Re-Order Point Problems Set 1: General. 2 Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety...
-
Upload
raquel-robie -
Category
Documents
-
view
226 -
download
3
Transcript of Re-Order Point Problems Set 1: General. 2 Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety...
Re-Order Point Problems Set 1: General
2Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory
Notations
L
R
LTD
L
L
R
R
ROP
Isafety
LTD
LTD
:Time Lead of Dev. Std.
:Time Lead Average
:Time Lead
:Demand of Dev. Std.
:Demand Average
:periodper Demand
:PointReorder
:StockSafety
:Demand Time Lead Dev. Std.
:Demand Time Lead Average
:Demand Time Lead LTD
R
L
3Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory
ROP Problemsa) If average demand per day is 20 units and lead time is
10 days. Assuming zero safety stock. Isafety=0, compute ROP.
b) If average demand per day is 20 units and lead time is 10 days. Assuming 70 units of safety stock. Isafety=70, compute ROP?
c) If average demand during the lead time is 200 and standard deviation of demand during lead time is 25. Compute ROP at 90% service level. Compute safety stock.
d) If average demand per day is 20 units and standard deviation of daily demand is 5, and lead time is 16 days. Compute ROP at 90% service level. Compute safety stock.
e) If demand per day is 20 units and lead time is 16 days and standard deviation of lead time is 4 days. Compute ROP at 90% service level. Compute safety stock.
4Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory
ROP; Fixed R, Fixed L, Zero Safety Stock
a) If average demand per day is 20 units and lead time is 10 days. Assuming zero safety stock.
Isafety = 0, L=10, R=20Compute ROP.
ROP = average demand during lead time + safety stock
ROP = LTD+ Isafety ROP = LTD + 0LTD = L × RLTD = 20 × 10 = 200ROP = 200
5Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory
ROP; Fixed R, Fixed L, Isafety >0
b) If average demand per day is 20 units and lead time is 10 days. Assuming 70 units of safety stock.
Isafety = 70, L=10, R=20Compute ROP.
ROP = average demand during lead time + Safety Stock
ROP = LTD + Isafety LTD = R × L = 20 × 10 = 200Isafety = 70ROP = 200 + 70 = 270
6Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory
ROP; total demand during lead time is variablec) If average demand during the lead time
is 200 and standard deviation of demand during lead time is 25. Compute ROP at 90% service level. Compute safety stock.
7Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory
Safety Stock and ROP
Risk of astockout
Service level
Probability ofno stockout
Safety stock
0 z
Quantity
z-scale
Each Normal variable x is associated with a standard Normal Variable zx is Normal (Average x , Standard Deviation x) z is Normal (0,1)
Averagedemand
ROP
There is a table for z which tells us a) Given any probability of not exceeding z. What is the
value of z. b) Given any value for z. What is the probability of not
exceeding z.
8Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory
Popular z Valuesz 0.00 0.01 0.02 0.03 0.04 0.05 0.06 0.07 0.08
0 0.5000 0.5040 0.5080 0.5120 0.5160 0.5199 0.5239 0.5279 0.53190.1 0.5398 0.5438 0.5478 0.5517 0.5557 0.5596 0.5636 0.5675 0.57140.2 0.5793 0.5832 0.5871 0.5910 0.5948 0.5987 0.6026 0.6064 0.61030.3 0.6179 0.6217 0.6255 0.6293 0.6331 0.6368 0.6406 0.6443 0.64800.4 0.6554 0.6591 0.6628 0.6664 0.6700 0.6736 0.6772 0.6808 0.68440.5 0.6915 0.6950 0.6985 0.7019 0.7054 0.7088 0.7123 0.7157 0.71900.6 0.7257 0.7291 0.7324 0.7357 0.7389 0.7422 0.7454 0.7486 0.75170.7 0.7580 0.7611 0.7642 0.7673 0.7704 0.7734 0.7764 0.7794 0.78230.8 0.7881 0.7910 0.7939 0.7967 0.7995 0.8023 0.8051 0.8078 0.81060.9 0.8159 0.8186 0.8212 0.8238 0.8264 0.8289 0.8315 0.8340 0.83651 0.8413 0.8438 0.8461 0.8485 0.8508 0.8531 0.8554 0.8577 0.85991.1 0.8643 0.8665 0.8686 0.8708 0.8729 0.8749 0.8770 0.8790 0.88101.2 0.8849 0.8869 0.8888 0.8907 0.8925 0.8944 0.8962 0.8980 0.89971.3 0.9032 0.9049 0.9066 0.9082 0.9099 0.9115 0.9131 0.9147 0.91621.4 0.9192 0.9207 0.9222 0.9236 0.9251 0.9265 0.9279 0.9292 0.93061.5 0.9332 0.9345 0.9357 0.9370 0.9382 0.9394 0.9406 0.9418 0.94291.6 0.9452 0.9463 0.9474 0.9484 0.9495 0.9505 0.9515 0.9525 0.95351.7 0.9554 0.9564 0.9573 0.9582 0.9591 0.9599 0.9608 0.9616 0.96251.8 0.9641 0.9649 0.9656 0.9664 0.9671 0.9678 0.9686 0.9693 0.96991.9 0.9713 0.9719 0.9726 0.9732 0.9738 0.9744 0.9750 0.9756 0.97612 0.9772 0.9778 0.9783 0.9788 0.9793 0.9798 0.9803 0.9808 0.98122.1 0.9821 0.9826 0.9830 0.9834 0.9838 0.9842 0.9846 0.9850 0.98542.2 0.9861 0.9864 0.9868 0.9871 0.9875 0.9878 0.9881 0.9884 0.98872.3 0.9893 0.9896 0.9898 0.9901 0.9904 0.9906 0.9909 0.9911 0.99132.4 0.9918 0.9920 0.9922 0.9925 0.9927 0.9929 0.9931 0.9932 0.99342.5 0.9938 0.9940 0.9941 0.9943 0.9945 0.9946 0.9948 0.9949 0.99512.6 0.9953 0.9955 0.9956 0.9957 0.9959 0.9960 0.9961 0.9962 0.99632.7 0.9965 0.9966 0.9967 0.9968 0.9969 0.9970 0.9971 0.9972 0.99732.8 0.9974 0.9975 0.9976 0.9977 0.9977 0.9978 0.9979 0.9979 0.99802.9 0.9981 0.9982 0.9982 0.9983 0.9984 0.9984 0.9985 0.9985 0.99863 0.9987 0.9987 0.9987 0.9988 0.9988 0.9989 0.9989 0.9989 0.9990
Risk Service level z value0.1 0.9 1.280.05 0.95 1.650.01 0.99 2.33
9Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory
z = (x-Average x)/(Standard Deviation of x)x = Average x +z (Standard Deviation of x)μ = Average x σ = Standard Deviation of x
x = μ +z σ
ROP = LTD +z σLTD
ROP = LTD +Isafety
ROP and Isafety
10Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory
ROP and Isafety
LTD = Lead Time Demand (Demand during lead time)LTD = Average LTD = L×R LTD = Standard Deviation of Lead Time DemandIsafety = zLTD
11Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory
ROP; total demand during lead time is variable
z = (X- μ )/σ
X= μ +z σ
ROP = LTD + Isafety
Isafety = z σLTD
ROP=LTD + zσLTD
SL = 90%
z = 1.28
LTD = 200
σLTD = 25
ROP= 200+ 1.28 × 25
ROP = 200 + 32
ROP = 232
Isafety = 32
c) If average demand during the lead time is 200 and standard deviation of demand during lead time is 25. Compute ROP at 90% service level. Compute safety stock
12Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory
d) If average demand per day is 20 units and standard deviation of demand is 5 per day, and lead time is 16 days. Compute ROP at 90% service level. Compute safety stock.
ROP; Variable R, Fixed L
13Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory
Previous Problem: If average demand during the lead time is 200 and standard deviation of demand during lead time is 25. Compute ROP at 90% service level. Compute safety stock.
This Problem: If average demand per day is 20 units and standard deviation of demand per day is 5, and lead time is 16 days. Compute ROP at 90% service level. Compute safety stock.
If we can transform this problem into the previous problem, then we are done, because we already know how to solve the previous problem.
ROP; Variable R, Fixed L
14Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory
d) If average demand per day is 20 units and standard deviation of demand is 5 per day, and lead time is 16 days. Compute ROP at 90% service level. Compute ss.
What is the average demand during the lead time
What is standard deviation of demand during lead time
ROP; Variable R, Fixed R
15Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory
If Demand is variable and Lead time is fixed
L: Lead Time
R: Demand per period (per day, week, month)
R: Average Demand per period (day, week, month)
R: Standard deviation of demand (per period)
LTD: Average Demand During Lead Time
LTD = L × R
LTD: Standard deviation of demand during lead time
μ and σ of demand per period and fixed L
=
16Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory
If demand is variable and Lead time is fixed
L: Lead Time = 16 days
R: Demand per day
R: Average daily demand =20
R: Standard deviation of daily demand =5
LTD: Average Demand During Lead Time
LTD = L × R = 16 × 20 = 320
LTD: Standard deviation of demand during lead time
μ and σ of demand per period and fixed L
= =
17Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory
The Problem originally was: If average demand per day is 20 units and standard deviation of demand is 5 per day, and lead time is 16 days. Compute ROP at 90% service level. Compute safety stock.
We transformed it to: The average demand during the lead time is 320 and the standard deviation of demand during the lead time is 20. Compute ROP at 90% service level. Compute safety stock.
Which is the same as the previous problem: If average demand during the lead time is 200 and standard deviation of demand during lead time is 25. Compute ROP at 90% service level. Compute safety stock.
Now It is Transformed
18Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory
SL = 90% z = 1.28
x = μ + z σ
ROP= LTD +z σLTD
LTD = 320
σLTD = 20
ROP= 320+ 1.28 × 20
ROP= 320 + 25.6
ROP= 320 + 26
ROP = 346
Isafety = 26
ROP; Variable R, Fixed L
19Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory
e) If demand per day is 20 units and lead time is 16 days and standard deviation of lead time is 4 days. Compute ROP at 90% service level. Compute Isafety.
What is the average demand during the lead time
What is standard deviation of demand during lead time
ROP; Variable R, Fixed L
20Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory
If Lead time is variable and Demand is fixed
L: Lead Time
L: Average Lead Time
L: Standard deviation of Lead time
R: Demand per period
LTD: Average Demand during lead time
LTD = L × R
LTD: Standard deviation of demand during lead time
μ and σ of L and Fixed R
=R
21Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory
If Lead time is variable and Demand is fixed
L: Lead Time
L: Average Lead Time = 16 days
L: Standard deviation of Lead time = 4 days
R: Demand per period = 20 per day
LTD: Average Demand During Lead Time
LTD = 16 × 20 = 320
LTD: Standard deviation of demand during lead time
μ and σ of L and Fixed R
=R =20(4) =80
22Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory
LDT = 320
LTD = 80
SL = 90%
z =1.28
ROP = LTD +zLTD
ROP = 320 +1.28(80)
ROP = 320 + 102.4
Isafety = 102.4
μ and σ of L and Fixed R
23Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory
Average lead time demand is 20,000 units. Standard deviation of lead time demand is estimated to be 5,000 units. The warehouse currently orders a 14-day supply, 28,000 units, each time the inventory level drops to 24,000 units. Suppose holding cost is $2 per unit per year. LTD = 20,000, LTD = 5,000, ROP = 24,000, H=$2, R = 2,000 / day, Q or EOQ = 28,000. a) Compute the service level. ROP = LTD + Isafety Isafety = 24,000 – 20,000 = 4,000ROP = LTD +z LTD Isafety = z LTD =4000
z(5,000) = 4,000 z = 4,000/5,000 = 0.8z =0.8 P(z ≤ Z) = 0.7881 = 78.81%In 78.81 % of the order cycles, the warehouse will not have a stockout. Risk = 21.19%.
Given Safety Inventory Compute Service Level
24Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory
b) Compute the cycle inventory, and average inventory.At reorder point we order 28,000 units. Icycle = Q/2 = 28,000/2 = 14,000Isafety = 4,000 Average Inventory = I = Icycle + Isafety =14,000 + 4,000 = 18000.c) Compute the total holding costs per year.H(Average Inventory) = H(I) = 2 18,000 = 36,000/yeard) Compute the average flow time.R = 2,000 / day, I = 18,000RT = I 2000T = 18,000T = 99 days
Given Safety Inventory Compute Service Level
25Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory
MassPC Inc. produces a 4-week supply of its PC Pal model when stock on hand drops to 500 units. It takes 1 week to produce a batch. Orders average 400 units per week, and standard deviation of forecast errors is estimated at 125 units.
Problem 7.1
Normal table
Up to the first digitafterdecimal
Second digitafter decimal
Probability
z
7881.0)( ROPLTDPSL
LTD = N(400, 125).ROP = LTD + IsafetyROP = LTD +z LTD
500= 400+z(125)100 = 125zz = 100/125 = 0.8
ROP =500
Q =
L =
1 week
LTD = 400/week
=125 4(400)
26Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory
Safe
ty S
tock
Service Level
SL % change Z σLTD Is =zσLTD % change ROP = LTD +Is
0.8 100 0.84 125 105 100 5050.9 113 1.28 125 160 152 560
0.95 119 1.64 125 206 195 6060.99 124 2.33 125 291 276 691
Increasing service level increases the required safety inventory more than proportionately.
Problem 7.1
b) Compute Isafety for 80%, 90%, 95%, 99% service levels.
27Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory
Selecting service level and safety inventory level is an important strategic decision.
A firm may choose high quality service in terms of product availability. Or
The firm may choose to be a low cost supplier by holding down inventory costs. In either case, it is positioning itself along the quality vs. cost trade-off curve.
This graph is a perfect example to show how a strategic position could be operationalized.
Problem 7.1
Cost
Quality
28Ardavan Asef-Vaziri Sep-2012Flow Variability; Safety Inventory
Within 100 time intervals, stockouts occur in 20. Service Level = 80/100 = 80%.Probability of stock-out = 20%.Risk = # of stockout intervals/ Total # of intervals Service Level = 1- (# of stockout intervals/ Total # of intervals) Suppose that in each time interval in which a stockout occurred, the number of units by which we were short. Suppose that cumulative demand during the 100 time intervals was 15,000 units and the total number of units short in the 20 intervals with stockouts was 1,500 units. Fill rate = (15,000-1,500)/15,000 = 13,500/15,000 = 90%.Fill Rate = Expected Sales / Expected Demand Fill Rate = (1- Expected Stockout )/ Expected Demand
Service Level, Fill Rate