Risk Assesment for Precast Boundary Wall

12
RISK ASSESSMENT & RISK CONTROL REGISTER DATE OF ISSUE 10/25/2022 PROJECT ERECTION OF PRECAST BOUNDARY WALL FOR MACWANE IN ICAD REV NO: 1 GENERAL ACTIVITIES HAZARDS /RISKS RISK ASSESSMENT CONTROL MEASURES RISK RATING AFTER CONTROL Sever ity (SR) Prob. Ratin g (PR) Risk Rati ng (RR) Severi ty (SR) Prob . Rati ng (PR) Risk Rati ng (RR) 1 GENERAL 1.NON-AVAILABILITY OF PPE 1.PROVIDE PROPER PPE 1 1 1 2. NON AVAILABILITY OF FIRST AIDS 2 3 6 2. AT LEAST ONE FIRST AID BOX MUST BE AVAILABLEAT OUR POST. 3.POOR WEATHER 3. TOOL BOX TALKS MUST BE GIVEN 4. IMPROPER OR UNSAFE WORKING PLATFORM Approved by :………………………………….. Approved by :………………………………….. Main contractor: …………………………………. Consultant :……………………….…………

description

RISK ASSESMENT FOR BOUNDARY WALL CONSTRUCTION

Transcript of Risk Assesment for Precast Boundary Wall

Page 1: Risk Assesment for Precast Boundary Wall

RISK ASSESSMENT & RISK CONTROL REGISTER

DATE OF ISSUE4/28/2023

PROJECTERECTION OF PRECAST BOUNDARY WALL FOR MACWANE IN ICAD

REV NO: 1

GENERAL

ACTIVITIES HAZARDS /RISKS RISK ASSESSMENT CONTROL MEASURES RISK RATING AFTER CONTROL

Severity

(SR)

Prob. Rating

(PR)

Risk Rating(RR)

Severity

(SR)

Prob. Rating(PR)

Risk Rating(RR)

1 GENERAL 1.NON-AVAILABILITY OF PPE 1.PROVIDE PROPER PPE 1 1 1

2. NON AVAILABILITY OF FIRST AIDS 2 3 6 2. AT LEAST ONE FIRST AID BOX MUST BE AVAILABLEAT

OUR POST.3.POOR WEATHER 3. TOOL BOX TALKS MUST BE GIVEN4. IMPROPER OR UNSAFE WORKING PLATFORM

Approved by :………………………………….. Approved by :…………………………………..

Main contractor: …………………………………. Consultant :……………………….…………

Page 2: Risk Assesment for Precast Boundary Wall

RISK ASSESSMENT & RISK CONTROL REGISTER

DATE OF ISSUE4/28/2023

PROJECTERECTION OF PRECAST BOUNDARY WALL FOR MACWANE IN ICAD

REV NO: 1

ERECTION OF PRECAST ELEMENTS (BOUNDARY WALL) AT SITE

ACTIVITIES HAZARDS /RISKS RISK ASSESSMENT CONTROL MEASURESRISK RATING AFTER

CONTROLSeverity

(SR)

Prob. Rating(PR)

Risk Rating(RR)

Severity

(SR)

Prob. Rating(PR)

Risk Rating(RR)

2.(A) LIFTING AND HOISTING OPERATIONS.

1. FAILURE OF LIFTING EQUIPMENT 3 3 9

1.INSPECT THE EQUIPMENT AND CHECK FOR PROPER CERTIFICATION 2 1 2

(B) USE OF CRANES 2. FALL OF LOAD2.REGULAR MAINTAINENCE OF EQUIPMENTS AND CHECKING THE SAME

(C) ALIGNING OF STRUCTURE3. INJURY OF OPERATORS AND PERSONNELS 3. OPERATOR TO GET PROPER VISIBILITY4. FALL OF MATERIALS 4. USE PROPER PPE.5. DUST DUE TO DEMOLITION 5. ERECT WARNING SIGNS

6. PROPER FACE MASK 7. SAFE WORKING PROCEDURES MUST BE FOLLOWED8. PROPER SIGNALLING PRACTICES9.RESTRICTED ACCESS TO THE SITE AND CONFINE THE AREA OF OPERATION 10. ENSURE PROPER SUPERVISION ALL THE TIME DURING THE TIME OF EXECUTION OF JOB.11. EDUCATE THE PEOPLE REGARDING THE PROPER USE OF EQUIPMENTS AND TOOLS.

Approved by :………………………………….. Approved by :…………………………………..

Main contractor: …………………………………. Consultant :……………………….…………

Page 3: Risk Assesment for Precast Boundary Wall

RISK ASSESSMENT & RISK CONTROL REGISTER

DATE OF ISSUE4/28/2023

PROJECTERECTION OF PRECAST BOUNDARY WALL FOR MACWANE IN ICAD

REV NO: 1

ACTIVITIES HAZARDS /RISKS RISK ASSESSMENT CONTROL MEASURESRISK RATING AFTER

CONTROLSeverity

(SR)

Prob. Rating(PR)

Risk Rating(RR)

Severity

(SR)

Prob. Rating(PR)

Risk Rating(RR)

3.(A) CUTTING1.USE OF HAND TOOLS AND POWER TOOLS

2 3 6 1.TOXIC GASES AND DUST 1 2 2

2.ELECTRICAL HAZARDS2. VISUAL INSPECTION FOR DAMAGE TOOLS/CABLES, PLUGS.

3.TRIPPING HAZARDS3. ALL POWER TOOLS OPERATED SHOULD HAVE UP-TO-DATE PAT TEST.

(B) GROUTING 1.FALL OF PERSONS FROM HEIGHT4. CABLES MUST BE ROUTED AWAY FROM WALKWAYS.

2.ALLERGIES DUE TO CHEMICALS(CEMENT)

5.PROVIDE ADEQUATE PPE(HEARING PROTECTION,DUST MASKS,GOOGLES,HELMETS ETC)6. USE OF PROPER GLOVES AND MASKS.7. PROPER INSPECTION BEFORE AND AFTER THE WORK.

Approved by :………………………………….. Approved by :…………………………………..

Main contractor: …………………………………. Consultant :……………………….…………

Page 4: Risk Assesment for Precast Boundary Wall

RISK ASSESSMENT & RISK CONTROL REGISTER

DATE OF ISSUE4/28/2023

PROJECTERECTION OF PRECAST BOUNDARY WALL FOR MACWANE IN ICAD

REV NO: 1

ACTIVITIES HAZARDS /RISKS RISK ASSESSMENT CONTROL MEASURESRISK RATING AFTER

CONTROLSeverity

(SR)

Prob. Rating(PR)

Risk Rating(RR)

Severity

(SR)

Prob. Rating(PR)

Risk Rating(RR)

STRUCTURAL CIVIL WORKS

Approved by :………………………………….. Approved by :…………………………………..

Main contractor: …………………………………. Consultant :……………………….…………

Page 5: Risk Assesment for Precast Boundary Wall

RISK ASSESSMENT & RISK CONTROL REGISTER

DATE OF ISSUE4/28/2023

PROJECTERECTION OF PRECAST BOUNDARY WALL FOR MACWANE IN ICAD

REV NO: 1

ACTIVITIES HAZARDS /RISKS RISK ASSESSMENT CONTROL MEASURES RISK RATING AFTER CONTROL

Severity

(SR)

Prob. Rating(PR)

Risk Rating(RR)

Severity

(SR)

Prob. Rating(PR)

Risk Rating(RR)

Approved by :………………………………….. Approved by :…………………………………..

Main contractor: …………………………………. Consultant :……………………….…………

Page 6: Risk Assesment for Precast Boundary Wall

RISK ASSESSMENT & RISK CONTROL REGISTER

DATE OF ISSUE4/28/2023

PROJECTERECTION OF PRECAST BOUNDARY WALL FOR MACWANE IN ICAD

REV NO: 1

FABRICATION OF STEEL STRUCTURES

ACTIVITIES HAZARDS /RISKS RISK ASSESSMENT CONTROL MEASURES RISK RATING AFTER CONTROL

Severity

(SR)

Prob. Rating(PR)

Risk Rating(RR)

Severity

(SR)

Prob. Rating(PR)

Risk Rating(RR)

Approved by :………………………………….. Approved by :…………………………………..

Main contractor: …………………………………. Consultant :……………………….…………

Page 7: Risk Assesment for Precast Boundary Wall

RISK ASSESSMENT & RISK CONTROL REGISTER

DATE OF ISSUE4/28/2023

PROJECTERECTION OF PRECAST BOUNDARY WALL FOR MACWANE IN ICAD

REV NO: 1

ERECTION OF STEEL STRUCTURES AND WORKING AT HEIGHTS

ACTIVITIES HAZARDS /RISKS RISK ASSESSMENT CONTROL MEASURESRISK RATING AFTER

CONTROLSeverity

(SR)

Prob. Rating(PR)

Risk Rating(RR)

Severity

(SR)

Prob. Rating(PR)

Risk Rating(RR)

Approved by :………………………………….. Approved by :…………………………………..

Main contractor: …………………………………. Consultant :……………………….…………

Page 8: Risk Assesment for Precast Boundary Wall

RISK ASSESSMENT & RISK CONTROL REGISTER

DATE OF ISSUE4/28/2023

PROJECTERECTION OF PRECAST BOUNDARY WALL FOR MACWANE IN ICAD

REV NO: 1

TRANSPORTATION / LOADING / UNLOADING MATERIALS

ACTIVITIES HAZARDS /RISKS RISK ASSESSMENT CONTROL MEASURES RISK RATING AFTER CONTROL

Severity

(SR)

Prob. Rating(PR)

Risk Rating(RR)

Severity

(SR)

Prob. Rating(PR)

Risk Rating(RR)

Approved by :………………………………….. Approved by :…………………………………..

Main contractor: …………………………………. Consultant :……………………….…………

Page 9: Risk Assesment for Precast Boundary Wall

RISK ASSESSMENT & RISK CONTROL REGISTER

DATE OF ISSUE4/28/2023

PROJECTERECTION OF PRECAST BOUNDARY WALL FOR MACWANE IN ICAD

REV NO: 1

ELECTRICAL WORKS

ACTIVITIES HAZARDS /RISKS RISK ASSESSMENT CONTROL MEASURESRISK RATING AFTER

CONTROLSeverity

(SR)

Prob. Rating(PR)

Risk Rating(RR)

Severity

(SR)

Prob. Rating(PR)

Risk Rating(RR)

Approved by :………………………………….. Approved by :…………………………………..

Main contractor: …………………………………. Consultant :……………………….…………