1 Managing Flow Variability: Safety Inventory The Newsvendor ProblemArdavan Asef-Vaziri, Oct 2011...

34
1 Managing Flow Variability: Safety Inventory The Newsvendor Problem Ardavan Asef-Vaziri, Oct 2011 The Magnitude of Shortages (Out of Stock)

Transcript of 1 Managing Flow Variability: Safety Inventory The Newsvendor ProblemArdavan Asef-Vaziri, Oct 2011...

Page 1: 1 Managing Flow Variability: Safety Inventory The Newsvendor ProblemArdavan Asef-Vaziri, Oct 2011 The Magnitude of Shortages (Out of Stock)

1

Managing Flow Variability: Safety Inventory

The Newsvendor Problem

Ardavan Asef-Vaziri, Oct 2011

The Magnitude of Shortages (Out of Stock)

Page 2: 1 Managing Flow Variability: Safety Inventory The Newsvendor ProblemArdavan Asef-Vaziri, Oct 2011 The Magnitude of Shortages (Out of Stock)

2

Managing Flow Variability: Safety Inventory

The Newsvendor Problem

Ardavan Asef-Vaziri, Oct 2011

Optimal Service Level: The Newsvendor Problem

Cost of ordering too much: holding cost, salvage Cost of ordering too

little: loss of sale, low service level

The decision maker balances the expected costs of ordering too much with the expected costs of ordering too little to determine the optimal order quantity.

How do we choose what level of service a firm should offer?

Page 3: 1 Managing Flow Variability: Safety Inventory The Newsvendor ProblemArdavan Asef-Vaziri, Oct 2011 The Magnitude of Shortages (Out of Stock)

3

Managing Flow Variability: Safety Inventory

The Newsvendor Problem

Ardavan Asef-Vaziri, Oct 2011

News Vendor Model; Assumptions

Demand is random Distribution of demand is known No initial inventory Set-up cost is zero Single period Zero lead time Linear costs

Purchasing (production) Salvage value Revenue Goodwill

Page 4: 1 Managing Flow Variability: Safety Inventory The Newsvendor ProblemArdavan Asef-Vaziri, Oct 2011 The Magnitude of Shortages (Out of Stock)

4

Managing Flow Variability: Safety Inventory

The Newsvendor Problem

Ardavan Asef-Vaziri, Oct 2011

Optimal Service Level: The Newsvendor Problem

Demand Probability of Demand100 0.02110 0.05120 0.08130 0.09140 0.11150 0.16160 0.20170 0.15180 0.08190 0.05200 0.01

Cost =1800, Sales Price = 2500, Salvage Price = 1700Underage Cost = 2500-1800 = 700, Overage Cost = 1800-1700 = 100

What is probability of demand to be equal to 130? What is probability of demand to be less than or equal to 140?What is probability of demand to be greater than or equal to 140?What is probability of demand to be equal to 133?

0.090.02+0.05+0.08+0.09+0.11=

0.35

1-0.35+0.11= 0.760

P(R ≥ Q ) = 1-P(R ≤ Q)+P(R = Q) R is quantity of demandQ is the quantity ordered

Page 5: 1 Managing Flow Variability: Safety Inventory The Newsvendor ProblemArdavan Asef-Vaziri, Oct 2011 The Magnitude of Shortages (Out of Stock)

5

Managing Flow Variability: Safety Inventory

The Newsvendor Problem

Ardavan Asef-Vaziri, Oct 2011

Optimal Service Level: The Newsvendor Problem

Demand Probability of Demand100 0.002101 0.002102 0.002103 0.002104 0.002105 0.002106 0.002107 0.002108 0.002109 0.002

What is probability of demand to be equal to 116?What is probability of demand to be less than or equal to 116?What is probability of demand to be greater than or equal to 116?What is probability of demand to be equal to 113.3?

Demand Probability of Demand110 0.005111 0.005112 0.005113 0.005114 0.005115 0.005116 0.005117 0.005118 0.005119 0.005

0.0050.02+0.035 = 0.055

1-0.055+0.005 = 0.950

Page 6: 1 Managing Flow Variability: Safety Inventory The Newsvendor ProblemArdavan Asef-Vaziri, Oct 2011 The Magnitude of Shortages (Out of Stock)

6

Managing Flow Variability: Safety Inventory

The Newsvendor Problem

Ardavan Asef-Vaziri, Oct 2011

Optimal Service Level: The Newsvendor Problem

What is probability of demand to be equal to 130?

Average Demand Probability of Demand100 0.02110 0.05120 0.08130 0.09140 0.11150 0.16160 0.20170 0.15180 0.08190 0.05200 0.01

0

What is probability of demand to be less than or equal to 145?

What is probability of demand to be greater than or equal to 145?

0.02+0.05+0.08+0.09+0.11 = 0.35

1-0.35 = 0.65P(R ≥ Q) = 1-P(R ≤ Q)

Page 7: 1 Managing Flow Variability: Safety Inventory The Newsvendor ProblemArdavan Asef-Vaziri, Oct 2011 The Magnitude of Shortages (Out of Stock)

7

Managing Flow Variability: Safety Inventory

The Newsvendor Problem

Ardavan Asef-Vaziri, Oct 2011

Compute the Average Demand

Q i P( R =Q i )

100 0.02110 0.05120 0.08130 0.09140 0.11150 0.16160 0.20170 0.15180 0.08190 0.05200 0.01

N

1i

Demand Average )( ii QRPQ

Average Demand = +100×0.02 +110×0.05+120×0.08 +130×0.09+140×0.11 +150×0.16+160×0.20 +170×0.15 +180×0.08 +190×0.05+200×0.01Average Demand = 151.6

How many units should I have to sell 151.6 units (on average)? How many units do I sell (on average) if I have 100 units?

200

100

Page 8: 1 Managing Flow Variability: Safety Inventory The Newsvendor ProblemArdavan Asef-Vaziri, Oct 2011 The Magnitude of Shortages (Out of Stock)

8

Managing Flow Variability: Safety Inventory

The Newsvendor Problem

Ardavan Asef-Vaziri, Oct 2011

Suppose I have ordered 140 units.On average, how many of them are sold? In other words, what is the

expected value of the number of sold units?

When I can sell all 140 units? I can sell all 140 units if R ≥ 140Prob(R ≥ 140) = 0.76The expected number of units sold –for this part- is(0.76)(140) = 106.4Also, there is 0.02 probability that I sell 100 units 2 unitsAlso, there is 0.05 probability that I sell 110 units5.5Also, there is 0.08 probability that I sell 120 units 9.6Also, there is 0.09 probability that I sell 130 units 11.7106.4 + 2 + 5.5 + 9.6 + 11.7 = 135.2

Deamand (Qi) 100 110 120 130 140 150 160 170 180 190 200

Porbability 0.02 0.05 0.08 0.09 0.11 0.16 0.20 0.15 0.08 0.05 0.01Prob (R ≥ Qi) 1.00 0.98 0.93 0.85 0.76 0.65 0.49 0.29 0.14 0.06 0.01

Page 9: 1 Managing Flow Variability: Safety Inventory The Newsvendor ProblemArdavan Asef-Vaziri, Oct 2011 The Magnitude of Shortages (Out of Stock)

9

Managing Flow Variability: Safety Inventory

The Newsvendor Problem

Ardavan Asef-Vaziri, Oct 2011

Suppose I have ordered 140 units.On average, how many of them are salvaged? In other words, what is

the expected value of the number of salvaged units?

0.02 probability that I sell 100 units. In that case 40 units are salvaged 0.02(40) = .80.05 probability to sell 110 30 salvaged 0.05(30)= 1.5 0.08 probability to sell 120 20 salvaged 0.08(20) = 1.60.09 probability to sell 130 10 salvaged 0.09(10) =0.9 0.8 + 1.5 + 1.6 + 0.9 = 4.8

Total number Sold 135.2 @ 700 = 94640Total number Salvaged 4.8 @ -100 = -480Expected Profit = 94640 – 480 = 94,160

Deamand (Qi) 100 110 120 130 140 150 160 170 180 190 200

Porbability 0.02 0.05 0.08 0.09 0.11 0.16 0.20 0.15 0.08 0.05 0.01Prob (R ≥ Qi) 1.00 0.98 0.93 0.85 0.76 0.65 0.49 0.29 0.14 0.06 0.01

Page 10: 1 Managing Flow Variability: Safety Inventory The Newsvendor ProblemArdavan Asef-Vaziri, Oct 2011 The Magnitude of Shortages (Out of Stock)

10

Managing Flow Variability: Safety Inventory

The Newsvendor Problem

Ardavan Asef-Vaziri, Oct 2011

Cumulative Probabilities

Qi P(R=Qi) P(R<Qi) P(R≥Qi)

100 0.02 0 1110 0.05 0.02 0.98120 0.08 0.07 0.93130 0.09 0.15 0.85140 0.11 0.24 0.76150 0.16 0.35 0.65160 0.2 0.51 0.49170 0.15 0.71 0.29180 0.08 0.86 0.14190 0.05 0.94 0.06200 0.01 0.99 0.01

Probabilities

Page 11: 1 Managing Flow Variability: Safety Inventory The Newsvendor ProblemArdavan Asef-Vaziri, Oct 2011 The Magnitude of Shortages (Out of Stock)

11

Managing Flow Variability: Safety Inventory

The Newsvendor Problem

Ardavan Asef-Vaziri, Oct 2011

Number of Units Sold, Salvaged

Qi P(R=Qi) P(R<Qi) P(R≥Qi) Sold Salvage100 0.02 0 1 100 0110 0.05 0.02 0.98 109.8 0.2120 0.08 0.07 0.93 119.1 0.9130 0.09 0.15 0.85 127.6 2.4140 0.11 0.24 0.76 135.2 4.8150 0.16 0.35 0.65 141.7 8.3160 0.20 0.51 0.49 146.6 13.4170 0.15 0.71 0.29 149.5 20.5180 0.08 0.86 0.14 150.9 29.1190 0.05 0.94 0.06 151.5 38.5200 0.01 0.99 0.01 151.6 48.4

Probabilities Units Sold@700 Salvaged@-100

Page 12: 1 Managing Flow Variability: Safety Inventory The Newsvendor ProblemArdavan Asef-Vaziri, Oct 2011 The Magnitude of Shortages (Out of Stock)

12

Managing Flow Variability: Safety Inventory

The Newsvendor Problem

Ardavan Asef-Vaziri, Oct 2011

Total Revenue for Different Ordering Policies

Qi P(R=Qi) P(R<Qi) P(R≥Qi) Sold Salvaged Sold Salvaged Total100 0.02 0 1 100 0 70000 0 70000110 0.05 0.02 0.98 109.8 0.2 76860 20 76840120 0.08 0.07 0.93 119.1 0.9 83370 90 83280130 0.09 0.15 0.85 127.6 2.4 89320 240 89080140 0.11 0.24 0.76 135.2 4.8 94640 480 94160150 0.16 0.35 0.65 141.7 8.3 99190 830 98360160 0.2 0.51 0.49 146.6 13.4 102620 1340 101280170 0.15 0.71 0.29 149.5 20.5 104650 2050 102600180 0.08 0.86 0.14 150.9 29.1 105630 2910 102720190 0.05 0.94 0.06 151.5 38.5 106050 3850 102200200 0.01 0.99 0.01 151.6 48.4 106120 4840 101280

Probabilities Units Revenue

Page 13: 1 Managing Flow Variability: Safety Inventory The Newsvendor ProblemArdavan Asef-Vaziri, Oct 2011 The Magnitude of Shortages (Out of Stock)

13

Managing Flow Variability: Safety Inventory

The Newsvendor Problem

Ardavan Asef-Vaziri, Oct 2011

Denim Wholesaler; Marginal Analysis

The demand for denim is:

– 1000 with probability 0.10

– 2000 with probability 0.15

– 3000 with probability 0.15

– 4000 with probability 0.20

– 5000 with probability 0.15

– 6000 with probability 0.15

– 7000 with probability 0.10

Unit Revenue (p ) = 30Unit purchase cost (c )= 10Salvage value (v )= 5Goodwill cost (g )= 0

How much should we order?

Page 14: 1 Managing Flow Variability: Safety Inventory The Newsvendor ProblemArdavan Asef-Vaziri, Oct 2011 The Magnitude of Shortages (Out of Stock)

14

Managing Flow Variability: Safety Inventory

The Newsvendor Problem

Ardavan Asef-Vaziri, Oct 2011

Marginal Analysis

Marginal analysis: What is the value of an additional unit ordered?

Suppose the wholesaler purchases 1000 units

What is the value of having the 1001st unit?

Marginal Cost: The retailer must salvage the additional unit and losses $5 (10 – 5).

P(R ≤ 1000) = 0.1

Expected Marginal Cost = 0.1(5) = 0.5

Page 15: 1 Managing Flow Variability: Safety Inventory The Newsvendor ProblemArdavan Asef-Vaziri, Oct 2011 The Magnitude of Shortages (Out of Stock)

15

Managing Flow Variability: Safety Inventory

The Newsvendor Problem

Ardavan Asef-Vaziri, Oct 2011

Marginal Analysis

Marginal Profit: The retailer makes and extra profit of $20 (30 – 10)

P(R > 1000) = 0.9

Expected Marginal Profit= 0.9(20) = 18

MP ≥ MC

Expected Value = 18-0.5 = 17.5

By purchasing an additional unit, the expected profit increases by $17.5

The retailer should purchase at least 1,001 units.

Page 16: 1 Managing Flow Variability: Safety Inventory The Newsvendor ProblemArdavan Asef-Vaziri, Oct 2011 The Magnitude of Shortages (Out of Stock)

16

Managing Flow Variability: Safety Inventory

The Newsvendor Problem

Ardavan Asef-Vaziri, Oct 2011

Marginal Analysis

Should he purchase 1,002 units?Marginal Cost: $5 salvage P(R ≤ 1001) = 0.1 Expected Marginal Cost = 0.5Marginal Profit: $20 profit P(R >1002) = 0.9 18

Expected Marginal Profit = 18

Expected Value = 18-0.5 = 17.5

Conclusion:

Wholesaler should purchase at least 2000 units.

Assuming that the initial purchasing quantity is between 1000 and 2000, then by purchasing an additional unit exactly the same savings will be achieved.

Page 17: 1 Managing Flow Variability: Safety Inventory The Newsvendor ProblemArdavan Asef-Vaziri, Oct 2011 The Magnitude of Shortages (Out of Stock)

17

Managing Flow Variability: Safety Inventory

The Newsvendor Problem

Ardavan Asef-Vaziri, Oct 2011

Marginal Analysis

Marginal analysis: What is the value of an additional unit ordered?

Suppose the retailer purchases 2000 units

What is the value of having the 2001st unit?

Marginal Cost: The retailer must salvage the additional unit and losses $5 (10 – 5).

P(R ≤ 2000) = 0.25

Expected Marginal Cost = 0.25(5) = 1.25

Page 18: 1 Managing Flow Variability: Safety Inventory The Newsvendor ProblemArdavan Asef-Vaziri, Oct 2011 The Magnitude of Shortages (Out of Stock)

18

Managing Flow Variability: Safety Inventory

The Newsvendor Problem

Ardavan Asef-Vaziri, Oct 2011

Marginal Analysis

Marginal Profit: The retailer makes and extra profit of $20 (30 – 10)

P(R > 2000) = 0.75

Expected Marginal Profit= 0.75(20) = 15

MP ≥ MC

Expected Value = 15-1.25 = 13.75

By purchasing an additional unit, the expected profit increases by $13.75

The retailer should purchase at least 2,001 units.

Page 19: 1 Managing Flow Variability: Safety Inventory The Newsvendor ProblemArdavan Asef-Vaziri, Oct 2011 The Magnitude of Shortages (Out of Stock)

19

Managing Flow Variability: Safety Inventory

The Newsvendor Problem

Ardavan Asef-Vaziri, Oct 2011

Marginal Analysis

Should he purchase 2,002 units?Marginal Cost: $5 salvage P(R ≤ 2001) = 0.25 Expected Marginal Cost = 1.25Marginal Profit: $20 profit P(R >2002) = 0.75

Expected Marginal Profit = 15

Expected Value = 15-1.25 = 13.75

Conclusion:

Wholesaler should purchase at least 3000 units.

Assuming that the initial purchasing quantity is between 2000 and 3000, then by purchasing an additional unit exactly the same savings will be achieved.

Page 20: 1 Managing Flow Variability: Safety Inventory The Newsvendor ProblemArdavan Asef-Vaziri, Oct 2011 The Magnitude of Shortages (Out of Stock)

20

Managing Flow Variability: Safety Inventory

The Newsvendor Problem

Ardavan Asef-Vaziri, Oct 2011

Marginal Analysis

Why does the marginal value of an additional unit decrease, as

the purchasing quantity increases?

– Expected cost of an additional unit increases

– Expected savings of an additional unit decreases

Demand ProbabilityCumulative Probability

Expected Marginal Cost

Expected Marginal Profit

Expected Marginal Value

1000 0.10 0.1 0.50 18 17.502000 0.15 0.25 1.25 15 13.753000 0.15 0.40 2.00 12 10.004000 0.20 0.60 3.00 8 5.005000 0.15 0.75 3.75 5 1.256000 0.15 0.90 4.50 2 -2.507000 0.10 1.00 5.00 0 -5.00

Page 21: 1 Managing Flow Variability: Safety Inventory The Newsvendor ProblemArdavan Asef-Vaziri, Oct 2011 The Magnitude of Shortages (Out of Stock)

21

Managing Flow Variability: Safety Inventory

The Newsvendor Problem

Ardavan Asef-Vaziri, Oct 2011

Marginal Analysis

What is the optimal purchasing quantity?

– Answer: Choose the quantity that makes marginal value: zero

Quantity

Marginal value

1000 2000 3000 4000 5000 6000 7000 8000

17.5

13.75

10

5

1.3

-2.5

-5

Page 22: 1 Managing Flow Variability: Safety Inventory The Newsvendor ProblemArdavan Asef-Vaziri, Oct 2011 The Magnitude of Shortages (Out of Stock)

22

Managing Flow Variability: Safety Inventory

The Newsvendor Problem

Ardavan Asef-Vaziri, Oct 2011

Additional Example

On consecutive Sundays, Mac, the owner of your local

newsstand, purchases a number of copies of “The Computer

Journal”. He pays 25 cents for each copy and sells each for 75

cents. Copies he has not sold during the week can be returned to

his supplier for 10 cents each. The supplier is able to salvage the

paper for printing future issues. Mac has kept careful records of

the demand each week for the journal. The observed demand

during the past weeks has the following distribution:Qi 4 5 6 7 8 9 10 11 12 13P(R=Qi) 0.04 0.06 0.16 0.18 0.2 0.1 0.1 0.08 0.04 0.04

Page 23: 1 Managing Flow Variability: Safety Inventory The Newsvendor ProblemArdavan Asef-Vaziri, Oct 2011 The Magnitude of Shortages (Out of Stock)

23

Managing Flow Variability: Safety Inventory

The Newsvendor Problem

Ardavan Asef-Vaziri, Oct 2011

Additional Example

a) How many units are sold if we have ordered 7 units

There is 0.18 + 0.20 + 0.10 + 0.10 + 0.08 + 0.04 + 0.04 = 0.74

There is 0.74 probability that demand is greater than or equal to 7.

There is 0.16 probability that demand is equal to 6.

There is 0.06 probability that demand is equal to 5.

There is 0.04 probability that demand is equal to 4.

The expected number of units sold is

0.74(7) + 0.16 (6) + 0.06 (5) + 0.04 (4) = 6.6

Qi 4 5 6 7 8 9 10 11 12 13P(R=Qi) 0.04 0.06 0.16 0.18 0.2 0.1 0.1 0.08 0.04 0.04

Page 24: 1 Managing Flow Variability: Safety Inventory The Newsvendor ProblemArdavan Asef-Vaziri, Oct 2011 The Magnitude of Shortages (Out of Stock)

24

Managing Flow Variability: Safety Inventory

The Newsvendor Problem

Ardavan Asef-Vaziri, Oct 2011

Additional Example

b) How many units are salvaged?

7-6.6 = 0.4. Alternatively, we can compute it directly

There is 0.74 probability that we salvage 7 – 7 = 0 units

There is 0.16 probability that we salvage 7- 6 = 1 units

There is 0.06 probability that we salvage 7- 5 = 2 units

There is 0.04 probability that we salvage 7-4 = 3 units

The expected number of units salvaged is

0.74(0) + 0.16 (1) + 0.06 (2) + 0.04 (3) = 0.4 and 7-0.4 = 6.6 sold

Qi 4 5 6 7 8 9 10 11 12 13P(R=Qi) 0.04 0.06 0.16 0.18 0.2 0.1 0.1 0.08 0.04 0.04

Page 25: 1 Managing Flow Variability: Safety Inventory The Newsvendor ProblemArdavan Asef-Vaziri, Oct 2011 The Magnitude of Shortages (Out of Stock)

25

Managing Flow Variability: Safety Inventory

The Newsvendor Problem

Ardavan Asef-Vaziri, Oct 2011

Additional Example

c) Compute the total profit if we order 7 units.

Out of 7 units, 6.6 sold, 0.4 salvaged.

P = 75, c= 25, v=10.

Profit per unit sold = 75-25 = 50

Cost per unit salvaged = 25-10 = 15

Total Profit = 6.6(50) + 0.4(15) = 330 - 6 = 324

Page 26: 1 Managing Flow Variability: Safety Inventory The Newsvendor ProblemArdavan Asef-Vaziri, Oct 2011 The Magnitude of Shortages (Out of Stock)

26

Managing Flow Variability: Safety Inventory

The Newsvendor Problem

Ardavan Asef-Vaziri, Oct 2011

Additional Example

d) Compute the expected Marginal profit of ordering the 8th unit.

MP = 75-25 = 50

P(R ≥ 8) = 0.2 + 0.1 + 0.1 + 0.08 + 0.04 + 0.04 = 0.56

Expected Marginal profit = 0.56(50) = 28

e) Compute the expected Marginal cost of ordering the 8th unit.

MC = 25 – 10 = 15

P(R ≤ 7) = 1-0.56 = 0.44

Expected Marginal cost = 0.44(15) = 6.6

Qi 4 5 6 7 8 9 10 11 12 13P(R=Qi) 0.04 0.06 0.16 0.18 0.2 0.1 0.1 0.08 0.04 0.04

Page 27: 1 Managing Flow Variability: Safety Inventory The Newsvendor ProblemArdavan Asef-Vaziri, Oct 2011 The Magnitude of Shortages (Out of Stock)

27

Managing Flow Variability: Safety Inventory

The Newsvendor Problem

Ardavan Asef-Vaziri, Oct 2011

Another Example

Swell Productions (The Retailer) is sponsoring an outdoor conclave for owners of collectible and classic Fords. The concession stand in the T-Bird area will sell clothing such as official Thunderbird racing jerseys. The following table shows the probability of jerseys sales quantities.

Probability 0.05 0.10 0.30 0.20 0.20 0.15

Demand 100 200 300 400 500 600

A) Compute the average demand (units that can be sold) for Swell Productions jerseys. 0.05 100

0.1 200

0.3 300

0.2 400

0.2 500

0.15 600

1 385

Page 28: 1 Managing Flow Variability: Safety Inventory The Newsvendor ProblemArdavan Asef-Vaziri, Oct 2011 The Magnitude of Shortages (Out of Stock)

28

Managing Flow Variability: Safety Inventory

The Newsvendor Problem

Ardavan Asef-Vaziri, Oct 2011

Another Example

B) Given the average demand you have obtained in the previous

part. How many units should Swell Productions order to be able

to have the average number of units sold equal to the average

demand.

600

C) Supposed Swell Productions has ordered 400 units. Compute

the marginal profit of ordering one more unit.

40(0.35) = 14

Page 29: 1 Managing Flow Variability: Safety Inventory The Newsvendor ProblemArdavan Asef-Vaziri, Oct 2011 The Magnitude of Shortages (Out of Stock)

29

Managing Flow Variability: Safety Inventory

The Newsvendor Problem

Ardavan Asef-Vaziri, Oct 2011

Another Example

D) Supposed Swell Productions has ordered 400 units. Compute

the marginal cost of ordering one more unit.

20(0.65) = 13

E) Suppose your computations indicates that it is at Swell

Productions’ benefit to order 401 units (this may or may not the

correct answer). How many units should Swell Productions

order?

500

Page 30: 1 Managing Flow Variability: Safety Inventory The Newsvendor ProblemArdavan Asef-Vaziri, Oct 2011 The Magnitude of Shortages (Out of Stock)

30

Managing Flow Variability: Safety Inventory

The Newsvendor Problem

Ardavan Asef-Vaziri, Oct 2011

Another Example

F) Suppose Swell Productions has ordered 500 units. Compute

the expected value of the number of units salvaged.

0.05(400)+0.1(300) +0.3 (200) + 0.2 (100) =

20+30+60+20 = 130

G) Suppose Swell Productions orders 500 jerseys. Compute the

expected number of jerseys that can be sold.

500-130= 3700.05 100

0.1 2000.3 3000.2 400

0.35 500370

Page 31: 1 Managing Flow Variability: Safety Inventory The Newsvendor ProblemArdavan Asef-Vaziri, Oct 2011 The Magnitude of Shortages (Out of Stock)

31

Managing Flow Variability: Safety Inventory

The Newsvendor Problem

Ardavan Asef-Vaziri, Oct 2011

Another Example

H) Supposed Swell Productions has ordered 500 units. Compute

the expected value of Swell Productions’ total net profit.

-130(20) + 370(40) = -2600+ 14800 = 12200

I) At what purchasing price (current purchasing price is $40 and

current salvage value is 20) will you order 600 units?

MC=0.85 (c-20) = 0.85c -17

MP = 0.15(80-c) = 12- 0.15c

12-0.15c> 0.85c-17

29> c

Page 32: 1 Managing Flow Variability: Safety Inventory The Newsvendor ProblemArdavan Asef-Vaziri, Oct 2011 The Magnitude of Shortages (Out of Stock)

32

Managing Flow Variability: Safety Inventory

The Newsvendor Problem

Ardavan Asef-Vaziri, Oct 2011

Another Example

It really does not make sense to say the break-even point is where

385(40) = 215X. Because X and 40 are not independent.

To correct the above statement, one may say: the break-even point

is where 385(80-c) = 215(c-20)

One may try to solve the above equation. But it does not make

sense because in that case and under the price of c, we will

make 0 profit if we order 600. While we already make $12200,

by ordering 500. Therefore no matter what c value comes out

of the above equation, it makes our profit equal 0. Why we

should order 600 for 0 profit compared to 500 with $12200

profit.

 

Page 33: 1 Managing Flow Variability: Safety Inventory The Newsvendor ProblemArdavan Asef-Vaziri, Oct 2011 The Magnitude of Shortages (Out of Stock)

33

Managing Flow Variability: Safety Inventory

The Newsvendor Problem

Ardavan Asef-Vaziri, Oct 2011

Another Example

A correct second procedure to solve the problem is to say; we order

600 if its total expected revenue is greater than ordering 500.  

Ordering 500 # of units sold is 370 and salvaged 130

Ordering 600 # of units sold is 385 and salvaged 215

For sale we get (80-c) for salvage we pay (c-20)

Therefore, total revenue of 600 must be greater than that of 500

385(80-c) – 215(c-20) > 370(80-c) – 130(c-20)

By solving this equation we will get 29>c

Page 34: 1 Managing Flow Variability: Safety Inventory The Newsvendor ProblemArdavan Asef-Vaziri, Oct 2011 The Magnitude of Shortages (Out of Stock)

34

Managing Flow Variability: Safety Inventory

The Newsvendor Problem

Ardavan Asef-Vaziri, Oct 2011

Another Example

Indeed we could have also said that by ordering 600 we sell 15 units

more and salvage 85 units more. And the sale revenue must be

greater than salvaged marginal cost

15(80-c) > 85(c-20)

29>c