Ramping & Snapback

25
Ramping & Snapback Andy Butterworth AB/RF Chamonix XIV 17 January 2005

description

Ramping & Snapback. Andy Butterworth AB/RF. Chamonix XIV 17 January 2005. Outline. Procedure for ramping the LHC Initial conditions for ramp commissioning Outline of ramp commissioning Moving to the nominal cycle Getting through snapback Ramping further - PowerPoint PPT Presentation

Transcript of Ramping & Snapback

Page 1: Ramping & Snapback

Ramping & Snapback

Andy Butterworth AB/RF

Chamonix XIV

17 January 2005

Page 2: Ramping & Snapback

Outline

• Procedure for ramping the LHC• Initial conditions for ramp commissioning• Outline of ramp commissioning

– Moving to the nominal cycle– Getting through snapback– Ramping further

• Measurements and commissioning of accelerator equipment

• Conclusions

Page 3: Ramping & Snapback

Baseline energy ramp

Parabolic-Exponential-Linear-Parabolic (PELP)

0

1

2

3

4

5

6

7

0 100 200 300 400 500 600 700 800 900 1000 1100 1200 1300 1400 1500 1600 1700

Time/s

TeV

Einj Injection Energy [GeV] 450

Eft Flat-top Energy [GeV] 7000

E’max Max Ramp rate [GeV/s] 5.9

E’pRamp rate at end of parabolic section [GeV/s] 2.125

tpLength of parabolic section [s] 405

Ri Start Round-out level [% Eft] 98

PELPs are also used for any synchronized setting

– e.g. applying a trim

Parabolic

I t2

Exponential

I et

Linear

I t

Parabolicround-out

I t2

will vary

c/o Paul Collier

Page 4: Ramping & Snapback

Baseline energy ramp

PELP• minimize voltage discontinuities

– start with dI/dt = 0

• ramp starts slowly– 9 GeV in the first minute– minimize dynamic errors– slow snapback: ~70 seconds

• respect ramp rate of the power converters• round-off at high energy

– persistent currents, ramp-induced eddy currents

Page 5: Ramping & Snapback

Ramp implementation: functions & timing

• Ramp is driven by current, voltage and frequency as functions of time, pre-loaded to the power converters and RF– as an array of points (delta-time, delta-reference)– 1 ms granularity– arbitrary time spacing– requires linear interpolation of supplied points

• for all powering circuits - 1700 power converters– mains, quads, triplets, insertions, spool pieces, orbit

correctors...

• Functions must take into account static & dynamic magnet errors– geometric, beam screen, eddy current in ramp– persistent current decay, snapback

Page 6: Ramping & Snapback

Functions & timing (contd.)

• The control system for the LHC power converters has dedicated controller embedded in every converter– function generation (current versus time)– current regulation– state monitoring and control (on, off, reset etc.)

• The same function generator module is also used in the RF systems– voltage & phase, frequency, radial position, power coupler

position etc.

Page 7: Ramping & Snapback

Functions & timing (contd.)

• Execution of functions is triggered by a “start ramp” timing event– the operator decides when to ramp and requests the timing

system to send the event

• The ramp stops naturally when the functions come to an end– not possible to stop while the functions are executing

• a stop “during the ramp” means generating functions which stop at the desired time

Page 8: Ramping & Snapback

Real time corrections

• The function generator controller also has a real-time input– accepts corrections up to 50 Hz– in combination with time dependent functions

• as an offset: Ref = F(t) +dFrt

• or as a fractional gain: Ref = F(t)(1 + Grt)

• Real-time corrections are eventually foreseen...– operator-controlled real-time knobs– beam-based feedback

• orbit – local and global• tune, chromaticity - will not be in place for commissioning

– feed-forward from online reference magnets• open to question…

Page 9: Ramping & Snapback

Other systems

RF• Low-level loops control the beam

– phase loop locks RF to beam to avoid emittance blowup– must eventually use synchro loop when we want to collide

• both rings locked to the same frequency program• avoids rephasing before physics

– but radial loop used during ramp commissioning since exact beam energy is not well known

• adjusts RF frequency to centre beam at pickup in IR4• measure frequency offset and feed correction forward into

functions

Beam Dump– loaded with the reference energy ramp– supplies strengths for septum, MKD, MKB as function of

beam energy– tracks the energy using a hardware ‘energy meter’

Page 10: Ramping & Snapback

Pre-requisites & initial conditions

• Circulating beams in both rings at 450 GeV with well adjusted beam parameters

• Relaxed tolerances:

– low intensities more tolerance on beam parameter variation: tune, Q' etc.

– commissioning tunes• QH and QV widely separated, more coupling allowed

– no crossing angle bumps or spectrometer compensation more aperture

Page 11: Ramping & Snapback

Pre-requisites (contd)

• Beam instrumentation– continuous PLL tune measurement available (no feedback)

• with tune history

• must be possible with pilot bunches

• feed-forward to correct the tune – closing the loop will come later

– Q’ measurement with RF frequency modulation• online (head-tail) Q’ measurement highly desirable

– orbit acquisition through the ramp• and eventually feedback around the beam dump and

collimation regions

• RMS– predictions of persistent current effects & snapback after a

fixed time on injection plateau

Page 12: Ramping & Snapback

Pre-requisites (contd)

• Machine Protection– beam dump commissioned at 450 GeV

– initial commissioning of beam loss monitors at 450 GeV

– beam interlocks verified system by system

– initial collimation settings: as for injection• TDI out, collimators at coarse settings (~ 7/8.5)

• Controls– function generation and management (trims, incorporation)

– sequencer, ramp timing commissioned

• RF– beam control: phase, synchro & radial loops operational

• Transverse feedback OFF– only needed at this stage for injection damping

Page 13: Ramping & Snapback

Phases of ramp commissioning

Single beam through snapback

Switch to nominal cycle

Ramp – single beam

Single beam to physics energy

Two beams to physics energy

[ring1, ring2]

[ring1, ring2] pilot

[ring1, ring2] pilot++

[ring1, ring2]

Start

End

450 GeV on “degauss” cycle

moderate intensity (3x1010 ppb) single bunch at 7 TeV

Page 14: Ramping & Snapback

Move to nominal cycle

“Degauss” cycle used during initial commissioning at 450 GeV– degauss “blip” eliminates

persistent current decay on the injection plateau

– but hysteresis & snapback mean we cannot ramp

0

200

400

600

800

1000

1200

1400

1600

-500 0 500 1000 1500time from beginning of injection (s)

curr

ent

(A)

standard cycle

de-magnetization cycle

must switch to nominal cycle to continue

• need to transfer all trims made on the degauss cycle to the nominal cycle – transfer of 450 GeV corrections & incorporation into the ramp

functions

Page 15: Ramping & Snapback

Initial Commissioning – Nominal Cycle

• Wait 15-20 minutes on injection plateau before injecting:

– reduced persistent currents

“nominal” snapback – bigger but reproducible

– limited further decay

• but will still need to re-commission 450 GeV

• Look at decay with beam:– energy offset vs. time– tune, chromaticity, orbit drifts– reproducibility after cycling etc.

• Establish standard operational procedure at 450 GeV– standard checks: momentum, tune, orbit, chromaticity, coupling, dispersion– then launch the ramp as quickly as possible...– try to avoid large scale readjustment of beam parameters every cycle

• Full recycle to top energy after every attempt– may initially set up for cycling to a lower energy to save time

1

1.5

2

2.5

3

0 250 500 750 1000 1250time from beginning of injection (s)

b3 (

units @

17 m

m)

15

15.5

16

16.5

17

nominal cycle

degauss cycle

Page 16: Ramping & Snapback

0

5000

10000

15000

-2000 0 2000 4000 6000

time from beginning of injection (s)

dip

ole

curr

ent

(A)

0

1

2

3

4

5

0 500 1000 1500

time from beginning of injection (s)

b3 (

units @

17 m

m)

500

700

900

1100

1300

1500

dip

ole

curr

ent

(A)

snap-back

decay

Injection ~ 1200 s

Snapback ~ 70 s

Decay & snapback – the problem

• Drift in multipole components due to decay of persistent currents and consequent snapback at start of ramp

• The challenge will be anticipating the depth of the snapback and attempting to deal with associated swing of beam parameters

Parameter Nominal tolerance Limit on bn(MB) – Inj. Approx. Decay Parameter swing

Q' Q'2 Q'± 1 ± 0.02 1.7 Q'+71/-64

c/o L. Bottura

Page 17: Ramping & Snapback

Managing snapback

• Procedure:– establish length of time on injection plateau– reference model or measurements to establish depth of

snapback– predict required corrector functions and incorporate into the

machine settings– load functions to hardware– launch ramp (timing event)– track key beam parameters through snapback: tune, orbit,

Q‘• for feed-forward to the next cycle

Page 18: Ramping & Snapback

e.g. Chromaticity

Infer persistent current change I

Extract total b3 correction

Invoke fit for snapback prediction

Convert to currents for b3 spool pieces

Incorporate into ramp functions & download

Functions invoked at ramp start

talk: L. Bottura

I

ItIsnapback

injection

ebtb

33

slow Q’ measurements andb3 corrections during injection

Just before ramping…

Extract sextupole change in dipoles b3

since b3 and I are correlated

RT corrections still possible

Timing event

Page 19: Ramping & Snapback

RMS

First attempts at ramping need model predictions good enough to get low intensities through full snapback

• If online RMS measurements were available, feed-forward of these to the next cycle would help refine the prediction of the snapback

Page 20: Ramping & Snapback

Beyond Snapback

• Things should calm down once the snapback is over

– dynamic effects considerably reduced after first 100 GeV

– eddy currents small & reproducible

– correctors optimised using feed-forward• Measurements made ‘on-the-fly’ during the ramp are used to

modify the corrector functions for subsequent cycles

L. Bottura

Page 21: Ramping & Snapback

Stopping with beam in the ramp

• Must be programmed before starting the ramp– with appropriate round-off behaviour of the functions– need to handle decay after the stop

• Restart with beam is possible in theory, but problematic– requires a new set of PELP functions to be loaded– including corrections for handling the associated snapback

Used for commissioning of beam dump, beam loss monitors, beam measurements, optics checks, physics...

Page 22: Ramping & Snapback

Machine Protection

Single beam through snapback

Switch to nominal cycle

Ramp – single beam

Single beam to physics energy

Two beams to physics energy

Start

End

Low intensity, single bunch, low energy... same as at 450 GeV

– BLMs: acquisition – no dump, check losses against thresholds

– collimators & TDCQ coarse settings

Critical machine protection systems must be in place

– minimum subset of BLMs connected to beam interlock system

– collimators interlocked in place– local orbit stabilisation around

beam cleaning insertions and dump region

– further commissioning of beam dump & BLMs

Page 23: Ramping & Snapback

System commissioning: Beam dump

• Commissioning in ramp (with pilot):– extract at pre-defined energies (small steps - to be defined)

• energy tracking (MKD, MSD, MKB)• measure, correct & check trajectories and settings, dilution

kicker sweep• check instrumentation, feedback, reference settings, interlock

thresholds, kicker timings/retriggering

– interpolate to build reference functions for settings and interlock thresholds

– increase intensity gradually at each energy• optimisation of interlocks and settings where necessary

Page 24: Ramping & Snapback

System commissioning: RF

• Control B-field correction procedures to obtain dB/B < 10-4

– single bunch pilot, inject/dump

• Control acceleration through snapback– single bunch pilot, accelerate

– dump at progressively higher energies

• Measure:– capture losses (flash loss of out-of-bucket beam at start of ramp)

– continuous measurements of frequency response of loops during ramp

– bunch length (emittance growth) - injection mismatch, RF noise

– beam losses

• Feed-forward of measured frequency offset – for eventual switch to synchro loop operation

• In preparation for physics beams:– Commissioning of programmed longitudinal emittance blowup via

RF noise

Page 25: Ramping & Snapback

Conclusions

• The procedure and mechanisms for ramping the LHC are well defined

• Strategy for commissioning the nominal cycle– wait for current decay to play out before injecting– aim for reproducibility of snapback– iterative process with feed-forward of corrections– relaxed tolerances during commissioning but the target is

likely to be moving

• RMS– Predictions essential for getting through snapback

• Machine protection– starts to become critical when ramping further than the end

of snapback– even at low intensities