UK CMS Oversight Committee Mtg 23.5.2008 STFCR AL D Cockerill The CMS ECAL Endcaps UK Responsibilities Procurement and testing of VPTs Design and procurement of the VPT HV system Design/procurement of the mechanical structures Electronics systems integration SC and Dee assembly Test beam appraisal and analysis

description

The CMS ECAL Endcaps. UK Responsibilities Procurement and testing of VPTs Design and procurement of the VPT HV system Design/procurement of the mechanical structures Electronics systems integration SC and Dee assembly Test beam appraisal and analysis. EE front end readout. - PowerPoint PPT Presentation

Transcript of The CMS ECAL Endcaps

Page 1: The CMS ECAL Endcaps

UK CMS Oversight Committee Mtg 23.5.2008

STFCRAL

D Cockerill

The CMS ECAL Endcaps

UK Responsibilities

• Procurement and testing of VPTs

• Design and procurement of the VPT HV system

• Design/procurement of the mechanical structures

• Electronics systems integration

• SC and Dee assembly

• Test beam appraisal and analysis

Page 2: The CMS ECAL Endcaps

UK CMS Oversight Committee Mtg 23.5.2008

STFCRAL

D Cockerill

VPTs SC HV cardsUmbilical cablesEE Motherboards All delivered EE VFE cards EE FE cards Polyethylene moderator

EE front end readout

Page 3: The CMS ECAL Endcaps

UK CMS Oversight Committee Mtg 23.5.2008

STFCRAL

D Cockerill

Naked SC assembly rates

Naked SC assembly rate, per week

‘Naked’ SC assembly

All 14648 VPTs and crystals glued

All SCs completed(Monday of this week!)

16/wk

Nov OsC

Page 4: The CMS ECAL Endcaps

UK CMS Oversight Committee Mtg 23.5.2008

STFCRAL

D Cockerill

SC assembly

Plot:Crystal deliveryNaked SC assemblyHV tested SCs

- All SCs HV tested and ready or mounted on Dees

Nov OsC

Page 5: The CMS ECAL Endcaps

UK CMS Oversight Committee Mtg 23.5.2008

STFCRAL

D Cockerill

Dee assembly – SC mounting

SC mounting

Dees 1-3 SC mounting completed

Dee4 completed by today, 23.5.081 Quad

1 Dee

Nov OsC

23 May 08

Page 6: The CMS ECAL Endcaps

UK CMS Oversight Committee Mtg 23.5.2008

STFCRAL

D Cockerill

Power cooling

Power cooling

2 of the 8 versions of ‘super cooling units’ needed per Dee

Each is a fully welded and tested system

The last 2 (of 32) have been completed this week and are undergoing pressure/leak tests A fully welded column of 2

cooling blocks

Super unit to be welded together

Transferframe

Page 7: The CMS ECAL Endcaps

UK CMS Oversight Committee Mtg 23.5.2008

STFCRAL

D Cockerill

Dee4

Dee4

As of Thursday, 9 left to mount

Expect mounting to be completed by Fri 23.5.08.

Page 8: The CMS ECAL Endcaps

UK CMS Oversight Committee Mtg 23.5.2008

STFCRAL

D Cockerill

Dee3

Dee3

HV looming completed

Moderator mounted

Stability fibres and LV mounted

Trigger mapping into readout motherboardscompleted (this photo)

Page 9: The CMS ECAL Endcaps

UK CMS Oversight Committee Mtg 23.5.2008

STFCRAL

D Cockerill

Dee2

Dee2 with its complete set of SCs Dee2All super cooling units mountedInstallation of VFE and FE cards underway

OPAL transfer frame to point

5

Page 10: The CMS ECAL Endcaps

UK CMS Oversight Committee Mtg 23.5.2008

STFCRAL

D Cockerill

Dee1

Dee1Fibre optic readout support panels in place, ready for final fibre optic routing

Dee1All electronics in placeAll towers tested and working

Page 11: The CMS ECAL Endcaps

UK CMS Oversight Committee Mtg 23.5.2008

STFCRAL

D Cockerill

EE Assembly and Integration Status

Dee Assembly and Integration Status, 22.5.2008

Dees 1–3 All 10986 channels checked and OK for signal continuity

Dee1 Single tower readout – pedestal width on all channels ~2ADC counts in line with expectations for electronics noise of 3500-4000 electrons per channel

Page 12: The CMS ECAL Endcaps

UK CMS Oversight Committee Mtg 23.5.2008

STFCRAL

D Cockerill

EE Risks

Insufficient ECAL effort (ED/ID)Continually monitored

New cooling schemeAt end of production

Electronics integrationGood progress, teams in place

Cable crimpsAll replaced, checked at each levelof subsequent integration

Fibre optic routing – possible delays/misroutingDatabase ready. Routing on Dee1 commencing

Page 13: The CMS ECAL Endcaps

UK CMS Oversight Committee Mtg 23.5.2008

STFCRAL

D Cockerill

EE Risks (cont’d)

Installation and commissioning at point 5

ECAL installation and commissioning led by K Bell (RAL)Brings full experience from the mounting of the36 supermodules for the barrel ECAL

Point 5 installation and commissioning team establishedTeam involves CERN CMS (point 5) and CERN ECAL engineers and techniciansand a dedicated ECAL DAQ team

Weekly meetingsDetailed installation sequence in place, from surface of point 5 to mounting on HE

Commissioning will be carried out in sectors with close feedback from the DAQ/DQM teams

Page 14: The CMS ECAL Endcaps

UK CMS Oversight Committee Mtg 23.5.2008

STFCRAL

D Cockerill

Planning for EE

Dee1 and Dee2 at point 5, r.f.i. by 16 June 2008Dee3 and Dee4 at point 5, r.f.i. by 21 July 2008

Page 15: The CMS ECAL Endcaps

UK CMS Oversight Committee Mtg 23.5.2008

STFCRAL

D Cockerill

Conclusions

SC assembly and mounting on Dees (nearly) completed

Good progress with the installation of electronics and services on Dees 1-3

Dee1 and Dee2 to point 5 by 16 June

Dee3 and Dee4 to point 5 by 21 July