed recommendations are outlined in Section 6 - Conclusions and Recommendations.
38
5. Whole of Queensland Consolidated NRM Assessment
Attribute 1: Action for Sustainability Outcomes
Three elements were considered for Attribute 1, Action for Sustainability Outcomes. Element 1.1
assessed the degree to which projects addressed regional NRM assets and threats, Element 1.2 measured
the regional coordination of natural resource action, while Element 1.3 measured the achievement of
sustainability action based on investment.
In terms of Element 1.1 - Projects addressed regional NRM assets and threats, the results show that:
• The investments in NRM governance capacity building made in the first phase of NRM
investment (2002-2008) led to rapid improvements in NRM protection, particularly in pest,
animal, and plant control across the state.
• It was difficult to obtain consolidated data showing the impact of investments on NRM
protection from the datasets in the second investment phase (2008-2012). The evidence
suggested that NRM action was maintained, however the focus of action was narrowed
down to specific assets and sustainability risks and the ability of projects to be adapted to
other regional sustainability priorities declined. Delivery was also challenged by contracts
that did not provide flexibility to adapt work around climatic conditions and community
capacity that constrained project delivery. Nonetheless, the capacity to address NRM threats
remained relatively high due to investments in regional capacity - driven by a large
investment by the state in the previous phase. Regional evaluative capacity was also
beginning to emerge as a result of the strategic state government focus on evaluation.
• The third investment phase (2013-2015), saw a considerably narrowed scope of NRM
investment and heightened regional insecurity about funding continuity for NRM action.
As projects engaged local partners and communities, poor socio-economic conditions in
some regions/areas limited the potential for NRM action and activities, and change was
minimal. Projects struggled to achieve milestone targets set to address key assets or threats.
Taken together (narrowed scope + poor socio-economic conditions in communities +
reduced funding to organisations) this resulted in an overall decline in the state-wide
regional NRM capacity to address the sustainability of regional NRM assets and key
sustainability threats. If this trend continues it is expected that NRM protection will only be
localised in stable and affluent communities in Queensland (most likely in coastal areas).
• The decline in resources for regional NRM projects is related to the declining health of
regional communities and this is linked to a decline in investments in regional NRM
governance capacity building.
Table 6 presents the summary of the evidence base and conclusions for Element 1.1.
Value Proposition of Regional NRM in Queensland Final Report
39
40
Table 6. Summary of the evidence base and conclusions for Attribute Element 1.1 - Projects address regional NRM assets and key threats
NRM
Investment
Phase
Evidence Conclusions Assessment
(/5)
Phase 3
(2013-
2015)
• From 2013-2015, the Queensland Government funded NRM projects
primarily focused on landscape and environmental activities to address
regional assets and key threats (namely, pests and weeds, water quality, and
agricultural land).
• Previously agreed workplans, output targets and performance indicator
monitoring were the primary methods employed by NRM projects to address
regional assets and threats.
• Project milestones and targets agreed to with the State before the start of a
project were usually always achieved (and at times, far exceeded agreed
outcomes). This demonstrates a strong effort on behalf of NRM bodies to
achieve agreed upon activities and the flexibility to work around long-term
projects and/or an underestimation in the contracting phase.
• Guaranteed investment for NRM activities was not possible due to on-going
funding uncertainty. Many communities and private landholders relied heavily
on this investment to implement activities. Funding uncertainty was expected
to worsen with increased competition to secure funds.
• Threats such as pests and weeds required on-going and stable monitoring,
maintenance and control. Project success and NRM achievements were
therefore particularly reliant on the stability and certainty of Queensland
Government investments.
• State-recorded outputs included achievements towards specific quantitative
targets. For example, almost 2,500,000 hectares of pest plant and animal
control was implemented to reduce the impact of priority and emerging
invasive species from 2014-2015.
• This dataset included information
about NRM project activity
performance against the targets
agreed under this investment
program. However, this does not
necessarily mean that there was
sufficient information to adequately
address regional assets and key
threats.
• Evidence of how NRM projects
identify regional assets and values,
and key threats was available, such as
spatial mapping and assessment
information.
• While most NRM projects provided
outputs and met milestones, a
dependency on investment programs
that the Queensland Government
provides for funding NRM project
activity remained.
• Some NRM issues, such as those
dealing with pests and weeds, were
more dependent on the long-term
certainty of Queensland Government
2
Value Proposition of Regional NRM in Queensland Final Report
41
NRM
Investment
Phase
Evidence Conclusions Assessment
(/5)
• Regional NRM bodies used regional and local approaches to secure ownership
of project outcomes. For example, local knowledge was used to: map and
identify key pest and weed species; develop sub-regional strategic pest
management plans; implement devolved grant programs to address the
management of emerging issues; develop property and best practice
management plans.
• 2,567 hectares of native vegetation received protection. A number of
community groups received assistance and a number of training and
community awareness events took place.
• When conditions permitted, NRM activities were catalysts for action and
change at the local scale. For example, in some regions, landholders that had
experienced drought had more time to devote to weed control (due to a
reduced effort in productivity related activities). This also demonstrates the
necessity of having a stable community capacity to successfully implement
projects and meet agreed landscape protection targets.
• Local communities’ socio-economic conditions did not favour NRM activities
in some regions, and action and change were therefore minimal. Projects
struggled to achieve milestone targets set to address key assets or threats in
these regions.
• When projects did not accomplish the agreed targets, this was reported as
being related to difficult climatic conditions, financial limitations, lack of
community interest, lack of community capacity, and poor investment partner
decision-making.
funds and investment, as they require
on-going and consistent attention.
• The environmental protection of
natural assets focused on sustainable
agriculture, water quality, and pest
and weed control in this investment
phase as these were the three themes
for the state NRM program.
Biodiversity, climate and air, social,
heritage, and governance dimensions
were given limited attention.
• All funded projects engaged with
communities and multiple partners at
the local level to manage the
protection of natural assets.
• Landscape management remained
vulnerable to climatic and
geographical challenges.
• Projects that engaged private
landholders and/or local partners may
have also been more dependent on a
stable and affluent community (e.g.,
for leverage). This raises an emerging
equity issue for governments.
Value Proposition of Regional NRM in Queensland Final Report
42
NRM
Investment
Phase
Evidence Conclusions Assessment
(/5)
• Regional bodies used a diverse scope
of landscape management practices at
both the regional and local levels.
• Agreed targets need to take into
account the social capacity of the
local communities who are expected
to implement activities.
• NRM regional bodies were
concerned about the long-term
potential of projects to achieve
sustainability outcomes when secure
investment is never guaranteed.
Phase 2
(2008-
2012)
• NRM projects detailed recorded outputs during this investment phase. For
example, state summary outputs recorded just over 2 million hectares of
native vegetation protected and almost 3 million hectares of pest plant and
animal control implemented in the 2011-2012 annual reporting year.
• NRM regional bodies employed surveys and asset assessments and identified
areas at risk from land-use activities (e.g., coal mining activities) to prioritise
the future investments required in the regions.
• In 2012, some NRM regional bodies’ narrative reports included evaluation
and reviews of program and project logic. This represents a potentially useful
resource to inform future assessments of program logic (i.e., how this might
be achieved, and how the NRM bodies considered it). The Queensland
Murray Darling catchments (QMDC) was one region that implemented
evaluation frameworks to assess project direction and logic.
• There was some analysis of program
logic and activities in performance
reports during this investment phase.
• NRM bodies played a significant role
in connecting community awareness
with the protection of regional assets,
such as key species, and the potential
development of community
ownership and interest in future
environmental protection and
sustainability.
• NRM bodies developed and
enhanced the range of landscape
3.5
Value Proposition of Regional NRM in Queensland Final Report
43
NRM
Investment
Phase
Evidence Conclusions Assessment
(/5)
• NRM bodies prioritised key species protection through increased community
awareness of biodiversity and conservation in areas of significance. For
example, an independent evaluator described Condamine Alliance’s Dewfish
Demonstration Reach Program as being first class. The success of the program
was attributed to strong and dense relationships, where support was given to
key individuals to act as ‘champions’ and provide community ownership of the
program.
• Climate and weather considerations impacted on project delivery. The
inflexibility of contracts and investments impacted on NRM activities.
services offered, including resource
assessments.
• Climatic events had an impact on
projects and this is an issue when
using inflexible short-term funding
contracts that do not allow for
variations in workplans (e.g.,
seasonal factors).
• Some regions, such as QMDC,
demonstrated high quality
institutional capital. These regions
were generally more advanced in
project assessment.
Phase 1
(2002-08)
• NRM projects for all Queensland regional bodies focused primarily on
organisational development, capacity building, and NRM regional planning
during Phase 1. This was reported in regional body annual performance
reports, particularly up until 2006.
• Over 1,000,000 hectares of native vegetation was protected, enhanced,
rehabilitated or re-vegetated during this investment phase, as recorded in the
state-wide summary outputs.
• State wide summary outputs reported almost 4,000,000 hectares of pest
animal and plant control between 2002 and 2008.
• The area of protected native vegetation and area controlled for pest plants and
animals increased steadily from 2002 and 2007. The highest pest controlled
area reports were during the 2006-2007 reporting year (1,429,417), followed
• This phase represented the beginning
of regionalism and the need to
integrate state and local levels to
protect and enhance environmental
assets and address key threats to
Queensland landscapes.
• The focus should be on NRM
governance and capacity
development in the early phase of
this investment program so that NRM
is well-positioned to protect and
assess the condition of resources and
threats, as well as develop strategies
3.5/4
Value Proposition of Regional NRM in Queensland Final Report
44
NRM
Investment
Phase
Evidence Conclusions Assessment
(/5)
by the 2007-2008 reporting year (1,212,087 hectares), while 2003-2004 was
the lowest recorded year (379.4 hectares).
• The recorded rise in output area was less dramatic when the area measured
included native vegetation that was protected, enhanced, rehabilitated, or re-
vegetated. The highest area reported was 364,979 hectares (2005-2006),
followed by only 327,018 hectares the subsequent reporting year (2006-2007).
• Multiple projects covered a range of assets, including pests and weeds,
sustainable agriculture, salinity, and water quality. Many projects and outputs
focused on traditional owners. The comprehensive review of the assets
detected no significant change, survey and assessment of regional assets is
therefore urgently required.
and implement plans to protect
cultural assets.
• There is clear evidence that NRM is
considered a long-term solution to
maintain cultural landscapes.
• There is evidence that investments in
NRM governance and capacity have
resulted in gains in NRM protection,
though this diminished towards the
end of the investment phase.
45
In terms of Element 1.2 – natural resource action is regionally co-ordinated, the results show that:
• There is considerable evidence that the regional delivery system coordinates natural
resource action at a regional level. This capacity is fragile, and is challenged by the
competitive funding model because of:
▪ the focus on state priorities - fully coordinated action requires that local groups and
individuals (those targeted to implement activities) be involved in setting priorities
and identifying capabilities needed to implement outcomes. The alignment of local,
state priorities is difficult to achieve in a competitive model when regions are
competing against other organisations (and other regions) for funding;
▪ the uneven socio-economic conditions of regions – some regions have poor socio-
economic conditions. This has led to a loss of social capital within regions and a
declining ability to attract NRM funding and is a growing problem for maintaining
regional coordination capacity outside of the more heavily populated coastal
regions;
▪ poor agricultural industry confidence in some regions – this impacts on local
interest in NRM activities and ability of NRM organisations to leverage resources
for natural resource action; and
▪ other NRM projects (ie other Queensland and local government NRM action) -
there is no integration and coordination of NRM projects across Queensland. There
are insufficient mechanisms to link projects at a strategic level and multiple (and
unlinked) reporting requirements.
• The capacity for regional-level coordination of NRM projects in the first phase (2002-2008),
was built through NRM planning (including water quality improvement plans, or WQIPs),
regional brokerage of projects, and joint steering committee processes. In NHT II the
Queensland and Australian Governments invested significant financial investments and
government human resources to coordinate all funding through the bilateral partnership and
integrated governance processes resulting in a high level of coordination.
• The capacity for NRM coordination increased slightly in the second phase (2008-2013).
Though some regions were not funded to update their regional NRM plans, and this was a
problem, others were able to fund partial updates. Regional body delivery partnerships
across regions also clearly emerged in this phase. The governance foundations built through
NHT II coordination processes helped regional bodies to coordinate cross-regionally and
the networks they had built at a sub-regional level enabled them to maintain the coordination
of community and volunteer input into action for sustainability, despite declining funding
for planning.
Value Proposition of Regional NRM in Queensland Final Report
46
• The evidence suggests a decline in the overall number of community groups and projects
assisted in the first phase (2002-2008). Declining social and financial positions and industry
optimism is a big problem for some regions. Reporting inconsistencies (the way that
‘projects’ are defined, counted, and reported across Queensland and over time) could be
concealing the real story in terms of the regional coordination of NRM activity. Some
regions dominated in state-wide projects. This reflects a widening inconsistency in the
capacity of regional bodies.
Table 7 presents the summary of the evidence base and conclusions for Element 1.2.
47
Table 7. Summary of the evidence base and conclusions for Attribute Element 1.2- Natural resource action is regionally coordinated
NRM
Investment
Phase
Evidence Conclusions Assessment
(/5)
Phase 3
(2013-15)
• Natural resource action was coordinated between multiple parties, which
included traditional owners (including native title holders), sub-regional
delivery partners, targeted community groups, landholders/managers and
volunteers, state and federal governments, local council, and sometimes
industry and/or professional groups. All parties coordinated to implement
natural resource action.
• According to the output summary aggregate (a collation of all regional body
reported achievements), 180 community groups/projects received assistance
across Queensland in the 2014- 2015 reporting year.
• In some projects, particularly in remote areas with low population numbers
and available resources, coordinated natural resource action depended on the
growth and stability of community group.
• The financial and social capacity of some local communities impeded
coordinated natural resource action in some regions. Evidently, external
pressures and priorities, such as financial and health considerations, can
impact community interest and the ability to implement natural resource
action.
• Multiple regional bodies were also engaged in the governance of state-wide
projects (not just regional projects). For example, under the Queensland
Wetlands Program, the Department of Agriculture, Forests and Fisheries
(DAFF) established regional advisory groups involving key government,
• Regional action was coordinated with
and across many different sectors,
including local, state, and federal
governments, traditional owner groups
and industry.
• Even though there was ample evidence
of coordination at the local scale level
(e.g., private landholders), fully
coordinated action was dependent on
the priorities and capabilities of the
local groups or individuals targeted to
implement these activities.
• The socio-economic conditions of
landholders could potentially worsen in
some regions and development of the
capacity of social capital is necessary to
continue regional coordination of
natural resource management activities.
• Industry confidence was down in some
regions. A lack of confidence
negatively impacts local interest in
NRM activities.
3
Value Proposition of Regional NRM in Queensland Final Report
48
NRM
Investment
Phase
Evidence Conclusions Assessment
(/5)
industry, NRM, and other relevant non-government organisations to provide
advice and guidance specific to each region. These groups are in place and
operational for the Mackay, lower Burdekin and Hinchinbrook areas. There
was also engagement in the Fitzroy Basin Association; however, no formal
group was established. DAFF also engaged with stakeholders at a reef-wide
level via the Reef Plan Management Practices Advisory Group (DAFF Reef
Wetlands Report, J2015).
• Specific detail of regional body engagement in state-wide projects in this
dataset was insufficient to adequately assess regional coordination. For
example, the Queensland Wetlands Program appears to only hold an advisory
role and not a fully coordinated or shared role in program implementation,
(though the responsibilities of the partnerships in delivering natural resource
action are not fully explained in the dataset) (DAFF, QNRM Reef Wetlands,
June 2015).
• How NRM regional bodies were
engaged in other NRM projects (state-
wide) was important and impacted on
regional coordination. A more passive
engagement role (not an active
contributor) means that there is no
integration and coordination of state-
wide operational projects. This means
that there are insufficient ways to link
projects at a strategic level. It is
important that regional bodies, industry,
traditional owner groups and agencies
are involved in this function,
particularly to meet the strategic
coordination of regional natural
resource management action.
Phase 2
(2008-12)
• There was evidence of coordinated action at a regional level. For example:
o Community and volunteer collection of monitoring data is fed annually
into regional scale asset objectives (e.g., for water quality).
o Coordinated action through involvement in regional management
strategies and planning (e.g., NRM REGIONAL BODY involvement in
the regional pest management strategy or working with local councils to
map and survey areas for future weed management strategies).
o Coordinated action with local landholders to address regional feral pig
• Coordination of regional NRM action
took place in multiple ways in order to
implement natural resource
management activities and was flexible
enough to reach across regional
boundaries to support the delivery of
regional, state, and federal objectives.
• NRM coordinated action can provide
the impetus for the change required at
various levels of governance.
3.5/4
Value Proposition of Regional NRM in Queensland Final Report
49
NRM
Investment
Phase
Evidence Conclusions Assessment
(/5)
issues (e.g., landholders with mound springs on their properties).
• There was evidence of coordinated action across regional boundaries. For
example:
o Northern Gulf and Terrain coordinated their weed and fire management
program in priority ecosystems.
o Desert Channels Queensland, South West NRM, and Southern Gulf
Catchments established a partnership to protect the productive and
biodiversity values of the rangelands from invasive cacti through the
mapping of infestation, education, on-ground control of invasive
species, and monitoring.
o Strategic groups action supported the development of mapping
databases, prioritisation, and strategic management of weeds, cross
regional action, and sharing of resources.
• There is evidence that planning frameworks were used to guide NRM
activities to protect key regional assets from future development in urban
and peri-urban regions. For example, this was through:
o Promotion of local government guidelines and an open access
website that translates the SEQ Ecosystem Services Framework into
an educational and decision support tool for SEQ stakeholders.
o Development of metrics to consistently measure land units for
potential provision of services based on ecosystem condition.
Supported by the regional coordination groups, which provided a
forum for regional body, local government and Queensland
government discussions.
• Evidence indicated that planning
frameworks were used as a tool to
assist regional NRM activities.
Value Proposition of Regional NRM in Queensland Final Report
50
NRM
Investment
Phase
Evidence Conclusions Assessment
(/5)
o Enhancement of the spatial planning and decision support tool to
identify priority services for the wellbeing of the community and to
connect the community, policy, and investment to the landscapes
that provide these services.
Phase 1
(2002-08)
• The summary outputs between 2002 and 2008 (Jan-Jun) reported that the
highest number of community groups or projects assisted was between the
reporting year 2007 (Jul-Dec) and 2008 (Jan-Jun), with over 4,000
community groups or projects assisted. This is in comparison to 2003, when
only 718 community groups or projects received assistance.
• The Joint Steering Investment Panel (JSIP) processes provided a mechanism
for data sharing between regional bodies, and the Queensland and Australian
Governments; however, the evidence did not identify cross-regional NRM
coordination projects or state-wide processes for coordinating action across
regional boundaries; though this could be due to the methods used to report
the data, rather than a lack of cross-regional or state-wide coordination.
• Sub-regional processes were being
developed to coordinate NRM activities
and broker environmental and
landscape outcomes with multiple
community groups and partners, in this
investment phase.
• It was difficult to assess coordination
across regions and between state,
federal, and regional levels in the
available data.
3
51
In terms of Element 1.3 - Investments achieve on ground results, the results show that:
• NRM investments through the regional delivery systems achieve natural resource
management action, though this capacity has changed over time with changing government
priorities. Data to evaluate trends in outcomes achievement over time remains inconsistent.
• The first phase (2002-2008) exhibited rapid growth in NRM activities, biophysical surveys
and studies, and conservation agreements. NRM action for sustainability outcomes
addressed a diverse range of NRM assets and sustainability threats in each region.
• Reporting became more quantitative in the second phase (2008-2013), though this was not
particularly informative in regards to the level of natural resource management outcomes
achieved. Severe weather events in Queensland during that time were reflected in project
results and some funding had to be re-prioritised to address changed environmental
conditions and to reduce the spread of threats.
• There was a substantial decline in the volume of reported outputs in the third phase (2013-
2015). Climate factors and funding uncertainty has caused some projects to be delayed and
confidence that projects can achieve results in the current financial and governance context
declined. Funding was also more fragmented in this phase compared to earlier phases.
Consequently, not all NRM projects and sustainability action is captured in this dataset.
Table 8 presents the summary of the evidence base and conclusions for Element 1.3.
52
Table 8. Summary of the evidence base and conclusions for attribute Element 1.3 - Investments achieve natural resource management action
NRM
Investment
Phase
Evidence Conclusions Assessment
(/5)
Phase 3
(2013-15)
• NRM report summaries provided annual summaries of the recorded outputs
compiled by the Queensland Government, such as the number of hectares of pest
and weed control. For example, NRM regional bodies implemented 2,264,698
hectares of pest animal control and 2,567 hectares of plant control in the 2014-2015
year.
• Reported outputs declined as a result of tighter funds and uncertainty of
investments, which has led to a delay in some on-ground project results.
• Results of many natural resource management projects were reliant on ongoing
funding stability and the capacity of communities to implement the work,
particularly in weed and pest control, riparian restoration, sustainable land
management practices, water quality monitoring, etc.
• A number of NRM issues and themes investigated pest and weed control related
activities, such as through agricultural best management practices (BMPs),
sustainable agricultural programs, native vegetation protection, enhancement,
rehabilitation and re-vegetation, collaborative arrangements, and awareness raising
events.
• There was a substantive decline in the volume of results in this investment phase
reported by NRM bodies to the state. Declines in reported results were likely due
to the lack of State interest in NRM outputs and activities to support communities
and NRM action.
• Project recovery to achieve results was slow following severe weather events or
financial issues, and expenditure and investment in NRM decreased as a result.
• The reporting of outputs and
results of NRM activities to the
Queensland Government was
largely limited to quantitative
targets.
• Although NRM projects were
providing some results, the results
depended on projects that require
investment and support from state
funds.
• Some on ground sustainability
action was reported, such as pest
and weed control, agricultural best
management practices (BMPs),
sustainable agricultural programs,
native vegetation protection,
enhancement, rehabilitation and
re-vegetation, collaborative
arrangements, and awareness
raising.
• Some NRM projects were more
vulnerable to either climatic and
terrain/geographical conditions, or
both.
2
Value Proposition of Regional NRM in Queensland Final Report
53
NRM
Investment
Phase
Evidence Conclusions Assessment
(/5)
• Most NRM regional bodies identified decreasing confidence in the ability for
projects to achieve results as a result of the current financial, climatic, community,
and governance contexts in Queensland regions.
• Both climatic conditions and the
current financial state of NRM
were affecting NRM project
results, and no recovery was
evident.
Phase 2
(2008-12)
• Results of investments were primarily reported in quantitative terms, for
example, 355 hectares of native vegetation and habitat managed through
incentives and targeted stewardships.
• 200 hectares of native habitat were managed through voluntary conservation
agreements developed with land managers for priority areas as a result of
investments.
• Natural resource management results were achieved as a result of investments by
engaging communities and locals to implement activities (engineering works to
rehabilitate erosion, stock control through fencing, flood recovery activities and
implementation of measures to allow natural regeneration for biodiversity
outcomes).
• Climate and severe weather events impacted and influenced the priority and
investment given to activities (e.g., water quality):
o In response to changed environmental conditions, the Fitzroy Basin
Association funded weed control in 3,168 hectares and contracted work
over 3,000 hectares post flood.
o South West NRM eradicated flood-related mosquito infestations.
o Southern Gulf NRM increased investment in the removal of prickly acacia
• NRM investments achieved
sustainability action.
• Both climatic uncertainty and the
financial uncertainty of the NRM
program were affecting NRM
project results, though there was
evidence of adaptation and some
resilience in the late 2000s.
• Providing ownership and control
of local communities, and the
grassroots level, increased NRM
outcomes in each region.
• NRM sustainability action helped
the Queensland Government to
meet their landscape and
environmental targets, such as the
control of identified National
(Federal) Weeds and Pests of
Significance.
3.5/4
Value Proposition of Regional NRM in Queensland Final Report
54
NRM
Investment
Phase
Evidence Conclusions Assessment
(/5)
after heavy, wet season rainfalls.
• Indirect NRM results were also evident (e.g., North Queensland Dry Tropics
reported restoration of optimum water bird habitats, improved connectivity, and
water quality in the Wongaloo wetlands as a result of its weed management
program);
• Investments provided NRM outcomes in sustainable agriculture. In total, 72,069
hectares of improved land management was protected and enhanced. Training to
improve land management was also undertaken, such as reducing soil erosion, crop
rotation management, increased crop residue retention, and water use efficiency.
• Investments also provided NRM outcomes for nationally significant sites (e.g.,
investment in land management and improved water quality in the Moreton Bay
Ramsar site enhanced 34.1 hectares of critical coastal waterways).
Phase 1
(2002-08)
• In terms of surveying for land for biophysical study and NRM action, the most
active surveying phase was during 2006/7 reporting year with over 770,000,000
hectares, this compares to 2003/4 with only 23,500 hectares. This demonstrates a
rapid increase in the number of hectares surveyed for NRM action across the
Queensland region (summary outputs).
• Similarly, the number of hectares protected by conservation agreements, a total of
812,000 hectares, increased between 2002-2008 Jan-Jun, with a slight dip in the
years 2006-2007. However, the majority of hectares were protected in the 2007-
2008 reporting period (almost 600,000 hectares protected by conservation
agreements).
• Recorded investment outcomes
presented this phase as
characterised by rapid growth in
the number of NRM activities,
such as biophysical studies and
conservation agreements.
• The variety of outputs and results
recorded by NRM bodies reflected
the multitude of roles NRM can
assist with and perform.
3.5/4
55
Attribute 2: Performance and Accountability and Return on Investment
Four elements were considered for Attribute 2, Performance and accountability and return on
investment. Element 2.1 assessed the governance of NRM investments through an analysis of
organisational policies and procedures related to financial matters, HR management, asset management,
fraud control, project-management, and project delivery. Element 2.2 explored the regularity of regional
bodies’ reporting on investments, projects, output, and outcomes at the sub-regional level, as well as the
scope of the reporting frameworks. Element 2.3 assessed regional NRM communication in terms of
accountability to stakeholders and investment leveraging, while Element 2.4 assessed monitoring and
continuous improvement programs in terms of the presence or absence of these programs in the datasets.
In terms of Element 2.1 - Organisational policies and procedures (for finance, HR management,
asset management, fraud control, project management, and project delivery) provide evidence that NRM
investments are well governed, the results show that:
• The available evidence limited the ability to assess the value and trends in organisational
policies and procedures for financial, HR management, asset management, fraud control,
project management, and project delivery. This information requires supplementation of
data from other sources (i.e., the business excellence framework). The limited insight gained
from these data sets does not mean that the regional delivery system is not governed by
effective organisational policies and procedures. Improvements in reporting, the regular use
of reporting tools, and local body experimentation with new data collection processes
indicate that operational procedures have matured.
• Intense growth and development occurred during the first phase (2002-2008), which
included a focus on establishing organisational policies and procedures and growing the
accountability of regional bodies, with strong support from the Queensland and Australian
Governments.
• Reporting and communication improved significantly during the second phase (2008-
2013); however, reporting information about operational matters was limited. This
primarily pertained to the internal organisational procedures developed by individual
regional bodies to manage local demand and interest in NRM.
• The reporting frameworks in the third phase (2013-2015) constrained the evidence available
to judge the trends in regional-level organisational policies and procedures. Information
systems were developed and widely used to manage data about project delivery, and regions
experimented with processes and systems to collect and present data in a tightened funding
context.
• There is an opportunity to improve information about the governance arrangements and
accountabilities of regional delivery arrangements and improve transparency. This occurs
Value Proposition of Regional NRM in Queensland Final Report
56
at the national level through the Australian Government “Performance Framework for
Regional NRM Organisations” – which covers contractual reporting and voluntary self-
assessments of governance review processes. The framework could be configured to
improve state-level assessments of governance and regional accountabilities.
Table 9 presents the summary of the evidence base and conclusions for Element 2.1.
57
Table 9. Summary of the evidence base and conclusions for Attribute Element 2.1 - Organisational policies and procedures (for finance, HR management, asset
management, fraud control, project management and project delivery) provide evidence that NRM investments are well governed
NRM
Investment
Phase
Evidence Conclusions Assessment
(/5)
Phase 3
(2013-15)
• This dataset provided little evidence regarding the organisational policies and procedures
of NRM regional bodies, with much of the focus on performance reviews of NRM
operations and activities against agreed milestones. Inclusion of the findings from the
evaluation of regional bodies against the business excellence framework could enhance
this data.
• There was evidence of some Queensland operational policies influencing the nature of
the reporting of NRM projects for project investors (primarily the Queensland
government in this dataset). This investment phase required an NRM body report every
six months (bi-annually), as well as a detailed milestone report and program output
reporting. Monitoring and evaluation of each milestone or subprogram was also required.
• Transparent communications about project delivery enabled the Queensland government
to be assured that projects and operations were on track and could achieve all targets, as
indicated by the annual NRM Outlook Report, 2015.
• The use of the IT system ‘Enquire’ was required to be used by all NRM regional bodies
to report information to the Queensland Government. There was also evidence of the
development of their own IT systems to hold and collate data; however, some challenges
arose in relation to the storage and recording of data (particularly confidential and/or
sensitive data).
• Some regions were evaluating current investment approval processes to adapt to new
external pressures, and there was some evidence of coordinating or leveraging
investment to achieve activities in expected timeframes (e.g., employing more
economical and effective ways to present data in the context of tightening funds). This
• A comprehensive review of NRM
operational policy was not possible
based on the available dataset, only
reviews and the performance of
milestones and key activities
implemented by the NRM bodies
were available for evaluation.
• Transparency and ongoing
reporting assured governments that
programs remained on track.
• Further justification about the
governance and arrangements of
NRM bodies was required to better
inform investors about the low
risks involved when investing in
NRM bodies and NRM activities
(e.g., landscape services based
etc.).
• Terrain NRM suggested that an
ecological services framework
could provide independence from
Queensland Government funds
(over a period of time). The
3
Value Proposition of Regional NRM in Queensland Final Report
58
NRM
Investment
Phase
Evidence Conclusions Assessment
(/5)
demonstrated a good understanding of business, overheads, and costs, and a strong
accountability to investment partners.
processes that NRM used were
already related to this principle.
Phase 2
(2008-12)
• Basic operational policies were evident, including a review of internal plans and policies,
and the implementation of monitoring and evaluation plans for each
milestone/subprogram, which were usually reported every six months (through Enquire);
• There was evidence of improved
reporting operations and
communication; however, little
evidence was provided about NRM
operational policy in Queensland
Government summaries.
• Individual examples showed that
some NRM regional bodies were
internally developing their
organisational operations and their
capacity to meet increasing local
demands and interest in NRM.
4
Phase 1
(2002-08)
• This data set provided some evidence of operational policies. For example,
administrative arrangements in the state summaries of NRMs, including: the
Commonwealth/State joint steering committee membership and membership details of
the Joint Australian/Queensland Government Steering Committee; financial
management arrangements, including management of accounts and internal review
processes; bilateral agreement information and funding issues, such as the need for state
agencies to match the Trust investment by region; and regional arrangements, including
partnership with regional agency coordination groups and other state and local
government officers.
• This was a time of growth and
development, with much focus on
operational policies, in particular,
NRM capacity development and
support by the Queensland
Government.
3.5
Value Proposition of Regional NRM in Queensland Final Report
59
NRM
Investment
Phase
Evidence Conclusions Assessment
(/5)
• This was a time of rapid growth for most NRM regional bodies, including
amalgamations, implementing new boards, recruiting new staff, and developing new
administrative systems. Nonetheless, funding issues regarding state agencies matching
trust investment commitments by region were evident.
60
In terms of Element 2.2 - Project output and outcome-reporting accounts for investments at the sub-
regional level, the results show that:
• Regional bodies regularly reported on investments, projects, outputs, and outcomes to the
government at a sub-regional level.
• The reporting frameworks narrowed considerably over time.
• Decisions about funding were more transparent during the first investment phase (2002-
2008), for example, with regards to the use and leveraging of funds at the regional level,
and how funds related to regional activities.
• The focus changed to targeted outcomes (activities, targets and milestones) during the
second (2008-2013) and third (2013-2015) investment phases. Reports were more detailed
but contained less information about additional activities and the outcomes achieved. The
quality of reporting also varied considerably between groups. It was difficult to record
internal capacity pressures (and regional bodies’ innovative responses) in the reporting
frameworks used during these phases.
Table 10 presents the summary of the evidence base and conclusions for Element 2.2.
61
Table 10. Summary of the evidence base and conclusions for Attribute Element 2.2 - Project, output, and outcome reporting accounts for investments at the sub-
regional level
NRM
Investment
Phase
Evidence Conclusions Assessment
(/5)
Phase 3
(2013-15)
• Reports reviewed for the investment activities agreed to in the 2013-2015 phase
included bi-annual performance reports, milestone reports, and funding reports, which
provided the progress of activities and some information about additional
outcomes/significance of the outcomes, the key lessons learnt, and risks of the project.
• There were some nuances in the reporting of each NRM body.
• Regional bodies reported on project results in this dataset. Some regions evaluated
projects in their milestone reports, either against the stated agreed outcomes/outputs of
an approved investment milestone for that investment phase, or against the agreed
outcomes for a whole subprogram milestone.
• Sub-regional investment reports have become progressively more and more detailed,
but appeared to be rigidly focussed on reporting the value of investments within those
specific activities approved by the state. The results reported for regional investments
were only for the activities approved by the Queensland Government under the NRM
investment program (outcomes for other NRM activities were not reported). This
makes additional outcomes or other activities (that could also be used to assist and
complete the agreed activities) difficult to report on or value against such rigid
frameworks.
• Some regions experienced issues with the process of mandatory investments being
provided straight to community groups after contracts were approved. Mandatory funds
are currently provided to community groups, even if of the groups do not have the
capacity to report activities without close assistance from NRM regional group bodies.
• Reporting for the Queensland
Government was very detailed and
provided a clear overview of the
progression of projects against
approved milestones and targets,
and sub-program outcomes.
• There was a lack of funds to
support NRM regional bodies in
regards to sub-regional reporting
difficulties.
• The quality of sub-regional
reporting is more vulnerable when
community capacity is lacking.
• Sub-regional reporting did not fully
evaluate actual project outcomes
and results (beyond those recorded
by the state).
• The quality of sub regional
reporting was impacted by
mandatory funds being given to
community groups.
3
Value Proposition of Regional NRM in Queensland Final Report
62
NRM
Investment
Phase
Evidence Conclusions Assessment
(/5)
Phase 2
(2008-12)
• Reports in the 2012 phase included narrative and final project reports, state-wide
summaries of assets, case profiles, and JSIP narrative summaries. All of the reports
included information about the sub-regional activities implemented and some
investment accounts at the sub-regional level.
• Sub-regional reporting included
detailed output reports and
qualitative summaries.
3.5/4
Phase 1
(2002-08)
• This data set described the use of federal and state funds. For example, early on in this
investment phase a decision was made that all regional Trust funding should be used to
establish regional NRM bodies and invest in the development of regional NRM plans
rather than spreading funds too thinly, in order to maintain priority action projects from
NHT1. Federal investments can therefore be leveraged for use in capacity building and
planning activities (not only regional NRM activities).
• This data set provides evidence regarding some awareness that levels of investment
between NRM regional bodies differ according to their levels of human and social
capital and the potential requirement for some NRM bodies to secure further funding at
a later date, particularly to support the Queensland focus on NRM planning activities.
• Fund reports included those provided to facilitators and coordinator support, in addition
to foundation funding and a breakdown of funding across these funding types,
demonstrating transparency and clarity about how funds are divided and used at the
sub-regional level.
• Transparency was evident at the
state and federal level and
regarding the use of these funds at
the regional and sub-regional level.
4
63
In terms of Element 2.3 - Regional NRM communication demonstrates accountability to
stakeholders and leverages investment, the results show that:
• Regions appear to have adopted diverse and innovative ways to communicate with and
maintain community interest in NRM. NRM bodies provide important communication hubs
for technical experts, scientists, governments, and community groups to meet,
communicate, and learn together (through organised workshops and events).
• The changes to reporting over the three phases demonstrate that:
▪ Reporting in the first phase (2002-2008) highlighted the communication challenges
for distant communities and the size of the communication task involved in
empowering communities in NRM.
▪ Reporting in the second phase (2008-2013) of regional NRM was more narrowly
focused on quantitative reporting of achievements, with less information provided
in reporting products about the communication strategies and systems used by
regional bodies. However, this does not mean that regions did not evolve their
communications during this time.
▪ Reporting in the third phase (2013-2015) highlighted the diverse approaches
regions are currently utilising when communicating. Regions used a variety of
mediums, such as published material, media opportunities, presentations,
organisation website platforms, workshops, partnerships, and coordination and
involvement in other relevant programs and plans. Social media has emerged as an
important method for regional bodies to disseminate information and regions are
also using positive branding to engage the grassroots level.
• The evidence demonstrates the important role that regions play in communicating about
sustainability action where communication was targeted at the grass-roots level. Regions
disseminated messages from governments, research, and consultants to local communities
through targeted communications.
Table 11 presents the summary of the evidence base and conclusions for Element 2.3.
64
Table 11. Summary of the evidence base and conclusions for Attribute Element 2.3 - Regional NRM communication demonstrates accountability to stakeholders
and leverages investment
NRM
Investment
Phase
Evidence Conclusions Assessment
(/5)
Phase 3
(2013-15)
• Regional NRM communication included a variety of mediums, such as published
material, media opportunities, presentations, organisation website platforms, workshops
and partnerships, coordination, and involvement in other relevant programs and plan.
• Published pamphlets and flyers, community awareness events, and the use of online
social media were some of the many ways that the NRM regional groups disseminated
information at the grassroots level. This could be through regional coordinators,
Landcare groups, or other project partners and/or community groups.
• In some cases, the dataset provided good examples of how NRM groups attempted to
improve the effectiveness of communication methods (e.g., positive branding like
‘productive land’ instead of negative titles like ‘degraded soils’).
• NRM bodies formed communication hubs where technical experts, scientists,
government, and community groups could meet, communicate, and learn together
(through organised workshops and events).
• There was a demonstrated use of available reporting processes to help monitor and
contribute to the strategic direction of Queensland state projects (e.g., reef quality report
cards). This demonstrates the ability of NRM regional organisations to use available
reporting processes to help meet project priorities at the state-wide level.
• The Queensland Government summary output table indicated no development of new
monitoring programs, collaborative arrangements, or sub-regional plans. However, there
was evidence of the development of these programs/plans in the performance reports,
indicating a possible lack of recognition by the Queensland Government or poor
• More research is required to
consider/explore how NRM
outcomes/results for this attribute
can be better recorded and
communicated (and that the
evidence is still well demonstrated
for accuracy and accountability).
• More media opportunities and
pamphlets did not always equate to
more interest and attendance, the
use and framing of this
communication is also key.
• Whether NRM regional bodies
could be used as a hub for
communication and information
dissemination (given their access to
NRM knowledge) is unclear due to
a dependence on Queensland
Government funds for activities.
• State-wide reporting processes set
up by the Queensland Government
can be used by NRM regional
4
Value Proposition of Regional NRM in Queensland Final Report
65
NRM
Investment
Phase
Evidence Conclusions Assessment
(/5)
communication between the government and NRM regional bodies during this
investment phase.
bodies to help meet state priorities
and targets.
• Queensland government reporting
frameworks were narrow. They did
not capture the diverse
communication and reporting
measures regional bodies used to
be accountable stakeholders or to
leverage investment.
Phase 2
(2008-12)
• Quantitative terms were used to summarise the results of NRM investments for the
State (e.g., 355 hectares of native vegetation and habitat managed through incentives
and targeted stewardships or 200 hectares of native habitat managed through voluntary
conservation agreements developed with land managers for priority areas).
• Although other outcomes and results were considered in the narrative reports and in the
case study summaries, there was no clear or consistent method to report other
outcomes to the State Government in a comprehensive way (beyond that usually
reported in the summary output sheet).
• The summary output sheet compiled by the State showed that activities were
decreasing and there were no recorded outputs of hectares protected through the
development of conservation agreements or subregional plans, or the implementation
of biophysical studies or improved Natural Resource Monitoring programs, which
could indicate a lack of communication.
• Investment results were primarily
recorded using quantitative
measures.
• There were limited methods
available to report and show
evidence of performance. More
research is required to
consider/explore improvements in
how NRM outcomes/results are
recorded and communicated.
3
Phase 1
(2002-08)
• Some regions demonstrated that distance impacts communication, and subsequently, the
sense of ownership over a project (e.g., the Northern Gulf Resource Management Group
experienced difficulties when they engaged consultants to undertake the plan, as distance
• Distance was considered to be a
significant factor when considering
NRM communication (in addition
3
Value Proposition of Regional NRM in Queensland Final Report
66
NRM
Investment
Phase
Evidence Conclusions Assessment
(/5)
hindered communication and the ability of community members to maintain personal
relationships with planners).
• Effective communication was required to allow communities to feel as though they were
contributing to NRM projects, especially those that employed external consultants and
expertise in NRM projects (e.g., the Annual State NRM Summary Narrative reported
that planning activities proceeded satisfactorily with significant consultation with the
local community, including the Indigenous sector, and strong ownership of the plan by
local people). This was assisted by regular visits and the use of locals to contribute to
sections of the plan (particularly the Indigenous and capacity expansion sections).
• There were reports and evidence of communication about the National Action Plan and
the regional component of the Trust in priority actions across the different types of NRM
key themed areas. This included for salinity, soil condition, rivers and wetlands, nutrients
in aquatic environments, surface water salinity, significant native species and vegetation,
significant invasive pests and estuarine, coastal, and marine.
to the importance of a connection
to the areas that are the focus and
concern of NRM projects). NRM
bodies did provide this information
and it was only the employment of
external consultants from other
regions that caused some
difficulties in communication to
emerge.
• Effective communication at the
local level was required to provide
the community with a sense of
power and ownership over NRM
activities and outcomes.
67
In terms of Element 2.4 - Monitoring and continuous improvement programs are in place, the
results show that:
• Monitoring was a central tool used by NRM bodies for strategic planning and targeting
across the region. This assisted with planning/prioritisation and the administration of on
ground works across all Queensland regions
• NRM bodies obtained important knowledge from local communities and landholders to
prioritise work within regions. The Queensland Government would find it difficult to collate
and use this knowledge without NRM bodies.
• The capacity for regions to collect monitoring data was highly varied, both spatially and
temporally. Large gains were made in the GBR regions, while others lagged behind.
• It was not clear from the dataset how monitoring and continuous improvement programs
inform adaptive management within regions or by the Queensland or Australian
governments.
The results also noted several trends in monitoring, namely that:
• The first phase (2002-2008) developed monitoring programs at the regional and state level.
• The second phase (2008-2013) saw NRM bodies increase the application and use of MERI
frameworks. Some individual regions made significant gains in improving the monitoring
data available for investment prioritisation and to evaluate the efficacy of NRM actions.
However data collection was not funded and MERI plans were not fully implemented.
• In the third phase (2013-2015), all regions used MERI frameworks and the State adopted a
MERI framework, though no new monitoring and evaluation program was adopted. Data
collection remained unfunded and MERI plans not fully implemented. Despite this trend
toward the adoption of MERI frameworks:
▪ Monitoring and reporting became disjointed, sub-programs were individually
evaluated, which meant monitoring across similar sub-programs was not
coordinated or scaled up to assess broader trends and impacts of programs or
emerging challenges.
▪ Monitoring frameworks focussed on program targets only. Other information,
particularly related to the social, organisational, and governance aspects of regional
delivery, could help regional stakeholders to protect natural assets and improve
local communities and the grassroots engagement, particularly if they were scaled
up across NRM regions to assist with program design and advocacy.
▪ Tracking of the methods used to monitor against NRM targets and other
performance indicators should be initiated in order for projects to be monitored
Value Proposition of Regional NRM in Queensland Final Report
68
against previously agreed activities, and against comprehensive NRM objectives
and values.
Table 12 presents the summary of the evidence base and conclusions for Element 2.4.
69
Table 12. Summary of the evidence base and conclusions for Attribute Element 2.4 - Monitoring and continuous improvement programs are in place
NRM
Investment
Phase
Evidence Conclusions Assessment
(/5)
Phase 3
(2013-15)
• The Queensland Regional Natural Resource Management Program ‘Monitoring,
Evaluation and Reporting Framework’ was used to measure the success of delivering
the program objectives and outcomes. It established performance indicators for targets
(as specific measures to be observed over time) to indicate progress in delivering the
agreed levels of performance against the program targets.
• NRM bodies sent formal monitoring and evaluation plans to the Queensland
Government for approval for most subprograms in the projects. Monitoring and
reporting activities, as specified in monitoring and evaluation (M&E) reports, can
include mapping of progress with invasive species, activating and implementing the
community participation register (in particular, to track interaction with partners), and
contract management and review systems.
• According to the 2014-2015 Queensland Government summary output Excel
spreadsheet, no new monitoring programs were established during this phase. This is
concerning given the changing context of the NRM regional program, such as
tightening funds and the vulnerability of projects to climate change, community
interest, and other external impacts.
• Coordination of the improvement and evaluation of NRM projects addressing the same
regional assets/threats does not always occur, and multiple evaluation and
improvement panels are completed separately for individual sub-program projects,
causing protection of key regional assets to be disjointed rather than comprehensive.
• Monitoring of data collected by volunteers and community groups across the region is
used by some NRM bodies to enhance strategic prioritisation and targeting of areas in
the region for future works across the region.
• Monitoring of NRM progress
occurred against Queensland
Government agreed program
targets only. This is not necessarily
the performance required to protect
natural assets or to adequately
engage with local communities and
the grassroots.
• Methods for monitoring against
NRM targets (with their own
performance indicators used for
observation) may need to be
initiated to ensure that projects are
not only monitored against
previously agreed activities, but
also against comprehensive NRM
objectives and values.
• Within the existing monitoring
framework, sub-programs should
be individually evaluated, to ensure
that monitoring across similar sub-
programs is coordinated and not
disjointed.
• Monitoring was a central tool used
by NRM REGIONAL BODIEs for
3
Value Proposition of Regional NRM in Queensland Final Report
70
NRM
Investment
Phase
Evidence Conclusions Assessment
(/5)
strategic planning and targeting
across the region, which assisted
planning/prioritisation and the
administration of works across the
Queensland region.
• Significantly, the prioritisation of
future works is comprised of the
knowledge of local communities
and landholders across the region.
This is a useful source of
knowledge that the Queensland
government might not be able to
compile and use without NRM
bodies.
Phase 2
(2008-12)
• Monitoring was a key tool used individually by NRM bodies to improve environmental
outcomes (e.g., through surveillance and eradication activities for weeds of national
significance, collation of baseline biodiversity information to guide activities, and
whole of property assessment, planning, and land management practices that integrate
biodiversity values).
• Under the Reef Rescue Program, NRM bodies in the reef catchment monitored water
quality to inform the Reef Plan water quality targets and were key contributors to
regional scale data.
• NRM regional bodies aimed to monitor and improve water quality through the
establishment of their own water quality guidelines, as well as networks of water
quality sites. Monitoring data collected by volunteers was supplied to meet regional
objectives (e.g., the SEQ Catchments water quality monitoring program continued to
• Monitoring frameworks were
applied individually by NRM
organisations to assess the
condition and extent of natural
assets, and the processes and
operational policies that were
applied to address key regional
assets and threats.
• NRM bodies were key contributors
to regional scale monitoring data
and assisting with the connection
between State and Federal scales to
3
Value Proposition of Regional NRM in Queensland Final Report
71
NRM
Investment
Phase
Evidence Conclusions Assessment
(/5)
invest in increasing their volunteer numbers, which was at 414, with 923 registered
water quality monitoring sites in key catchment areas. An annual amount of 66,456
data points were fed into the Bureau of Meteorology and the SEQ water quality
objectives).
meet their priorities (e.g., the Reef
Plan).
• Monitoring created ownership
through community support and
volunteers that assist with
achieving outcomes (e.g., data to
improve regional outcomes is
collected by volunteers and
communities in some regions).
Phase 1
(2002-08)
• There was some evidence of monitoring at the national level. For example, Queensland
had developed an NRM monitoring, evaluation, reporting and improvement (MERI)
framework to assess progress towards sustainable regional natural resource
management. The Annual State NHT Summary Narrative (2003-2004) reported that
this framework focused on the measurement and assessment of:
o The condition and trend in land, water, vegetation, biological, and cultural
resources, and landscape health, and
o The performance of programs, strategies, policies, and structures that support
and promote the sustainable use, conservation, and rehabilitation of these
resources,
• Initiatives that were the focus of the Queensland NRM monitoring and evaluation
framework delivered or supported the delivery of regional NRM planning and
implementation within the State. This was broader than just supporting the delivery of
agreed activities, but also related to state-level policy to support strong regional
arrangements. During this investment phase, NRM regional group initiatives
supporting NRM management were developed to ensure that the State strategic
objectives relating to NRM were met.
• There was evidence of a
Queensland framework for
monitoring that was used against
the condition of natural assets and
the processes applied to address
key regional assets and threats.
• Frameworks for monitoring can
include initiatives to support the
integration of NRM within state
government processes.
4
Value Proposition of Regional NRM in Queensland Final Report
72
NRM
Investment
Phase
Evidence Conclusions Assessment
(/5)
• Monitoring plans were also used to clarify State responsibilities vis a vis those of NRM
regional bodies for data collection, and management, reporting, review, and evaluation.
• Over 2,000 recorded monitoring programs were put in place across the Queensland
region between 2002 and 2008.
73
Attribute 3: Community Participation and Engagement
One element was considered for Attribute 3, Community Participation and Engagement. Element
3.1 referred to the diversity of the community membership base and the degree to which projects
engaged with a diversity of networks and sectors.
In terms of Element 3.1 - NRM has a diverse community membership base, projects engage diverse
networks and sectors, and partnerships are responsive to needs, the results show that:
• NRM arrangements do engage diverse stakeholder groups (industry groups, traditional
owner groups, Queensland and Australian Government Departments and others) at local
and community level, and in diverse ways.
• The first investment phase (2002-2008) focused on collaborative arrangements and
agreements, and regional facilitators were key to involving and manage involvement in
NRM activities.
• Collaborations became more targeted around government priorities in the second phase
(2008-2013); however, strong levels of community and grass roots participation in NRM
actions is an indicator that NRM arrangements were successful in engaging grassroots and
local communities to meet government needs.
• Collaboration efforts decreased in the third phase (2013-2015) in a few key areas:
▪ There was a decrease in the motivation of landholders to conduct NRM action,
particularly those in more rural and remote regions.
▪ The tighter capacity of NRM groups compared to earlier investment phases
decreased their ability to provide assistance to community groups lacking in the
available skills knowledge and the capacity for NRM action.
• The extent of collaboration could be concealed by the narrow way data was reported in this
phase (e.g., networks, partnerships, and projects may not be reported effectively against
milestones and outputs).
• Data is currently not available to assess the individual memberships analysed by industry
and scale, requiring further assessment.
Table 13 presents the summary of the evidence base and conclusions for Element 3.1.
74
Table 13. Summary of the evidence base and conclusions for Attribute Element 3.1 - NRM has a diverse community membership base, projects engage diverse
networks and sectors. Partnerships are responsive to needs
NRM
Investment
Phase
Evidence Conclusions Assessment
(/5)
Phase 3
(2013-15)
• According to the state summary output sheet, Queensland had 193 collaborative
arrangements in place in the year 2014-2015. Communities in some regions were
dependent on NRM REGIONAL BODY assistance and found it hard to find
community groups with the adequate capacity and skills to meet project
milestones, demonstrating a poor level of community capacity in this investment
phase.
• Although community interest and motivation increased somewhat in some regions
after difficult climatic conditions, there was a generally negative impact on the
motivation and capacity of landholders to engage in NRM activities after a hard
climatic season.
• The performance reports in these years also identified a decrease in the motivation
of landholders to conduct NRM action, particularly those in more rural and remote
regions.
• Data is not currently available to assess the individual memberships analysed by
industry and scale, requiring further assessment.
• The tighter capacity of NRM groups compared to earlier investment phases also
meant a decrease in assisting community groups lacking in available skills and
knowledge.
• Collaborative arrangements were
affected in the years 2014-2015 and there
was a decrease in the number of
community groups assisted by NRM
REGIONAL BODIEs, reflecting an
inability to offer assistance for
community groups.
• Community motivation and capacity
were vulnerable to the impacts of climate
and financial shifts, particularly in
remote and rural areas. This is expected
to continue.
• NRM Regional bodies were not able to
assist communities to build capacity for
action due to financial shortages.
Strategic selection of delivery partners
and community groups is occurring as a
result.
2.5
Value Proposition of Regional NRM in Queensland Final Report
75
NRM
Investment
Phase
Evidence Conclusions Assessment
(/5)
Phase 2
(2008-12)
• Regional bodies supported community involvement in NRM through funding of
projects and awareness and education programs. This included a range of
projects, such as weed and pest management, sustainable agriculture and coastal
risk management.
• There was involvement between groups who shared similar values. For example,
during this investment phase, Reef Catchments was an active member of the
Mackay Regional Pest Management Group, which includes government
agencies, Mackay Regional Councils (Mackay, Whitsunday, Isaac), Queensland
Department of Agriculture Fisheries & Forestry (Biosecurity Queensland),
Queensland Parks & Wildlife Service, Sunwater, the Department of Transport &
Main Roads, the private sector, Queensland Rail, Ergon Energy, Mackay Area
Productivity Services, North Queensland Bulk Ports and industry groups,
AgForce, and Landcare groups (Whitsundays, Pioneer, Sarina).
• Partnerships were formed with other community groups to work closely to
overcome new and ongoing challenges (e.g., Yasi recovery work).
• Indigenous groups were involved in the assessment of some assets and threats to
develop workplans for Indigenous rangers and were closely involved with local
communities and traditional owners in identifying key environmental and
cultural assets.
• Involvement was sometimes dependent on the structure of the program. For
example, a significant component of the Cape York NRM coastal program
involved education and awareness-raising. In the last reporting phase, Cape York
NRM engaged traditional owners, volunteers, and community members through
field training, data collection, and monitoring events. Cape York NRM is
invested in the long-term capacity building program for the training and
mentoring of partner indigenous communities for monitoring and control
• There was evidence of the involvement
of multiple groups, sectors, and
communities in NRM projects.
• The success of projects was usually due
to the ways communities were involved
and how they took ownership of the
activities.
3
Value Proposition of Regional NRM in Queensland Final Report
76
NRM
Investment
Phase
Evidence Conclusions Assessment
(/5)
programs. One of these programs is the monitoring and mapping of coastal turtle
populations.
• Targeted community engagement programs achieved NRM results. For example,
Reef Catchments increased its engagement with coastal communities through
coastal dune protection and weed control works, coast care events, and volunteer
involvement in their coastal program. Reef Catchments’ successfully invested in
the planting of 800 native plants, 600 metres of fencing of sensitive coastal
zones, and 150ha of weed control through its community engagement program.
• The success of projects can reflect the continued interest of communities and
landholders to undertake additional NRM works at their own expense.
Phase 1
(2002-08)
• The highest number of collaborative arrangements was made during the 2006/7
reporting period, with 2,253 collaborative arrangements reported during this
period, demonstrating a steady increase between 2002-2008.
• Collaborative arrangements were a catalyst for other community-related
outcomes. For example, there was a total of 3,449 conservation agreements in the
2002-2008 reporting period, while the 2004-2005 period saw the creation of an
additional 200 community facilitator positions, bringing the total to 392.
• Collaborative arrangements were crucial
for other key outcomes to be met (e.g.,
conservation agreements).
• At a regional level, the facilitator
position was key to involving and project
managing the multiple groups involved
in NRM activities.
3
77
Attribute 4: Resilient Institutions and Capacity Building
One element was considered for Attribute 4 - Resilient institutions and capacity building. Element
4.1 referred to the stability of the regional presence and capacity building.
In terms of Element 4.1 - Stable NRM presence in the region and regional skills retention and
development, the results show that:
• The declining investment in regional governance capacity over time was evident in the
changing nature of NRM activity. The first phase (2002-2008) was an intensive phase of
capacity building within NRM bodies and across NRM regions. This saw participation rates
and training and education grow and allowed regions to build strong ties between
stakeholders and communities.
• Capacity in the second phase (2008-2013) reflected the gains made in the first phase.
• Prolonged under-investment in regional governance, coupled with declining funding and
funding uncertainty, reduced the capacity of and destabilised NRMs within regions in the
third phase (2013-2015). This impacted on staff recruitment, the extent to which regions
have been able to engage stakeholders in NRM action, and the extent of NRM activity
occurring across Queensland.
Table 14 presents the summary of the evidence base and conclusions for Element 4.1.
78
Table 14. Summary of the evidence base and conclusions for Attribute Element 4.1 - Stable NRM presence in the region and regional skills retention and
development
NRM
Investment
Phase
Evidence Conclusions Assessment
(/5)
Phase 3
(2013-15)
• The capacity and stability of regional bodies was reliant on the stability and capabilities of the
expertise and resources available in the region.
• There was some evidence of operational difficulties associated with HR and employment (e.g.,
lack of expertise, staff shortages, and retention). These were common challenges across many
of the NRM bodies, with some suggesting that they were not competitive enough to employ
and/or keep high quality staff.
• In some instances, communities supported by NRM bodies were empowered to implement
their own monitoring and management practices and develop long-term skills and
independence.
• There was evidence of some NRM bodies investing in ways that were cost efficient in
responding to funding uncertainties, such as the presentation of data outputs.
• The relationship between event participants and the attendance numbers of NRM events
showed the highest levels of interest and attendance to be in the projects that were a high
priority or a major community concern.
• Communities who suffered from considerable financial and health difficulties, especially those
in remote rural locations (where climates are sometimes also harsher) were not always able to
participate in NRM workshops and capacity training events.
• Community members, landholders, or partners in NRM projects were not always able to be
supported by NRM partnerships due to tightening funds and investment uncertainties.
• NRM bodies remained heavily
dependent on the funds
provided by the Queensland
Government and in being
competitive to attract good
staff with quality expertise.
• NRM bodies were seen as
capacity hubs for
communities, but lacked
stability.
• NRM bodies were not able to
offer assistance to
communities who were most
in need of some help and
assistance during this period.
2
Value Proposition of Regional NRM in Queensland Final Report
79
NRM
Investment
Phase
Evidence Conclusions Assessment
(/5)
Phase 2
(2008-12)
• Individual landholder needs and goals were accommodated through projects, and in some cases
landholders reported greater confidence in managing their resources and preparedness for
change.
• Regional bodies were working with schools and industry groups to increase awareness of
environment issues. For example, the Fitzroy Basin Association was developing materials to
support the Australian curriculum environmental education in classrooms, as well as industry
groups. Northern Gulf partnered with Greening Australia to increase weed control of over 40
hectares of beach scrub, and SEQ Catchments successfully conducted 13 awareness raising
events about coastal hotspot issues, including concerns on migratory shorebirds, Ramsar
wetlands, Moreton Bay Marine Park, engaging over 504 participants.
• Projects were tailored to
individual landholder and
community needs,
demonstrating the flexibility
of processes to respond to
communities’ needs.
• Regional bodies focused on
future generations to share
knowledge about taking action
to care for and protect
environmental resources.
3
Phase 1
(2002-08)
• During this period, the focus of NRM REGIONAL BODIEs was on organisational
development, capacity building, and NRM regional planning (this was demonstrated in
REGIONAL BODIE annual performance reports, particularly up until 2006), to position the
NRM to protect and assess the condition of resources and threats, as well as develop
strategies and implement plans to protect cultural assets. There was clear evidence that the
NRM was considered a long-term solution to maintaining and protecting landscapes.
• There were almost 8,000 training events held for landholders or managers, community groups,
or members during the period between 2002-2008 Jan-Jun, with over 50% of the total training
events held between 2002-2008 Jan-Jun.
• Participation rates for training events steadily increased between 2002-2008. In total, almost
90,000 people participated in the training events.
• NRM bodies created strong
links with stakeholders,
communities, or anyone
interested in the natural
environment – which is key to
driving action and change.
4
80
Attribute 5: Strategic Partnerships
One element was considered for Attribute 5 - Strategic Partnerships. Element 5.1 referred to
strategic investment partnerships at local, state, and federal levels, and across diverse sectors
(agriculture, indigenous, conservation).
In terms of Element 5.1 - Strategic investment partnerships at local, state, and federal levels, and
across diverse sectors (agriculture, indigenous, conservation), the results show that:
• The regional delivery model clearly delivers diverse investment partnerships.
• These partnerships are so diverse that it would be useful to consider modelling how these
partnerships vary across regions and how this impacts on NRM outcomes.
• Partnerships contribute valuable knowledge into NRM project outcomes and expand the
available solutions.
• There was an increasing focus on state-wide (and national) priorities in phases 2 (2008-
2013) and 3 (2013-2015) and diminished opportunities for regions to set the NRM
sustainability agenda.
• Partnerships appear to have stagnated or are not growing, though this may be because they
are not being recorded, requiring further investigation. The health of partnerships does not
appear to have improved over time.
Table 15 presents the summary of the evidence base and conclusions for Element 5.1.
81
Table 15. Summary of the evidence base and conclusions for Attribute Element 5.1- Strategic investment partnerships at local, state, and federal levels, and
across diverse sectors (agriculture, indigenous, conservation)
NRM
Investment
Phase
Evidence Conclusions Assessment
(/5)
Phase 3
(2013-15)
• This dataset provided evidence regarding multiple partners who had invested in
and/or were involved in most NRM projects, including other regional
organisations, traditional owners, landholders, community and Landcare groups,
national level NGOs, and industry partners, such as Growcom.
• In some cases, partners (excluding the Queensland Government) helped to fund
50% of NRM actions and activities in projects (e.g., local partners, such as
landholders in priority areas helped to implement activities, including fencing, new
water monitoring /trial sites). Some regions reported that it was becoming more
and more difficult due to financial and climatic stresses at the community level.
• No new partnerships (collaborations) were formed (output summary sheet)
between 2014 and 2015, which might be indicative of poor confidence in NRM
project viability.
• The knowledge that is brought by each partner is considered important for NRM
project partnerships, such as for the targeting of future priority areas and advice
regarding the state of current assets. However, the capacity of local groups to
partner with NRM projects is decreasing, indicating that local knowledge and
guidance is more limited in NRM.
• Roles of the same type of partner can differ depending on the project type. For
example, the Queensland Government could have an investment role in a project
partnership and could also be a partner that provides the authorisation for the
implementation of the activities.
• There was no overview or model
available that displayed the
partnerships and the type of
partnerships formed by NRM
REGIONAL BODIEs.
• Climatic and financial pressures
most likely impacted local
investment partners.
• Projects were there to help support
State priorities; however, it was
unclear how they supported
community partner priorities and
needs (and the room for negotiation
between partners). There was a high
risk that local involvement in NRM
would further decline unless
priorities also addressed local
concerns.
• There was a lack of reporting of
Indigenous involvement in this
dataset.
• Some NRM regional bodies had
their own rules for developing
relationships.
3
Value Proposition of Regional NRM in Queensland Final Report
82
NRM
Investment
Phase
Evidence Conclusions Assessment
(/5)
• Indigenous groups (and native title holder groups when specified, though rarely
so) were beginning to become engaged in some regions, though it is not clear how
many more indigenous groups need to be engaged to represent the values, interests,
and aspirations of traditional owner groups.
• Community groups involved were from diverse commercial sectors; however,
there were some commercial sectors that were more commonly engaged in NRM,
such as those that are in agricultural industries.
• There was evidence of contract management and the development of formal
agreements (e.g., Memorandums of Understanding) with investment partners.
• In some cases, communication and relationships were better managed when a
group coordinator was employed at the local level to help manage and guide
community partners and volunteers to help reach project milestones and targets
and develop trust in institutional partnerships.
• Projects were usually aligned to meet milestones previously agreed to with the
Queensland Government, and how these partnerships aligned to state priorities was
usually clearly outlined. However, there was no clear outline of the priorities and
desires of other partners and what they might have wanted to achieve from these
projects.
• In some cases, mandatory partnership processes that the Queensland Government
expected from project partners influenced and added to the difficulties that NRM
regional bodies faced in establishing regional projects.
• The State Government could terminate partnership contracts. One formal
partnership agreement had previously been negotiated with Reef Catchment
Solutions for the coordination of Paddock to Reef activities in the Burnett Mary
• Effective processes for managing
partnerships could sometimes be
made more difficult when
mandatory rules were laid down by
the Queensland government.
• NRM regional bodies were not
always able to assist or be involved
in state-wide projects, despite the
importance of their involvement.
• The financial capacity of NRM
bodies was uncertain and could
impact the effectiveness of projects.
Value Proposition of Regional NRM in Queensland Final Report
83
NRM
Investment
Phase
Evidence Conclusions Assessment
(/5)
region. This agreement was terminated on 31 December 2014 at the request of
the Queensland Government. In phase three, the Regional Groups Collective
became responsible for providing regional coordination under a separate contract
with the QLD Government.
Phase 2
(2008-12)
• Partnerships helped to meet and expand solutions to consider and address regional
assets. For example, the Healthy Waterwatch Alliance, which included: Great
Barrier Reef Marine Park Area (GBRMPA), Australian Centre for Tropical
Freshwater Research at James Cook University (JCU), DERM, QLD DAFF, and
the Department of Infrastructure and Planning, Mackay, Whitsunday and Isaac
Regional Council’s, Canegrowers, Australian Rivers Institute at Griffith
University and River Improvement Trusts, expanded the potential solution for
water quality management;
• Partnerships were strategic in supporting cost savings for project implementation
(e.g., other alliances and steering committees).
• Partnerships with community groups were used to protect key assets, such as
wetlands or high value wetland areas, this could include sub-catchment planning
being applied, as well as land condition monitoring sites or workshops that
addressed wetland/biodiversity protection outcomes.
• Partnerships could expand the
solutions available to address and
protect key regional assets and
threats.
3.5
Phase 1
(2002-08)
• The full participation of all NRM bodies was required to ensure state-wide
implementation; however, NRM groups were not always able to commit to
schemes or to make funding available to landholders (e.g., the Nature Assist
Incentives Tender). Similarly, it was difficult for state agencies to meet federal
commitments for each region early in this investment period, demonstrating the
different levels of human and social resources between levels.
• NRM projects and operations
needed to take into account the
different resource levels and
capacities of investment partners at
all scales, including the federal,
state, regional, and local levels.
3.5
Value Proposition of Regional NRM in Queensland Final Report
84
NRM
Investment
Phase
Evidence Conclusions Assessment
(/5)
• A number of investment projects included state-wide community groups. For
example, maximising outcomes for reef rescue horticulture with coordination and
support from Queensland Fruit and Vegetable Growers (or Growcom).
85
Attribute 6: Strategic and Integrated Regional Planning
One element was considered for Attribute 6 - Strategic and Integrated Regional Planning. Element
6.1 referred to the degree to which plans were collectively endorsed and the connectivity within and
among key decision-making institutions and sectors.
In terms of Element 6.1 - Collectively endorsed plans and connectivity within and among key
decision-making institutions and sectors, the results show that:
• The first investment phase (2002-2008) focused on developing regional NRM plans as a
basis for achieving resource condition targets. Plans were linked to targets, NRM activities,
and community engagement.
• There was evidence that regional bodies had continued to be involved in landscape and
catchment scale planning in the second phase (2008-2013), even though they were not
funded to update or revise regional NRM plans. Some regions found ways to improve
mapping and introduce property management planning systems.
• Despite a new round of NRM planning in the third investment phase (2013-2015), plans
were not strongly connected to activities and other arrangements.
• Property management planning tools, which are important for achieving NRM actions and
improving the resilience of landscapes require further support.
Table 16 presents the summary of the evidence base and conclusions for Element 6.1.
86
Table 16. Summary of the evidence base and conclusions for Attribute Element 6.1 - Collectively endorsed plans and connectivity within and among key
decision making institutions and sectors
NRM
Investment
Phase
Evidence Conclusions Assessment
(/5)
Phase 3
(2013-15)
• NRM groups have primarily undertaken regional and sub-regional planning.
The documents provided showed little or no evidence of how activities
connected to NRM regional planning, indicating a lack of alignment with
NRM regional plan objectives and priorities (although some REGIONAL
BODIEs were reviewing their regional plans in this investment period).
• Most of the evidence provided about planning was in regards to sub-regional
planning. However, according to the state output summary there were no sub-
regional plans developed between the years 2014-2015.
• It was evident that property management plans (PMPs) were very valuable
tools for landholders looking at all aspects of their property management and
incorporating good natural resource management.
• Projects lacking good strategic planning at the site level were the most
impacted by seasonal changes, terrain difficulties, and an overall inability to
meet project milestones and outputs.
• Local landholders or private landholders were usually the main groups
targeted for subregional planning. Some NRM groups noted that there was
less interest in subregional planning for public land compared to privately
owned lands, or where the landowner had an invested interest in improving
land management practices.
• There was limited information about how activities met the objectives of the
local planning scheme strategies, and this seemed to be an increasing concern
for NRM regional bodies.
• The connection to NRM regional planning was
not well developed in this investment period.
• There was little evidence of ‘whole of region’
planning, with little information about
coordination at the landscape scale/catchment
level.
• Though NRM regional groups developed some
sub-regional planning, primarily with groups
of landholders within priority areas, these
plans were still reliant on the interest and
capabilities of these individuals.
• Sub-regional planning varied heavily due to
landholders not always having the capacity
and interest to partake in subregional planning.
This became worse when bad weather
occurred or farm incomes were very low.
• Connection and coordination with traditional
owner plans needed to be better considered to
meet the priorities and needs of traditional
owners in the regions. How this knowledge is
could be used to influence whole of region
planning was not yet clear.
2
Value Proposition of Regional NRM in Queensland Final Report
87
NRM
Investment
Phase
Evidence Conclusions Assessment
(/5)
Phase 2
(2008-12)
• NRM organisations employed catchment and landscape management
planning, which was used to encourage sustainable land management
practices in high value wetlands or establish clear environmental values and
water monitoring guidelines for improved water quality outcomes.
• A number of traditional owner plans were developed in partnership with
traditional owner groups; however, how these plans influenced and
strategically directed NRM activities and projects was unclear in the reviewed
data.
• Regions were active partners in the implementation of regional plans (e.g.,
regional pest management plans).
• Evidence suggested that some NRM REGIONAL BODIESs successfully
used mapping, awareness raising events, and PMPs to improve the knowledge
and skills of land managers in NRM.
• Planning to protect and rehabilitate assets involved the use of technology. For
example, Wetlands SEQ Catchments improved protection of high level
ecosystem service areas through spatial planning and decision-support tools
to identify priority services, and metrics to consistently measure land units.
Using regional AES mapping, Terrain NRM and its partners, invested in
habitat connectivity and restoration of priority wetland and riparian sites.
Cape York NRM worked with fire mapping technology to meet its protection
and rehabilitation objectives for threatened habitat and species, wetlands, and
agricultural activities.
• There was evidence of catchment/landscape
scale planning to improve landscape
outcomes.
• There was evidence of coordination with key
national and state plans to align key regional
assets and threats.
• A number of NRM planning tools helped to
build community skills and knowledge.
• Technological advances were used to improve
the efficiency of planning, and future
workplans for investments.
2.5
Value Proposition of Regional NRM in Queensland Final Report
88
NRM
Investment
Phase
Evidence Conclusions Assessment
(/5)
Phase 1
(2002-08)
• All NRM bodies had accredited regional plans in place by 2008.
• The rapid rise of regional planning in this period was due to the Queensland
Government’s decision to concentrate federal trust funds on the planning and
capacity building activities necessary to develop regional NRM plans. This
demonstrated the need to divert funds to these activities, specifically to
improve NRM planning and capacity building.
• A steady increase and momentum was found when considering the number of
sub-regional plans implemented between the reporting years 2002-2008 Jan-
Jul. The total number was 5,908 and the highest outcomes were during the
reporting periods 2007/8 (1,874) and 2006/7 (1,879).
• NRM planning worked in tandem with resource condition targets, which
became considerably more sophisticated over time as regional investment
strategies secured funding for NRM activities, capacity building initiatives,
and resource assessment specifically targeted at managing or protecting a
particular resource asset. This also demonstrated the important symbiotic
relationship between planning and NRM activities and community
engagement to address key regional assets and threats.
• The concentration of federal funds to support
Queensland NRM planning and capacity
building activities was a major reason behind
the rapid development of NRM planning and
capacity building for NRM regional planning
in Queensland.
3.5/4
89
Attribute 7: Community Awareness and Knowledge Brokerage
One element was considered for Attribute 7 - Community Awareness and Knowledge Brokerage.
Element 7.1 referred to knowledge brokerage and the level of community awareness of NRM.
In terms of Element 7.1, Community Awareness and Knowledge Brokerage, the results show that:
• Regional NRM bodies were very actively involved in community awareness raising events.
Regional delivery partners worked together to hold community awareness events.
• Raising community awareness of NRM and brokering knowledge was a key theme in the
first phase (2002-2008) during the establishment of NRM arrangements, and for regional
NRM planning and target setting.
• Regional bodies had developed quite diversified approaches to raising community
awareness by the third phase (2013-2015). Approaches had become more coordinated and
messages highlighted the successes of NRM.
• Knowledge management was a concern - the storage and collection of data (particularly
confidential data) was a primary concern, and knowledge and skills of grass roots project
delivery partners was a problem that requires training and investment. This is a problem for
scaling data up from NRM projects into regional level reporting.
Table 17 presents the summary of the evidence base and conclusions for Element 7.1.
90
Table 17. Summary of the evidence base and conclusions for Attribute Element 7.1 - Community Awareness and Knowledge Brokerage
NRM
Investment
Phase
Evidence Conclusions Assessment
(/5)
Phase 3
(2013-15)
Community awareness:
• NRM REGIONAL BODIESs and participant numbers from community awareness events
were used to benchmark community awareness. According to the State output summary, 166
awareness raising events were organised, with 5,653 participants in total. However, this nature
of benchmarking does not assist with the evaluation of community understanding and
knowledge about NRM matters in a comprehensive way;
• Specific examples provided by NRM performance reporting could help to indicate the level of
awareness that specific sectors or private individuals might have about NRM. Feedback from
community groups and landholders was always appreciative of the advice provided in these
events, regardless of whether or not they received funding assistance.
• Some of the NRMs found that community delivery partners (e.g., Landcare groups) preferred
to organise community awareness events over workshops or training events.
• Coordination between media releases and updating information on the website was important
to promote the positive work done by communities (and not only what NRM regions are
doing).
• Community awareness events were more successful when coordinated with seasonal changes
(e.g., when the event was of a higher concern for landholders during that particular season).
Knowledge brokerage:
• The storage and collection of data was a primary concern of NRMs and the available
technology was sometimes too advanced for communities to use or unsuitable for NRM (e.g.,
unable to work in far remote or rural locations). It seems that each NRM group was
developing or partnering with various technical groups to come up with their own solutions to
these problems.
• There was no available data
to benchmark levels of
community awareness about
NRM matters.
• Community awareness
events about NRM were
appreciated by communities,
regardless of whether or not
they received funding
assistance.
• Community awareness
events were more successful
when organised around
seasonal considerations.
• Community awareness
events should promote the
positive contributions
communities can offer to
NRM (e.g., not only being
about what NRM offers to
communities).
• Data collection and storage
of data were two major
concerns for NRM regional
3.5/4
Value Proposition of Regional NRM in Queensland Final Report
91
NRM
Investment
Phase
Evidence Conclusions Assessment
(/5)
• The collection and storage of confidential information was also another cause for concern and
some NRM regions were working on ways to store this information securely and ethically.
• Workshops offered skills and capacity training for participants, such as skills in monitoring
the health of assets, undertaking asset assessments, and managing and interpreting data that is
useful for business and long-term capacity building. However, these events were usually not
as well attended as community awareness events.
• Partnerships were formed to share data sets, particularly with local councils who had access to
a lot of data that NRM regional bodies could use to help align activities with local council
strategic targeting and planning;
body groups in this
investment period.
• Workshops were important
for improving the capacity of
communities to conduct and
implement NRM activities.
Phase 2
(2008-12)
• NRM groups worked closely with landholders to improve land management practices,
including on-farm engagement through field days, one-on-one visits, training, and awareness
raising events.
• Some NRM groups reported that the use of one-to-one extension officers (e.g., who assisted
landholders with soil tests analysis, advised on decisions about fertiliser application),
increased the effectiveness of their projects (sustainable agriculture projects).
• Some NRM RGs had a regional land care facilitator who assisted with training and
community awareness to improve sustainable land management practices.
• Youth involvement in NRM had increased through the establishment of junior Landcare in
schools and ‘Healthy Habitat Schools’, there seemed to be a strong focus on engaging youth in
NRM activities about biodiversity, land, and riparian management, etc.
• Community awareness was used to complement asset protection. For example, wetland
programs were protected through awareness raising programs to complement wetland
protection, which also involved traditional owners and landholder groups. The Northern Gulf
NRM also worked with indigenous groups to protect priority areas of the lower Gulf coastal
• Community awareness
events should be used to
complement resource
condition assessments and
surveys.
• Increased numbers of Junior
Landcare programs focused
on educating youth about
natural resource
management.
3.5/4
Value Proposition of Regional NRM in Queensland Final Report
92
NRM
Investment
Phase
Evidence Conclusions Assessment
(/5)
region and Staaten River Catchment. Southern Gulf, Burnett Mary, Condamine Alliance and
North Queensland Dry Tropics were protecting and restoring their wetland areas through
removal/modification of barriers to fish passage and migration.
Phase 1
(2002-08)
• Over 9,000 awareness raising events took place between the 2002-2008 reporting-period. The
highest year was 2007/8, with over 2,200 awareness events.
• Participation rates for awareness raising events increased rapidly during the year 2007/8 (over
110,000 people attended these events). There was an otherwise steady increase between 2002-
2007, with the next highest being the 2006/7 reporting period, which had approximately half
of the number of participants compared to 2007/8.
• A number of methods were used to spread awareness amongst the community (not only
events). For example, the production of 35 displays, 98 demonstrations, 51 field days, and 31
brochures in 2004/5.
• Community awareness and
knowledge brokerage was a
key theme during this period.
3.5/4
93
6. Conclusions and Recommendations
This assessment considered the value proposition of regional NRM in Queensland against four
questions:
1. What is the value-add of regional NRM arrangements?
2. How did the value-add change under the different governance models of the past programs?
3. How can existing value be maintained and built upon in a new program and through regional
arrangements?
4. How can these areas of value be monitored, evaluated, and reported on in a future program?
Question 1 – What is the value-add of regional NRM arrangements?
The dataset showed that regional NRM arrangements have positively contributed to outcomes
against all attributes of a healthy NRM system. However, this contribution was stronger in some areas
than others, was inconsistent, and declined in some areas over time.
The attributes with the highest value-add from regional NRM arrangements over time were
Attribute 2 - Performance and accountability and return on investment and Attribute 7 - Community
awareness and knowledge brokerage. These attributes consistently scored at 3 or above and sometimes
reached 4 (out of a maximum of 5) on the index scale.
First, in terms of Attribute 2 Performance and accountability and return on investment,
regional bodies were required to report on this attribute as a condition of funding in all investment
periods. The reporting showed that NRM arrangements delivered consistently strong outcomes, as
outlined below:
Element 2.1 - Organisational policies and procedures (for financial, HR management,
asset management, fraud control, project management and project delivery) provide
evidence that NRM investments were well governed – this was reasonably strong over time
and was particularly strong in the second phase (2008-2013). The dataset provided limited data
about organisational policies and procedures for financial, HR management, asset management,
fraud control, project management, and project delivery. However, improvements in reporting
and communications, experimentation with new data collection and reporting processes, and
information systems did occur over time.
Element 2.2 - Project, output, and outcome reporting accounts for investments at the sub-
regional level demonstrated accountability of decision making to stakeholders – was
reasonably strong over time and was particularly strong in the first (2002-2008) and second
(2008-2013) phases. Regional bodies reported regularly, and abided by state reporting
94
templates. However, reporting frameworks became more focussed on achievements in terms of
activities, targets, and milestones, and offered less information about the additional value
achieved through regional NRM partnerships.
Element 2.3 - Regional NRM communication demonstrates accountability to stakeholders
– was reasonably strong over time and was particularly strong in the third investment phase
(2013-2015). Social media and alternative ways of communicating emerged as an important
way for regional bodies to link messages from government, research, and consultants to local
communities through targeted communication and to disseminate information using positive
branding to engage the grassroots level.
Element 2.4 - Monitoring and continuous improvement programs are in place – was
reasonably strong over time and was particularly strong in the first investment phase (2002-
2008). NRM bodies obtained important knowledge from local communities and landholders to
prioritise work within regions, and other levels of government would find it difficult to collate
and use this knowledge in the way that NRM regions do. There were significant spatial and
temporal differences in the regional capacity to collect monitoring data (e.g., GBR regions).
Large gains were made in GBR regions in terms of baseline monitoring, while others lagged
behind.
Second, in terms of Attribute 7 - Community awareness and knowledge brokerage, regional
NRM arrangements delivered consistently strong outcomes in building community awareness about
NRM and the adaptive use of integrated knowledge sets. All three investment phases from 2002-2015
demonstrated strong performance.
Attribute 5 - Strategic partnerships was another area in which regional NRM arrangements
delivered reasonably consistent outcomes from 2002-2015. The database clearly showed that regional
NRM arrangements built diverse partnerships at all levels and across sectors and that this contributed
valuable knowledge to NRM projects and expanded the available solutions. Partnerships appeared to
have stagnated in the third phase, though this requires further investigation, as it may be related to the
targeted focus of the reporting in this phase. It could, however, also be related to a reduction in funding
driving a lack of resources available to undertake integration when it is needed most. These partnerships
across regions were so diverse that it would be useful to understand how governance models vary across
regions and how this impacts on NRM outcomes.
Attribute 3 - Community participation and engagement was the final area in which regional
NRM arrangements delivered reasonably consistent outcomes from 2002-2015. This attribute scored 3
in the first (2003-2008) and second (2008-2013) phases, though this dropped to 2.5 in the third phase
(2013-2015). The analysis found that NRM arrangements added value by engaging diverse stakeholder
groups at the local and community levels. NRM arrangements engaged industry groups, traditional
95
owner groups and the Queensland and Australian governments, and others in diverse ways. The dataset
highlighted that the drop in performance against this outcome was due to a the decreasing motivation of
landholders to conduct NRM action and the reduced ability of NRM groups to build the capacity of
community groups that were lacking in the available skills, knowledge, and capacity for NRM action.
The extent of community participation, collaboration, and engagement in this last phase could be
concealed by the narrow way that data was reported, while networks, partnerships, and projects may not
have been reported against milestones and outputs. The dataset was not detailed enough to assess the
individual membership base of NRM bodies, requiring further assessment to understand the
relationships between NRM bodies and industry groups and organisations at local, state, national, and
international levels.
The area with the lowest overall level of outcome performance was Attribute 6 - Strategic and
integrated regional planning. This attribute had one of the highest value-adds in the first investment
phase (2002-2008), with a score of 3.5-4 out of 5. This reflected the focus of NHT II on developing
strategic and integrated regional NRM plans as a basis for achieving resource condition targets. Delivery
against this attribute had room to improve; however, the value-add dropped to 2.5 in the second phase
(2008-2013) and dropped further to 2 in the third phase (2013-2015). This represents an interesting
finding. Regional bodies were not funded to update or revise regional NRM plans in this phase; however,
there was evidence that regional bodies had continued to be involved in landscape and catchment scale
planning, building on the legacy of regional planning foundations established in NHT II. Regional
bodies received federal funding to update regional NRM plans in the third phase (2013-2015); however,
the dataset evaluated for this project did not reflect those plans. This reflects the narrowed scope of
regional reporting in this last phase, which did not seek to capture data related to regional plans.
Consequently, this attribute was the lowest area of value-add from regional NRM arrangements based
on the analysis of this dataset, and it would be useful to investigate the connections between the latest
regional NRM plans and other NRM arrangements in greater detail.
There were two other instances where outcomes measured below 3 (out of a maximum of 5):
Attribute 1 - Action for sustainability and Attribute 4 - Resilient institutions and capacity building.
In both cases, outcomes measured below 3 only in the third phase (2013-2015).
In terms of Attribute 1 - Action for sustainability there was variation in the level of value-add by
regional arrangements against this attribute at the level of the individual elements and across
Queensland, as follows:
Element 1.1 - Projects address regional NRM assets and key threats – this element scored
2.5 in the third phase (2013-2015), compared with 3.5 in the second phase (2008-2013), and
3.5-4 in the first phase (2003-2008). Two problems were identified: the scope of NRM
investment into projects narrowed considerably, and funding uncertainty became an issue for
96
NRM action in less stable and affluent regions. This was a noted problem in regions away from
the more populated East Coast and outside the GBR. This was not favourable towards NRM
action and NRM projects in those regions struggled to achieve milestone targets set to address
key assets or threats.
Element 1.2 - natural resource action is regionally coordinated – this element was
reasonably consistent between 2003-2015, scoring 3 in the first phase (2002-2008), 3.5-4 in the
second phase (2008-20013), and 3 in the third phase (2013-2015). The evidence suggested a
decline in the overall number of community groups and projects assisted and the growing
dominance of some regions in state wide-projects.
Element 1.3 - Investments have achieved on ground results - this element dropped from 3.5
in the first (2002-2008) and second (2008-2013) phases to 2 in the third phase, reflecting a
substantial decline in the volume of reported outputs.
In terms of Attribute 4 - Resilient institutions and capacity building, this attribute dropped from
4 in the first phase (2002-2008) to 3 in the second phase (2008-2013), to 2 in the third phase (2013-
2015). The first phase (2003-2008) was an intensive period of capacity building within NRM bodies
and across NRM regions. The second phase (2008-2013) benefited from the capacity building legacy of
the first phase. The third phase (2013-2015) highlighted that prolonged under-investment in regional
governance, coupled with declining funding and funding uncertainty, reduced the capacity of NRMs
and destabilised their role within regions. This impacted on staff recruitment, the extent to which regions
were able to engage stakeholders in NRM action, and the extent of NRM activity occurring across
Queensland.
Question 2 – How has the value-add changed under the different governance models of NRM
programs?
The assessment identified that the outcomes observed in the dataset as being delivered by regional
arrangements changed over time. Figure 3 summarises the NRM outcomes measured between 2002-
2015 against each of the seven attributes.
97
Figure 3. A comparison of the NRM outcomes measured between 2002-2015 against attributes3
The reported outcomes of regional NRM arrangements between 2003 and 2015 highlight a change
in focus in government priorities over the three main NRM investment periods. The narrowed scope of
government interest in regional NRM partnerships in the third phase (2003-2015) was a particular
problem for integrated and strategic regional NRM planning and for regional resilience and capacity
building.
Planning was a core focus of NHT II. It sought to align programs across the Queensland and
Australian governments and guide the achievement of resource condition targets through NRM
achievements and community engagement. Despite a new round of funding from the Australian
Government to develop climate ready regional NRM plans from 2013-2016, the complex plethora of
state and federal based policy and governance plans were not strongly connected to activities and other
arrangements. These climate ready plans did not enhance strategic integration and alignment in planning
and policy action across the Queensland and Australian governments and community interests.
Regional resilience was demonstrated through a stable regional presence and strong governance
capacity. Capacity was built intensively during the initial establishment phase of NRM in Queensland,
reflected in high rates of regional body participation in training and education. This established capacity
was carried through as a positive NRM legacy in the second phase. However, a prolonged under-
3 Attribute 1 - Action for Sustainability Outcomes; Attribute 2 - Performance and Accountability and Monitoring
Return on Investment; Attribute 3 - Community Participation and Engagement; Attribute 4 - Resilient Institutions
with Capacity Building Capacity; Attribute 5 - Strategic Partnerships; Attribute 6 - Strategic and Integrated
Regional Planning; and Attribute 7 - Community Awareness and Knowledge Brokerage.
0
5
10
15
20
25
1 2 3 4 5 6 7
Outcomes summary
Attribute Maximum Phase 3 (2013-2015) Phase 2 (2008-2013) Phase 1 (2003-2008)
98
investment in regional governance became acutely evident in the third phase (2013-2015). This,
combined with funding uncertainty, destabilised NRMs and impacted on staff recruitment, stakeholder
engagement, and the ability to carry out NRM activity in Queensland.
This had an impact on efforts to achieve sustainability outcomes and presented as a substantial
decline in the volume of reported outputs. The narrowed scope of interest in NRM, coupled with poor
socio-economic conditions in many regions resulted in an overall decline in the state-wide capacity to
take sustainability action. Figure 4 depicts the changed value-add under the different governance models
of changed programs.
Attributes of moderately healthy NRM regional bodies were detected in the areas of accountability
(e.g., communication to stakeholders, monitoring, and evaluation), diverse investment partnerships, and
community awareness and knowledge brokering. It is clear that regions were innovating to address the
tightened funding and changing scope of Queensland government interest. In particular, an increased
focus on awareness raising was evident over time. This had local benefits, but was also a response to
narrowing support and concerns about uncertainty.
Figure 4. The value-add of Queensland’s regional arrangements scored against a 1-5 index scale where
1 = least desired and 5 = most desired.
99
Question 3 – How can existing value be maintained and built upon in a new program and
regional arrangements?
The assessment of the value-add of regional NRM arrangements between 2003 and 2015 showed
that regional NRM bodies in Queensland worked hard to maintain NRM outcomes in the face of
changing government roles in NRM partnerships and changed funding priorities. Figure 4 highlighted
that regional NRM bodies worked around these changing priorities to provide relatively stable outcomes
in terms of: Attribute 2 - Performance and Accountability and Monitoring Return on Investment,
Attribute 3 - Community Participation and Engagement, Attribute 5 - Strategic Partnerships, and
Attribute 7 - Community Awareness and Knowledge Brokerage. This provides a strong foundation
for regional NRM action in Queensland.
However, to reverse the downward trend observed against Attribute 1 - Action for Sustainability
Outcomes, urgent attention is required to strengthen the frameworks for regional NRM bodies to
undertake strategic and integrated regional planning, and to support regional bodies to grow their
capacity for regional NRM. For this reason, it is recommended that NRM Regions Queensland and the
Queensland Water and Land Carers seek the following to enhance regional arrangements in a new NRM
program and phase of NRM:
Recommendation 1: Strengthen the integrative role of regional NRM plans in promoting
strategic target setting across government and non-government organisations, alignment of
government and non-government activity to improve implementation, and as the basis for
collaborative monitoring and review in the next phase of regional NRM.
Recommendation 2: Grow the human and governance capacity of NRM bodies to provide
leadership and support for achieving regional resilience (in the face of changing institutional
and regional conditions), to improve the longevity of investments in sustainability action for the
Queensland and Australian governments and regional communities.
The assessment also highlighted that, although Queensland’s regional NRM bodies have
maintained outcomes in the face of changing government roles in NRM, changing state and federal
partnerships and changing funding priorities, incremental changes to government NRM programs have
had a cumulative impact on the regional NRM model and the governance context since 2002. The
Queensland regional NRM model was built on the principles of collaboration, subsidiarity, and adaptive
management and was introduced under a bilateral agreement between the Queensland and Australian
governments. The dataset showed a changed focus on competition, MERI frameworks, and metricised
reporting to meet accountability concerns. The loss of the bilateral partnership between the Queensland
and Australian governments was evident in the reports from 2010 onwards. Information comparing the
regional models and approaches underpinning partnerships and NRM delivery across the 14 regions was
not clear from this dataset. How the NRM models differ across Queensland, have evolved over time
within regions, and have impacted on NRM outcomes as a result of program and other changes remains
100
a critical gap in the knowledge base about NRM. How the Queensland models and their NRM outcomes
compare to other states in Australia and NRM systems internationally is a related critical knowledge
gap. This knowledge would help NRM Regions the Queensland and Australian Governments to
understand how Queensland’s NRM models can be enhanced to better achieve sustainability outcomes
in future NRM programs, as outlined in the recommendation below. It is strongly recommended that the
Queenlsland Government:
Recommendation 3: NRM partners (e.g., regions, the Queensland and Australian Governments,
non-government organisations and the research consultancy community) should evaluate the different
regional models and approaches underpinning partnerships and NRM delivery across Queensland’s 14
regions and assess the effects of nuances in governance models on NRM outcomes. How the Queensland
models and their NRM outcomes compare to other states in Australia and NRM systems should also be
evaluated.
Question 4 – How can these areas of value be monitored, evaluated, and reported on in a future
program?
Monitoring, evaluating, and reporting the outcomes from regional NRM arrangements represents
an ongoing challenge for program design and review in Queensland. Regions and the State have adopted
MERI frameworks since 2008; however, it should be noted that these frameworks have not included
monitoring and evaluation programs.
This analysis developed a framework to evaluate the outcomes and value proposition of regional NRM.
An assessment matrix and analytical approach was also developed to apply the framework to the dataset
to estimate the impact of regional NRM. First, measurement of each attribute included a series of
elements. Second, a sampling frame was developed and the relevant samples from the dataset were
coded into themes against each element. A series of key words from the literature review and workshop
discussions were used to describe each attribute, element, and direct the coding of the data in the reports.
Third, evidence pointing to the presence (or absence) of each element was summarised, synthesised into
conclusions, and rated according to an index scale. An analysis of each region was performed and a
summary of the whole of Queensland consolidated review was based on a synthesis of the results across
the regions. Finally, an expert panel was convened to review and critique the findings and support the
development of the conclusions and recommendations.
This assessment is the first comprehensive synthesis of reported outputs and outcomes since the
introduction of regional NRM arrangements in Queensland and some reporting trends were identified.
First, the assessment highlights that monitoring and reporting became increasingly disjointed and more
narrowly focussed on metrics over time. This was a challenge for developing the assessment of
101
outcomes, because it is not clear whether elements of the value proposition of regional arrangements
were present and under reported (or potentially not reported) in this dataset, or not present at all.
Second, the review highlights that the scope and contents of regional reporting were widely
inconsistent across the 14 NRM regions, and over time. Key areas of inconsistency included:
(i) The frameworks underpinning reporting and data collection from regional bodies (including the
metrics used), which varied over time.
(ii) The narrative and case study material provided by regions, which varied considerably over time
and across regions within single years in terms of the depth of detail and supporting evidence
about reported achievements.
(iii) The different terminology applied by regional bodies in reporting, making comparison difficult.
Queensland’s NRM reporting frameworks provide limited opportunities for regions to identify the
problems and pressures confronting NRM action or how they are innovating to address these challenges.
There is scant publicly available information about governance models, the scope of collaborative
partnerships, and regional delivery accountabilities within or across regions. Moreover, information
related to regional capacities, integration and planning, and regional governance aspects of regional
delivery, which is important for understanding the role and contribution of regional NRM arrangements
in delivering outcomes, is not routinely collected. This appeared to be most problematic in the third
investment phase, which was the most tightly focussed on project output delivery. Regularised reporting
of these elements could assist with better understanding of how different regional partnership and
delivery models work with government and non-government stakeholders to protect natural assets and
improve local communities and for grassroots engagement. If scaled up across NRM regions, this data
would build an evidence base that could help to identify the reforms required in program design and
partnerships for NRM. It could also assist with prioritising regional body advocacy for effective and
productive reform.
The following is recommended to regions Queensland, the Queensland and Australian
Governments to improve the alignment and scaling-up of monitoring, evaluation, and reporting of areas
of value across Queensland:
Recommendation 4: Provide for a higher level of consistency in reporting frameworks over
time, and broaden the scope of relevant data collection, and the scope of the participating
organisations (government and non-government) involved in monitoring and evaluation.
Improve reporting on: i) efforts to build regional capacity and resilience, ii) strategic and
integrated regional planning, iii) regional partnership models, and iv) sustainability action
across government and non-government organisations.
102
This assessment is the first known synthesis of NRM reporting over the 2002-2015 period. Some
consistency was found in qualitative reports within the NHT II reporting period and between NHTII and
CFoC/Q2C&C; however, a lack of overall consistency in reporting frameworks was evident across
regions and over time.
First, the assessment identified inconsistencies in reporting frameworks associated with changed
government perspectives about the role of NRM programs in each major phase. Monitoring, evaluation,
review, and improvement (MERI) processes and frameworks were introduced in the second phase of
NRM. Despite this, MERI reporting varied from region-to-region. Regional bodies used different MERI
frameworks, MERI reports emphasised different aspects, and some were more comprehensive than
others. Some regions provided more detailed case study information or information about challenges,
additional outputs, or additional outcomes achieved. The lack of reporting consistency is likely to
conceal difficulties that regional bodies face, which are inadequately highlighted in existing reporting
frameworks. Scaling data up to the state-wide level and to identify outcome trends over time will require
some effort to identify appropriate frameworks and datasets.
Second, the assessment identified reporting gaps against key outcomes of NRM against the attribute
framework. The literature review demonstrated that there is a very clear and highly consistent theoretical
framework for regional NRM. The dataset provided detailed information against some attributes and
was inconsistent against some important attributes. For Attribute 1 - Action for sustainability
outcomes, data easily provided attribute elements; however, data was limited for Element 1.3 -
Investments achieve on ground results, largely because of the way the activities were reported. Data
was also inconsistent for the following attributes: Attribute 2 - Performance and accountability and
return on investment, Attribute - 5 Strategic Partnerships, Attribute 6 - Strategic and Integrated
Regional Planning, and Attribute 7 - Community awareness and knowledge brokerage, where it
provided evidence for only some of the attribute elements.
Third, the assessment identified that the scope of deliberative frameworks underpinning NRM
reporting also narrowed, particularly during the third investment phase in Queensland. In the first and
second phases, data from regional bodies was shared and discussed across state and federal boundaries
through joint steering committee processes, such as JSIP. This provided a deliberative space to discuss
problems and opportunities to align action and resources across the Queensland and Australian
Governments. The third phase included reporting to the Queensland Department of Natural Resources
and Mines.
There was a lack of integrated reporting of NRM action and progress by agencies involved in NRM
activity across the Queensland Government, agricultural bodies, and environmental non-government
organisations in regions in all phases. There was some experience of joint reporting from regional bodies
to the Queensland and Australian Governments in the NHT II reporting period, which should be
103
reinstated. Regional NRM bodies are only one element of the regional NRM delivery system. As a range
of other government and non-government organisations play important roles in regional NRM action
and regional delivery, there is a key need to capture and evaluate the impact of this effort on
sustainability outcomes. This analysis identified little information about the role of government (state
and federal) and non-government organisations in facilitating or enhancing NRM outcomes. As a result,
how these other organisations contribute to (or detract from) regional outcomes or the value proposition
of regional arrangements for NRM despite the resources they invest is not clear.
Recommendation 5: NRM regions and reporting partners (e.g., the Queensland and Australian
Governments, industry groups, traditional owner groups, conservation groups) should work
together to develop a consistent language for narrative reporting and decision rules to guide
qualitative assessments of outcomes achieved by programs. This will enable data about
investments and outcomes to be better shared across Queensland, and scaled up for adaptive
management.
This appraisal of regional reporting found that the language and yardsticks used by regional bodies
to measure performance was highly inconsistent across regions and over time. Regional bodies evaluated
‘success’ (e.g., the achievement of milestones) in highly varied ways. For example, in some contexts,
some groups considered 30% achievement toward a target to be significant, but this was not the case in
other contexts. The interim outcome measures used by groups to report on progress differed widely from
region to region. The term ‘project’ was heavily used in different ways and not defined. This is of
particular relevance, as regional narratives report on complex combinations of parent and child
‘projects’, and line of sight relationships between ‘projects’, partnerships, and outcomes is unclear. This
inconsistent use of terminology was a problem for some elements of the value assessment and is a
problem for scaling up data in general. Decision rules and appraisal processes should be developed to
improve the consistency of regional reporting.
Recommendation 6: NRM regions, the Queensland and Australian Governments and other
non-government organisations (e.g., industry groups, traditional owner groups, conservation
groups) should work together to develop an integrated long-term program for evaluating
Queensland’s regional NRM system. This should be based on clear evaluation questions about
links between activities and outcomes and use data harvesting, targeted new data collections
and regional synthesis to evaluate efforts across the NRM governance system toward addressing
sustainability outcomes. It needs to be broader than the regional NRM organisations, include
other government and non-government NRM activity, be more than monitoring, continue
beyond the life of individual projects, and be linked to adaptive management.
This assessment highlights the need for an integrated monitoring and evaluation program that scales
up available data, gathers data from other regional NRM partnerships, and collects new data to fill
104
important gaps. These key gaps are in the areas of integrated regional planning, regional resilience,
regional partnership accountabilities, and sustainability action.
The evaluation also highlighted the limitations of the reporting dataset, which only included
reporting on NRM activities through contracts between regional NRM organisations and the Department
of Natural Resources and Mines. The operational environment for regional NRM in Queensland includes
(but is not limited to) agricultural industry groups, traditional owner groups, conservation groups, state
agencies, and local governments. These organisations participate in NRM programs and sustainability
action at a regional scale through a plethora of regional planning and partnership processes to manage
assets and sustainability problems including (but not limited to) water, pests, biodiversity and
vegetation, and climate adaptation. Current reporting processes do not capture the efforts across
the NRM system toward addressing sustainability outcomes. There is a need to understand the
impact of action across the governance system on NRM outcomes. How do the efforts of organisations
across the entire NRM governance system impact on sustainability outcomes across Queensland? How
do these different efforts impact on the efficacy, appropriateness, and efficiency of the delivery of NRM
programs?
It may be possible to harvest benefits from MERI programs that are already in place. Examples
include the state and federal NRM Investment Programs, Reef Rescue, Reef Plan Best Management
Program, Reef Alliance, and the Major Integrated Projects. Many of these programs already have data
collection processes. However, these processes do not currently scale lessons up into a state-wide
monitoring and evaluation approaches for regional NRM.
Consideration should be given to how to map, monitor, and evaluate the benefits and impacts of
emerging NRM partnership models, such as Reef Alliance and cross-regional partnerships about
regional sustainability outcomes, and to consider what opportunities or lessons this offers in other
Queensland contexts. Technologies and processes for improving the efficiency of already collected data
and linkages to larger issues should also be considered, such as the Reef 2050 Integrated Monitoring
and Reporting Program.
If addressed, these recommendations would improve NRM capacities and outcomes, or at least
clarify what these outcomes are. Some of these actions are within the ability of regional bodies to
address, or could be with appropriate resources, while some may be more in the domain of State agencies
or others.
105
7. References
Auditor General. (1997). Commonwealth Natural Resource Management and Environment Programs:
Audit Report No. 36 1996-97. Canberra. The Australian National Audit Office.
Auditor General. (1998). Commonwealth Management of the Great Barrier Reef: Great Barrier Reef
Marine Park Authority, ANAO, Canberra.
Auditor General. (2001). Performance Information for Commonwealth Financial Assistance under the
Natural Heritage Trust: Audit Report No.42 2000-2001. Canberra: Australian National Audit
Office.
Auditor General. (2004). The Administration of the National Action Plan for Salinity and Water Quality. Audit Report No, 17 2004-05, The Australian National Audit Office, Canberra,
Australia.
Australian Government. (2003). Review of the National Landcare Program. Department of
Agriculture Fisheries and Forestry, Canberra.
Australian Government (2017). National Landcare Program Phase One. Accessed online 3 November
2017. Retrieved from http://www.nrm.gov.au/national-landcare-programme/phase-one
Bellamy, J. A., (ed.) (1999). Evaluation of Integrated Catchment Management In a Wet Tropical
Environment: Collected Papers of LWRRDC R&D Project CTC7, 7 vols., CSIRO Tropical
Agriculture, Brisbane.
Bellamy, J. A., McDonald, G. T., Syme, G. J., & Butterworth, J. E. (1999). Policy Review Evaluating
Integrated Resource Management, Society and Natural Resources, 12(4), 337-53. doi:
10.1080/089419299279632
Bellamy, J. A., Walker, D. H., McDonald, G. T. and Syme, G. J. (2001). A systems approach to the
evaluation of natural resource management initiatives. Journal of Environmental Management,
63, 407-23. doi: 10.1006/jema.2001.0493
Benham, C. F., Beavis, S. G., & Hussey, K. E. (2015). The cost of collaboration: How Caring for Our
Country has shaped regional Natural Resource Management in an Australian river catchment.
Australasian Journal of Environmental Management, 22(3), 285-297. doi:
10.1080/14486563.2014.976847
Campbell, A. (2007). Improving regional arrangements for Natural Resource Management in
Queensland. Regional Groups Collective Toowoomba.
Caring for our Country Review Team (2012). Report on the Review of the Caring for our Country
Initiative. Canberra, Australia. Retrieved from
http://nrmonline.nrm.gov.au/downloads/mql:2697/PDF:Australian Government Land and Coasts.
Commonwealth of Australia (2008). Caring for our country outcomes 2008–2013, Department of
Environment, Water, Heritage and the Arts, and the Department of Agriculture, Fisheries and
Forestry, Canberra.
Curtis, A., & De Lacy, T. (1996). Landcare in Australia: does it make a difference? Journal of
Environmental Management, 46, 119-137. doi: 10.1006/jema.1996.0011
Curtis, A., Ross, H., Marshall, G. R., Baldwin, C., Cavaye, J., Freeman, C., Carr, A. and Syme, G. J.
(2014). The great experiment with devolved NRM governance: lessons from community
engagement in Australia and New Zealand since the 1980s. Australasian Journal of
Environmental Management, 21(2), 175-199. doi: 10.1080/14486563.2014.935747
106
Dale, A., & Bellamy, J. (1998). Regional Resource Use Planning in Rangelands: an Australian
Review (Occasional Paper No 06-98), Land and Water Resources Research and Development
Corporation, Canberra.
Dawson, S. (2005). Carbon management and energy use, in G McDonald, B Taylor & C Robinson
(eds), Findings from a review of regional NRM plans, CSIRO and Tropical Savannas
Management CRC, Brisbane, pp. 88-94.
Department of Agriculture, Fisheries and Forestry (DAFF) and Department of Sustainability,
Environment, Water, Population and Communities (DSEWPaC), (2011). Caring for Our
Country. Retrieved from http://nrmonline.nrm.gov.au/catalog/
Department of the Environment and Heritage (DEH). (2004). Natural Heritage Trust: annual report 2002-2003, Department of the Environment and Heritage, Canberra, ACT. Retrieved from
http://nrmonline.nrm.gov.au/catalog/mql:1862
Department of Environment and Resource Management. (2011). Regional NRM Policy. Queensland
Regional Natural Resource Management Framework, November 2011. The State of Queensland
(Department of Environment and Resource Management, Brisbane.
Department of Natural Resources and Mines (DNRM). 2017. Queensland Regional Natural Resource
Management Investment Program: Progress Report 2016. State of Queensland. Retrieved from
https://www.dnrm.qld.gov.au/__data/assets/pdf_file/0016/1240306/dnrm-investment-report-
2016.pdf
Dovers, S. (2013). The Australian Environmental Policy Agenda. Australian Journal of Public
Administration, 72(2), 114-128. doi: 10.1111/1467-8500.12013
Environmental Protection Agency (2008). State of the Environment Queensland 2007. The State of
Queensland. Retrieved from www.ehp.qld.gov.au/state-of-the-environment/pdf/soe-report-
2007.pdf
Fenton, D. M. (2004). Socio-economic indicators for NRM (Project A1.1) Indicators of capacity,
performance and change in regional bodies. National Land and Water Resources Audit,
Canberra.
Fenton, D. M. (2006). Socio-economic Indicators and Protocols for the National NRM Monitoring
and Evaluation Framework: The Social and Institutional Foundations of NRM. National Land
and Water Resources Audit, Canberra.
Fenton, D. M., & Rickert, A. (2006a). Monitoring and evaluating the performance of NAPSWQ
regional bodies in Queensland (State Summary Report). Burdekin Dry Tropics NRM and the
National Land and Water Resources Audit, Canberra.
Fenton, D. M., & Rickert, A. (2006b). Refining indicators for monitoring and evaluating the social and institutional foundations of regional NRM programs. Department of Environment and
Heritage and The Department of Agriculture, Fisheries and Forestry, Canberra.
Fenton, D. M., & Rickert, A. (2008a). Monitoring and evaluating the social and institutional foundations of natural resource management (RECAP): A National Paper. National Land and
Water Resources Audit, Canberra.
Fenton, D. M., & Rickert, A. (2008b). A national baseline of the social and institutional foundations
of natural resource management programs. National Land and Water Resources Audit, Canberra.
Hassall and Associates (2005). Natural Heritage Trust Phase 1 Final Evaluation. Canberra: Australian
Government Department of Agriculture, Fisheries and Forestry and Department of the
Environment and Heritage.
107
Keogh, K., Chant, D., & Frazer, B. (2006). Review of Arrangements for Regional Delivery of Natural
Resource Management Programmes: Report prepared by the Ministerial Reference Group for
Future NRM Programme Delivery Final Report. Canberra: Australian Government.
Lane, M., Robinson, C., & Taylor, B. (Eds.) (2009). Contested Country. Collingwood: CSIRO
Publishing
Lockwood, M., & Davidson, J. (2010). Environmental governance and the hybrid regime of Australian
natural resource management. Geoforum, 41 (3), 388-398. doi: 10.1016/j.geoforum.2009.12.001.
Love, C. (2012). Evolution of Landcare in Australia: in the context of Australian Government natural
resource management policy and programs, Department of Agriculture, Fisheries and Forestry,
Canberra, ACT. Retrieved from http://nrmonline.nrm.gov.au/catalog/mql:2993
McDonald, G. T., McAlpine, C. A., Taylor, B. M., & Vagg, A. R. (2003). Evaluating regional plans
in Australian tropical savannas: A guide for planners and reviewers. Tropical Savannas CRC,
Darwin.
McDonald, G. T., McAlpine, C. A., Taylor, B. M. & Vagg, A. (2004). Criteria and Methods for
Evaluating Regional Natural Resource Management Plans in Tropical Savanna Regions, Stage 1
Report for Project 3.2.1, Bioregional Planning in the Tropical Savannas, CSIRO, Brisbane.
McDonald, G. T., Taylor, B., Bellamy, J. A., Robinson, C., Walker, M., Smith, T., Hoverman, S.,
McAlpine, C., Peterson, A., & Dawson, S. (2005). Benchmarking Regional Planning
Arrangements for Natural Resource Management 2004–05: Progress, constraints and future
directions for regions, Healthy Savanna Planning Systems Project. Tropical Savanna
Management CRC, Brisbane.
National Heritage Trust (NHT) (2004). Bilateral Agreement between the Commonwealth of Australia
and the State of Queensland to Deliver the Natural Heritage Trust in Queensland, National
Heritage Trust, Canberra.
Queensland Government (2017). Natural Resource Management Investment Program. Retrieved from
https://www.qld.gov.au/environment/agriculture/sustainable-farming/nrm-investment-program#
Queensland Murray-Darling Committee (QMDC) (2011). Queensland Murray-Darling Committee
Performance Report, Toowoomba, Queensland. Retrieved from
http://www.qmdc.org.au/resources/publications/browse/79/qmdc-reports-2011-12
Queensland NRM Bodies. (2015). Thursday Island Meeting Minutes. Regional Groups Collective,
Toowoomba.
Regional Groups Collective. (2015). NRM Discussions/Minutes. Regional Groups Collective
Toowoomba.
Robins, L., & Dovers, S. (2007). NRM Regions in Australia: the ‘Haves’ and the ‘Have Nots’.
Geographical Research, 45 (3), 273-290. doi: 10.1111/j.1745-5871.2007.00460.x.
Robins, L., & Kanowski, P. (2011). ‘Crying for our Country’: eight ways in which ‘Caring for our
Country’ has undermined Australia's regional model for natural resource management.
Australasian Journal of Environmental Management, 18(2), 88-108. doi:
10.1080/14486563.2011.566158
Senate Standing Committee on Rural and Regional Affairs and Transport (2010). Rural and Regional
Affairs and Transport References Committee: Natural Resource Management and Conservation
Challenges. Canberra: Commonwealth of Australia.
108
SEQ Catchments (2012). SEQ Catchments Narrative Report for JSIP Contracts: Caring for our
Country; Queensland State NRM Programs; Queensland Natural Disaster Recovery; EnQuire,
Dec/Jan – Jun 2012. Brisbane.
Taylor, B., McDonald, G., Heyenga, S., Hovermann, S., Smith, T., & Robinson, C. (2006). Evaluation
of Regional Planning Arrangements for Natural Resource Management 2005-06: Benchmark Report II, Milestone Report 4 Healthy Savanna Planning Systems Project, Tropical Savannas
Management. CSIRO, Brisbane.
Turnbull. W. (2005). Evaluation of Current Governance Arrangements to Support Regional
Investment under the NHT and NAP. P. Canberra: Departments of Environment Water Heritage
and the Arts and Agriculture Forestry Fisheries.
Vella, K., Sipe, N., Dale, A., & Taylor, B. (2015). Not learning from the past: adaptive governance
challenges for Australian natural resource management. Geographical Research, 53 (4), 379-392.
doi: 10.1111/1745-5871.12115
Wallington, T. J., & Lawrence, G. (2008). Making democracy matter: Responsibility and effective
environmental governance in regional Australia. Journal of Rural Studies, 24 (3), 277-290. doi:
10.1016/j.jrurstud.2007.11.003.
Zammit C., & Vogel N. (2013). Review of regional NRM arrangements in Queensland. Regional
Groups Collective, Toowoomba
109
8. Appendices
Appendix 1: Summary of all data acquired
NHT II & NAPSWQ
Caring for Country and Q2 Coasts and
Country
NLP & Investment
Program
Report
2002-
2003
2003-
2004
2004-
2005
2005-
2006
2006-
2007
2007-
2008
2008-
2009
2009-
2010
2010-
2011
2011-
2012
2012-
2013
2013-
2014
2014-
2015
2015-
2016
J
D5
JJ6
J
D JJ
J
D JJ
J
D JJ
J
D JJ
J
D JJ
J
D JJ
J
D JJ
J
D JJ
J
D JJ
J
D JJ
J
D JJ
J
D JJ
J
D JJ
Outputs y y y y y y y
6-monthly
performance y y y y y y y y y y y y y y
Annual y y y y y y y y
JSC1 summary y y y y y y y y y y y y
State-wide strategic
projects (including
SIPs2) y y y y y y y y y y y y y y y y
RCT3 and MAT4
progress y y y
Field check y y
State-wide summary y7
y y y y y
1JSC - Joint Steering Committee
2SIP - State-level Investment Program
3RCT – Resource Condition Target
4MAT – Management Action Target
5JD - July to December
6JJ - January to June
7y - Data available for this category
110
Appendix 2: Data used in assessment
NHT II & NAPSWQ
Caring for Country and Q2 Coasts and
Country
NLP & Investment
Program
Report
2002-
2003
2003-
2004
2004-
2005
2005-
2006
2006-
2007
2007-
2008
2008-
2009
2009-
2010
2010-
2011
2011-
2012
2012-
2013
2013-
2014
2014-
2015
2015-
2016
J
D JJ
J
D JJ
J
D JJ
J
D JJ
J
D JJ
J
D JJ
J
D JJ
J
D JJ
J
D JJ
J
D JJ
J
D JJ
J
D JJ
J
D JJ
J
D JJ
Outputs
y
y y y y
y y
Six monthly
performance
y
y
y
y
y y y
y
y
y y y y y
Annual
y
y
y
y
y
y
y
y
Joint steering
committee summary
y y y y y y y
y y y y y
State-wide strategic
projects (including
SIPs)
y y y y y y y y y
y
y y
y y y y
RCT and MAT progress
y
y y
Field check
y
y
State-wide summary
y
y
y y
y
y
111
Appendix 3: How sources of data were used to evaluate NRM Attributes
Attribute 1: Achieving Sustainability
Main data sources
for attribute
Attribute elements
considered by
source
Provisional indicators for attribute element Notes about source evidence
QLD summary
output sheet (all
years)
1.1, 1.2, 1.3 • Recorded NRM activities and results (e.g., Hectares of
native vegetation protected, hectares of pest and plant
control implemented, etc.)
Quantitative overview of QLD NRM
recorded outputs as summarised by the QLD
Government and overview of recorded
activity results.
Regional body
funding and
milestone reports for
all NRM bodies
(2013-2015 only)
1.1, 1.2, 1.3 • Project overview, milestones and outcomes achievements
against agreed state priorities and targets.
• Scope of landscape and NRM activities for each NRM
regional body and subprogram coordination with state
priorities;
• Coordination with state priorities and local and regional
control of outcomes and solutions.
Quantitative six-month review of project
progress and financial update provided by
NRM regional bodies.
Regional body bi-
annual performance
reports (all years
though more detailed
in NRM LNP NRM
1.1, 1.2, 1.3, • The management of risk and the key challenges arising in
NRM projects;
• social and institutional capital required to sustain and
implement projects,
Qualitative six-month detailed review of
project progress, significance of project
outcomes, provided by NRM regional
bodies.
112
Investment program
(2013-2015)
• long-term outcomes/ results of investments and
improvement in resource condition;
• ability to coordinate with federal and state priorities;
• Detailed state and federal policy priorities.
State-wide
summaries (all
investment periods
though mainly 2002-
2008 and 2008-2013)
1.1, 1.2, 1.3 • QLD summary of the assets and threats addressed;
• Scope of QLD landscape NRM activities across NRM
bodies;
• Indigenous and traditional owner equity and access
issues;
• Evidence of restoration to natural resource base and
resource conditions.
State-wide summaries in this review covered
the following periods: 2015-2016, 2011-
2012 and 2003-4.
Attribute 2: Accountability
Main data sources
for attribute
Elements of
attribute considered
by source
Potential indicators for attribute element Notes about source evidence
QLD summary
output sheet (all
years)
2.2, 2,3, 2.4 • Recorded NRM regional body outputs in NRM
communication and summaries of investment outcomes at
sub-regional level (e.g., number of monitoring plans
implemented).
Quantitative overview of QLD NRM
recorded outputs as summarised by the QLD
Government.
Regional groups
funding and
milestone reports for
all NRM bodies
2.1, 2.2, 2.3, 2.4 • Scope of activities for each NRM regional body and
subprogram connection to state priorities;
• Coordination with state priorities;
• Monitoring reports submitted.
Quantitative six-month review of project
progress and financial update provided by
regional groups.
113
Regional groups bi-
annual performance
reports (all years
though summarised
in more detail in
NRM LNP
Investment program
(2013-2015)
2.2, 2.3, 2.4 • Access to expertise, resources and funding;
• Evidence of internal IT and systems management;
• Long-term outcomes/results of investments;
• Effectiveness of project and culture of evaluation and
reporting on performance.
Qualitative six-month detailed review of
project progress, significance of project
outcomes, provided by regional groups.
State-wide
summaries (all
investment periods
(mainly 2002-2008
and 2008-2013)
2.1, 2.2, 2.3, 2.4 • Implementation of activities;
• The transparency of reporting and communication,
• Governance, financial, operational information for
specific investment period;
• QLD Government assurance of NRM program and
project success.
State-wide summaries in this review covered
the following periods 2011-2012 and 2003-4
primarily
Attribute 3: Involvement
Main data sources
for attribute
Elements of
attribute considered
by Source
Potential indicators for attribute element Notes about source evidence
QLD summary
output sheet (all
years)
3.1 • Recorded NRM regional body outputs (e.g., number of
collaborative arrangements made, number of participants
and attendees, number of volunteers involved
Quantitative overview of QLD NRM
recorded outputs as summarised by the QLD
Government
Regional body
funding and
milestone reports for
all NRM bodies
3.1 • Scope of community involvement and grassroots
involvement;
• aligns with the interest of community members and
groups involved in NRM;
Quantitative six-month review of project
progress and financial update provided by
NRM regional bodies
114
Regional body bi-
annual performance
reports (all years
though summarised
in more detail in
NRM LNP
Investment program
(2013-2015)
3.1 • Access to communities and the capacity of communities
in the region;
• levels of community confidence and motivation for NRM
activities;
• Ability to respond adequately to community needs;
• Evidence of government and institutional support in NRM
activities.
Qualitative six-month detailed review of
project progress, significance of project
outcomes, provided by regional groups.
Attribute 4: Resilience
Main data sources
for attribute
Elements of
attribute considered
by source
Potential indicators for attribute element Notes about source evidence
QLD Summary
Output Sheet (all
years)
4.1 • Recorded NRM regional body outputs (e.g., number of
training workshops hosted).
Quantitative overview of QLD NRM
recorded outputs as summarised by the QLD
Government.
Regional body bi-
annual performance
reports (all years
though summarised
in more detail in
NRM LNP
Investment program
(2013-2015)
4.1 • Ability to offer a stable presence, particularly when
natural disasters hit or more generally in times of need;
• Alignment to community interests and needs at the time;
• Capacity building and the ability to offer and share
expertise at the local level;
• Strengthening or developing community self-
empowerment and social capital (independence and
ownership)
Qualitative six-month detailed review of
project progress, significance of project
outcomes, provided by NRM regional bodies
115
Attribute 5: Strategic Partnerships
Main data sources
for attribute
Elements of
attribute considered
by source
Potential indicators for attribute element Notes about source evidence
QLD Summary
Output Sheet (all
years)
5.1 • Recorded NRM regional body outputs in NRM
communication and summaries of investment outcomes at
sub-regional level (e.g., number of collaborative
agreements made.
Quantitative overview of QLD NRM
recorded outputs as summarised by the QLD
Government
Regional body bi-
annual performance
reports (all years
though summarised
in more detail in
NRM LNP
Investment program
(2013-2015)
5.1 • Specific partner information;
• Scope local, regional and national partners and cross-
asset/threat NRM project analysis;
• Duration of partnerships and trust/loyalties to
partnerships;
• Specified investment partners.
Qualitative six-month detailed review of
project progress, significance of project
outcomes, provided by NRM regional bodies
State-wide
summaries (all
investment periods
(mainly 2002-2008
and 2008-2013)
5.1 • NRM regional body coordination across state-wide
projects or those that involve multiple NRM Regional
Bodies;
• Partnership leverage;
• Linking partners to connect and coordinate shared
objectives and concerns.
State-wide summaries in this review covered
the following periods 2011-2012 and 2003-4
primarily.
116
Attribute 6: Planning
Main data sources
for attribute
Elements of
attribute considered
by source
Potential indicators for attribute element Notes about source evidence
QLD Summary
Output Sheet (all
years)
6.1 • Recorded NRM regional body outputs (e.g., number of
sub-regional plans implemented, type of plans
implemented/reviewed
Quantitative overview of QLD NRM
recorded outputs as summarised by the QLD
gov.
Regional body bi-
annual performance
reports (all years
though summarised
in more detail in
NRM LNP
Investment program
(2013-2015)
6.1 • Specific information such as plan type, scale of plan,
strategic aims and objectives, who develops, implements
and reviews plans;
• Integration of NRM planning with state priorities;
• Community capacity for planning and engagement in
planning structures;
• Local decision-making and empowerment.
Qualitative six-month detailed review of
project progress, significance of project
outcomes, provided by NRM regional bodies
State-wide
summaries (all
investment periods
(mainly 2002-2008
and 2008-2013)
6.1 • Funds diverted for planning and capacity building;
• integration with other state plans and community
engagement;
• Stakeholder engagement
• Traditional owner engagement and involvement in
Traditional owner land and sea management plans.
State-wide summaries in this review covered
the following periods 2011-2012 and 2003-4
primarily
117
Attribute 7: Community Awareness and Knowledge Brokerage
Main data sources
for attribute
Elements of
attribute considered
by source
Potential indicators for attribute element Notes about source evidence
QLD summary
output sheet (all
years)
7.1 • Recorded NRM regional body outputs (e.g., number of
community awareness events hosted, number of
participants and attendees).
Quantitative overview of QLD NRM
recorded outputs as summarised by the QLD
Government.
Regional body bi-
annual performance
reports (all years
though summarised
in more detail in
NRM LNP
investment program
(2013-2015)
7.1 • Specific information such as data collected, types of data
collected, methods of data collection and use of data;
• Integration of data for future NRM investment planning
and works programs;
• Levels of expertise at the local and regional levels to
adequately record and hold data;
• Integration of knowledge types (e.g., professional, local,
traditional owner, industry, business).
Qualitative six-month detailed review of
project progress, significance of project
outcomes, provided by NRM regional bodies
118
Appendix 4: Example of the first page of the data assessment table for SEQ region
ATTRIBUTE
ELEMENT
EVIDENCE (2013-2015) CONCLUSIONS (2013-2015)
Assessment
(/5)
1.1 Projects
address
regional
NRM assets
and key
threats
• There is no comprehensive overview of all activities; however, the SEQC
NRM have a number of reportable project activities (in the QG funding
program) that address a number of key threats and assets in the region. In
2013-2015 projects address creek and canal restoration (weed and pest
management) across various areas (e.g., Enoggera, Myrtletown). Other
projects consider activities that engage with landholders to restore creeks in
key locations (e.g., Browns Parade). Project funding for all three state
priorities has an original approved budget of around A$2.5 million from the
QLD State Priorities Funding program (Funding report JJ 2015).
• These assets are protected by a variety of reportable activities. In SEQC, this
includes (but is not limited to) working with community groups to conduct
control to manage invasive species (e.g., cats claw), surveillance, monitoring
and surveying of the current state of threats and assets, community
awareness, training sessions and workshops, etc. demonstrating an ability to
achieve multiple types of outputs.
• SEQC NRM projects over the 2013-2015 period employ multiple and various
milestones and outputs to address specific activity agreements (e.g., for the
Brisbane Restoration project there were three sub-programs that focussed on
milestones that included landholder engagement and restoration work).
Output types were dependent on the milestones (though no comprehensive
overview of output logic for projects). For example, restoration sub-programs
could include milestones of revegetation but the outputs would differ (e.g., it
could be media opportunity outputs or signing contracts with communities for
activities to progress) (Attachment E, SEQC, 2015 milestone performance
report).
• No comprehensive evaluation of all
the activities implemented by
NRM regional bodies to address
assets protected though some
insights provided by reportable
activities (e.g., number of hectares
protected, surveyed or controlled).
• Projects are based on previous
activity agreements to address key
assets and regions.
• Planning and targeting of key
milestones/outputs is required to
adequately address key assets and
threats.
• Projects are challenged by climatic
conditions and this requires better
management in future project
management.
• Projects reliant on QLD
Government funds and current
funding arrangements are
inadequate for long term
sustainability and NRM project
support.
3
119