Software Measurement and AnalysisTeam Assignment 13Team 04
Agenda
Member
Introduce
Combination of Wideband Delphi to generates schedule, budget and resource
1
2
3
4
Estimates for the Viking project
•Members
Name Role
Hoàng Thị Kim Dâng Leader
Thái Thanh Nhã Sub
Trần Tiễn Hưng Member
Từ Huỳnh Thắng Member
Chu Thị Thu Hương Member
Trần Thị Mộng Hà Member
Agenda
Member
Introduce
Combination of Wideband Delphi to generates schedule, budget and resource
1
2
3
4
Estimates for the Viking project
Traditional ScheduleBig Requirements Up Front
Use WBS to decompose the project into tasksUse Estimating Technique to estimate tasksExpert Judgment (Wideband Delphi)
Re-estimating (when more is known) is often not doneMust estimate each change, or re-estimate project if f enough change occurs
Introduce
Agenda
Member
Introduce
Combination of Wideband Delphi to generates schedule, budget and resource
1
2
3
4
Estimates for the Viking project
WBS for Viking project
Wideband DelphiAssumptions established by teamTeam discusses assumptions where
estimates varyGoal: Team working with same & correct
assumptions
Estimates for the Viking project
Agenda
Member
Introduce
Combination of Wideband Delphi to generates schedule, budget and resource
1
2
3
4
Estimates for the Viking project
•List all task of Viking project ( base on WBS )•Members estimate time (hour) to complete the task. Members check each other estimate, and adjust to be more suitable and explain in Assumption.•After that, teams discuss each task to find the best estimated time for the task.
Combination of Wideband Delphi
When we have estimated numbers, we will calculate as below:
• Because > 10 tasks, so team using a complex standard deviation calculation:• Compute the SD of each task (or feature): Individual SD = (IndividualWorstCaseEst- IndividualBestCaseEst)/6• Compute each task’s variance: Task variance = Task’s SD2
• Total the variances• Take the square root of the total
Combination of Wideband Delphi
% Confidence Calculation
2% Expected Case - (2 *Standard Deviation)
10% Expected Case - (1.28 * Standard Deviation)
16% Expected Case - (1 * Standard Deviation)
20% Expected Case - (.84 * Standard Deviation)
25% Expected Case - (.67 * Standard Deviation)
30% Expected Case - (.52 * Standard Deviation)
40% Expected Case - (.25 * Standard Deviation)
50% Expected Case
60% Expected Case + (.25 *Standard Deviation)
70% Expected Case + (.52 * Standard Deviation)
75% Expected Case + (.67 * Standard Deviation)
80% Expected Case + (.84 * Standard Deviation)
84% Expected Case + (1 * Standard Deviation)
90% Expected Case + (1.28 * Standard Deviation)98% Expected Case + (2 * Standard Deviation)
Combination of Wideband Delphi
% Confidence Calculation Effort estimate (hours)
2% Expected Case - (2 *Standard Deviation) 1120,4272
10% Expected Case - (1.28 * Standard Deviation) 1131,0734
16% Expected Case - (1 * Standard Deviation) 1135,2136
20% Expected Case - (.84 * Standard Deviation) 1137,5794
25% Expected Case - (.67 * Standard Deviation) 1140,0931
30% Expected Case - (.52 * Standard Deviation) 1142,3111
40% Expected Case - (.25 * Standard Deviation) 1146,3034
50% Expected Case 1150
60% Expected Case + (.25 *Standard Deviation) 1153,6966
70% Expected Case + (.52 * Standard Deviation) 1157,6889
75% Expected Case + (.67 * Standard Deviation) 1159,9069
80% Expected Case + (.84 * Standard Deviation) 1162,4206
84% Expected Case + (1 * Standard Deviation) 1164,7864
90% Expected Case + (1.28 * Standard Deviation) 1168,9266
98% Expected Case + (2 * Standard Deviation) 1179,5728
Combination of Wideband Delphi
% Confidence Calculation Budget estimate
2% Expected Case - (2 *Standard Deviation) 1409661.2831
10% Expected Case - (1.28 * Standard Deviation) 1436819.2212
16% Expected Case - (1 * Standard Deviation) 1447380.6416
20% Expected Case - (.84 * Standard Deviation) 1453415.7389
25% Expected Case - (.67 * Standard Deviation) 1459828.0299
30% Expected Case - (.52 * Standard Deviation) 1465485.9336
40% Expected Case - (.25 * Standard Deviation) 1475670.1604
50% Expected Case 1485100.0000
60% Expected Case + (.25 *Standard Deviation) 1494529.8396
70% Expected Case + (.52 * Standard Deviation) 1504714.0664
75% Expected Case + (.67 * Standard Deviation) 1510371.9701
80% Expected Case + (.84 * Standard Deviation) 1516784.2611
84% Expected Case + (1 * Standard Deviation) 1522819.3584
90% Expected Case + (1.28 * Standard Deviation) 1533380.7788
98% Expected Case + (2 * Standard Deviation) 1560538.7169
Budget
% Confidence Calculation Effort estimate
2% Expected Case - (2 *Standard Deviation) 36
10% Expected Case - (1.28 * Standard Deviation) 37
16% Expected Case - (1 * Standard Deviation) 37
20% Expected Case - (.84 * Standard Deviation) 37
25% Expected Case - (.67 * Standard Deviation) 37
30% Expected Case - (.52 * Standard Deviation) 37
40% Expected Case - (.25 * Standard Deviation) 38
50% Expected Case 38
60% Expected Case + (.25 *Standard Deviation) 38
70% Expected Case + (.52 * Standard Deviation) 39
75% Expected Case + (.67 * Standard Deviation) 39
80% Expected Case + (.84 * Standard Deviation) 39
84% Expected Case + (1 * Standard Deviation) 39
90% Expected Case + (1.28 * Standard Deviation) 39
98% Expected Case + (2 * Standard Deviation) 40
Resource