Real Estate (Regulation & Development) Act, 2016...
Transcript of Real Estate (Regulation & Development) Act, 2016...
Real Estate (Regulation &
Development) Act, 2016
(RERA)
EXPLAINED BY MILIND DESHPANDE
What we shall see today ?
TerminologiesDuties of a
Promoter
Penalties for an
offence
Revocation of
the registration
Conveyance
What is the
final message
that RERA
gives us ?
It asks us to
DELIVER
It asks us to
DELIVER in time
It asks us to
DELIVER as
promised
If you don’t
deliver
Compensation
PenaltyInterest
Refund
Terminologies -
Real Estate Project –
Development of a building / apartments
Developing existing building into apartments
Development of land into plots or apartments
But only for the purpose of selling all or some of them
Shall include common areas & all development works
Co - Promoter –
Means and includes any person(s) or organisation(s)
who, under any agreement or arrangement with the
Promoter of a Real Estate Project is allotted to or
entitled to a share of total revenue generated from the
sale of apartments or share of total area developed in
the real estate project.
Terminologies -
Carpet Area –
Carpet area is basically the net usable area of an
apartment. Hence it should be calculated from
skirting to skirting
It does not include the area under the external walls,
areas under service shafts, exclusive balcony,
veranda or an exclusive (attached or overhead)
open terrace
It however includes area under the internal partition
walls but shall exclude the area under structural
columns on the external walls & the internal partition
walls
Terminologies -
Covered Parking Space –
Enclosed or covered area as approved by the Competent
Authority as per the applicable DCR for the parking of
vehicles of the allottees which may be provided in basements
and / or stilt and / or podium and / or parking provided by
mechanised parking arrangements and but shall not include
a garage and / or open parking.
Terminologies -
Phase of a Real Estate Project –
May consist of a building or a wing of
the building in case of building with
multiple wings or defined number of
floors in a multi-storeyed building /
wing. (This will not include land)
Terminologies -
Complainant –
Is any aggrieved person having any interest in the
project and includes an association of allottees and
voluntary organisation registered under any law
Terminologies -
Obligations -
Each project needs to be registered with
MAHARERA before advertisement,
promotion, selling etc. Ongoing projects
can be registered anytime up to 31st July
2017
Submit all the information associated
with the project to the MAHARERA
and get registration ID
Obligations -
The authority shall issue a Login ID &
Password to create a Webpage on
MAHARERA website
www.maharera.mahaonline.gov.in
Once created this webpage needs
to be updated every quarter
disclosing no of apartments booked
and status of the project
Obligations -
No misleading or
false advertisement
Advertisement can be an email, print ad,
whatsapp message, the Model flat on the
site or publicity of any nature
In case of false or misleading
content of advertisement
Obligations -
The allottee can continue the
booking but claim compensation
He can cancel his booking and claim
refund along with interest &
compensation
The Authority can impose
penalty on the Promoter for
providing false information
• SBI MCLR + 2%Rate of
Interest
• Within 30 days
along with
compensation &
interest
Refund
Obligations -
Prominently display the
Authority’s website address and
the Registration ID obtained, in
all the advertisement material
Provide all the documents like
sanctioned plan, layout plan,
specification, stage wise
schedule of construction etc at
the time of booking
Obligations -Agreement for Sale
Promoter shall not accept an amount more than 10% of the cost
of apartment without registering the Agreement for Sale which
shall contain
Particulars of
development of
the project
SpecificationsInternal & External
developments
Dates & manner of
paymentDate of possession
Interest rate for
allottee & Promoter
When an allottee pays you
Obligations -
Keep 70% of the amount received
in a separate bank account
Withdraw the amounts from this
account only when they are certified
by Architect, Engineer & CA
Use it only for the purpose
of the development of the
project
Obtain a certificate from the
statutory auditor stating that the
amount withdrawn
At the end of financial year
Has been utilised for the
same project
Has been in proportion
to the percentage of
completion of the
project
Obligations -
Obligations -
Not to make any
changes with respect
to the apartment
without prior written
consent of the allottee Not to transfer majority
of the rights & liabilities
to any other person
without prior written
consent of 2/3rd of the
allottee
Not to make any
alterations or additions
in layout plan or
specifications without
prior written consent of
2/3rd of the allottee
If the proposed plans /
specifications are disclosed in an
agreement with the allottee which
is executed before the registration
of the project
No Consent is
required
for any modifications in the
sanctioned plans, layout plans and
specifications of the building or
common areas, that is directed by
the competent authority.
No Consent is
required
Consent of 2/3rd allottees for any
change in plans, specifications
Consent
Promoter
Obtain Occupancy /
Completion / Lease
Certificate
Make it available to
the allottee
Provide & maintain
essential services till
the project is handed
over to the society
Obligations -
Form a society or
association of
apartments
Execute the
conveyance in favour of
the society or individual
allottees
Obligations -
Defect liability for 5 years from the
date of possession
The possession date can be different
for buildings and common areas.
Hence the defect liability period also
shall change accordingly
Penalties -
Sells without obtaining
registration with
MAHARERA
Up to 10% of the project cost
In case he continues to do
so even after imposing
penalty
imprisonment up to three
hears or with a fine up to 10%
of the project cost or both
Penalties -
Provides false information for
registration or contravenes any
provision of section 4
Up to 5% of the project
cost
If the promoter contravenes
any other provision of the act,
rules or regulations
Up to 5% of the project
cost
Penalties -
Fails to comply with or
contravenes with any of the
directions of the Authority
Penalty for each day –
maximum up to 5% of the
project cost
If the promoter ails to comply
with or contravenes any of the
directions issued by Appellate
Tribunal
Penalty for each day –
maximum up to 10% of the
project cost
Compounding of
Offences by Court
Minimum 5% of the estimated cost of the project, which may be
extended up to 10%
No further proceedings
shall be taken against
the accused
If any proceedings are
already initiated, the
they shall stand abated
If the accused is
already in custody, he
shall be discharged
Revocation of registration-
Fails to comply with any of the above
obligations r violates the terms of the
approval
Falsely represents that the services
are of a particular standard
Indulges into fraudulent practices
After
Revocation
of
registration-
Debar the promoter
from accessing the
MAHARERA website for
that project
Specify his name n the
list of defaulters and
display his photograph
on its website
Develop the project
with consultation of
state govt
Inform the RERA of
other states & Union
Territories
Freeze the bank
account where the
70% amount was
deposited
If no period is agreed
Conveyance
Single building
Society / entity to be formed
within 3 months from the date on
which 51% units are booked
Conveyance in 3 months from
the date of OC or date on
which 51% of the allottees pay
100% consideration, whichever
is earlier
Society / entity to be formed within 3
months from the date on which 51% units
are booked
If no period is agreed
Apex Body / Federation to be formed
within 3 months from the date on
which OC for the last building is
issued.
Conveyance of building to be done
within 1 month from the society
formation or 3 months from the date
of OC, whichever is earlier
Conveyance of land to be done within
3 month from the Apex Body formation
or the date of OC of the last building,
whichever is earlier
Conveyance
Layout of
buildings
Completion of the project under RERA shall mean –
Completing the entire construction of the project / phase,
Obtaining the OC, handing over the possession,
Formation of the society / association of apartments,
Conveyance,
Completion of all the amenities
Handing over of all title documents, approvals, Insurance papers etc
In general fulfilment of each obligation under RERA.
All such obligations shall be required to be fulfilled before the registration
expires
Milind Deshpande