Re-Order Point Problems Set 1: General. 2 Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety...

28
Re-Order Point Problems Set 1: General

Transcript of Re-Order Point Problems Set 1: General. 2 Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety...

Page 1: Re-Order Point Problems Set 1: General. 2 Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory Notations.

Re-Order Point Problems Set 1: General

Page 2: Re-Order Point Problems Set 1: General. 2 Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory Notations.

2Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory

Notations

L

R

LTD

L

L

R

R

ROP

Isafety

LTD

LTD

:Time Lead of Dev. Std.

:Time Lead Average

:Time Lead

:Demand of Dev. Std.

:Demand Average

:periodper Demand

:PointReorder

:StockSafety

:Demand Time Lead Dev. Std.

:Demand Time Lead Average

:Demand Time Lead LTD

R

L

Page 3: Re-Order Point Problems Set 1: General. 2 Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory Notations.

3Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory

ROP Problemsa) If average demand per day is 20 units and lead time is

10 days. Assuming zero safety stock. Isafety=0, compute ROP.

b) If average demand per day is 20 units and lead time is 10 days. Assuming 70 units of safety stock. Isafety=70, compute ROP?

c) If average demand during the lead time is 200 and standard deviation of demand during lead time is 25. Compute ROP at 90% service level. Compute safety stock.

d) If average demand per day is 20 units and standard deviation of daily demand is 5, and lead time is 16 days. Compute ROP at 90% service level. Compute safety stock.

e) If demand per day is 20 units and lead time is 16 days and standard deviation of lead time is 4 days. Compute ROP at 90% service level. Compute safety stock.

Page 4: Re-Order Point Problems Set 1: General. 2 Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory Notations.

4Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory

ROP; Fixed R, Fixed L, Zero Safety Stock

a) If average demand per day is 20 units and lead time is 10 days. Assuming zero safety stock.

Isafety = 0, L=10, R=20Compute ROP.

ROP = average demand during lead time + safety stock

ROP = LTD+ Isafety ROP = LTD + 0LTD = L × RLTD = 20 × 10 = 200ROP = 200

Page 5: Re-Order Point Problems Set 1: General. 2 Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory Notations.

5Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory

ROP; Fixed R, Fixed L, Isafety >0

b) If average demand per day is 20 units and lead time is 10 days. Assuming 70 units of safety stock.

Isafety = 70, L=10, R=20Compute ROP.

ROP = average demand during lead time + Safety Stock

ROP = LTD + Isafety LTD = R × L = 20 × 10 = 200Isafety = 70ROP = 200 + 70 = 270

Page 6: Re-Order Point Problems Set 1: General. 2 Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory Notations.

6Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory

ROP; total demand during lead time is variablec) If average demand during the lead time

is 200 and standard deviation of demand during lead time is 25. Compute ROP at 90% service level. Compute safety stock.

Page 7: Re-Order Point Problems Set 1: General. 2 Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory Notations.

7Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory

Safety Stock and ROP

Risk of astockout

Service level

Probability ofno stockout

Safety stock

0 z

Quantity

z-scale

Each Normal variable x is associated with a standard Normal Variable zx is Normal (Average x , Standard Deviation x) z is Normal (0,1)

Averagedemand

ROP

There is a table for z which tells us a) Given any probability of not exceeding z. What is the

value of z. b) Given any value for z. What is the probability of not

exceeding z.

Page 8: Re-Order Point Problems Set 1: General. 2 Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory Notations.

8Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory

Popular z Valuesz 0.00 0.01 0.02 0.03 0.04 0.05 0.06 0.07 0.08

0 0.5000 0.5040 0.5080 0.5120 0.5160 0.5199 0.5239 0.5279 0.53190.1 0.5398 0.5438 0.5478 0.5517 0.5557 0.5596 0.5636 0.5675 0.57140.2 0.5793 0.5832 0.5871 0.5910 0.5948 0.5987 0.6026 0.6064 0.61030.3 0.6179 0.6217 0.6255 0.6293 0.6331 0.6368 0.6406 0.6443 0.64800.4 0.6554 0.6591 0.6628 0.6664 0.6700 0.6736 0.6772 0.6808 0.68440.5 0.6915 0.6950 0.6985 0.7019 0.7054 0.7088 0.7123 0.7157 0.71900.6 0.7257 0.7291 0.7324 0.7357 0.7389 0.7422 0.7454 0.7486 0.75170.7 0.7580 0.7611 0.7642 0.7673 0.7704 0.7734 0.7764 0.7794 0.78230.8 0.7881 0.7910 0.7939 0.7967 0.7995 0.8023 0.8051 0.8078 0.81060.9 0.8159 0.8186 0.8212 0.8238 0.8264 0.8289 0.8315 0.8340 0.83651 0.8413 0.8438 0.8461 0.8485 0.8508 0.8531 0.8554 0.8577 0.85991.1 0.8643 0.8665 0.8686 0.8708 0.8729 0.8749 0.8770 0.8790 0.88101.2 0.8849 0.8869 0.8888 0.8907 0.8925 0.8944 0.8962 0.8980 0.89971.3 0.9032 0.9049 0.9066 0.9082 0.9099 0.9115 0.9131 0.9147 0.91621.4 0.9192 0.9207 0.9222 0.9236 0.9251 0.9265 0.9279 0.9292 0.93061.5 0.9332 0.9345 0.9357 0.9370 0.9382 0.9394 0.9406 0.9418 0.94291.6 0.9452 0.9463 0.9474 0.9484 0.9495 0.9505 0.9515 0.9525 0.95351.7 0.9554 0.9564 0.9573 0.9582 0.9591 0.9599 0.9608 0.9616 0.96251.8 0.9641 0.9649 0.9656 0.9664 0.9671 0.9678 0.9686 0.9693 0.96991.9 0.9713 0.9719 0.9726 0.9732 0.9738 0.9744 0.9750 0.9756 0.97612 0.9772 0.9778 0.9783 0.9788 0.9793 0.9798 0.9803 0.9808 0.98122.1 0.9821 0.9826 0.9830 0.9834 0.9838 0.9842 0.9846 0.9850 0.98542.2 0.9861 0.9864 0.9868 0.9871 0.9875 0.9878 0.9881 0.9884 0.98872.3 0.9893 0.9896 0.9898 0.9901 0.9904 0.9906 0.9909 0.9911 0.99132.4 0.9918 0.9920 0.9922 0.9925 0.9927 0.9929 0.9931 0.9932 0.99342.5 0.9938 0.9940 0.9941 0.9943 0.9945 0.9946 0.9948 0.9949 0.99512.6 0.9953 0.9955 0.9956 0.9957 0.9959 0.9960 0.9961 0.9962 0.99632.7 0.9965 0.9966 0.9967 0.9968 0.9969 0.9970 0.9971 0.9972 0.99732.8 0.9974 0.9975 0.9976 0.9977 0.9977 0.9978 0.9979 0.9979 0.99802.9 0.9981 0.9982 0.9982 0.9983 0.9984 0.9984 0.9985 0.9985 0.99863 0.9987 0.9987 0.9987 0.9988 0.9988 0.9989 0.9989 0.9989 0.9990

Risk Service level z value0.1 0.9 1.280.05 0.95 1.650.01 0.99 2.33

Page 9: Re-Order Point Problems Set 1: General. 2 Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory Notations.

9Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory

z = (x-Average x)/(Standard Deviation of x)x = Average x +z (Standard Deviation of x)μ = Average x σ = Standard Deviation of x

x = μ +z σ

ROP = LTD +z σLTD

ROP = LTD +Isafety

ROP and Isafety

Page 10: Re-Order Point Problems Set 1: General. 2 Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory Notations.

10Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory

ROP and Isafety

LTD = Lead Time Demand (Demand during lead time)LTD = Average LTD = L×R LTD = Standard Deviation of Lead Time DemandIsafety = zLTD

Page 11: Re-Order Point Problems Set 1: General. 2 Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory Notations.

11Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory

ROP; total demand during lead time is variable

z = (X- μ )/σ

X= μ +z σ

ROP = LTD + Isafety

Isafety = z σLTD

ROP=LTD + zσLTD

SL = 90%

z = 1.28

LTD = 200

σLTD = 25

ROP= 200+ 1.28 × 25

ROP = 200 + 32

ROP = 232

Isafety = 32

c) If average demand during the lead time is 200 and standard deviation of demand during lead time is 25. Compute ROP at 90% service level. Compute safety stock

Page 12: Re-Order Point Problems Set 1: General. 2 Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory Notations.

12Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory

d) If average demand per day is 20 units and standard deviation of demand is 5 per day, and lead time is 16 days. Compute ROP at 90% service level. Compute safety stock.

ROP; Variable R, Fixed L

Page 13: Re-Order Point Problems Set 1: General. 2 Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory Notations.

13Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory

Previous Problem: If average demand during the lead time is 200 and standard deviation of demand during lead time is 25. Compute ROP at 90% service level. Compute safety stock.

This Problem: If average demand per day is 20 units and standard deviation of demand per day is 5, and lead time is 16 days. Compute ROP at 90% service level. Compute safety stock.

If we can transform this problem into the previous problem, then we are done, because we already know how to solve the previous problem.

ROP; Variable R, Fixed L

Page 14: Re-Order Point Problems Set 1: General. 2 Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory Notations.

14Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory

d) If average demand per day is 20 units and standard deviation of demand is 5 per day, and lead time is 16 days. Compute ROP at 90% service level. Compute ss.

What is the average demand during the lead time

What is standard deviation of demand during lead time

ROP; Variable R, Fixed R

Page 15: Re-Order Point Problems Set 1: General. 2 Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory Notations.

15Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory

If Demand is variable and Lead time is fixed

L: Lead Time

R: Demand per period (per day, week, month)

R: Average Demand per period (day, week, month)

R: Standard deviation of demand (per period)

LTD: Average Demand During Lead Time

LTD = L × R

LTD: Standard deviation of demand during lead time

μ and σ of demand per period and fixed L

=

Page 16: Re-Order Point Problems Set 1: General. 2 Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory Notations.

16Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory

If demand is variable and Lead time is fixed

L: Lead Time = 16 days

R: Demand per day

R: Average daily demand =20

R: Standard deviation of daily demand =5

LTD: Average Demand During Lead Time

LTD = L × R = 16 × 20 = 320

LTD: Standard deviation of demand during lead time

μ and σ of demand per period and fixed L

= =

Page 17: Re-Order Point Problems Set 1: General. 2 Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory Notations.

17Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory

The Problem originally was: If average demand per day is 20 units and standard deviation of demand is 5 per day, and lead time is 16 days. Compute ROP at 90% service level. Compute safety stock.

We transformed it to: The average demand during the lead time is 320 and the standard deviation of demand during the lead time is 20. Compute ROP at 90% service level. Compute safety stock.

Which is the same as the previous problem: If average demand during the lead time is 200 and standard deviation of demand during lead time is 25. Compute ROP at 90% service level. Compute safety stock.

Now It is Transformed

Page 18: Re-Order Point Problems Set 1: General. 2 Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory Notations.

18Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory

SL = 90% z = 1.28

x = μ + z σ

ROP= LTD +z σLTD

LTD = 320

σLTD = 20

ROP= 320+ 1.28 × 20

ROP= 320 + 25.6

ROP= 320 + 26

ROP = 346

Isafety = 26

ROP; Variable R, Fixed L

Page 19: Re-Order Point Problems Set 1: General. 2 Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory Notations.

19Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory

e) If demand per day is 20 units and lead time is 16 days and standard deviation of lead time is 4 days. Compute ROP at 90% service level. Compute Isafety.

What is the average demand during the lead time

What is standard deviation of demand during lead time

ROP; Variable R, Fixed L

Page 20: Re-Order Point Problems Set 1: General. 2 Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory Notations.

20Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory

If Lead time is variable and Demand is fixed

L: Lead Time

L: Average Lead Time

L: Standard deviation of Lead time

R: Demand per period

LTD: Average Demand during lead time

LTD = L × R

LTD: Standard deviation of demand during lead time

μ and σ of L and Fixed R

=R

Page 21: Re-Order Point Problems Set 1: General. 2 Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory Notations.

21Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory

If Lead time is variable and Demand is fixed

L: Lead Time

L: Average Lead Time = 16 days

L: Standard deviation of Lead time = 4 days

R: Demand per period = 20 per day

LTD: Average Demand During Lead Time

LTD = 16 × 20 = 320

LTD: Standard deviation of demand during lead time

μ and σ of L and Fixed R

=R =20(4) =80

Page 22: Re-Order Point Problems Set 1: General. 2 Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory Notations.

22Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory

LDT = 320

LTD = 80

SL = 90%

z =1.28

ROP = LTD +zLTD

ROP = 320 +1.28(80)

ROP = 320 + 102.4

Isafety = 102.4

μ and σ of L and Fixed R

Page 23: Re-Order Point Problems Set 1: General. 2 Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory Notations.

23Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory

Average lead time demand is 20,000 units. Standard deviation of lead time demand is estimated to be 5,000 units. The warehouse currently orders a 14-day supply, 28,000 units, each time the inventory level drops to 24,000 units. Suppose holding cost is $2 per unit per year. LTD = 20,000, LTD = 5,000, ROP = 24,000, H=$2, R = 2,000 / day, Q or EOQ = 28,000. a) Compute the service level. ROP = LTD + Isafety Isafety = 24,000 – 20,000 = 4,000ROP = LTD +z LTD Isafety = z LTD =4000

z(5,000) = 4,000 z = 4,000/5,000 = 0.8z =0.8 P(z ≤ Z) = 0.7881 = 78.81%In 78.81 % of the order cycles, the warehouse will not have a stockout. Risk = 21.19%.

Given Safety Inventory Compute Service Level

Page 24: Re-Order Point Problems Set 1: General. 2 Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory Notations.

24Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory

b) Compute the cycle inventory, and average inventory.At reorder point we order 28,000 units. Icycle = Q/2 = 28,000/2 = 14,000Isafety = 4,000 Average Inventory = I = Icycle + Isafety =14,000 + 4,000 = 18000.c) Compute the total holding costs per year.H(Average Inventory) = H(I) = 2 18,000 = 36,000/yeard) Compute the average flow time.R = 2,000 / day, I = 18,000RT = I 2000T = 18,000T = 99 days

Given Safety Inventory Compute Service Level

Page 25: Re-Order Point Problems Set 1: General. 2 Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory Notations.

25Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory

MassPC Inc. produces a 4-week supply of its PC Pal model when stock on hand drops to 500 units. It takes 1 week to produce a batch. Orders average 400 units per week, and standard deviation of forecast errors is estimated at 125 units.

Problem 7.1

Normal table

Up to the first digitafterdecimal

Second digitafter decimal

Probability

z

7881.0)( ROPLTDPSL

LTD = N(400, 125).ROP = LTD + IsafetyROP = LTD +z LTD

500= 400+z(125)100 = 125zz = 100/125 = 0.8

ROP =500

Q =

L =

1 week

LTD = 400/week

=125 4(400)

Page 26: Re-Order Point Problems Set 1: General. 2 Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory Notations.

26Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory

Safe

ty S

tock

Service Level

SL % change Z σLTD Is =zσLTD % change ROP = LTD +Is

0.8 100 0.84 125 105 100 5050.9 113 1.28 125 160 152 560

0.95 119 1.64 125 206 195 6060.99 124 2.33 125 291 276 691

Increasing service level increases the required safety inventory more than proportionately.

Problem 7.1

b) Compute Isafety for 80%, 90%, 95%, 99% service levels.

Page 27: Re-Order Point Problems Set 1: General. 2 Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory Notations.

27Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory

Selecting service level and safety inventory level is an important strategic decision.

A firm may choose high quality service in terms of product availability. Or

The firm may choose to be a low cost supplier by holding down inventory costs. In either case, it is positioning itself along the quality vs. cost trade-off curve.

This graph is a perfect example to show how a strategic position could be operationalized.

Problem 7.1

Cost

Quality

Page 28: Re-Order Point Problems Set 1: General. 2 Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory Notations.

28Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory

Within 100 time intervals, stockouts occur in 20. Service Level = 80/100 = 80%.Probability of stock-out = 20%.Risk = # of stockout intervals/ Total # of intervals Service Level = 1- (# of stockout intervals/ Total # of intervals) Suppose that in each time interval in which a stockout occurred, the number of units by which we were short. Suppose that cumulative demand during the 100 time intervals was 15,000 units and the total number of units short in the 20 intervals with stockouts was 1,500 units. Fill rate = (15,000-1,500)/15,000 = 13,500/15,000 = 90%.Fill Rate = Expected Sales / Expected Demand Fill Rate = (1- Expected Stockout )/ Expected Demand

Service Level, Fill Rate