Status of the CMS ECAL Endcaps LHCC Comprehensive Review, June 2006 D Cockerill
description
Transcript of Status of the CMS ECAL Endcaps LHCC Comprehensive Review, June 2006 D Cockerill
LHCC Comprehensive Review 26/6/06 D.J.A. Cockerill - RAL 1
Status of the CMS ECAL Endcaps
LHCC Comprehensive Review, June 2006D Cockerill
EE EE large mechanics VPTs and Supercrystal assembly Electronics Trigger The “Dee4” project
ES ES mechanics Micromodules and readout
EE and ES Planning
Conclusions
LHCC Comprehensive Review 26/6/06 D.J.A. Cockerill - RAL 2
The CMS ECAL Endcaps – EE/ES
Tapered crystalsOff-Pointing ~ 3o from vertex
Crystal Endcaps: 4 Dees (2 per endcap)14648 Crystals Total mass 22.9 t
Preshower2Xo, 1Xo Pb, 2mm Si strips, 2 x 2 orthogonal layers
LHCC Comprehensive Review 26/6/06 D.J.A. Cockerill - RAL 3
EndCap EE
All large mechanical pieces are at CERN
Dry assembly of env. screen produced in Russia
LHCC Comprehensive Review 26/6/06 D.J.A. Cockerill - RAL 4
EE: VPT production & gluing, Supercrystals
EE VPT to crystal gluing
2800 VPTs shipped from UK to CERNAll tested upon receipt by Russia - INR
Up to 50 EE crystals/VPTs glued each week
110 of current EE crystal stock (~350 xtals) done
First “Russian” SC completed
in June 2006 built using CRISTAL database
LHCC Comprehensive Review 26/6/06 D.J.A. Cockerill - RAL 5
EE electronics
Preliminary results, ~ 3900 e- per channelCross talk < 0.1%Meets EE requirements
SC HV cards 105 pre-production cards completed All R & C components for EE delivered
Motherboards 2 prototypes on Dee4 600 cards by end 2006
EE VFE cardsRC feedback on MGPA tuned for EEInput diode for VPT spark protection 30 prototypes produced in Feb 06 250 cards now under test
3130 cards by end July 06
FE cards80 pre-production cards tested
800 cards produced by Sep 2006
LHCC Comprehensive Review 26/6/06 D.J.A. Cockerill - RAL 6
EE trigger
Pseudostrip (5 crystal) allocationsEE+ towards I.P
Consequent trigger towers (TCC level)EE+ towards I.P
LHCC Comprehensive Review 26/6/06 D.J.A. Cockerill - RAL 7
EE : preparing for the assembly
Ensuring correct cabling of the channels
Trigger map (H.Heath)LED cabling tester from UVa
LHCC Comprehensive Review 26/6/06 D.J.A. Cockerill - RAL 8
EE data and trigger readout
The fibre readout fan-out boxes (two layers) serving the EE DCCs and TCCs in the control room
900 readout fibres to correctly route per Dee
LHCC Comprehensive Review 26/6/06 D.J.A. Cockerill - RAL 9
“Dee4” project
“Dee4”
First large scale test of integration philosophy
20 SCs mounted on BP Dee4 by end 2006
Trigger mapping at motherboard
10 cooling blocks, main manifold
“Dee4” to testbeam in May 2007
EE assembly has started
“Dee4” will provide crucial assembly and test beam insights
Dee1 assembly from September 2006
LHCC Comprehensive Review 26/6/06 D.J.A. Cockerill - RAL 10
(Preshower) ES: Engineering
Windows ready with Paraffin : first elements to be installed before beam pipe closure
First brazing of cooling screenBlanks for outer drums/patch panels
LHCC Comprehensive Review 26/6/06 D.J.A. Cockerill - RAL 11
ES: Silicon micro-modules
Si sensors availableAll ceramics supports and Al tiles producedSmall mod to allow for backplane bonding(follow. ES and Tracker experience)All ASICS available
Problem with hybrids productionFirst large series of PCBs not good ! Immediate action: change PCB manufacturing companyWill probably eat a large part of schedule contingency
LHCC Comprehensive Review 26/6/06 D.J.A. Cockerill - RAL 12
ES: On and Off detector digital electronics
Successful test of Mother boards pre-seriesincluding 12 boards token ring and test of several ladders
→Production launched ESR for ES-DCC last May
OptoRx: proto ok. Final version in a few weeks
VME board end of Summer (collab. with TOTEM)
MB tester (NTU)
OptoRx
LHCC Comprehensive Review 26/6/06 D.J.A. Cockerill - RAL 13
EE Planning
Dee 1 End Sep 2007Dee 2 End Dec 2007Dee 3 Mid Mar 2008Dee 4 Mid Apr 2008
CMS windowfor Dee1end Sep 07
EE+mid Jan 08
EE-mid Mar 08
LHCC Comprehensive Review 26/6/06 D.J.A. Cockerill - RAL 14
EE planning
Crucial to introduce as much parallel assembly and integration as possible
Quality control at each crucial step
Suggestion to carry out all SC mounting and Dee assembly in bldg 867
This offers many very attractive features- all major activities under one roof- proximity of expert teams- realisation of the EE trigger, from motherboard level to fibre readout level- multiple DAQ test systems, needed for EE QA, available locally- cooling capacity for one entire Dee- LV power
Crystal Palace
Advance preparation of all large mechanics- Dees into OPAL frames- dry assembly tests of Environmental screens- BP cooling installation- Mounting laser monitoring system
LHCC Comprehensive Review 26/6/06 D.J.A. Cockerill - RAL 15
ES planning
Good progress with engineering/mechanics
Bare micromodule production has startedProblem with hybrid PCB production: change of producer necessary; will try to minimize impact on overall ES schedule
Delay on system motherboards but production should start soon and should be faster than originally envisaged
Important progress in DAQ (software and ES-DCC) and good advances in offline/physics software
“Ready for Installation” dates so far unaffected by delays. Some contingency now exists due to revised V35 schedule but will probably be “eaten” by hybrid delay
ES+ Dee1 assembly finished 15.3.07ES+ Dee2 assembly finished 30.6.07ES- Dee1 assembly finished 30.8.07ES- Dee2 assembly finished 30.11.07
ES- RFI 31.8.07ES+ RFI 31.12.07
LHCC Comprehensive Review 26/6/06 D.J.A. Cockerill - RAL 16
EE - Conclusions
EE and ES assembly has started
Much progress with the EE large mechanics, VPTs, SC assembly, electronics, and trigger and data mapping
“Dee4” will provide crucial assembly and test beam insights Dee1 assembly from September 2006
Good progress with ES engineering/mechanics Bare micromodule production has started
We are on the learning curve for EE and ES assembly
LHCC Comprehensive Review 26/6/06 D.J.A. Cockerill - RAL 17
Additional info follows, next slide