VERSION 1.0 10/29/2019 TRANSPORTATION BUILDING Roof Restoraon 2019 Arkansas City Public Schools REQUEST FOR PROPOSAL (RFP) / PROJECT MANUAL WILL PFANNENSTIEL DIRECTOR OF BUSINESS AND OPERATIONS USD #470

Transcript of REQUEST FOR PROPOSAL (RFP) / PROJECT MANUAL · REQUEST FOR PROPOSAL (RFP) / PROJECT MANUAL WILL...

Page 1: REQUEST FOR PROPOSAL (RFP) / PROJECT MANUAL · REQUEST FOR PROPOSAL (RFP) / PROJECT MANUAL WILL PFANNENSTIEL DIRECTOR OF BUSINESS AND OPERATIONS USD #470. 1 ... repair of any additional

VERSION 1.0

10/29/2019

TRANSPORTATION BUILDINGRoof Restora�on 2019

Arkansas City Public Schools

REQUEST FOR PROPOSAL (RFP) / PROJECT MANUAL

WILL PFANNENSTIEL

DIRECTOR OF BUSINESS AND OPERATIONSUSD #470

Page 2: REQUEST FOR PROPOSAL (RFP) / PROJECT MANUAL · REQUEST FOR PROPOSAL (RFP) / PROJECT MANUAL WILL PFANNENSTIEL DIRECTOR OF BUSINESS AND OPERATIONS USD #470. 1 ... repair of any additional

1

TABLE OF CONTENTS

Proposal Bid Form

Project Bid Information

Instructions to Bidders

General Conditions

Specifications

Page 3: REQUEST FOR PROPOSAL (RFP) / PROJECT MANUAL · REQUEST FOR PROPOSAL (RFP) / PROJECT MANUAL WILL PFANNENSTIEL DIRECTOR OF BUSINESS AND OPERATIONS USD #470. 1 ... repair of any additional

2

PROPOSAL BID FORM

Date: _____________________

To: USD 470

C/O Will Pfannenstiel Director of Business and Operations

Subject: Roof Restoration Specifications – Transportation Building

The undersigned, having familiarized himself with the attached Contract Documents, which are as follows: Proposal Bid Form, Project Bid Information, Instruction to Bidders, General Conditions, Attachments, and Specifications; all of which Contract documents are made a part hereof, hereby proposes, in compliance with said Contract documents, to furnish all labors, equipment, material, tools, supervision, etc., and to complete all said work as herein specified.

1. To provide Supervision, Labor, Materials, and Equipment for the Roof Restoration of the Transportation Building Located at:

420 S. 5th Street, Arkansas City, KS

*Lump Sum Price $_____________________________

TIME FOR PERFORMANCE: The undersigned proposes to furnish all Base Bid

work within ___________ calendar days.

Start Date: _______________ Completion Date: _______________

The undersigned understands and agrees that the Owner has the right to reject any and all bids, to waive informalities or other requirements for its benefit and to accept such proposals as it deems in its best interest.

Signature: _______________________________

Firm: _________________________________

Individual: _______________________________

Title: _________________________________

Address: ________________________________

*Please staple all pages together and submit in duplicate with bond.

Page 4: REQUEST FOR PROPOSAL (RFP) / PROJECT MANUAL · REQUEST FOR PROPOSAL (RFP) / PROJECT MANUAL WILL PFANNENSTIEL DIRECTOR OF BUSINESS AND OPERATIONS USD #470. 1 ... repair of any additional

3

PROJECT BID INFORMATION

Owner: USD #470

Project: Transportation Building Roof Restoration

Mandatory Pre-bid Conference:

Date:

Time:

Place: 420 S. 5th Street, Arkansas City, KS 67005

Bid-date Information:

Due Date:

Time:

Place: 12545 Greenway, Arkansas City, KS 67005

Page 5: REQUEST FOR PROPOSAL (RFP) / PROJECT MANUAL · REQUEST FOR PROPOSAL (RFP) / PROJECT MANUAL WILL PFANNENSTIEL DIRECTOR OF BUSINESS AND OPERATIONS USD #470. 1 ... repair of any additional

4

INSTRUCTION TO BIDDERS

The NOTICE TO BIDDERS along with the following instructions constitute the formal instructions to bidders.

Pre-Bid Conference

Following the distribution of these specifications, all Contractors shall visit the job site to ensure comprehension of these specifications. Contractors who do not visit the job shall be disqualified from bidding this project.

Insurance

Contractor shall procure and maintain during life of this contract, bodily injury and property damage liability insurance under a comprehensive general form and a comprehensive automobile injury and property damage liability contract. Amounts of such bodily injury and property damage liability is stipulated in Division 07240; 1.09.

Contractor's comprehensive liability insurance coverage is to include a completed operation insurance for a period of one (1) year after completion of this contract.

b) Workmen's Compensation and Employer's Liability

Contractor shall maintain during life of this contract statutory workmen's compensation and employer's liability insurance for all his employees engaged in work on project.

c) Statement of Insurance Compliance

Contractor shall furnish Owner a properly signed and notarized statement on his letterhead stating that he has complied with all provisions of this specification relating to insurance coverage and that none of the insurance coverage specified will be canceled or materially altered except after (30) days written notice has been received by Owner. Only exception permitted is that a notarized certificate indicating compliance with completed insurance will not be required until lien waivers and other final papers are submitted.

d) Exchange of Policies

Contractor, by executing statement of insurance compliance acknowledges to the Owner that he has totally complied with coverage requirements of contract documents.

e) Certificate Delivery

The Contractor shall not commence work under the contract until he has obtained all insurance required under these specifications and all insurance has been received by Owner.

Guarantee

The Garland Company will supply a five (5) year guarantee to the Owner, upon final approval of the restoration work. The Contractor will supply Garland with a one (1) year warranty on labor and installation. The Contractor must qualify as an "Approved Contractor" by the Garland Company.

Bid Opening

The Owner reserves the right to reject any or all bids and to accept the bid which, in his opinion, is in the best interest of the Owner. No bid shall be withdrawn for a period of thirty (30) days after the time set for the opening thereof.

Questions

Page 6: REQUEST FOR PROPOSAL (RFP) / PROJECT MANUAL · REQUEST FOR PROPOSAL (RFP) / PROJECT MANUAL WILL PFANNENSTIEL DIRECTOR OF BUSINESS AND OPERATIONS USD #470. 1 ... repair of any additional

5

Questions regarding this bid can be directed to Mr. John Geist, Director of Plant Facilities, Garden City Public Schools. Mr. Geist will be referenced herein as “Owner’s Representative.”

Responsibility of Measurements and Quantities

The bidding Contractor shall be solely responsible for the accuracy of all measurements and for estimating the material quantities required to satisfy these specifications.

Pre-job Meeting

The pre-job meeting shall be held prior to the start of the project. This meeting shall include the Contractor and the Owner's representative. The condition of the buildings and grounds areas shall be recorded, and the Contractor shall be responsible for the correction and/or repair of any additional damage to the facilities resulting from the related work, and in addition to the conditions noted at the pre-job meeting.

Discrepancies and Addendum

Should a bidder find any discrepancies in the drawings and specifications, or should he be in doubt as to their meaning, he shall notify the Owner’s Representative at once, who will send a written addendum to all bidders concerned. Oral instructions or decisions, unless confirmed by addendum, will not be considered valid or binding. All discrepancies must be submitted to the Owner’s representative no later than five (5) days prior to the due date. No extras will be authorized because of failure of the Contractor to include work called for in the addendum in their bid.

Performance

Should the Contractor fail to substantially complete the work on the date set forth above for substantial completion, the Owner shall retain from compensation otherwise owed the Contractor, the amount of Five Hundred Dollars ($500.00) for each calendar day thereafter that the Contract remains substantially incomplete.

Competency of Bidder

To enable the Owner to evaluate the competency and financial responsibility of the Contractor, the low bidder shall, when requested by Owner’s Representative, furnish the following information which shall be sworn to under oath by him or by a properly authorized representative of the bidder.

The address and description of the bidder's plant and place of business.

The name and/or articles of co-partnership or incorporation.

Itemized list of equipment available for use on the project.

Contractor will furnish a Statement of Qualifications (SOQ) upon request of the Owner. SOQ is to be valid and current. The Owner may require that any of the items contained be further verified.

General Information

Contractor’s Name.

Type of Business Entity.

In which State was the Contractor organized.

Whether the Contractor is legally authorized to conduct business in Kansas

(mandatory requirement).

Page 7: REQUEST FOR PROPOSAL (RFP) / PROJECT MANUAL · REQUEST FOR PROPOSAL (RFP) / PROJECT MANUAL WILL PFANNENSTIEL DIRECTOR OF BUSINESS AND OPERATIONS USD #470. 1 ... repair of any additional

6

Contractor’s ownership and Principal Officers.

Contractor’s contact person, including phone number, e-mail address and

other relevant contact information.

Contractor’s business address and contact information, including email address.

Number of years in the General Construction Business.

Contractor License Information

Primary License Classification.

State of Kansas License Number and date issued (mandatory requirement).

License Holder.

Type of License.

Supplemental Classification held, if any.

State and explain any disciplinary actions taken by any agency of the State of

Kansas to revoke or suspend the above license or attempts to investigate the

license holder for business or construction related reasons.

Contractor’s maximum available bonding amount.

Certifications (Failure to include may result in the rejection of the SOQ)

A statement acknowledging that the Contractor will accept all of the conditions as

stated in this RFQ shall be contained within the body of the letter.

The cover letter is to be signed by an officer of the Contractor who is

authorized to bind the Contractor.

No Conflict Statement - Provide a statement that no conflict of interest issues exist at

the time of submission of the SOQ, signed by an officer of the Contractor who is

authorized to bind the firm. In addition, no-conflict of interest statements must also

be provided by any identified subcontractor.

Such additional information as may be required that will satisfy the Owner that the bidder is adequately prepared in technical experience, or otherwise, to fulfill the contract.

Insurance and Bond Requirements

A Performance and Payment and 5% Bid Bond are required for this project.

Required limits for Insurance and Bond are set forth within Specification Division 07240; 1.09

Disqualification of Bidders

Any one or more of the following causes may be considered sufficient for disqualification of a bidder and the rejection of his bid or bids:

1. Failure to attend the pre-bid meeting. 2. Evidence of collusion among bidders. 3. Lack of responsibility as revealed by either financial, experience or equipment

statements as submitted. 4. Lack of expertise as shown by past work and judged from the standpoint of

workmanship and performance history.

Page 8: REQUEST FOR PROPOSAL (RFP) / PROJECT MANUAL · REQUEST FOR PROPOSAL (RFP) / PROJECT MANUAL WILL PFANNENSTIEL DIRECTOR OF BUSINESS AND OPERATIONS USD #470. 1 ... repair of any additional

7

5. Uncompleted work under other contracts which, in the judgment of the Owner, might hinder or prevent the prompt completion of additional work if awarded.

6. Being in arrears on existing contracts, litigation with an Owner, or having defaulted on a previous contract.

Employees On Site

Bidders shall be required to provide certification that no employees of Bidder who might work on the project or at the project site are offenders or sex offenders, as defined by KSA 22-4902, or sexually violent predators as defined by KSA 59-29a02. USD 457 specifically prohibits individuals so defined to be on or in district property occupied at any time by students or staff

Sub-Contractors

The contractor shall be prepared to submit in writing the names and places of business of the sub-contractors. The standing and ability of the Contractor and subcontractors will be taken into consideration and agreed upon before awarding the contract.

Payment

When the job is in progress, the Owner agrees to pay upon request of the Contractor, ninety percent (90%) of the total contract price equivalent to the percentage of work completed at that time. If, requested by the Owner’s Representative.

Such payment shall be viewed by both parties as progress payments and shall not in any way relieve the Contractor of performance obligations under this contract, nor shall such payments by viewed as approval or acceptance of work performed under this contract.

Final payment shall be withheld until provisions of the specifications are met, including all necessary clean up, and the Owner receives written verification of completion.

Waiver of Lien

Partial waiver of lien from major material suppliers shall accompany each payment request to confirm and acknowledge disbursement of the payment. Partial waivers of lien shall be properly completed and shall list the cumulative amount of payment received by the date of the waiver. This requirement shall not be waived unless agreed upon in writing by the Owner.

Page 9: REQUEST FOR PROPOSAL (RFP) / PROJECT MANUAL · REQUEST FOR PROPOSAL (RFP) / PROJECT MANUAL WILL PFANNENSTIEL DIRECTOR OF BUSINESS AND OPERATIONS USD #470. 1 ... repair of any additional

8

GENERAL CONDITIONS

DESCRIPTION

The work consists of furnishing and installing all EIFS Exterior Restoration Labor and Non-Garland Material as specified in the accompanying documents and as specified herein.

LOCAL RULES

The Owner has certain rules and the Contractor and Job Site Personnel shall abide by them. The Contractor shall contact the Owner's representative for specific information regarding the rules governing all operations of this project.

CONCURRENT OPERATIONS

Because other activities of the Owner will be proceeding at the same time as the work covered by this specification, the Contractor shall cooperate with the Owner's representative to ensure that all contract work progresses in a manner which does not conflict with other activities.

WORKMANSHIP

All workmen shall be thoroughly experienced in the particular class of work in which they are employed. All materials shall be securely in place in a watertight, neat, and workmanlike manner.

CLEAN UP

Contractor shall be responsible for maintaining all work areas in a neat and orderly manner. Immediately upon completion, all clean up shall be performed to the satisfaction of the Owner's representative.

SAFETY

The Contractor shall comply with all applicable provisions of the Occupational Safety and Health Act throughout the duration of the specified work.

INSPECTION OF WORK IN PROGRESS AND UPON COMPLETION

At the completion of all patching flashing repair and cleaning, and prior to any resurfacing and restoration work, the Contractor shall notify the Owner's representative. Twenty-four (24) hours’ notice shall be given to above, at which time an inspection of the prepared surface will be made.

The Owner shall authorize the material manufacturer's representative to periodically examine the work in progress, as well as upon completion to assist in ascertaining the extent to which the materials and procedures conform to the requirements of these specifications and to the published instruction of the material manufacturer.

The authorized material manufacturer's field representative may/shall be responsible for:

1. Rendering inspection services at the Owner's representative’s request. 2. Keeping the Owner's representative informed after periodic inspections as to the

progress and quality of the work as observed. 3. Calling to the attention of the Contractor those matters observed which he

considers to be in violation of the contract requirements. 4. Reporting to the Owner's representative in writing any failure or refusal of the

Contractor to correct unacceptable practices called to his attention. 5. Supervise the taking of test cuts and the restoration of such areas.

Page 10: REQUEST FOR PROPOSAL (RFP) / PROJECT MANUAL · REQUEST FOR PROPOSAL (RFP) / PROJECT MANUAL WILL PFANNENSTIEL DIRECTOR OF BUSINESS AND OPERATIONS USD #470. 1 ... repair of any additional

9

6. Confirming, after completion of the work based on his observations and tests, that he has observed no application procedures in conflict with the specifications other than those that may have been previously reported. Final payment will not be released until his confirmation has been received by the Owner.

The presence and activities of the material manufacturer's field representative shall in no way relieve the Contractor of his contractual responsibilities. In the event of a dispute, the Owner's representative shall have final authority.

Noncompliance with the terms of this specification and ensuing contract can result in either the cancellation of the contract or complete replacement of the defective areas at the Contractor's expense. In the event of cancellation, the Owner will not be obligated to compensate the Contractor for any work undertaken. Furthermore, damages caused by water infiltration resulting from the failure of the Contractor to secure each day's work in a watertight manner, will be corrected at the Contractor's expense. Included as damages will be all labor costs incurred by the Owner as a result of such water infiltration.

TAXES (this project is tax exempt)

Except where tax exempt status exists, the Contractor shall pay all sales and use taxes, and shall pay all social security taxes, unemployment taxes and withholding taxes, and any other state, federal, and municipal requirements as directed by the governing bodies with regard to the project delivery site.

PERMITS

The Contractor shall obtain and pay for all permits, licenses, certificates, inspection, and other legal fees required, both permanent and temporary.

TEMPORARY UTILITIES

Contractor shall use at the Owner's expense, any existing electricity, lighting, water and other utilities necessary for construction purposes.

Page 11: REQUEST FOR PROPOSAL (RFP) / PROJECT MANUAL · REQUEST FOR PROPOSAL (RFP) / PROJECT MANUAL WILL PFANNENSTIEL DIRECTOR OF BUSINESS AND OPERATIONS USD #470. 1 ... repair of any additional

10

BID SUBMITTAL INSTRUCTIONS

Preparation / Submission of the Bid

Each bid delivered must be submitted with the following documents:

1. 5% Bid Bond 2. Proposal Bid Form

Bearing on the outside of each envelope must clearly state the name of the bidder with his/her address.

If forwarded by mail, the sealed envelopes containing the qualification statement and bid must be enclosed in another envelope and addressed to:

Will Pfannenstiel Director of Business and Operations

2545 Greenway

Arkansas City, KS 67005

Bids Due

At the time of the bid submission, each bidder will be presumed to have inspected the site and to have read and be thoroughly familiar with the Contract Documents. The failure or omission of any bidder to examine any form, instrument or document shall in no way relieve the bidder from any obligation in respect to this bid.

All bids are due on:

Page 12: REQUEST FOR PROPOSAL (RFP) / PROJECT MANUAL · REQUEST FOR PROPOSAL (RFP) / PROJECT MANUAL WILL PFANNENSTIEL DIRECTOR OF BUSINESS AND OPERATIONS USD #470. 1 ... repair of any additional

11

Page 13: REQUEST FOR PROPOSAL (RFP) / PROJECT MANUAL · REQUEST FOR PROPOSAL (RFP) / PROJECT MANUAL WILL PFANNENSTIEL DIRECTOR OF BUSINESS AND OPERATIONS USD #470. 1 ... repair of any additional

SCOPE OF WORK (abbreviated)

ROOF REPAIR & RESTORATION OF EXISTING METAL ROOF

Arkansas City USD #470 Transportation Building

CPR METAL RESTORATION

ROOF FIELD – HORIZONTAL SURFACES

1. Preparation (Field):

2. Clean every surface to be coated per manufacturers recommendation (Simple Green and

pressure washer).

3. Fasteners: tighten ALL existing fasteners, replace ANY loose fasteners with wider diameter

fasteners and neoprene washers.

4. Apply Rust-Go primer at any surface where rust was present and removed.

5. Seal (fully encapsulate) ALL fasteners with Garland Tuff Stuff urethane sealant (allow to cure).

6. Seams: seal all panel rib seams, panel to rake seams, and butt-end lap seams with Unibond ST

tape (4” minimum).

7. Application of CPR Seam Sealer: Install CPR Seam Sealer to all seams where Unibond ST was

installed, extend CPR Seam Sealer a minimum of 2” beyond the Unibond ST.

8. Coating Application: Blow dust off surface. Apply full field coats of CPR Base Coat and Top Coat

at manufacturers recommendation, allowing each coat to cure a minimum of 24 hours between

applications.

ROOF WALL – VERTICAL SURFACES

1. No Roof Wall Coating Scope

LOWER KICKOUT ROOF SECTION (Section B per drawing sheet 1, Fiberglass Panel)

1. No Restoration or Coating Scope

APPLICATION GUIDE ATTACHED

Page 14: REQUEST FOR PROPOSAL (RFP) / PROJECT MANUAL · REQUEST FOR PROPOSAL (RFP) / PROJECT MANUAL WILL PFANNENSTIEL DIRECTOR OF BUSINESS AND OPERATIONS USD #470. 1 ... repair of any additional

07563-1

SECTION 07 56 3 FLUID APPLIED ROOFING RESTORATION

PART 1 GENERAL

1.1 SECTION INCLUDES

A. Metal Surface Roof Restoration (1.4)(2.2)

B. Accessories (2.3)

1.2 Related Sections:

A. Section 072218 – Preparation for Re-roofing

B. Section 076200 – Sheet Metal Flashing and Trim

C. Section 079200 – Joint Sealants

1.3 REFERENCES

A. ASTM C 92 - Standard Test Methods for Sieve Analysis and Water Content of Refractory Materials.

B. ASTM C 920 - Standard Specification for Elastomeric Joint Sealants.

C. ASTM C 1250 - Standard Test Method for Nonvolatile Content of Cold Liquid-Applied Elastomeric Waterproofing Membranes.

D. ASTM D 92 - Standard Test Method for Flash and Fire Points by Cleveland Open Cup Tester.

E. ASTM D 93 - Standard Test Methods for Flash Point by Pensky-Martens Closed Cup Tester.

F. ASTM D 412 - Standard Test Methods for Vulcanized Rubber and Thermoplastic Elastomers-Tension.

G. ASTM D 562 - Standard Test Method for Consistency of Paints Measuring Krebs Unit (KU) Viscosity Using a Stormer-Type Viscometer.

H. ASTM D 624 - Standard Test Method for Tear Strength of Conventional Vulcanized Rubber and Thermoplastic Elastomers

I. ASTM D 816 - Standard Test Methods for Rubber Cements.

J. ASTM D 1002 - Standard Test Method for Apparent Shear Strength of Single-Lap-Joint Adhesively Bonded Metal Specimens by Tension Loading (Metal-to-Metal).

K. ASTM D 1475 - Standard Test Method For Density of Liquid Coatings, Inks, and Related Products.

Page 15: REQUEST FOR PROPOSAL (RFP) / PROJECT MANUAL · REQUEST FOR PROPOSAL (RFP) / PROJECT MANUAL WILL PFANNENSTIEL DIRECTOR OF BUSINESS AND OPERATIONS USD #470. 1 ... repair of any additional

07563-2

L. ASTM D 1876 - Standard Test Method for Peel Resistance of Adhesives (T-Peel Test).

M. ASTM D 2042 - Standard Test Method for Solubility of Asphalt Materials in Trichloroethylene.

N. ASTM D 2196 - Standard Test Methods for Rheological Properties of Non-Newtonian Materials by Rotational (Brookfield type) Viscometer.

O. ASTM D 2240 - Standard Test Method for Rubber Property-Durometer Hardness.

P. ASTM D 2369 - Standard Test Method for Volatile Content of Coatings.

Q. ASTM D 3111 - Standard Test Method for Flexibility Determination of Hot-Melt Adhesives by Mandrel Bend Test Method.

R. ASTM D 3960 - Standard Practice for Determining Volatile Organic Compound (VOC) Content of Paints and Related Coatings.

S. ASTM D 4209 - Standard Practice for Determining Volatile and Nonvolatile Content of Cellulosics, Emulsions, Resin Solutions, Shellac, and Varnishes.

T. ASTM D 4212 - Standard Test Method for Viscosity by Dip-Type Viscosity Cups.

U. ASTM D 5040 - Standard Test Methods for Ash Content of Adhesives.

V. ASTM D 5420 - Standard Test Method for Impact Resistance of Flat, Rigid Plastic Specimen by Means of a Striker Impacted by a Falling Weight (Gardner Impact).

W. ASTM E 1980 - Standard Practice for Calculating Solar Reflectance Index of Horizontal and Low-Sloped Opaque Surfaces

X. ASTM G 21 - Standard Practice for Determining Resistance of Synthetic Polymeric Materials to Fungi.

Y. SRI - Solar Reflectance Index calculated according to ASTM E 1980.

Z. South Coast AQMD Standards.

AA. SMACNA Architectural Sheet Metal Manual.

BB. ANSI/SPRI ES-1 - Testing and Certification Listing of Shop Fabricated Edge Metal

CC. National Roofing Contractors Association (NRCA) - Roofing and Waterproofing Manual.

1.4 SYSTEM DESCRIPTION

A. Metal Surface Roof Restoration: Renovation work includes: 1. Surface preparation: Remove loose flaking rust, dust, dirt, debris, secure all gaped

panels and replace all loose fasteners with next size larger. 2. Metal Panel Sections: Repair/Replace damaged metal panel sections 3. Primer: Spot prime rusted areas only. 4. Preparation: Apply Tuff Stuff or Greenlock Sealant XL over all fasteners, install

Unibond ST (4” minimum) to all seams, apply CPR Seam Sealer on seams (over Unibond ST), fasteners and around penetrations

5. Base Coat: Apply CPR Base Coat over entire roof surface 6. Top Coat: Apply CPR White over entire roof surface

1.5 SUBMITTALS

Page 16: REQUEST FOR PROPOSAL (RFP) / PROJECT MANUAL · REQUEST FOR PROPOSAL (RFP) / PROJECT MANUAL WILL PFANNENSTIEL DIRECTOR OF BUSINESS AND OPERATIONS USD #470. 1 ... repair of any additional

07563-3

A. Product Data: Manufacturer's data sheets on each product to be used, including: 1. Preparation instructions and recommendations. 2. Storage and handling requirements and recommendations. 3. Installation methods.

B. Shop Drawings: Submit shop drawings including installation details of roofing, flashing, fastening, insulation and vapor barrier, including notation of roof slopes and fastening patterns of insulation and base modified bitumen membrane, prior to job start.

C. Verification Samples: For each product specified, two samples, minimum size 6 inches (150 mm) square, representing actual product, and color.

D. Manufacturer's Certificates: Certify products meet or exceed specified requirements.

E. Closeout Submittals: Provide manufacturer's maintenance instructions that include recommendations for periodic inspection and maintenance of all completed roofing work. Provide product warranty executed by the manufacturer. Assist Owner in preparation and submittal of roof installation acceptance certification as may be necessary in connection with fire and extended coverage insurance on roofing and associated work.

1.6 QUALITY ASSURANCE

A. Perform Work in accordance with NRCA Roofing and Waterproofing Manual.

B. Manufacturer Qualifications: Manufacturer: Company specializing in manufacturing products specified in this section with documented ISO 9001 certification and minimum twelve years and experience.

C. Installer Qualifications: Company specializing in performing Work of this section with minimum five years documented experience and a certified Pre-Approved Garland Contractor.

D. Installer's Field Supervision: Maintain a full-time Supervisor/Foreman on job site during all phases of roofing work while roofing work is in progress.

E. Product Certification: Provide manufacturer's certification that materials are manufactured in the United States and conform to requirements specified herein, are chemically and physically compatible with each other, and are suitable for inclusion within the total roof system specified herein.

F. Source Limitations: Obtain all components of roof system from a single manufacturer. Secondary products that are required shall be recommended and approved in writing by the roofing system Manufacturer. Upon request of the Owner, submit Manufacturer's written approval of secondary components in list form, signed by an authorized agent of the Manufacturer.

1.7 PRE-INSTALLATION CONFERENCE

A. Convene a pre-roofing conference approximately two weeks before scheduled commencement of roofing system installation and associated work.

B. Require attendance of installers of deck or substrate construction to receive roofing, installers of rooftop units and other work in and around roofing which must precede or follow roofing work including mechanical work, Owner, roofing system manufacturer's representative.

C. Objectives include: 1. Review foreseeable methods and procedures related to roofing work, including set up

Page 17: REQUEST FOR PROPOSAL (RFP) / PROJECT MANUAL · REQUEST FOR PROPOSAL (RFP) / PROJECT MANUAL WILL PFANNENSTIEL DIRECTOR OF BUSINESS AND OPERATIONS USD #470. 1 ... repair of any additional

07563-4

and mobilization areas for stored material and work area. 2. Tour representative areas of roofing substrates, inspect and discuss condition of

substrate, roof drains, curbs, penetrations and other preparatory work. 3. Review roofing system requirements, Drawings, Specifications and other Contract

Documents. 4. Review and finalize schedule related to roofing work and verify availability of

materials, installer's personnel, equipment and facilities needed to make progress and avoid delays.

5. Review required inspection, testing, certifying procedures. 6. Review weather and forecasted weather conditions and procedures for coping with

unfavorable conditions, including possibility of temporary roofing. 7. Record conference including decisions and agreements reached. Furnish a copy of

records to each party attending.

1.8 DELIVERY, STORAGE, AND HANDLING

A. Deliver and store products in manufacturer's unopened packaging with labels intact until ready for installation.

B. Store all roofing materials in a dry place, on pallets or raised platforms, out of direct exposure to the elements until time of application. Store materials at least 4 inches above ground level and covered with "breathable" tarpaulins.

C. Stored in accordance with the instructions of the manufacturer prior to their application or installation. Store roll goods on end on a clean flat surface. No wet or damaged materials will be used in the application.

D. Store at room temperature wherever possible, until immediately prior to installing the roll. During winter, store materials in a heated location with a 50 degree F (10 degree C) minimum temperature, removed only as needed for immediate use. Keep materials away from open flame or welding sparks.

E. Avoid stockpiling of materials on roofs without first obtaining acceptance from the Owner/Engineer.

F. Adhesive storage shall be between the range of above 50 degree F (10 degree C) and below 80 degree F (27 degree C). Area of storage shall be constructed for flammable storage.

1.9 PROJECT CONDITIONS

A. Maintain environmental conditions (temperature, humidity, and ventilation) within limits recommended by manufacturer for optimum results. Do not install products under environmental conditions outside manufacturer's absolute limits.

B. Weather Condition Limitations: Do not apply roofing system during inclement weather or when a 30 percent chance of precipitation or greater is expected.

C. Proceed with roofing work only when existing and forecasted weather conditions will permit unit of work to be installed in accordance with manufacturer's recommendations and warranty requirements.

D. Do not expose materials vulnerable to water or sun damage in quantities greater than can be weatherproofed during same day.

E. When applying materials with spray equipment, take precautions to prevent over spray and/or solvents from damaging or defacing surrounding walls, building surfaces, vehicles or other property. Care should be taken to do the following:

Page 18: REQUEST FOR PROPOSAL (RFP) / PROJECT MANUAL · REQUEST FOR PROPOSAL (RFP) / PROJECT MANUAL WILL PFANNENSTIEL DIRECTOR OF BUSINESS AND OPERATIONS USD #470. 1 ... repair of any additional

07563-5

1. Close air intakes into the building. 2. Have a dry chemical fire extinguisher available at the jobsite. 3. Post and enforce "No Smoking" signs.

F. Avoid inhaling spray mist; take precautions to ensure adequate ventilation.

G. Protect completed roof sections from foot traffic for a period of at least 48 hours at 75 degrees F (24 degrees C) and 50 percent relative humidity or until fully cured.

H. Take precautions to ensure that materials do not freeze.

I. Minimum temperature for application is 40 degrees F (4 degrees C) and rising for solvent based materials.

1.10 WARRANTY

A. Upon completion of the work, provide the Manufacturer's written and signed limited labor and materials Warranty, warranting that, if a leak develops in the roof during the term of this warranty, due either to defective material or defective workmanship by the installing contractor, the manufacturer shall provide the Owner, at the Manufacturer's expense, with the labor and material necessary to return the defective area to a watertight condition. 1. Warranty Period:

a. 5 plus 5 (10 years): 5 years from date of acceptance plus 5 additional years after required inspection by Garland.

B. Installer is to guarantee all work against defects in materials and workmanship for a period indicated following final acceptance of the Work. 1. Warranty Period:

a. 2 years from date of acceptance.

PART 2 PRODUCTS

2.1 MANUFACTURERS

A. Acceptable Manufacturer: Garland Company, Inc. (The), which is located at: 3800 E. 91st St.; Cleveland, OH 44105; Toll Free Tel: 800-321-9336; Tel: 216-641-7500; Fax: 216-641-0633; Email: [email protected] or Search: www.garlandind.com

B. Requests for substitutions will be considered in accordance with provisions of the specification.

C. The Products specified are intended and the Standard of Quality for the products required for this project. If other products are proposed the bidder must disclose in the bid the manufacturer and the products that they intend to use on the Project and the Manufacturer must meet the parameters listed below. If no manufacturer and products are listed, the bid may be accepted only with the use of products specified. 1. Bidder will not be allowed to change materials after the bid opening date. 2. If alternate products are included in the bid, the products must be equal to or exceed

the products specified. Supporting technical data shall be submitted to the Owner for approval prior to acceptance.

3. In making a request for substitution, the Bidder/Roofing Contractor represents that it has: a. Personally investigated the proposed product or method, and determined that it

is equal or superior in all respects to that specified. b. Will provide the same guarantee for substitution as for the product and method

specified.

Page 19: REQUEST FOR PROPOSAL (RFP) / PROJECT MANUAL · REQUEST FOR PROPOSAL (RFP) / PROJECT MANUAL WILL PFANNENSTIEL DIRECTOR OF BUSINESS AND OPERATIONS USD #470. 1 ... repair of any additional

07563-6

c. Will document that a Full-Time employee of the Manufacturer will be onsite a minimum of 2 days per week during the application of the restoration coating to verify substrate cleanliness, approve preparation of substrate, fasteners and seams, verify application rates, and approve of weather conditions and temperature ranges. Verification to be delivered to the Owner via weekly Progress Reports including photos and captions.

d. Will coordinate installation of accepted substitution in work, making such changes as may be required for work to be completed in all respects.

e. Will waive all claims for additional cost related to substitution, which consequently become apparent.

f. Cost data is complete and includes all related cost under his/her contract or other contracts, which may be affected by the substitution.

g. Will reimburse the Owner for any/all redesign costs that may arise for accommodation of the substitution.

4. Owner reserves the right to be the final authority on the acceptance or rejection of any or all bids, proposed alternate roofing systems or materials that has met ALL specified requirement criteria.

5. Failure to submit substitution package, or any portion thereof requested, will result in immediate disqualification and consideration for that particular contractors request for manufacturer substitution.

2.2 ROOF RESTORATION SYSTEM FOR METAL SURFACE ROOFS

A. Cold Applied CPR System: 1. Primer: Rust-Go Primer: 2. Coating: CPR Base Coat/ CPR White: 3. Flashing: CPR Seam Sealer on seams and penetrations. 4. Reinforcement: Applied on seams and penetrations only.

a. Unibond ST (peel and stick primer/tape) 5. Surfacing: None

2.3 ACCESSORIES:

A. Fasteners: Non-ferrous metal or galvanized steel, except aluminum or stainless steel nails shall be used with aluminum; Fasteners shall be self-clinching type of penetrating type as recommended by the coating manufacturer. Fasten fasteners with neoprene washers and take care to not strip the hole created with fastening.

B. Urethane Sealant - Tuff-Stuff: One part, non-sag sealant as approved and furnished by the membrane manufacturer for moving joints. 1. Tensile Strength, ASTM D 412: 250 psi 2. Elongation, ASTM D 412: 950% 3. Hardness, Shore A ASTM C 920: 35 4. Adhesion-in-Peel, ASTM C 92: 30 pli

2.4 EDGE TREATMENT AND ROOF PENETRATION FLASHINGS

A. Fabricated Flashings: 1. Fabricated flashings and trim shall conform to the detail requirements of SMACNA

"Architectural Sheet Metal Manual" and/or the CDA Copper Development Association "Copper in Architecture - Handbook" and/or the NRCA "Roofing and Waterproofing Manual" as applicable.

PART 3 EXECUTION

3.1 EXAMINATION

Page 20: REQUEST FOR PROPOSAL (RFP) / PROJECT MANUAL · REQUEST FOR PROPOSAL (RFP) / PROJECT MANUAL WILL PFANNENSTIEL DIRECTOR OF BUSINESS AND OPERATIONS USD #470. 1 ... repair of any additional

07563-7

A. Do not begin installation until substrates have been properly prepared.

B. Verify that work penetrating the roof deck, or which may otherwise affect the roofing, has been properly completed.

C. If substrate preparation is the responsibility of another installer, notify Owner of unsatisfactory preparation before proceeding.

3.2 ROOF PREPARATION AND REPAIR

A. General: 1. Repair/replace (in-kind) any sections of damaged panels and secure with drill point

fasteners with neoprene washers. 2. Existing roof surfaces shall be primed in rusting areas as necessary and allowed to

dry prior to installing the roofing system.

B. Prepare surfaces using the methods recommended by the manufacturer for achieving the best result for the substrate under the project conditions.

C. Repair all defects such as deteriorated roof decks; replace loose or brittle metal panels. Verify that exiting conditions meet the following requirements: 1. Application of roofing materials over a brittle metal panel is not recommended.

D. Remove all loose dirt and foreign debris from the roof surface. Do not damage roof membrane in cleaning process.

E. Clean and seal all metal seams where necessary. Seal watertight all fasteners and penetrations where water could enter the building envelope.

F. Clean the entire roof surface by removing all dirt, algae, paint, oil, talc, rust or foreign substance. Use a 10 percent solution of TSP (tri-sodium phosphate), Simple Green and warm water. Scrub heavily soiled areas with a brush. Rinse with fresh water to remove all TSP solution. Allow roof to dry thoroughly before continuing.

G. Repair existing roof membrane as necessary to provide a sound substrate for the liquid membrane. All surface defects (cracks, blisters, tears) must be repaired with similar materials.

H. Pre-Treatment of Known Growth - General Surfaces: Once areas of moss, mold, algae and other fungal growths or vegetation have been removed and surfaces have also been thoroughly cleaned, apply a biocide wash at a maximum spread rate of 0.2 gallons/square (0.08 liters/m), to guard against subsequent infection. Allow to dry onto absorbent surfaces before continuing with the application. On non-absorbent surfaces, allow to react before thoroughly rinsing to remove all traces of the solution.

I. Power washing of metal roof surfaces to remove all loose rust or scale is mandatory before application. Use a high volume air broom or compressed air to remove residual dust rust perforations, etc. Deteriorated metal roof decks must be repaired or replaced prior to the application of the coating system.

3.3 INSTALLATION

A. General Installation Requirements: 1. Install in accordance with manufacturer's instructions. Apply to minimum coating

thickness required by the manufacturer. 2. Cooperate with manufacturer, inspection and test agencies engaged or required to

perform services in connection with installing the roof system. 3. Insurance/Code Compliance: Where required by code, install and test the roofing

Page 21: REQUEST FOR PROPOSAL (RFP) / PROJECT MANUAL · REQUEST FOR PROPOSAL (RFP) / PROJECT MANUAL WILL PFANNENSTIEL DIRECTOR OF BUSINESS AND OPERATIONS USD #470. 1 ... repair of any additional

07563-8

system to comply with governing regulation and specified insurance requirements. 4. Protect work from spillage of roofing materials and prevent materials from entering or

clogging drains and conductors. Replace or restore work damaged by installation of the roofing system.

5. All primers must be top coated within 24 hours of application. Re-prime If more time passes after priming.

6. Keep roofing materials dry during application. Phased construction can be allowed as long as no, more than 7 days pass between coats excluding primers.

7. Coordinate counter flashing, cap flashings, expansion joints and similar work with work specified in other Sections under Related Work.

8. Coordinate roof accessories and miscellaneous sheet metal accessory items, including piping vents and other devices with work specified in other Sections under Related Work.

B. Metal Surface Roof Restoration: Renovation work includes: 1. Surface Preparation: Remove loose flaking rust, dust, dirt, debris, secure all gaped

panels and replace all loose fasteners with next size larger. a. Remove rust by the most rigorous method suitable for the particular project and

as approved by Garland. b. Tighten all fasteners and verify that neoprene washers are in place. c. Replace missing fasteners using oversize fasteners as necessary. d. Seal all fastener heads by applying a heavy dab of compatible sealant to the

tops and around of all fastener heads. 1) Tuff Stuff or Greenlock Sealant XL

2. Flashings: Repair/Replace metal panels 3. Primer:

a. Immediately after rust has been removed, apply Rust-Go Primer rust inhibitive primer over properly prepped rusted areas only at 1/4 gallon per 100 SF.

4. Reinforcement: a. Apply Unibond ST tape to all panel and butt end seams

1) Use care to lay the Tape tight to the roof surface without air pockets, wrinkles, fishmouths, etc.

b. Application of CPR Seam Sealer on all seams and extending a minimum of 1” beyond Unibond ST: 1) Verify that the surface to be coated is properly prepared. 2) Restore the surface to a suitable condition if roof surface becomes

contaminated with dirt, dust or other materials that will interfere with adhesion of the coatings.

3) Apply materials at specified dry film thickness. 4) Apply CPR Seam Sealer to field seams, fasteners and around

penetrations as required. 5) Allow to dry for a minimum of 24 hours before applying finish coats.

5. Coating: a. Use special attention to coating flashings and other critical areas to build

adequate membrane thickness. b. Use multiple coats on verticals to prevent sagging. c. Apply to Garland's minimum membrane thickness over the entire roof surface. d. Base Material: Apply CPR Base Coat in a uniform manner at 1.5 gallons per

100 SF over the entire roof surface. 1) Allow to dry for a minimum of 24 hours before applying finish coats.

e. Cap Material: Apply CPR White in a uniform manner at 1.5 gallons per 100 SF over the entire roof surface.

f. Use special attention to coating flashings and other critical areas to build adequate membrane thickness.

g. Use multiple coats on verticals to prevent sagging. h. Apply to minimum recommended membrane thickness over the entire roof

Page 22: REQUEST FOR PROPOSAL (RFP) / PROJECT MANUAL · REQUEST FOR PROPOSAL (RFP) / PROJECT MANUAL WILL PFANNENSTIEL DIRECTOR OF BUSINESS AND OPERATIONS USD #470. 1 ... repair of any additional

07563-9

surface.

3.4 CLEANING

A. Clean-up and remove daily from the site all wrappings, empty containers, paper, loose particles and other debris resulting from these operations.

B. Remove markings from finished surfaces.

C. Repair or replace defaced or disfigured finishes caused by Work of this section.

3.5 PROTECTION

A. Provide traffic ways, erect barriers, fences, guards, rails, enclosures, chutes and the like to protect personnel, roofs and structures, vehicles and utilities.

B. Protect exposed surfaces of finished walls with tarps to prevent damage.

3.6 FIELD QUALITY CONTROL

A. Require attendance of roofing materials manufacturers' representatives at site during installation of the roofing system.

B. Correct defects or irregularities discovered during field inspection.

3.7 FINAL INSPECTION

A. At completion of roofing installation and associated work, meet with Contractor, installer, installer of associated work, roofing system manufacturer's representative and others directly concerned with performance of roofing system.

B. Walk roof surface areas, inspect perimeter building edges as well as flashing of roof penetrations, walls, curbs and other equipment. Identify all items requiring correction or completion and furnish copy of list to each party in attendance.

C. Repair or replace deteriorated or defective work found at time above inspection as required to a produce an installation that is free of damage and deterioration at time of Substantial Completion and according to warranty requirements.

D. Following the final inspection, provide written notice of acceptance of the installation from the roofing system manufacturer.

3.8 PROTECTION

A. Protect installed products until completion of project.

B. Touch-up, repair or replace damaged products before Substantial Completion.

3.9 SCHEDULES

A. Coatings: 1. Coating: CPR White: Highly reflective multi- purpose, single-component solvent based

SEBS, liquid waterproofing membrane. a. Tensile Strength: ASTM D 412, 200 psi b. Elongation: ASTM D 412, 200% c. Density @ 77 degrees F (25 degrees C, ASTM D 1475) 9.0 lb./gal d. Flash Point: ASTM D 93, 105 degrees F min. (40.6 degrees C) e. Non-Volatile: ASTM D 1644, Typical 75%

Page 23: REQUEST FOR PROPOSAL (RFP) / PROJECT MANUAL · REQUEST FOR PROPOSAL (RFP) / PROJECT MANUAL WILL PFANNENSTIEL DIRECTOR OF BUSINESS AND OPERATIONS USD #470. 1 ... repair of any additional

07563-10

f. VOC: 430 g/l g. Reflectance: 0.77 h. Emittance: 0.86 i. SRI: 95

2. Coating: CPR Base Coat: Multi- purpose, single-component solvent based SEBS, liquid waterproofing membrane. a. Tensile Strength: ASTM D 412, 200 psi b. Elongation: ASTM D 412, 200% c. Density @ 77 degrees F (25 degrees C, ASTM D 1475) 9.0 lb./gal d. Flash Point: ASTM D 93, 105 degrees F min. (40.6 degrees C) e. Non-Volatile: ASTM D 1644, Typical 75% f. VOC: 400 g/l

3. Coating: CPR Seam Sealer BG: Brush grade multi- purpose, single-component solvent based SEBS, liquid waterproofing sealer for details on a metal roof system. a. Tensile Strength: ASTM D 412, 200 psi b. Elongation: ASTM D 412, 200% c. Density @ 77 degrees F (25 degrees C, ASTM D 1475) 9.12 lb./gal d. Flash Point: ASTM D 93, 105 degrees F min. (40.6 degrees C) e. Non-Volatile: ASTM D 1644, Typical 75% f. VOC: 420 g/l

4. Coating: CPR Seam Sealer TG: Trowel grade multi- purpose, single-component solvent based SEBS, liquid waterproofing sealer for details on a metal roof system. a. Tensile Strength: ASTM D 412, 600 psi b. Elongation: ASTM D 412, 400% c. Density @ 77 degrees F (25 degrees C, ASTM D 1475) 8.9 lb./gal d. Flash Point: ASTM D 93, 105 degrees F min. (40.6 degrees C) e. Non-Volatile: ASTM D 1644, Typical 60% f. VOC: 300 g/l

5. Reinforcement: Unibond ST: high performance, fatigue resistant, self-priming, 100% solids tape used to seal seams on a metal roof system. a. Tensile Strength: 4,500 psi b. Elongation: 500% c. Low Temperature Flexibility: -70 degrees F

END OF SECTION