PSU Supervisor Training Manual

109
Penn State University (PSU) FAMS – Manager/Supervisor/Lead Training Manual Prepared By Revision History

description

Training Manual

Transcript of PSU Supervisor Training Manual

Page 1: PSU Supervisor Training Manual

Penn State University (PSU)

FAMS – Manager/Supervisor/Lead Training Manual

Prepared By

Revision History

Page 2: PSU Supervisor Training Manual

2   Manager/Supervisor/Lead  Training  Manual  

Revision Date: February 18, 2014

Revision Number: 1

Revision # Date Collaborator Description 1.0 February 18, 2014 EDI Initial Document Click here to enter

a date.

Record of Review Date Reviewer Purpose Click here to enter a date.

Click here to enter a date.

Click here to enter a date.

Click here to enter a date.

Page 3: PSU Supervisor Training Manual

Manager/Supervisor/Lead  Training  Manual   3  

Training Guide Contents 1   FAMS – Manager/Supervisor/Lead Training..................................................................................... 8  

1.1   FAMS Project Overview.................................................................................................... 8  

1.2   Maximo Overview ............................................................................................................. 8  

1.3   Manager/Supervisor/Lead Training Manual...................................................................... 8  

2   OPP Work Order Management........................................................................................................... 9  

2.1   Overview of Work Orders and Workflow........................................................................... 9  

2.2   Work Types..................................................................................................................... 10  

2.3   Work Order Workflow Process for On Demand Work (CM, SVC, TS, MP, and EV) ...... 11  

2.3.1   Phase 1 – Triage and Planning ........................................................................................... 14  

2.3.1.1   WRC Triages........................................................................................................................................ 14  

2.3.1.2   Planner Plans (Optional) ................................................................................................................ 16  

2.3.1.3   Approval (Optional) ........................................................................................................................... 18  

2.3.2   Phase 2 – Scheduling and Execution .............................................................................. 20  

2.3.2.1   Scheduler Schedules (Optional) ................................................................................................ 21  

2.3.2.2   Supervisor Assigns ........................................................................................................................... 22  

2.3.2.3   EXERCISE: Supervisor Assigns Work Orders Using Assignment Manager .... 24  

2.3.2.4   EXERCISE: Supervisor Reassigns Work Order Using Assignment Manager . 27  

2.3.2.5   EXERCISE: Supervisor Assigns Work Orders Using Work Order Tracking ..... 28  

2.3.2.6   EXERCISE: Supervisor Routes Work Order for Reassignment to Another Work Group in Work Order Tracking ............................................................................................................................ 30  

2.3.2.7   Craftsperson Executes/Updates ................................................................................................ 32  

Page 4: PSU Supervisor Training Manual

4   Manager/Supervisor/Lead  Training  Manual  

2.3.3   Phase 3 – Post Completion Review and Closure ...................................................... 36  

2.3.3.1   Planner Post-Completion Review (Optional)....................................................................... 36  

2.3.3.2   Final Billing Complete (Integration) .......................................................................................... 37  

2.3.3.3   Work Order Closed ........................................................................................................................... 37  

2.4   Work Order Workflow for Key Request Process............................................................. 39  

2.4.1   Phase 1A – Non-OPP Request Triage and Approval.............................................. 41  

2.4.1.1   P & PS Reviews Request .............................................................................................................. 41  

2.4.1.2   OPP Approval of Controlled Keys ............................................................................................. 45  

2.4.2   Phase 1B – OPP Request Triage and Approval ........................................................ 49  

2.4.2.1   OPP Access Coordinator Creates Key Request ............................................................... 49  

2.4.2.2   OPP Access Coordinator Coordinates Approval for Key Request .......................... 50  

2.4.3   Phase 2 – Planning, Scheduling and Execution......................................................... 54  

2.4.4   Phase 3 – Key Pick Up and Closure ................................................................................ 54  

2.4.4.1   Work Reception Center Records Pick Up Information ................................................... 55  

2.4.4.2   Final Billing Complete (Integration) .......................................................................................... 56  

2.4.4.3   Work Order Closed ........................................................................................................................... 56  

2.5   Work Order Workflow Process for Preventive Maintenance........................................... 57  

2.5.1   Phase 1 – Work Order Generation .................................................................................... 58  

2.5.2   Phase 2 – Planning, Scheduling and Execution......................................................... 58  

2.5.3   Phase 3 – Post-Completion Review and Closure...................................................... 58  

2.6   Work Order Workflow Process for Jobs.......................................................................... 59  

2.6.1   Phase 1 – Create Job ............................................................................................................... 61  

Page 5: PSU Supervisor Training Manual

Manager/Supervisor/Lead  Training  Manual   5  

2.6.1.1   OPP Accounting Creates Job...................................................................................................... 61  

2.6.2   Phase 2 – Planning, Scheduling and Execution......................................................... 62  

2.6.3   Phase 3 – Post-Completion Review and Closure...................................................... 62  

2.7   Work Order Workflow Process for Fixed Tasks .............................................................. 63  

2.7.1   Phase 1 – Create Fixed Task ............................................................................................... 64  

2.7.2   Phase 2 – Execution ................................................................................................................. 64  

2.7.3   Phase 3 – Closure ...................................................................................................................... 65  

2.9   Components of a Work Order ......................................................................................... 66  

2.9.1   Work Order Tab – Header Section .................................................................................... 66  

2.9.2   Work Order Tab – Job Details Section ............................................................................ 68  

2.9.3   Work Order Tab – Budget Section .................................................................................... 68  

2.9.4   Work Order Tab – Priority Section ..................................................................................... 69  

2.9.5   Work Order Tab – Scheduling Information Section .................................................. 70  

2.9.6   Work Order Tab – Responsibility Section ...................................................................... 71  

2.9.7   Plans Tab – Tasks Section .................................................................................................... 72  

2.9.8   Plans Tab – Labor Section .................................................................................................... 72  

2.9.9   Plans Tab – Material Section................................................................................................ 73  

2.9.10   Assignments Tab – Assignments Section ................................................................. 73  

2.9.11   Actuals Tab – Labor Section ............................................................................................ 74  

2.9.12   Actuals Tab – Materials Section ..................................................................................... 75  

2.9.13   Cost Tab – Current Billing Section ................................................................................ 76  

2.9.14   Cost Tab – Fiscal Work Order Costs Section.......................................................... 76  

Page 6: PSU Supervisor Training Manual

6   Manager/Supervisor/Lead  Training  Manual  

2.9.15   Cost Tab – Work Order Costs Section........................................................................ 78  

2.9.16   Log Tab – Work Log Section............................................................................................ 79  

2.9.17   Failure Reporting Tab .......................................................................................................... 80  

3   Inventory Management for Satellite Storerooms ........................................................................... 81  

3.1   Overview of Inventory ..................................................................................................... 81  

3.2   Working with Inventory ................................................................................................... 81  

3.2.1   Reordering Inventory ................................................................................................................ 82  

3.2.1.1   Supervisor Runs Reorder for Storeroom ............................................................................... 82  

3.2.1.2   EXERCISE: Supervisor Runs Reorder for Satellite Storeroom ............................... 82  

3.2.1.3   Supervisor Reviews and Submits PR for Satellite Storeroom ................................... 86  

3.2.1.4   EXERCISE: Supervisor Reviews and Submits PR for Satellite Storeroom Reorder   87  

3.2.1.5   OPP Stores Reviews and Approves PR for Satellite Storeroom .............................. 88  

3.3   Overview of Inventory Usage.......................................................................................... 89  

3.4   Working with Inventory Usage ........................................................................................ 89  

3.4.1   Issuing Parts from Satellite Storeroom ............................................................................ 91  

3.4.1.1   EXERCISE: Issue Parts in Inventory Usage ...................................................................... 91  

3.4.2   Returning Parts to Satellite Storeroom ............................................................................ 94  

3.4.2.1   EXERCISE: Return Parts in Inventory Usage ................................................................... 94  

3.5   Refrigerant Tracking Overview ....................................................................................... 98  

3.5.1   Issuing Refrigerant ...................................................................................................................101  

3.5.1.1   EXERCISE: Issue Refrigerant from Craftsperson to Work Order in Inventory Usage   101  

3.5.1.2   EXERCISE: Approving (Completing) Refrigerant Issue in Inventory Usage . 104  

Page 7: PSU Supervisor Training Manual

Manager/Supervisor/Lead  Training  Manual   7  

3.5.2   Transferring Refrigerant ........................................................................................................105  

3.5.2.1   EXERCISE: Transfer Refrigerant from Supervisor to Craftsperson in Inventory Usage   105  

Page 8: PSU Supervisor Training Manual

8   Manager/Supervisor/Lead  Training  Manual  

1 FAMS – Manager/Supervisor/Lead Training 1.1 FAMS Project Overview FAMS (Facilities Asset Management System) is a major step forward in the evolution of Enterprise Asset Management (EAM) at Penn State. The FAMS system is built on the Maximo 7.5 platform. Efficient use of the Maximo 7.5 system to perform everyday asset and work management tasks will be critical to realizing the goals of the FAMS project. 1.2 Maximo Overview IBM® Maximo® Asset Management is an integrated productivity tool and database that helps you manage all of your asset types on a single software platform. Built on a service-oriented architecture (SOA), Maximo Asset Management delivers a comprehensive view of all asset types, their conditions and locations, and the work processes that support them, to provide you with optimal planning, control, audit, and compliance capability. The Maximo database provides critical information about assets and locations, including key attributes, their configuration, and their physical and logical relationships to other resources. Using Maximo, you can manage and track events related to your assets from cradle to grave including creating, assigning, monitoring, notifying, and reporting on key work and work support processes such as work orders and purchase orders, including status, from start to finish. 1.3 Manager/Supervisor/Lead Training Manual This training manual focuses on the role of the Manager/Supervisor/Lead user as it executes functions in the FAMS system. This manual will cover the applications and use cases that a Manager/Supervisor/Lead user will be expected to perform, on regular basis, inside of the system. The manual may not cover some functionality that the Manager/Supervisor/Lead user has access to if it is not directly related to a common activity that they are expected to perform. Specifically, this manual covers overviews, processes and specific exercise associated with the following topics:

• Work Management • Inventory Management of Satellite Storerooms

Page 9: PSU Supervisor Training Manual

Manager/Supervisor/Lead  Training  Manual   9  

2 OPP Work Order Management 2.1 Overview of Work Orders and Workflow Work Orders are used to identify, plan, schedule, execute and track the work that is performed at Locations and/or on Assets and systems throughout the campus. Initially, a work order is a request for work to be performed. Once completed, a work order is a record of activities performed that make up the history of our Locations, Assets and systems.

The information that is contained on a work order includes the following:

• The tasks that were performed • The labor hours involved in performing the work • The services used, if any • The materials used, if any • The tools required to do the work • The assets worked on • The locations where the work was performed

When you create a work order, you initiate the work management process and create a historical record of the work requested and performed. The work management process in the FAMS system is controlled by an electronic workflow process. This workflow, based on work types, ensures the right steps are performed, by the right people, in the right order and at the right time. At certain times in the workflow, direct assignments will determine who is to take action on a record. At other times, information on the work order including status, responsible group/individual, and assignment status will determine who is to take action. At all times, any status changes to be performed on a work order record will be done using workflow options.

As a work order record is processed through the work management workflow, more sections of the work order record will be populated with the information about what was both planned to be done and what was actually done.

In this section of the training manual you will learn about the basic components of Work Order and Job records, the different Work Types, and the workflow processes for each Work Type.

Page 10: PSU Supervisor Training Manual

10   Manager/Supervisor/Lead  Training  Manual  

2.2 Work Types

Work Types are assigned to Work Orders to categorize them by the nature of the work being performed. Ultimately, this serves two very important purposes:

• Categorization of Work • Processing of Work

Categorization is the concept that it allows you to sort the work already performed or still in progress to determine how your facilities are performing. For example, is most of the work you are doing trouble or breakdown work or is most of it preventive maintenance. An organization that is trying to establish an Enterprise Asset Management (EAM) program and not just a repair service considers this type of information.

Processing of work is the concept that different types of work require different pre-, post-, and in progress processing tasks. For example, a corrective maintenance work order to repair a failure requires planning to analyze the failure and identify a fix. Whereas, a preventive maintenance work order already has a plan defined for it and does not need any planning prior to execution. In order to ensure that the right steps are done by the right people at the right time, we must have processes that dictate what those steps are based on work type.

Along with the FAMS implementation, the following Work Types will be used for work orders:

Work Type Abbr. Definition

Corrective Maintenance

CM Work to return an asset/location to its designed intent after a failure.

Service Work SVC Work that does not affect the reliability or maintenance history of any assets/locations and is not related to a failure. Typically driven by customer request.

Minor Project MP Smaller changes, enhancements, and upgrades to assets/locations that do not require a contract. May require some design assistance and level 1 permitting, but limited to work with a single funding source.

Page 11: PSU Supervisor Training Manual

Manager/Supervisor/Lead  Training  Manual   11  

Work Type Abbr. Definition

Trouble Shooting

TS Performance of an assessment in support of the planning process prior to performing another work type. Should be a child to a work order of another type.

Event EV Work related to a distinct event that does not affect the reliability or maintenance history of any assets/locations.

Preventive Maintenance

PM Proactive work to maintain an asset/location in performance of its designed intent.

Job JOB Larger changes, enhancements, and upgrades to assets/locations that require a contract. Require design assistance, permitting beyond level 1, and may involve multiple funding sources. Typically associated with a Tririga Contract Number.

Fixed Task FT Routine, recurring, operational work. (Also known as Standing Orders.)

Key Request KR Work related to new keys or re-keying generated from a Key Request.

The following sections will describe how each of the above work types are processed. Note that Corrective Maintenance (CM), Service Work (SVC), Minor Project (MP), Trouble Shooting (TS), and Event (EV) work orders all follow the same workflow process and are collectively referenced as On-Demand Work in the following section.

2.3 Work Order Workflow Process for On Demand Work (CM, SVC, TS, MP, and EV)

On-demand work (CM, SVC, TS, MP and EV work types) is typically initiated based on a customer request, tradesperson problem report, or as a follow up work order. For this reason, these work orders must be triaged and, in some cases, planned before they are assigned and executed. It should be noted that any work order that is submitted without a work type will initially follow this

Page 12: PSU Supervisor Training Manual

12   Manager/Supervisor/Lead  Training  Manual  

workflow. From start to finish, work orders with these work types may proceed through the following phases, each of which will be described in greater detail:

Triage

Planning

Phase 1 – Triage and Planning

Approval

Scheduling

Assignment

Phase 2 – Scheduling and Execution

Execution

Post-Completion Review Phase 3 – Post-Completion Review and Closure Closure

The workflow is being presented in phases because the workflow is set up to behave a little differently in each of these phases.

During Phase 1 – Triage and Planning, workflow is set up to make discrete assignments to individuals and groups where the assigned individuals are the

1  -­‐  Triage  and  Planning  

2  -­‐  Scheduling  and  Execution  

3  -­‐  Review  and  Closure  

Page 13: PSU Supervisor Training Manual

Manager/Supervisor/Lead  Training  Manual   13  

only users that can access the workflow options for the record. During this phase, workflow actions show exactly who is assigned and records reside in specific users’ workflow inbox.

During Phase 2 – Scheduling and Execution, work orders are not actively in a workflow, meaning that there are not discrete assignments to individuals or groups and anyone with appropriate permissions is allowed to access the workflow options for the record. During this phase, users that are responsible for the record are engaged via Start Center result sets and/or saved queries in the appropriate applications. During this phase, users primarily use specific function-based applications like Scheduler, Assignment Manager, Mobile Work Manager, or Quick Reporting to interact with the record. Whenever a status change is required, the user still uses workflow, but is presented with all of the available status change options at that particular point in the process. The reason for this design is to allow applications like Assignment Manager and Mobile Work Manager to function most efficiently without workflow getting in the way.

During Phase 3 – Post-Completion Review, workflow is again set up to make discrete assignments to individuals and groups where the assigned individuals are the only users that can access the workflow options for the record. During this phase, workflow actions show exactly who is assigned and records reside in specific users’ workflow inbox. Once the Work Order is in a waiting to be closed (WCLOSE) status, the work orders are not in workflow at all. At this point, work orders are sitting in a “Waiting to Close” status and will automatically be close when an integration informs Maximo that billing is complete.

Page 14: PSU Supervisor Training Manual

14   Manager/Supervisor/Lead  Training  Manual  

2.3.1 Phase 1 – Triage and Planning

2.3.1.1 WRC Triages

The workflow begins when a work order is submitted via SuiteReq, a mobile device, or created directly in Maximo and routed. The workflow first assigns the record to the Work Reception Center (WRC) person group. Every person in this person group will receive an assignment for the work order and it will be displayed in their workflow in-box. Any user from that group can perform the next step in workflow to take ownership of the record for triage, which will end the assignment for all other users of the group and remove it from their workflow in-boxes. Once one of the users from the group has taken ownership of the record via workflow, the record will move into a status of “TRIAGE” and reside only in the owner’s workflow in-box.

Note: The owner will be the only user that can perform the next routing step.

At the “Triage” step in the workflow, the WRC can review and make updates to the record. Key fields to review/update:

WRC  Triages  Planner  Plans  

(Optional)  

Approval  (Optional)  

On  to  Phase  2  -­‐  

Scheduling  and  

Execution  

Page 15: PSU Supervisor Training Manual

Manager/Supervisor/Lead  Training  Manual   15  

Key Fields for Triage Step:

Description/Long Description Work Type

Asset/Location GL Account/Customer Billing Number

Urgency/Priority Target Start/Finish

Responsibility Fields

Once the WRC has completed their updates to the record, they have a limited number of workflow routing options that are described below:

Option What Happens Next Dependencies

Cancel the Work Order Work Order Status goes to Cancel (CAN) and workflow stops.

Process ends.

Not required, but might populate Work Log section with reason for cancellation.

Emerging work – Route directly to Work Group

Work Order Status goes to Approved (APPR) and workflow stops.

Work Order goes directly to Phase 2 of process.

Must do either of the below first:

• Populate the Work Group Field OR

• Create assignment for Technician (Emergencies)

Not Emerging work – Route to Planner Group

Work Order Status goes to Waiting Planning (WPLAN) and gets assigned to the specified Planner Group.

Must populate the Planner Group field first.

Page 16: PSU Supervisor Training Manual

16   Manager/Supervisor/Lead  Training  Manual  

Option What Happens Next Dependencies

Place Work Order back into WRC Queue.

Work Order Status goes back to New (NEW) and gets assigned to the WRC Person Group.

N/A

Note: It should be noted that the “Emerging Work” option would be selected in the case of an emergency Work Order, where the dispatched Technician has already been assigned.

2.3.1.2 Planner Plans (Optional)

If the “non-Emerging” option is selected, workflow will assign the Work Order to the Planner Group person group identified on the Work Order. Every person in this person group will receive an assignment for the work order and it will be displayed in their workflow in-box. Any user from that group can perform the next step in workflow to take ownership of the record for planning, which will end the assignment for all other users of the group and remove it from their workflow in-boxes. Once one of the users from the group has taken ownership of the record via workflow, the record will move into a status of “PLANNING” and reside only in the owner’s workflow in-box.

Note: The owner will be the only user that can perform the next routing step.

At the “Planning” step in the workflow, the Planner can review and make updates to the record. Key fields/sections to review/update:

Key Fields/Sections for Planning Step:

Description/Long Description Work Type

Asset/Location Urgency/Priority

Target Start/Finish Job Plan

Duration Work Group

Page 17: PSU Supervisor Training Manual

Manager/Supervisor/Lead  Training  Manual   17  

Plans Tab – Steps Plans Tab - Labor

Plans Tab – Materials

Once the Planner has completed their updates to the record, they have a limited number of workflow routing options that are described below:

Option What Happens Next Dependencies

Cancel the Work Order Work Order Status goes to Cancel (CAN) and workflow stops.

Process ends.

Not required, but might populate Work Log section with reason for cancellation.

Route Work Order for Waiting to be Scheduled

Work Order Status goes to Waiting to be Scheduled (WSCH) and workflow stops.

Work Order goes to Phase 2 of process.

Not required, but might populate the following first:

• Work Group • Scheduler Group

Place the Work Order into Backlog.

Work Order Status goes to Backlog (BACKLOG) and workflow stops.

Work Order can be resubmitted to workflow at any time and it will go back to the Planner.

Must populate the Backlog Reason field first.

Route the Work Order for Approval

Work Order Status goes back to Waiting Approval (WAPPR) and gets assigned to the Person in the Approver field.

Must populate Approver field first.

Page 18: PSU Supervisor Training Manual

18   Manager/Supervisor/Lead  Training  Manual  

Option What Happens Next Dependencies

Place the Work Order Back into the Waiting Planning Queue

Work Order Status goes back to Waiting Planning (WPLAN) and gets assigned to the Planner Person Group on the Work Order.

N/A

2.3.1.3 Approval (Optional)

If the “Route for Approvals” option is selected, workflow assigns the Work Order to the individual identified as the Approver on the Work Order.

Note: At this point, the Work Order will reside only in the Approvers workflow in-box. The Approver will be the only user that can perform the next routing step.

At the “Approval” step in the workflow, the Approver user would review all of the information provided on the Work Order and coordinate any necessary approvals that are exterior to the Maximo system.

Once the Approver has decided if they approve of the Work Order, they have a limited number of workflow routing options that are described below:

Option What Happens Next Dependencies

Approve the Work Order Work Order Status goes to Waiting to be Scheduled (WSCH) and workflow stops.

Work Order goes to Phase 2 of process.

N/A

Page 19: PSU Supervisor Training Manual

Manager/Supervisor/Lead  Training  Manual   19  

Option What Happens Next Dependencies

Not Approve the Work Order

Work Order Status goes back to the Planning (PLANNING) status and is assigned to the Planner that planned the Work Order

Not required, but might populate Work Log section with reason for not approving.

At the end of this phase of the process, the Work Order will be in one of the following conditions:

Possible Ending Conditions

for Phase 1 of Process

Next Steps

1. Canceled status with workflow stopped.

N/A

2. Approved status with workflow stopped.

Supervisor picks up Work Order in saved queries to be assigned. (Phase 2)

3. Waiting to be Scheduled status with workflow stopped.

Scheduler picks up Work Order in saved queries to be scheduled. (Phase 2)

4. Backlog Status with workflow stopped.

Planner picks up Work order in saved queries to be restarted at Planning step. (Phase 1)

Page 20: PSU Supervisor Training Manual

20   Manager/Supervisor/Lead  Training  Manual  

2.3.2 Phase 2 – Scheduling and Execution

As described above, during this phase, work orders are not actively in a workflow in between actions.

Note: This means that there are not discrete assignments to individuals or groups. It also means that anyone with appropriate permissions is allowed to access the workflow options for the record.

During this phase, users that are responsible for the record find their records via Start Center result sets and/or saved queries in the appropriate applications. During this phase, users primarily use specific function-based applications like Scheduler, Assignment Manager, Mobile Work Manager, or Quick Reporting to interact with the record.

Important: Whenever a status change is required, the user uses the workflow button and is presented with all of the available status change options at that particular point in the process.

Once an option is selected, the workflow fires to make the status change and then immediately stops again. The reason for this design is to allow applications like Assignment Manager and Mobile Work Manager to function most efficiently without workflow getting in the way.

Scheduler  Schedules  (Optional)  

Supervisor  Assigns  

Craftsperson  Executes/Updates  

Craftsperson  Completes  

On  to  Phase  3  -­‐  Review  and  Closure  

Page 21: PSU Supervisor Training Manual

Manager/Supervisor/Lead  Training  Manual   21  

In Phase 2 – Scheduling and Execution, a work order can begin in one of two places. Either:

1. A Work Order requires scheduling and comes into the process in a Waiting to be Scheduled status (WSCH)

OR

2. The Work Order is emerging work and comes into the process in the Approved (APPR) status.

Note: Work Orders in an Approved status bypass the scheduling steps and go directly to the Supervisor.

2.3.2.1 Scheduler Schedules (Optional)

For Work Orders in a Waiting to be Scheduled (WSCH) status, Schedulers would utilize a Start Center Result Set, Saved Query in Work Order Tracking, or Saved Query in a Scheduling application to identify which Work Orders are ready to be scheduled. They would use either Work Order Tracking or a Scheduling application to update the following Key Fields:

Key Fields for Scheduling Step:

Scheduled Start Scheduled Finish

Duration Work Group

Once the Scheduler has completed their updates to the record, they have a limited number of workflow routing options that are described below:

Option What Happens Next Dependencies

Route Work Order for Execution

Work Order Status goes to Approved (APPR) and workflow stops.

Supervisor picks up Work Order in saved queries to be assigned.

Must populate Work Group field.

Not required, but should populate the following first:

• Scheduled Start • Scheduled Finish

Page 22: PSU Supervisor Training Manual

22   Manager/Supervisor/Lead  Training  Manual  

Option What Happens Next Dependencies

Route the Work Order back to the Planner Group for additional planning

Work Order Status goes back to Requires Re-planning (REPLAN) and gets assigned to the Planner Person Group on the Work Order.

Work Order goes back to Phase 1.

Must populate the Planner Group first.

2.3.2.2 Supervisor Assigns

All work that is in an approved status is ready to be assigned to craftspeople. This includes Work Orders that have been scheduled, like in the previous step, or Work Orders that were identified as “Emerging” and routed directly to an approved status from the “Triage” steps in Phase 1.

To assign approved Work Orders, Supervisors would typically utilize a Saved Query in the Assignment Manager application to identify which Work Orders are ready to be assigned.

Note: a Supervisor might also use a Start Center Result Set or Saved Query in Work Order Tracking to catch one-off Work Orders that need to be assigned.)

In Assignment Manager, the Supervisor would assign the Work Order to a craftsperson or craftspeople.

Key Fields for Assignment Step:

Laborer Assignment Start Date

Note: Often, this step will be performed across multiple records at the same time.

Important: There is no need for a Supervisor to change the status of the Work Order at this point, if the work is assigned. Craftspeople will see their assigned records on the Mobile Device or in their Saved Queries regardless of status.

Page 23: PSU Supervisor Training Manual

Manager/Supervisor/Lead  Training  Manual   23  

The Supervisor does have the following workflow options available to them, if they choose to exercise them:

Note: All of these options only change the status of the record and then workflow stops immediately again.

Option What Happens Next Dependencies

Change Status to “Rescheduling Required”

Work Order Status goes to Rescheduling Required (RSCH) and workflow stops.

Scheduler picks up Work Order in saved queries to be scheduled.

Not required, but might populate Work Log section with reason for rescheduling.

Change Status to “Reassignment Required”

Work Order Status goes to Reassignment Required (REASSIGN) and workflow stops.

Supervisor picks up Work Order in saved queries to be assigned.

If moving to another Work Group, must populate Work Group field.

Change Status to “Waiting Materials”

Work Order Status goes to Waiting on Materials (WMATL) and workflow stops

Supervisor/Technician picks up Work Order in saved queries when materials arrive.

N/A

Page 24: PSU Supervisor Training Manual

24   Manager/Supervisor/Lead  Training  Manual  

Option What Happens Next Dependencies

Change Status to “In Progress”

Work Order Status goes to In Progress (INPRG) and workflow stops.

Technician continues to process Work Order just like APPR.

N/A

Note: The Supervisor Assigns step could be executed more than once on a Work Order. This is particularly true for multi-craft Work Orders or when work is interrupted across shifts.

Important: Emergency work (work that is dispatched before a Work Order is even created) will actually come out of the “Triage” steps with a craftsperson already assigned and in the approved status. These work orders will immediately show up as assigned for the craftsperson.

2.3.2.3 EXERCISE: Supervisor Assigns Work Orders Using Assignment Manager

Work Orders that require Assignment will be accessible via a Saved Query in the Assignment Manager application.

Note: Every Manager/Supervisor/Lead that will be assigning work should have a default saved query in Assignment Manager. Your saved query should be looking for Work Orders that are for your “Work Group” that aren’t currently assigned.

1. Use the “Go To” menu to navigate to Work Orders Assignment Manager.

Page 25: PSU Supervisor Training Manual

Manager/Supervisor/Lead  Training  Manual   25  

Note: You can also get to Assignment Manager by clicking on the link in your “Favorite Applications” portlet on your Start Center.

In Assignment Manager, your view will be split into two separate windows. The top window, “Work List”, will present you with Work Orders that require assignment. The bottom window, “Labor List”, will present you with Laborers that are available to be assigned to Work Orders. You should have default saved queries established to isolate work you, specifically, need to assign in the “Work List” and Laborers you, specifically, are responsible for in the “Labor List”. Your job will be to match up Work Orders with Laborers based on skill set and availability.

To assign a Work Order to a Laborer:

2. Place a checkmark in the box to the left of the Work Order to be assigned, by clicking on it.

Page 26: PSU Supervisor Training Manual

26   Manager/Supervisor/Lead  Training  Manual  

Note: If you want to assign more than one Work Order to a Laborer at one time, you can select multiple Work Orders from the Work List at once.

3. OPTIONAL: If you have more Laborers in your Work Group than will fit on

a single page in the Labor window, you can select the “Filter Labor to Match Work” button and then select “OK” to isolate only the Laborers whose Craft/Skill match the Craft/Skill required by the work.

4. To assign the Work Order to the Laborer on a specific day, you can click on the available hours displayed for that Laborer for the specific day.

Note: You can view other available days by selecting “Select Work Date” and choosing another date. By default, the system shows you today plus the next 6 days.

If there was a planned labor entry on the Work Order and it is a match with the Craft/Skill of the Laborer selected, the assignment will be made automatically and the availability of the Laborer updated to reflect the assignment.

Note: If there was not a planned labor entry on the Work Order or the Craft/Skill planned does not match the Craft/Skill of the Laborer selected, and additional pop-up window will be displayed where you can update the assigned duration and confirm the assignment.

Alternate Method: You can also make an assignment by placing a checkmark in the box to the left of the Laborer(s) you want to assign the work to and

selecting the Assign Labor icon from the toolbar. Please note that this method is the required method for assigning multiple Laborers to a Work Order at once (by checking the box for more than one Laborer.)

Page 27: PSU Supervisor Training Manual

Manager/Supervisor/Lead  Training  Manual   27  

Typically, a Manager/Supervisor/Lead would come into Assignment Manager on regular basis to assign multiple Work Orders for the next shift or next several shifts. The steps above can be repeated until all Work Orders to be assigned have been assigned to Laborers.

2.3.2.4 EXERCISE: Supervisor Reassigns Work Order Using Assignment Manager

Occasionally, a Manager/Supervisor/Lead may need to reassign Work Orders that have already been assigned. This can be done using the Assignment Manager application.

Important: This method should only be used if the assignment has not yet been started. If the assignment has been started, then the current assignment should be completed in the system and a new Assignment created for the Work Order.

To reassign an assignment that hasn’t been started:

1. Use the “Go To” menu to navigate to Work Orders Assignment Manager.

2. In the Labor List section, find the Laborer that currently has the assignment and select the “Show Assignments” icon in that row.

3. In the “Show Assignments” dialogue window, click on the “Mark for Deletion” icon to the right of the assignment to be reassigned and select “OK.”

Page 28: PSU Supervisor Training Manual

28   Manager/Supervisor/Lead  Training  Manual  

4. In the “Show Assignments” dialogue window, click on the “Mark for Deletion” icon to the right of the assignment to be reassigned and select “OK.”

To reassign the Work Order to a new Laborer:

5. Place a checkmark in the box to the left of the Work Order to be assigned,

by clicking on it.

6. To assign the Work Order to the new Laborer on a specific day, you can

click on the available hours displayed for the new Laborer for the specific day.

2.3.2.5 EXERCISE: Supervisor Assigns Work Orders Using Work Order Tracking

Work Orders can also be assigned one-at-a-time using the Work Order Tracking application. This method might be used when there is a need to quickly assign one specific Work Order outside of the normal assignment process.

Note: Every Manager/Supervisor/Lead that will be assigning work should have a result set on their Start Center that displays Work Orders that are for their “Work Group” that aren’t currently assigned.

1. From the “Work Orders Requiring Assignment – My Work Group” result set on your Start Center, click on the Work Order Number of the Work Order to be assigned.

Page 29: PSU Supervisor Training Manual

Manager/Supervisor/Lead  Training  Manual   29  

Note: You could also go into Work Order Tracking and search for the Work Order to be assigned.

2. Navigate to the “Assignments” tab by clicking on it.

If there is planned labor on the Work Order, there will already be row in the Assignments section that just needs to the Labor field to be populated:

Note: If there is no planned labor on the Work Order, the Manager/Supervisor/Lead can use the “New Row” button in the Assignments section to create an assignment manually.

3. With the appropriate Assignment row highlighted, select the “Available

Labor” button.

4. Search for and select the appropriate Laborer by clicking on their Labor ID.

Page 30: PSU Supervisor Training Manual

30   Manager/Supervisor/Lead  Training  Manual  

5. Optional: You can update the “Scheduled Start” and/or “Hours” for the assignment by updating those fields in the Assignments section.

6. Save the record. The Work Order is now assigned to the Laborer selected. Additional assignments can be made using the steps above or selecting “New Row”.

2.3.2.6 EXERCISE: Supervisor Routes Work Order for Reassignment to Another Work Group in Work Order Tracking

In some cases, a Manager/Supervisor/Lead may determine that a Work Order routed to them needs to be re-routed to another Work Group. The Manager/Supervisor/Lead can use the Work Order Tracking application and workflow to do this.

1. From the “Work Orders Requiring Assignment – My Work Group” result set on your Start Center, click on the Work Order Number of the Work Order to be re-routed.

Page 31: PSU Supervisor Training Manual

Manager/Supervisor/Lead  Training  Manual   31  

Note: You could also go into Work Order Tracking and search for the Work Order to be re-routed.

2. Use the “Detail Menu” icon next to the “Work Group” field in the Responsibilities section and then “Select Value” to select the new Work Group for the Work Order.

3. Use the “Detail Menu” icon next to the “Supervisor” field in the Responsibilities section and then “Select Value” to select the new Supervisor for the Work Order.

4. Select the “Route Workflow” icon from the toolbar. 5. Select the “Work Order needs to be re-assigned.” option and then select

“OK.”

Page 32: PSU Supervisor Training Manual

32   Manager/Supervisor/Lead  Training  Manual  

The Work Order will no longer be in your “Work Orders Requiring Assignment – My Work Group” result set and will show up in the result set and saved queries for the new Supervisor.

2.3.2.7 Craftsperson Executes/Updates

Craftspeople will be able to see the Work Orders that are assigned to them in several locations:

• Start Center Result Set • Quick Reporting (via Saved Query) • Mobile Work Manager

At this point in the process, craftspeople will begin preparing for and working on their assigned Work Orders. They will utilize Quick Reporting or Mobile Work Manager to perform updates like:

Key Fields/Sections for Updating Work Orders during Execution:

Labor Tab (Time Entries) Materials Tab

Failure Codes Work Log

Craftspeople via Mobile Work Manager and/or Quick Reporting have the ability to make several status changes while in the “Execution” phase of the process. The status changes will happen automatically based on actions in Mobile Work Manager, but can be initiated in Quick Reporting via workflow.

Note: Not all of these status changes are required. They are available to provide more information or alert the appropriate people of issues.

Page 33: PSU Supervisor Training Manual

Manager/Supervisor/Lead  Training  Manual   33  

Option What Happens Next Dependencies

Change Status to “Reassignment Required”

Work Order Status goes to Reassignment Required (REASSIGN) and workflow stops.

Supervisor picks up Work Order in saved queries to be assigned.

If moving to another Work Group, must populate Work Group field.

Change Status to “Waiting Materials”

Work Order Status goes to Waiting on Materials (WMATL) and workflow stops

Supervisor/Technician picks up Work Order in saved queries when materials arrive.

N/A

Change Status to “In Progress”

Work Order Status goes to In Progress (INPRG) and workflow stops.

Technician continues to process Work Order just like APPR.

N/A

Change Status to “Received” (MOBILE ONLY)

Work Order Status goes to Received (RECEIVED).

Technician continues to process Work Order just like APPR.

Happens automatically when a Work Order is received on the Mobile Device.

Page 34: PSU Supervisor Training Manual

34   Manager/Supervisor/Lead  Training  Manual  

Option What Happens Next Dependencies

Change Status to “Started” (MOBILE ONLY)

Work Order Status goes to Started (STARTED).

Technician continues to process Work Order just like APPR.

Happens automatically when a Work Order is started on the Mobile Device.

Change Status to “Hold” (MOBILE ONLY)

Work Order Status goes to Hold (HOLD).

Technician continues to process Work Order just like APPR.

Happens automatically when a Work Order is put on hold on the Mobile Device.

Change Status to “Complete”

Work Order Status goes to Complete (COMP).

Work Order enters back into workflow for post-completion processing, Phase 3 of process.

Not required, but the following should be entered first:

• Labor Time • Materials • Failure Codes • Work Log Updates

Note: Until the Work Order is in the complete (COMP) status, it might be reassigned multiple times and be taken through several of the statuses above. In some cases, it may even be taken the same status more than once.

Once a Work Order is taken to the complete (COMP) status, the workflow will automatically pick it up and take into Phase 3 of the process.

At the end of this phase of the process, the Work Order can only be in one condition:

Possible Ending Conditions for Phase 2 of Process

Next Steps

1. Complete status with workflow restarted.

Workflow will evaluate the Work Order for post-completion processing.

Page 35: PSU Supervisor Training Manual

Manager/Supervisor/Lead  Training  Manual   35  

Important: When the Work Order is set to the Complete (COMP) status, workflow will automatically uncheck the “Accepts Charges?” flag on the work order. This is to protect against new charges potentially being initiated after the financial system “final bills” the Work Order. All actuals updates should take place before completing the Work Order.

Page 36: PSU Supervisor Training Manual

36   Manager/Supervisor/Lead  Training  Manual  

2.3.3 Phase 3 – Post Completion Review and Closure

In Phase 3 – Post Completion Review and Closure, a work order is immediately evaluated and routed one of two ways. Either:

1. If the “JP Changes?” box is checked on the Work Order, the workflow will change the status to Waiting Review (WREVIEW) and assign the record to the Planner person group identified on the Work Order.

OR

2. If the “JP Changes?” box is not checked on the Work Order, workflow will change the status of the Work Order to waiting to be closed (WCLOSE) and workflow will stop on the record.

2.3.3.1 Planner Post-Completion Review (Optional)

If a post-completion review is required, the workflow will assign the record to the Planner person group identified on the Work Order. Every person in this person group will receive an assignment for the work order and it will be displayed in their workflow in-box.

Planner  Performs  Post-­‐Completion  Review  (Optional)  

Final  Billing  Complete  

(Integration)  

Work  Order  Closed  

(Automatic)  Process  Ends  

Page 37: PSU Supervisor Training Manual

Manager/Supervisor/Lead  Training  Manual   37  

Note: Any user from that group can perform the next step in workflow to record the review as complete.

A planner would review this Work Order to determine if, based on feedback from the crafts, the associated Job Plan needs to be updated. Other Work Order updates might be identified by the craft as well. The following key fields should be reviewed by the Planner in this situation:

Key Fields/Sections for Post-Completion Review Step:

Work Log (for Craft Comments) Plans Tab – Steps

Plans Tab - Labor Plans Tab - Materials

Actuals Tab – Labor Actuals Tab - Materials

Description/Long Description Job Plan

The only option available at this point in the process is to say that the review is complete, any actions as a result of the review take place independently of the Work Order or workflow.

Option What Happens Next Dependencies

Mark Review as Complete

Work Order Status goes to Waiting to be Closed (WCLOSE) and workflow stops.

N/A

2.3.3.2 Final Billing Complete (Integration)

Work Orders will remain in a waiting to be closed (WCLOSE) until they are “Final Billed.” An integration with the VM system will update the billing information on Work Orders and eventually mark the Work Order as “Final Billed”.

2.3.3.3 Work Order Closed

An escalation will monitor the system for Work Orders that are in the waiting to be closed (WCLOSE) status and are marked as “Final Billed” and will

Page 38: PSU Supervisor Training Manual

38   Manager/Supervisor/Lead  Training  Manual  

automatically change the status of these records to closed (CLOSE.)

Page 39: PSU Supervisor Training Manual

Manager/Supervisor/Lead  Training  Manual   39  

2.4 Work Order Workflow for Key Request Process

Key request work (the KEY work type) is initiated based on a customer request and requires a review for validity. For this reason, these work orders must be triaged before they are planned, assigned and executed. There are also some specific steps to perform prior to closure for these Work Orders. From start to finish, work orders with these work types may proceed through the following phases, each of which will be described in greater detail:

Triage Phase 1A – Non-OPP Request Triage and Approval Approval

Triage Phase 1B – OPP Request Triage and Approval Approval

Phase 2 – Planning, Scheduling and Planning

1A  -­‐  Non-­‐OPP  

Request  Approval  

1B  -­‐  OPP  Request  Approval  

2  -­‐  Planning,  Scheduling,  Execution  

3  -­‐  Key  Pick  Up  and  Closure    

Page 40: PSU Supervisor Training Manual

40   Manager/Supervisor/Lead  Training  Manual  

Scheduling

Assignment

Execution

Execution

Key Pick Up Phase 3 – Key Pick Up and Closure

Closure

The workflow is being presented in phases because the workflow is set up to behave a little differently in each of these phases.

During Phases 1A or 1B – the workflow is set up to make discrete assignments to individuals and groups where the assigned individuals are the only users that can access the workflow options for the record. During this phase, workflow actions show exactly who is assigned and records reside in specific users’ workflow inbox.

During Phase 2 – Planning, Scheduling and Execution, KEY Work Orders follow the exact same process as “On-Demand Work” described in the previous section. Once a Work Order leaves Phase 1A or 1B of this process, it starts at the “WPLAN” step of the “On-Demand Work” process and follows the same steps of that process until the Work Order is completed (COMP) at the end of Phase 2.

During Phase 3 – Key Pick Up and Closure, workflow is again set up to make discrete assignments to individuals and groups where the assigned individuals are the only users that can access the workflow options for the record. During this phase, workflow actions show exactly who is assigned and records reside in specific users’ workflow inbox. Once the Work Order is in a waiting to be closed (WCLOSE) status, the work orders are not in workflow at all. At this point, work orders are “Waiting to Close” status and will automatically be closed when an integration informs Maximo that billing is complete.

Page 41: PSU Supervisor Training Manual

Manager/Supervisor/Lead  Training  Manual   41  

2.4.1 Phase 1A – Non-OPP Request Triage and Approval

2.4.1.1 P & PS Reviews Request

The workflow begins when a Key Request is submitted via SuiteReq. The workflow first assigns the record to the Police and Public Services (P&PS) person group. Every person in this person group will receive an assignment for the work order and it will be displayed in their workflow in-box.

Exception: The assignment list for Master Keys will be a smaller sub-set of the P&PS Person group and is dictated by membership in the P&PSMAST person group.

Any user from that group can perform the next step in workflow to take ownership of the record for review, which will end the assignment for all other users of the group and remove it from their workflow in-boxes. Once one of the users from the group has taken ownership of the record via workflow, that record will only reside in the owner’s workflow in-box.

Note: The owner will be the only user that can perform the next routing step.

P  &  PS  Reviews  Request  

P  &  PS  Approves  Restricted  Keys  

(Optional)  

OPP  Approval  for  Controlled  

Keys  (Optional)  

Phase  2  -­‐  Planning  Scheduling  

and  Execution  

Page 42: PSU Supervisor Training Manual

42   Manager/Supervisor/Lead  Training  Manual  

At the “P&PS Review” step in the workflow, the P&PS user can review and make updates to the record. Key fields to review/update, most of which reside on the “Keys” tab of Work Order Tracking:

Key Fields for Triage Step:

Description/Long Description Work Type

Asset/Location Grand Master?

Building Master? Animal Facility?

Athletic Facility? Leased Property?

Building Entry? Can Be Facilitated Electronically?

Under AC’s Dept. Control? Mechanical, Electrical or Tele. Room?

Note: The Key Request should also have a Key Request Form attached to it that should be reviewed.

Once the P&PS user has completed their review/updates to the record, they will have a series of workflow routing options that are described below:

The initial options available to the user are:

1. The request is for non-Restricted Key.

OR

2. The request is for a Restricted Key.

Based on their selection, their next routing options are different.

If Non-Restricted Key is Selected

Option What Happens Next Dependencies

Requester is authorized to request for building specified.

Work Order Status goes to Waiting to be Planned (WPLAN) and is assigned to the Planner Group on the Work Order.

The Work Order goes to Phase 2.

Planner Group must be identified on Work Order.

Page 43: PSU Supervisor Training Manual

Manager/Supervisor/Lead  Training  Manual   43  

Option What Happens Next Dependencies

Requester is NOT authorized to request for building specified

THEN

External approval has been received.

Work Order Status goes to Waiting to be Planned (WPLAN) and is assigned to the Planner Group on the Work Order.

The Work Order goes to Phase 2.

Planner Group must be identified on Work Order.

The person contacted for approval should be captured in the Work Log.

Requester is NOT authorized to request for building specified

THEN

External approval has NOT been received

Work Order status goes to canceled (CAN). Workflow stops.

A Cancellation Reason should be captured in the Cancel Reason field on the Work Order.

Note: For the “Requester is NOT authorized to request for building specified” options above. The Work Order will remain assigned to the P&PS user immediately after this selection with instructions to get approval. Once approval is obtained, the user can workflow to record if approval was granted or not.

If Restricted Key is Selected

Option What Happens Next Dependencies

Key request is NOT for a controlled key. Proceed to options.

THEN

P&PS does not approve request

Work Order status goes to canceled (CAN). Workflow stops.

A Cancellation Reason should be captured in the Cancel Reason field on the Work Order.

Page 44: PSU Supervisor Training Manual

44   Manager/Supervisor/Lead  Training  Manual  

Option What Happens Next Dependencies

Key request is NOT for a controlled key. Proceed to options.

THEN

P&PS does not require external approvals and approves request.

Work Order status goes to Waiting Planning (WPLAN) and the record is assigned to the Planner Group on the Work Order.

The Work Order goes to Phase 2.

Planner Group must be identified on Work Order.

Key request is NOT for a controlled key. Proceed to options.

THEN

External approvals are required.

Work Order remains assigned to P&PS user until external approvals are obtained. User can then use workflow options to either approve or cancel request.

If approving, Planner Group must be identified.

If canceling, a Cancel Reason should be populated.

Key request IS for a controlled key. Route for approvals.

Work Order goes to a Waiting Approval status and is assigned to the OPP Director of Buildings and Grounds.

N/A

Note: The options with “THEN” in them above mean that the user is presented with a second set of routing options after selecting the first option.

Page 45: PSU Supervisor Training Manual

Manager/Supervisor/Lead  Training  Manual   45  

A process flow summarizing the routing possibilities available in the P&PS Review step is provided below:

2.4.1.2 OPP Approval of Controlled Keys

If the request is for an OPP Controlled key, the workflow will assign the record to the OPP Director of Buildings and Grounds person group.

Note: It is expected that there is only one person in this group, but it is set up as person group to allow for easy change out of the name, when applicable.

Any user from that group can perform the next step in workflow which is to make decisions on the level of approvals of required.

Request Owned by P&PS User

for Review

Restricted Key?

AC Authorized

for Building?

P&PS Obtains External Approval

Request Approved. Work Order to Waiting

Planning(Phase 2)

Request Rejected. Work

Order to Canceled

(END)

External Approvals Required?

OPP Controlled

Key?

P&PS Obtains External Approval

P&PS Approves?

Request Approved. Work Order to Waiting

Planning(Phase 2)

Request Rejected. Work

Order to Canceled

(END)

Request Rejected. Work

Order to Canceled

(END)

Request Requires OPP

Approval. Phase 1 Continues.

Y

N N

Y

N

Y

Y

N Y N

YN

Y

N

Page 46: PSU Supervisor Training Manual

46   Manager/Supervisor/Lead  Training  Manual  

At the “OPP Approval of Controlled Keys” step in the workflow, the Director can review and make updates to the record. Key fields to review/update, most of which reside on the “Keys” tab of Work Order Tracking:

Key Fields for Triage Step:

Description/Long Description Work Type

Asset/Location Grand Master?

Building Master? Animal Facility?

Athletic Facility? Leased Property?

Building Entry? Can Be Facilitated Electronically?

Under AC’s Dept. Control? Mechanical, Electrical or Tele. Room?

Note: The Key Request should also have a Key Request Form attached to it that should be reviewed.

Once the Director has completed their review/updates to the record, they will have a series of workflow routing options that are described below:

The initial options available to the user are:

1. The request is NOT for a Mechanical Room.

OR

2. The request is for a Mechanical Room.

Based on their selection, their next routing options are different.

If NOT a Mechanical Room Key is Selected

Option What Happens Next Dependencies

Appropriate approvals have been obtained outside the system.

Work Order Status goes to Waiting to be Planned (WPLAN) and is assigned to the Planner Group on the Work Order.

The Work Order goes to Phase 2.

Planner Group must be identified on Work Order.

Page 47: PSU Supervisor Training Manual

Manager/Supervisor/Lead  Training  Manual   47  

Option What Happens Next Dependencies

Appropriate approvals could NOT be obtained outside the system

Work Order status goes to canceled (CAN). Workflow stops.

A Cancellation Reason should be captured in the Cancel Reason field on the Work Order.

Note: For the “Request is NOT for a Mechanical Room” option above. The Work Order will remain assigned to the Directory immediately after this selection with instructions to get approval. Once approval is obtained, the user can workflow to record if approval was granted or not.

If Mechanical Room Key is Selected

Workflow will assign the record to users in each of the following person groups:

• Director of Building and Grounds • EH&S • OPP Safety

At least one user from each group will have to go in and select a routing option before the request can proceed. The options available to the user are provided below:

Option What Happens Next Dependencies

Request is approved. If all three reviews select this option, the Work Order status goes to Waiting Planning (WPLAN) and is assigned to the Planner Group on the Work Order.

The Work Order goes to Phase 2.

Planner Group must be identified on Work Order.

Page 48: PSU Supervisor Training Manual

48   Manager/Supervisor/Lead  Training  Manual  

Option What Happens Next Dependencies

Request is NOT approved.

If even one user selects this option, the Work Order status goes to canceled (CAN) and workflow stops.

A Cancellation Reason should be captured in the Cancel Reason field on the Work Order.

A process flow summarizing the routing possibilities available in the OPP Review step is provided below:

Request Owned by OPP Director of Buildings and

Grounds for Review

Mechanical Room?

Director Obtains External Approval

Request Approved. Work Order to Waiting

Planning(Phase 2)

Request Rejected. Work

Order to Canceled

(END)

All Approve?

Request Approved. Work Order to Waiting

Planning(Phase 2)

Request Rejected. Work

Order to Canceled

(END)

N

Y

Y

N

From P&PS Review, for OPP Controlled Key

(WAPPR)

EH&S, OPP Safety, and

Director of B&G All Review

N

Y

Page 49: PSU Supervisor Training Manual

Manager/Supervisor/Lead  Training  Manual   49  

At the end of this phase of the process, the Work Order will be in one of the following conditions:

Possible Ending Conditions for Phase 1A of Process

Next Steps

1. Canceled status with workflow stopped.

N/A

3. Waiting to be Planned (WPLAN) status with Work Order assigned to Planner Group.

Planner takes ownership of record to plan Work Order.

2.4.2 Phase 1B – OPP Request Triage and Approval

2.4.2.1 OPP Access Coordinator Creates Key Request

Key Requests for OPP Employees are created directly in Maximo by an OPP Access Coordinator (AC) based on a request from an OPP Employee (outside system.) The OPP AC will use Work Order Tracking to create the Key

OPP  Access  Coordinator  Creates  Key  Request  

OPP  Access  Coordinator  Coordinates  Approvals  for  Key  Request  

Phase  2  -­‐  Planning  

Scheduling  and  Execution  

Page 50: PSU Supervisor Training Manual

50   Manager/Supervisor/Lead  Training  Manual  

Request Work Order. Key fields to populate, most of which reside on the “Keys” tab of Work Order Tracking:

Key Fields for Key Request Creation Step:

Description/Long Description Work Type = KEY

GL Account Urgency

Asset/Location Grand Master?

Building Master? Animal Facility?

Athletic Facility? Leased Property?

Building Entry? Can Be Facilitated Electronically?

Under AC’s Dept. Control? Mechanical, Electrical or Tele. Room?

Planner Group Work Group

Important: The Work Type of “KEY” must be entered and saved on the new Work Order for Maximo to display the “Keys” tab that contains most of the Key Request information.

Once the Key Request Work Order has been created, the OPP AC will start workflow on the record by selecting the “Route Workflow” icon.

2.4.2.2 OPP Access Coordinator Coordinates Approval for Key Request

The workflow begins when a Key Request has been started in workflow by an OPP AC. The workflow first assigns the record to the OPP Access Coordinator person group. Every person in this person group will receive an assignment for the work order and it will be displayed in their workflow in-box.

Any user from that group can perform the next step in workflow to take ownership of the record for review, which will end the assignment for all other users of the group and remove it from their workflow in-boxes. Once one of the users from the group has taken ownership of the record via workflow, the record will only reside in the owner’s workflow in-box.

Note: The owner will be the only user that can perform the next routing step.

Page 51: PSU Supervisor Training Manual

Manager/Supervisor/Lead  Training  Manual   51  

At the “OPP AC Review” step in the workflow, the OPP AC user can review and make updates to the record, if needed.

Once the OPP AC user has completed their review/updates to the record, they will have a series of workflow routing options that are described below:

The initial options available to the user are:

1. The request is NOT for a Special Key.

OR

2. The request is for a Special Key.

Based on their selection, their next routing options are different.

If Non-Special Key is Selected

Option What Happens Next Dependencies

Key Request is approved.

Work Order Status goes to Waiting to be Planned (WPLAN) and is assigned to the Planner Group on the Work Order.

The Work Order goes to Phase 2.

Planner Group must be identified on Work Order.

Key Request is NOT approved.

Work Order status goes to canceled (CAN). Workflow stops.

A Cancellation Reason should be captured in the Cancel Reason field on the Work Order.

Page 52: PSU Supervisor Training Manual

52   Manager/Supervisor/Lead  Training  Manual  

If Special Key is Selected

The Work Order remains assigned to the OPP AC with instructions to obtain the appropriate approvals outside the system. Once the appropriate people have been contacted, the OPP AC will have the following workflow routing options.

Option What Happens Next Dependencies

Key Request is approved by outside approvers.

Work Order Status goes to Waiting to be Planned (WPLAN) and is assigned to the Planner Group on the Work Order.

The Work Order goes to Phase 2.

Planner Group must be identified on Work Order.

The people providing approval should be captured in the Work Log of the Work Order.

Key Request is NOT approved by outside approvers.

Work Order status goes to canceled (CAN). Workflow stops.

A Cancellation Reason should be captured in the Cancel Reason field on the Work Order.

Page 53: PSU Supervisor Training Manual

Manager/Supervisor/Lead  Training  Manual   53  

A process flow summarizing the routing possibilities available in the OPP AC Approval step is provided below:

At the end of this phase of the process, the Work Order will be in one of the following conditions:

Possible Ending Conditions for Phase 1A of Process

Next Steps

1. Canceled status with workflow stopped.

N/A

Request Owned by OPP AC and

for Review/Coordination

Special Key?OPP AC Obtains

External Approval

Request Approved. Work Order to Waiting

Planning(Phase 2)

Request Rejected. Work

Order to Canceled

(END)

Approve?

Request Approved. Work Order to Waiting

Planning(Phase 2)

Request Rejected. Work

Order to Canceled

(END)

N

Y

Y

N

Y

N

Page 54: PSU Supervisor Training Manual

54   Manager/Supervisor/Lead  Training  Manual  

Possible Ending Conditions for Phase 1A of Process

Next Steps

3. Waiting to be Planned (WPLAN) status with Work Order assigned to Planner Group.

Planner takes ownership of record to plan Work Order.

2.4.3 Phase 2 – Planning, Scheduling and Execution

Phase 2 of the Key Request workflow process begins with the Work Order being assigned to the Planner Group in a Waiting to be Planned (WPLAN) status. From this point, Phase 2 of the Key Request workflow process is identical to the “On Demand Work Management” process for planning, scheduling, and execution. The Work Order will follow those process steps until it reaches the status of Complete (COMP). Please see the appropriate steps of that section to see how a Key Request is planned, scheduled and executed.

When the Work Order reaches the complete (COMP) status, Phase 3 of the Key Request Process begins.

2.4.4 Phase 3 – Key Pick Up and Closure

WRC  Records  Pick  Up  Info  

Final  Billing  Complete  

(Integration)  

Work  Order  Closed  

(Automatic)  Process  Ends  

Page 55: PSU Supervisor Training Manual

Manager/Supervisor/Lead  Training  Manual   55  

2.4.4.1 Work Reception Center Records Pick Up Information

In Phase 3 – Key Pick Up and Closure, a Work order is initially assigned to the Work Reception Center person group. Every person in this person group will receive an assignment for the work order and it will be displayed in their workflow in-box.

Note: Any user from that group can perform the next step in workflow to record that the key pick up information has been entered.

A WRC user would review this Work Order and either:

1. Validate the Key(s) have already been picked up/delivered and information entered.

OR

2. Enter the pickup information when the Key(s) are picked up from the Work Reception Center, if applicable.

The key fields that should be update on the Keys tab of Work Order Tracking when the Key(s) are picked up/delivered are:

Key Fields/Sections for Key Pick Up Step: (All on Keys tab -> Key Table)

Owner ID/Name (if OPP) Non-OPP Owner ID/Name (if Non-OPP)

Issued Date

The only option available at this point in the process is to say that the information has been entered and keys picked up or delivered. This step would not be performed until this is true.

Option What Happens Next Dependencies

Mark Review as Complete

Work Order Status goes to Waiting to be Closed (WCLOSE) and workflow stops.

N/A

Page 56: PSU Supervisor Training Manual

56   Manager/Supervisor/Lead  Training  Manual  

2.4.4.2 Final Billing Complete (Integration)

Work Orders will remain in a waiting to be closed (WCLOSE) until they are “Final Billed.” An integration with the VM system will update the billing information on Work Orders and eventually mark the Work Order as “Final Billed”.

2.4.4.3 Work Order Closed

An escalation will monitor the system for Work Orders that are in the waiting to be closed (WCLOSE) status and are marked as “Final Billed” and will automatically change the status of these records to closed (CLOSE.)

Page 57: PSU Supervisor Training Manual

Manager/Supervisor/Lead  Training  Manual   57  

2.5 Work Order Workflow Process for Preventive Maintenance Preventive Maintenance work (the PM work type) is always initiated from the Work Order generation process off of a Preventive Maintenance record. A Preventive Maintenance record already contains the information that would be populated during Triage or Planning and is already approved. Therefore, these Work Orders can go directly to Scheduling or Assignment. Once generated, PM Work Orders follow the exact same process as “On Demand Work Management” beginning at Phase 2, all the way through closure.

Note: The “*” is there to denote that Phases 2 and 3 of this process are identical to Phases 2 and 3 of the “On Demand Work Management” process, detailed in a previous section.

Phase 1 – Work Order Generation Work Order Generation

Scheduling Phase 2 – Scheduling and Execution

Assignment

1  -­‐  Work  Order  

Generation  

2  -­‐  Scheduling  and  

Execution*  

3  -­‐  Post  Completion  Review  and  Closure*  

Page 58: PSU Supervisor Training Manual

58   Manager/Supervisor/Lead  Training  Manual  

Execution

Post-Completion Review Phase 3 – Post-Completion Review and Closure Closure

2.5.1 Phase 1 – Work Order Generation

Preventive Maintenance (PM) Work Orders are either generated automatically, via a cron-task, or manually from the Preventive Maintenance application. These Work Orders will either generate in a Waiting to be Scheduled (WSCH) or Approved (APPR) status and will enter Phase 2 of the “On Demand Work Management” process at the appropriate place based on that status.

2.5.2 Phase 2 – Planning, Scheduling and Execution

Phase 2 of the PM workflow process is identical to Phase 2 of the “On Demand Work Management” process for scheduling, assignment and execution. Please see the “On Demand Work Management Process – Phase 2” above to see how a PM Work Order is scheduled, assigned and executed.

2.5.3 Phase 3 – Post-Completion Review and Closure

Phase 3 of the PM workflow process is identical to Phase 3 of the “On Demand Work Management” process for post-completion review and closure. Please see the “On Demand Work Management Process – Phase 3” above to see how a PM Work Order is processed through post-completion reviews and closure.

Page 59: PSU Supervisor Training Manual

Manager/Supervisor/Lead  Training  Manual   59  

2.6 Work Order Workflow Process for Jobs Jobs (the JOB work type) are typically initiated based on the activation of a Project Contract in Tririga. For this reason, these work orders are created manually in the Jobs application in Maximo by an OPP Accounting user familiar with the project.

Important: There is also a Work Type of ‘1JOB’ which represents Jobs that have come directly from the VM system. These Work Orders can’t be work flowed in Maximo or have their status changed in Maximo. Time and Materials can be charged against them if they are open and are setup to accept to charges.

Job Work Orders must be planned before they are approved for use to record time and materials against. From start to finish, work orders with this work type may proceed through the following phases, each of which will be described in greater detail:

1  -­‐  Create  Job  2  -­‐  Planning,  Scheduling  

and  Execution  

3  -­‐  Post  Completion  Review  and  Closure  

Page 60: PSU Supervisor Training Manual

60   Manager/Supervisor/Lead  Training  Manual  

Phase 1 – Create Job Create Job

Planning

Approval

Scheduling

Phase 2 – Planning, Scheduling and Execution

Execution

Post-Completion Review Phase 3 – Post-Completion Review and Closure Closure

The workflow is being presented in phases because the workflow is set up to behave a little differently in each of these phases.

During Phase 1 – Create Job, the Job is not yet in workflow. The OPP Accounting user is creating the record in Maximo and populating key elements of the record. Once the Work Order has the critical project information, the user will initiate workflow, ending this phase.

During Phase 2 – Planning, Scheduling and Execution, Job Work Orders follow the exact same process as “On-Demand Work” described in the previous section. Once a Work Order leaves Phase 1 of this process, it starts at the “WPLAN” step of the “On-Demand Work” process and follows the same steps of that process until the Work Order is completed (COMP) at the end of Phase 2.

During Phase 3 – Post-Completion Review and Closure - Job Work Orders follow the exact same process as “On-Demand Work – Phase 3” described in an earlier section.

Page 61: PSU Supervisor Training Manual

Manager/Supervisor/Lead  Training  Manual   61  

2.6.1 Phase 1 – Create Job

2.6.1.1 OPP Accounting Creates Job

Jobs are created directly in Maximo, in the Jobs application, by an OPP Accounting user, based on the creation/authorization of a project (outside Maximo system.) The OPP Accounting user will use the Jobs application to create the Job Work Order. Key fields to populate are listed below:

Key Fields for the Job Creation Step:

Description/Long Description Contract #

Asset/Location Planner Group

Project Number* Contract Amount*

Job Type* Cost Type*

Job Start Date* Project Leader*

Planner/Estimator*

OPP  Accounting  Creates  Job  

OPP  Accounting  Routes  for  Planning  

On  to  Phase  2  -­‐  Planning,  Scheduling,  and  Execution  

Page 62: PSU Supervisor Training Manual

62   Manager/Supervisor/Lead  Training  Manual  

Note: The fields with “*” above will populate automatically, via integration with Tririga, when a valid Contract Number is entered.

Once the Job Work Order has been created, the OPP Accounting user will start workflow on the record by selecting the “Route Workflow” icon.

2.6.2 Phase 2 – Planning, Scheduling and Execution

Phase 2 of the Job workflow process begins with the Work Order being assigned to the Planner Group in a Waiting to be Planned (WPLAN) status. From this point, Phase 2 of the Job workflow process is identical to the “On Demand Work Management” process for planning, scheduling, and execution. The Work Order will follow those process steps until it reaches the status of Complete (COMP). Please see the appropriate steps of that section to see how a Job is planned, scheduled and executed.

When the Work Order reaches the complete (COMP) status, Phase 3 of the Jobs Process begins.

2.6.3 Phase 3 – Post-Completion Review and Closure

Phase 3 of the PM workflow process is identical to Phase 3 of the “On Demand Work Management” process for post-completion review and closure. Please see the “On Demand Work Management Process – Phase 3” above to see how a PM Work Order is processed through post-completion reviews and closure.

Page 63: PSU Supervisor Training Manual

Manager/Supervisor/Lead  Training  Manual   63  

2.7 Work Order Workflow Process for Fixed Tasks Fixed Tasks (the FT work type) are typically initiated based on a request to OPP Accounting. For this reason, these work orders are created manually in the Work Order Tracking application in Maximo by an OPP Accounting user familiar with the request. Fixed Task Work Orders require absolutely no Triage, Planning, or Scheduling, so they do not follow a traditional, assignment-based workflow. From start to finish, work orders with this work type may proceed through the following phases, each of which will be described in greater detail:

Phase 1 – Create Fixed Task Create Fixed Task

Phase 2 – Execution Execution

Phase 3 – Closure Closure

1  -­‐  Create  Fixed  Task  

2  -­‐  Execution   3  -­‐  Closure  

Page 64: PSU Supervisor Training Manual

64   Manager/Supervisor/Lead  Training  Manual  

2.7.1 Phase 1 – Create Fixed Task

During Phase 1, create fixed task, the Fixed Task is not yet in workflow. The OPP Accounting user is creating the record in Maximo and populating key elements of the record. Key fields to populate are listed below:

Key Fields for the Job Creation Step:

Description/Long Description Work Type = FT

GL Account Work Group

Op Codes (Job Steps) Asset/Location (if Applicable)

Once the Work Order has the critical information populated, the user will initiate workflow, and be presented immediately with two options:

Option What Happens Next Dependencies

Approve Fixed Task Work Order Status goes to Approved (APPR) and workflow stops.

Craftspeople can now charge time to this Work Order.

N/A

Cancel Fixed Task Work Order status goes to canceled (CAN). Workflow stops.

N/A

2.7.2 Phase 2 – Execution

During Phase 2, Execution, Fixed Task Work Orders are in the Approved (APPR) status and are not in workflow. During this phase, no status changes are expected on the Work Order. As long as the status of the Work Order is Approved (APPR) and the “Accepts Materials” and “Accepts Labor” boxes are checked, transactions can be processed against the Work Order.

Page 65: PSU Supervisor Training Manual

Manager/Supervisor/Lead  Training  Manual   65  

2.7.3 Phase 3 – Closure

During Phase 3, Closure, the Work Order is closed by OPP Accounting by selecting the “Route Workflow” icon on the record. If the current status is approved (APPR), routing the record in workflow will automatically take the record to Closed (CLOSE).

Page 66: PSU Supervisor Training Manual

66   Manager/Supervisor/Lead  Training  Manual  

2.8 2.9 Components of a Work Order In this section, you will learn about the different components of a Work Order. Each tab of the Work Order application will be presented along with a description of its use.

Specific sections or fields on the tab will be highlighted related to how the information is typically populated (i.e. Work Request, Triage, Planning, Scheduling, Execution, etc.)

2.9.1 Work Order Tab – Header Section

This section is where the basic detail and high-level scope of the Work Order is captured. The Key fields to be populated are identified below:

Field Populated

Work Order Number Auto-populated by System.

Description/Long Description

From Work Request, potentially updated during Triage or Planning

Asset/Location From Work Request, potentially updated during Triage or Planning

Page 67: PSU Supervisor Training Manual

Manager/Supervisor/Lead  Training  Manual   67  

Field Populated

Special Instructions Automatically populates from Location selected.

Work Type From Work Request, potentially updated during Triage or Planning

Status/Status Date Auto-populated by system as record is work flowed.

Backlog Reason By Planner, when Work Order placed in backlog.

Problem Code From Work Request, potentially updated during execution.

JP Changes? By Craftsperson, during execution.

Call Out? During Triage, if work is for an Emergency.

Call Out Labor Hours During execution or completion.

Accepts Charges/Labor/Material

Defaults to “Y”. Can be toggled throughout life of Work Order.

Page 68: PSU Supervisor Training Manual

68   Manager/Supervisor/Lead  Training  Manual  

2.9.2 Work Order Tab – Job Details Section

This section is where you have the Work Order’s association to a Job Plan, PM, Safety Plan or Contract. The Key fields to be populated are identified below:

Field Populated

Job Plan/Revision# During Planning, if applicable.

PM Auto-populated by system if Work Order generated from a PM.

Safety Plan During Planning, if applicable

Contract During Triage or Planning, if applicable.

2.9.3 Work Order Tab – Budget Section

This section is where you have the charge information for the Work Order The Key fields to be populated are identified below:

Page 69: PSU Supervisor Training Manual

Manager/Supervisor/Lead  Training  Manual   69  

Field Populated

GL Account From Work Request, potentially updated during Triage.

Customer Billing # From Work Request, potentially updated during Triage.

2.9.4 Work Order Tab – Priority Section

This section is where you can see the priority of the work for comparison to other Work Orders. The Key fields to be populated are identified below:

Field Populated

Urgency During Triage, potentially comes from Work Request. Could be updated during Planning.

Asset/Location Priority Auto-populated by system from Asset or Location.

Work Order Priority Auto-populated by system based on Urgency and Asset/Location Priority.

Page 70: PSU Supervisor Training Manual

70   Manager/Supervisor/Lead  Training  Manual  

Field Populated

Life Safety? Auto-populated by system from Asset or Location.

Asset/Location Area Auto-populated by system from Asset or Location.

2.9.5 Work Order Tab – Scheduling Information Section

This section is where you can see the critical dates related to the scheduling of the Work Order. The Key fields to be populated are identified below:

Field Populated

Target Start/Finish Auto-populated by system based on Work Order Priority.

Scheduled Start/Finish During Scheduling and/or Assignment.

Customer Req’d Start/Finish Date

From Work Request or PM record.

Actual Start Date Auto-populated by system when first assignment is started or Work Order goes to In Progress status unless set manually by user.

Page 71: PSU Supervisor Training Manual

Manager/Supervisor/Lead  Training  Manual   71  

Field Populated

Actual Finish Date Auto-populated by system when Work Order goes to Complete status unless set manually by user.

Duration During Planning or from Job Plan

2.9.6 Work Order Tab – Responsibility Section

This section is where you can see the people or person groups that have various roles or responsibilities associated with the Work Order. The Key fields to be populated are identified below:

Field Populated

Reported Date From Work Request

Reported By/Phone From Work Request

Contact Name/Phone/Email

From Work Request

Planner Grp During Triage, potentially from Work Request

Supervisor/Work Group During Triage, Planning or Scheduling

Owner Auto-populated by system based on workflow routing.

Page 72: PSU Supervisor Training Manual

72   Manager/Supervisor/Lead  Training  Manual  

Field Populated

Approver During Planning, if applicable

Scheduler Grp During Triage or Planning, if applicable

2.9.7 Plans Tab – Tasks Section

This section is where you can see the tasks (steps) for completing the Work Order. The Key fields to be populated are identified below:

Field Populated

ID During Planning

Summary During Planning

Duration During Planning

2.9.8 Plans Tab – Labor Section

This section is where you can see the Labor estimates/requirements for completing the Work Order. The Key fields to be populated are identified below:

Field Populated

Craft/Skill During Planning

Quantity During Planning

Regular Hours During Planning

Page 73: PSU Supervisor Training Manual

Manager/Supervisor/Lead  Training  Manual   73  

2.9.9 Plans Tab – Material Section

This section is where you can see the Material estimates/requirements (both special order and stock) for completing the Work Order. The Key fields to be populated are identified below:

Field Populated

Line Type During Planning

Item Number/Description During Planning

Quantity During Planning

Unit Cost During Planning

Storeroom During Planning, If applicable

Direct Issue? During Planning, If applicable

Vendor During Planning, If applicable

Required Date During Planning

2.9.10 Assignments Tab – Assignments Section

This section is where you can see the actual Labor assignments that have been or need to be made for the Work Order.

Note: This can also be done/seen across multiple Work Orders at once from the Assignment Manager application.

The Key fields to be populated are identified below:

Page 74: PSU Supervisor Training Manual

74   Manager/Supervisor/Lead  Training  Manual  

Field Populated

Craft/Skill During Assignment

Labor During Assignment

Scheduled Start/Finish From Scheduling or during Assignment

Duration From Planning or during Assignment

2.9.11 Actuals Tab – Labor Section

This section is where you can see the actual Labor transactions that have been posted for the Work Order.

Note: This can also be done/seen from the Quick Reporting application and Mobile Work Manager.

The Key fields to be populated are identified below:

Field Populated

Phase Code During Execution

Craft/Skill During Execution, defaults from Labor selected.

Labor During Execution

Start Date/Time and End Date/Time

During Execution

Regular Hours During Execution

Page 75: PSU Supervisor Training Manual

Manager/Supervisor/Lead  Training  Manual   75  

2.9.12 Actuals Tab – Materials Section

This section is where you can see the actual Material transactions that have been posted for the Work Order (stock and from orders.)

Note: These transactions can also be done/seen from the Inventory Usage application and Mobile Work Manager.

The Key fields to be populated are identified below:

Field Populated

Line Type During Execution, potentially from PO Line.

Item Number/Description During Execution, potentially from PO Line.

Quantity During Execution, potentially from PO Line.

Unit Cost Auto-populated from PO Line or Inventory.

Storeroom During Execution, if applicable.

Entered By/Date During Execution

Issue To During Execution

GL Accounts Auto-populated by system from Work Order and Inventory or PO Line.

Page 76: PSU Supervisor Training Manual

76   Manager/Supervisor/Lead  Training  Manual  

Field Populated

Transaction Type During Execution

2.9.13 Cost Tab – Current Billing Section

This section is where you can see the current billing status of a Work Order.

Note: This information comes to Maximo via an integration with VM.

There are no fields populated by users in Maximo.

Field Populated

Bill Amount Via integration with VM

Last Bill Date Via integration with VM

Billing Complete? Via integration with VM

2.9.14 Cost Tab – Fiscal Work Order Costs Section

This section is where you can see the accrued costs for the current fiscal year only.

Note: With the exception of Monthly Cost Target and Fixed Price SC Total Cost, this information is calculated by Maximo based on transactions posted to the Work Order.

Page 77: PSU Supervisor Training Manual

Manager/Supervisor/Lead  Training  Manual   77  

Field Populated

Actual Labor Auto-populated by Maximo

Actual Material Auto-populated by Maximo

Actual Tool Auto-populated by Maximo

Actual Service Auto-populated by Maximo

Actual Internal Labor Auto-populated by Maximo

Actual Outside Labor Auto-populated by Maximo

Actual Total Auto-populated by Maximo

Encumbered Cost Populated by Maximo when user selects the Encumbrance button.

Monthly Cost Target During Fixed Task Creation

Fixed Price SC Total Cost

During Fixed Task Creation

Page 78: PSU Supervisor Training Manual

78   Manager/Supervisor/Lead  Training  Manual  

2.9.15 Cost Tab – Work Order Costs Section

This section is where you can see the accrued costs for the Work Order from its inception.

Note: This information is calculated by Maximo based on transactions posted to the Work Order.

This section contains the following key fields.

Field Populated

Internal Labor Hours Auto-populated by Maximo

External Labor Hours Auto-populated by Maximo

Labor Hours Auto-populated by Maximo

Labor Costs Auto-populated by Maximo

Material Costs Auto-populated by Maximo

Tool Costs Auto-populated by Maximo

Service Cost Auto-populated by Maximo

Page 79: PSU Supervisor Training Manual

Manager/Supervisor/Lead  Training  Manual   79  

Field Populated

Internal Labor Cost Auto-populated by Maximo

External Labor Cost Auto-populated by Maximo

Total Cost Auto-populated by Maximo

2.9.16 Log Tab – Work Log Section

This section is where you can add/view Work Log notes (updates and comments) that have been posted to the Work Order from inception.

This section contains the following key fields.

Field Populated

Created By Auto-populated by Maximo

Date Auto-populated by Maximo

Type Selected when log is entered, at any time during lifecycle of Work Order

Percent Complete Selected when log is entered, at any time during lifecycle of Work Order

Page 80: PSU Supervisor Training Manual

80   Manager/Supervisor/Lead  Training  Manual  

Field Populated

Summary Selected when log is entered, at any time during lifecycle of Work Order

2.9.17 Failure Reporting Tab

This section is where you can add/view Failure Codes that have been posted to the Work Order to describe the problem, cause and remedy associated with the Work Order, if applicable.

Note: These codes will typically be added from the Quick Reporting or Mobile Work Manager applications.

This section contains the following key fields.

Field Populated

Failure Class Auto-populated by Maximo from Asset/Location or entered at any point of Work Order lifecycle.

Failure Date Entered at any point during Work Order Lifecycle

Problem/Cause/Remedy During Execution or Completion

Page 81: PSU Supervisor Training Manual

Manager/Supervisor/Lead  Training  Manual   81  

3 Inventory Management for Satellite Storerooms 3.1 Overview of Inventory The Inventory application is used to store information about all aspects of inventory materials. You can monitor the storeroom balance of inventory items and tools. You can track the condition of items and the cost of inventory stock, and you can reorder items when stock must be replenished.

You can check the balances of individual items and tools at the bin and lot level for each storeroom. If an item is stored in more than one location, you can view balances for all storeroom locations on one screen.

Use the Inventory application to perform the following tasks:

• Search the database for inventory items and tools. • Specify the balances of items and item costs. • Specify the bins and lots where items are stored, and view the storeroom

locations. • Issue and return inventory items by site and storeroom location. • Specify reorder details, such as the reorder point, the lead time, and the

order unit of an item. You can also specify information about the vendors that supply an item and the multiple manufacturers or models that are associated with each vendor.

• List all assets for which an item is listed as a subassembly or a spare part.

3.2 Working with Inventory Manager/Supervisor/Lead users will have the ability to perform several of the basic functions related to Inventory Management for the satellite (area or departmental) storerooms that they are responsible for. The primary function that Manager/Supervisor/Lead users will perform in the Inventory application (other than viewing balance information) is initiating the reorder of stock items.

Page 82: PSU Supervisor Training Manual

82   Manager/Supervisor/Lead  Training  Manual  

3.2.1 Reordering Inventory

3.2.1.1 Supervisor Runs Reorder for Storeroom

A Supervisor initiates the reorder process by running the “Reorder Items” action in the Inventory application for a specific set of items or all items in a particular storeroom. The reorder action will automatically create Purchase Requisitions (PRs) for the items that need to be reordered. The PRs will automatically enter a workflow to be reviewed and approved.

3.2.1.2 EXERCISE: Supervisor Runs Reorder for Satellite Storeroom

1. Click on the Go To menu Inventory Inventory.

Supervisor  Runs  Reorder  for  Storeroom  

Supervisor  Reviews/Submits  

Reorder  PRs  

OPP  Stores  Reviews/Approves  Reorder  PRs  

Page 83: PSU Supervisor Training Manual

Manager/Supervisor/Lead  Training  Manual   83  

2. On the List tab, enter ‘316900’ in the Item search field and ‘AREA 1’ in the Storeroom search field and hit “Enter”.

3. Open the Item from the displayed list by clicking on the “Item Number”.

4. Open the “Reorder Details” tab by clicking on it.

The fields that affect the Reorder Process are defined below. Field Description

Reorder? Determines if the Item is to be evaluated by the reorder action.

Page 84: PSU Supervisor Training Manual

84   Manager/Supervisor/Lead  Training  Manual  

Field Description

Reorder Point Defines the highest balance at which the reorder process can be automatically triggered.

Economic Order Quantity Defines (in terms of the Order unit) the increments in which the item is to be ordered.

5. From the “Select Actions” menu, select Reorder Reorder Items.

6. Place checkmark in the “Ignore Reorder Point?” checkbox by clicking on it.

Remove the checkmark in the “Run In Background Mode?” checkbox by clicking on it. Select “Preview”.

Page 85: PSU Supervisor Training Manual

Manager/Supervisor/Lead  Training  Manual   85  

Important: These settings are for the training exercise only. Typically you would NEVER want to select “Ignore Reorder Point?” if you were reordering for a storeroom based on the current balance and reorder information for the storeroom.

As different scenarios may dictate setting these properties differently, the critical fields and their description are below:

Field Description

Ignore Reorder Point? If this is set to ‘Y’ (checked), the system does not evaluate the current balance or reorder point of the item. It automatically creates a PR for the Item(s) selected.

All Items in Storeroom? If this is set to ‘Y’ (checked), the reorder process will run on all items on the storeroom, not just the item(s) that are currently selected.

Page 86: PSU Supervisor Training Manual

86   Manager/Supervisor/Lead  Training  Manual  

Field Description

Run in Background Mode?

If this is set to ‘Y’ (checked), the system will NOT wait for the reorder process to complete and provide you with a visual confirmation. Instead it will let you continue your user session while it works and will send an email to the specified email address when completed.

7. Select “Run Reorder”.

8. Select “OK” on the “Reorder Results” window that is displayed. The reorder process has automatically created the necessary PRs and they have been placed into a workflow for review and approval. The first assignment on the workflow is to the Supervisor that initiated the reorder.

3.2.1.3 Supervisor Reviews and Submits PR for Satellite Storeroom

Once the reorder PR has been generated by the system, it will automatically be routed to the Supervisor that initiated the reorder. The Supervisor will have the

Page 87: PSU Supervisor Training Manual

Manager/Supervisor/Lead  Training  Manual   87  

ability to review and update the PR in the Purchase Requisitions application and then either cancel it or route to the OPP Stores In Box for ordering.

Option What Happens Next Dependencies

PR Approved, submit to OPP Stores In Box.

PR Status goes to Supervisor Approved (SUPERAPPR) and is assigned to the OPP Stores Inbox.

N/A

PR not approved, Cancel.

PR status goes to canceled (CAN). Workflow stops.

N/A

3.2.1.4 EXERCISE: Supervisor Reviews and Submits PR for Satellite Storeroom Reorder

1. Go To your Start Center. 2. From your Inbox/Assignments portal on your Start Center, find and select

the PR that was generated during the previous exercise by clicking on it.

3. Navigate to the PR Lines tab by clicking on it.

You can review the details of the PR and make updates, if necessary. To submit the PR for ordering to the OPP Stores Inbox:

Page 88: PSU Supervisor Training Manual

88   Manager/Supervisor/Lead  Training  Manual  

4. Select the “Route Workflow” icon from the toolbar. 5. Select the “PR Approved, submit to OPP Stores In Box” option and select

“OK”.

The status of the PR will update to Supervisor Approved (SUPERAPPR) and the record will be routed to the OPP Stores Inbox.

3.2.1.5 OPP Stores Reviews and Approves PR for Satellite Storeroom

OPP Stores will receive PRs that have been submitted by Supervisors for Satellite Storeroom reorders in their inbox. They will have the ability to review and update these PRs and will also have the following workflow routing options:

Option What Happens Next Dependencies

Change status of PR to Approved (APPR).

PR Status goes to Approved (APPR.) Workflow stops.

N/A

PR not approved. Send back to Supervisor for rework or cancel.

PR status goes to Waiting Supervisor Review (WSUPER). Workflow assigns record to Supervisor that originated the PR.

Not required, but a rework/cancel reason should be provided in the workflow memo field prior to routing.

Page 89: PSU Supervisor Training Manual

Manager/Supervisor/Lead  Training  Manual   89  

Once the PR is approved, it will be processed like any other approved PR to ultimately become a Purchase Order (PO.)

3.3 Overview of Inventory Usage With the daily use of inventory items and tools, inventory materials must be moved between storerooms and out to craftspeople to supply the different areas of a site. The Inventory Usage application is used to create inventory usage records that track the issue, transfer, and return of inventory items within organizations. You can monitor the balance of inventory items that are in stock, and you can issue items directly to charge work orders.

Note: Issues and returns can also be executed in Work Order Tracking, Quick Reporting and in Mobile Work Manager. However, the Inventory Usage application provides the most efficient manner for entering multiple Issue or Return transactions quickly, like when processing the transactions listed on a storeroom form.

3.4 Working with Inventory Usage Inventory Usage records are created to track the issue, transfer, and return of inventory items within organizations. Inventory usage records can contain multiple usage lines, which track the movement of inventory items into and out of storerooms and bins. Inventory usage lines can be added or removed from inventory usage records so that records can be updated quickly and easily. Inventory usage records are categorized into types that summarize the intended purpose of the inventory usage record. Inventory usage types indicate that a record comprises only issue or return items, only transfer items, or a mixture of all item types. When you create a record in the Inventory Usage application, the default usage type is Mixed. You can change the usage type before you start filling out the record by adding inventory usage lines. Inventory usage records can have one of the following usage types:

• Issue - All usage lines in the record contain items for issue or return only. • Transfer - All usage lines in the record contain items for transfer only.

Page 90: PSU Supervisor Training Manual

90   Manager/Supervisor/Lead  Training  Manual  

• Mixed - The record contains a combination of issue lines, transfer lines, and return lines.

Changing the status of inventory usage records initiates transactions that adjust inventory information. Inventory transactions can adjust storeroom balances or the financial data that is associated with the inventory record. The following statuses apply to inventory usage records: Status Description

Entered The default status for an inventory usage record when it is created. When a record is in Entered status, some default fields cannot be modified.

Shipped Indicates that the item has been removed from the inventory storeroom and is in transit to its final destination.

Staged Indicates that inventory items are ready and waiting to be issued or transferred. When you set the usage record status to Staged, you must choose the stage bin that you want to use. You cannot change the status of the record to Staged if the record contains one or more usage lines of the type Return. You cannot change the status of the record to Staged if the status is Shipped, Cancelled, or Complete.

Complete Indicates that the issue, transfer, or return of items is complete. When you change the status to Complete, the appropriate transactions are generated to adjust the balance of inventory storerooms.

Cancelled Canceled records cannot be edited, and any staged balances are reversed. This status is available if the current inventory usage status is Entered or Staged.

Page 91: PSU Supervisor Training Manual

Manager/Supervisor/Lead  Training  Manual   91  

3.4.1 Issuing Parts from Satellite Storeroom

You can issue inventory items by assigning them to a work order. You can also issue items to satisfy reservations. The Issue transaction will remove the appropriate balance of the item from the storeroom and charge it to the specified Work Order.

3.4.1.1 EXERCISE: Issue Parts in Inventory Usage

1. Click on the Go To menu Inventory Inventory Usage.

2. Select the “New Inventory Usage” icon from the toolbar. 3. Enter ‘Issue to Work Order’ in the Description field.

4. Use the “Select Value” icon next to the “Usage Type” field to select ‘ISSUE’.

5. Enter the Work Order Number that you are issuing to in the “Work Order” field in the Default Table Data section.

Page 92: PSU Supervisor Training Manual

92   Manager/Supervisor/Lead  Training  Manual  

Note: Once the Work Order Number is entered, the GL Account, Location, and Asset from the Work Order will display, if populated. The Entered By will default to you.

6. Enter the Person ID of the person that the material was issued to in the “Issued To” field in the Default Table Data section.

7. Select “New Row” in the Usage Lines section.

8. Enter the Item Number of the Item being issued in the “Item” field.

9. Enter the Quantity being issued in the “Quantity” field.

Page 93: PSU Supervisor Training Manual

Manager/Supervisor/Lead  Training  Manual   93  

10. Save the record.

Note: If there are more Items to enter for this Work Order, you can repeat steps 7 through 10 to add all of the lines for the Work Order to this Inventory Usage record.

Note: If there Items to be issued at the same time to another Work Order, you can repeat steps 5 through 10 to add all of the lines for another Work Order to this Inventory Usage record.

Important: You can have usage lines for more than one Work Order on the same Inventory Usage record IF they are all executed at the same time. If the transactions for the separate Work Orders are not executed at the same time, you will need multiple Inventory Usage records.

Once all of the Inventory Usage lines have been added:

11. Select the “Set Inventory Usage record to complete” icon on the toolbar.

12. Select “OK” on the Change Status window.

Page 94: PSU Supervisor Training Manual

94   Manager/Supervisor/Lead  Training  Manual  

As a reminder, Issues and returns can also be executed in Work Order Tracking, Quick Reporting and in Mobile Work Manager directly on Work Order records. However, the Inventory Usage application provides the most efficient manner for entering multiple Issue or Return transactions quickly, like when processing the transactions listed on a storeroom form.

3.4.2 Returning Parts to Satellite Storeroom

You can return inventory items to the original storeroom. For example, you can return parts that were previously issued from a storeroom, but were not used. The Return transaction will credit the Work Order specified and will add the appropriate balance of the item back to the storeroom.

3.4.2.1 EXERCISE: Return Parts in Inventory Usage

1. Click on the Go To menu Inventory Inventory Usage.

2. Select the “New Inventory Usage” icon from the toolbar. 3. Enter ‘Return from Work Order’ in the Description field.

Page 95: PSU Supervisor Training Manual

Manager/Supervisor/Lead  Training  Manual   95  

4. Use the “Select Value” icon next to the “Usage Type” field to select ‘ISSUE’.

5. Select the “Select Items for Return” button in the Usage Lines section.

Important: You can also enter returns manually by selecting “New Row” and entering all of the information for the material being returned. However, when this method is used the return is not directly correlated with an issue transaction. This is regardless of whether a Work Order number is provided or not. This method is only recommended if you do not know what Work Order the materials were issued on or if the original Work Order is now Closed.

6. Click on the “Filter” link at the top of the “Items” section to open up a filter row.

Page 96: PSU Supervisor Training Manual

96   Manager/Supervisor/Lead  Training  Manual  

7. Enter the Work Order Number of the Work Order you are performing the return from in the filter field on the Work Order column and hit Enter.

8. Click on the box to the left of the Item to be returned and select “OK”.

Page 97: PSU Supervisor Training Manual

Manager/Supervisor/Lead  Training  Manual   97  

9. Open up a detail view of the transaction by selecting the “View Details” icon to the right of the row.

10. Enter the Person ID of the craftsperson returning the material in the “Returned By” field in the Charge Information section.

11. If applicable, update the Quantity being returned in the “Quantity” field.

Note: This would be done if the quantity returned is not the same quantity as the quantity that was issued.

12. Save the record.

Page 98: PSU Supervisor Training Manual

98   Manager/Supervisor/Lead  Training  Manual  

Note: If there Items to be returned at the same time to another Work Order, you can repeat steps 5 through 12 to add all of the lines for another Work Order to this Inventory Usage record.

Important: You can have usage lines for more than one Work Order on the same Inventory Usage record IF they are all executed at the same time. If the transactions for the separate Work Orders are not to be executed at the same time, you will need multiple Inventory Usage records.

Once all of the Inventory Usage lines have been added:

13. Select the “Set Inventory Usage record to complete” icon on the toolbar.

14. Select “OK” on the Change Status window.

As a reminder, you can also enter returns manually by selecting “New Row” and entering all of the information for the material being returned. However, when this method is used the return is not directly correlated with an issue transaction. This is regardless of whether a Work Order number is provided or not. This method is only recommended if you do not know what Work Order the materials were issued on or if the original Work Order is now Closed.

3.5 Refrigerant Tracking Overview Refrigerant materials that are physically moved from storerooms to supervisors to craftspeople and ultimately to Assets will be tracked as Inventory items in Maximo. To track each intermediate step in this process, Supervisors and Craftspeople will be set up as “Inventory Bins” for the refrigerant materials. With this virtual infrastructure, movement of refrigerant material between storerooms and Supervisors, Supervisors and Craftspeople, or just between Craftspeople will

Page 99: PSU Supervisor Training Manual

Manager/Supervisor/Lead  Training  Manual   99  

be entered as Transfer transactions in Maximo. Movement of refrigerant material between a Craftsperson and a Work Order will be entered as an Issue or Return transaction. The Inventory Usage application will be used to track the issue, transfer, and return of these refrigerant materials. Craftspeople will have permissions to enter these transactions, but not complete them. Supervisors will need to complete the transactions for them to take effect in the system and update balances. Each Supervisor and Craftsperson will have two bins named after themselves for each type of refrigerant item that they handle. One will be [PERSONID]-V to track their virgin (unused) refrigerant and the other will be [PERSONID]-R to track their reclaimed (used) refrigerant. Movement of “Virgin” Refrigerant:

Movement of “Reclaimed” Refrigerant:

Refrigerant  in  Storeroom  

Bin  

Transferred  to  Supervisor  "-­‐V"  Bin  

Transferred  to  

Craftsperson  "-­‐V"  Bin  

Issued  to  Work  Order  

Disposal  Transferred  to  Storeroom's  "-­‐

R"  Bin  

Transferred  to  Supervisor's  "-­‐

R"  Bin  

Returned  to  Craftsperson  "-­‐R"  Bin  (from  Work  Order)  

Page 100: PSU Supervisor Training Manual

100   Manager/Supervisor/Lead  Training  Manual  

The various refrigerant transaction scenarios are described in the table below:

Scenario Type of Transaction To and From Information for Transaction

Supervisor receives refrigerant material from stock location in storeroom.

Transfer From: Stock Bin in Main Storeroom

To: Supervisor’s “-V” Bin in Refrigerant Storeroom

Supervisor transfers refrigerant material to Craftsperson

Transfer From: Supervisor’s “-V” Bin in Refrigerant Storeroom

To: Craftperson’s “-V” Bin in Refrigerant Storeroom

Craftsperson transfers refrigerant material to another Craftsperson

Transfer From: Craftperson’s “-V” Bin in Refrigerant Storeroom

To: Craftperson’s “-V” Bin in Refrigerant Storeroom

Craftsperson issues refrigerant material to Asset via a Work Order

Issue From: Craftperson’s “-V” Bin in Refrigerant Storeroom

To: Work Order Number (Issue)

Page 101: PSU Supervisor Training Manual

Manager/Supervisor/Lead  Training  Manual   101  

Scenario Type of Transaction To and From Information for Transaction

Craftsperson returns refrigerant material from Asset via a Work Order

Return To: Craftperson’s “-R” Bin in Refrigerant Storeroom

From: Work Order Number (Return)

Craftsperson returns reclaimed refrigerant material to Supervisor

Transfer From: Craftsperson’s “-R” Bin in Refrigerant Storeroom

To: Supervisor’s “-R” Bin in Refrigerant Storeroom

Supervisor returns reclaimed refrigerant material to Storeroom

Transfer From: Supervisor’s “-R” Bin in Refrigerant Storeroom

To: Default “-R” Bin in Main Storeroom

3.5.1 Issuing Refrigerant

Refrigerant will be issued from the Inventory Usage application. Both Craftspeople and Supervisors will have the ability to enter an Inventory Usage record for refrigerant, but only Supervisor’s will have the ability to complete them.

3.5.1.1 EXERCISE: Issue Refrigerant from Craftsperson to Work Order in Inventory Usage

1. Click on the Go To menu Inventory Inventory Usage.

Page 102: PSU Supervisor Training Manual

102   Manager/Supervisor/Lead  Training  Manual  

2. Select the “New Inventory Usage” icon from the toolbar. 3. Enter ‘Issue Refrigerant to Work Order’ in the Description field.

4. Use the “Select Value” icon next to the “Usage Type” field to select ‘ISSUE’.

5. Enter ‘REF_BG’ in the “Storeroom” field.

6. Enter the Work Order Number that you are issuing to in the “Work Order” field in the Default Table Data section.

Page 103: PSU Supervisor Training Manual

Manager/Supervisor/Lead  Training  Manual   103  

Note: Once the Work Order Number is entered, the GL Account, Location, and Asset from the Work Order will display, if populated. The Entered By will default to you.

7. Enter ‘craftrain’ (the Person ID of the craftsperson that is issuing the material) in the “Issued To” field in the Default Table Data section.

Note: This is necessary only because the “Issue To” field is a required field when completing an issue. The value, in many cases, will be the same as the “Entered By” if a Craftsperson is entering their own transaction.

8. Select “New Row” in the Usage Lines section.

9. Enter ‘216800’ in the “Item” field.

Page 104: PSU Supervisor Training Manual

104   Manager/Supervisor/Lead  Training  Manual  

10. Enter ‘CTR01-V’ in the “From Bin” field. (This represents the virgin bin for this item for the ‘crafttrain’ user.)

11. Enter ‘5’ as the quantity being issued in the “Quantity” field. (This is in Lbs.)

12. Save the record.

The transaction is staged, but has not been executed at this point. If the user is a craftsperson, this is as far as they can go. A Supervisor will need to complete the Inventory Usage record.

3.5.1.2 EXERCISE: Approving (Completing) Refrigerant Issue in Inventory Usage

Supervisor’s will be required to approve (by completing) the Inventory Usage records for refrigerant issues entered by their craftspeople. They can be prompted to do this either through direct communication from the craftsperson or via a saved query for Inventory Usage records entered by their employees that are still in “Entered” status.

Any way that they are alerted, the process begins by finding and opening the Inventory Usage record. For this exercise we can continue with the Inventory Usage record we just created.

1. Select the “Set Inventory Usage record to complete” icon on the toolbar.

2. Select “OK” on the Change Status window.

Page 105: PSU Supervisor Training Manual

Manager/Supervisor/Lead  Training  Manual   105  

The issue transaction is now complete. The “-V” bin for the craftsperson has been decreased by the amount issued and that amount has been charged to the Work Order (and the Work Order’s Asset/Location.)

3.5.2 Transferring Refrigerant

Refrigerant will be transferred from the Inventory Usage application. Both Craftspeople and Supervisors will have the ability to enter an Inventory Usage record for refrigerant, but only Supervisor’s will have the ability to complete them.

3.5.2.1 EXERCISE: Transfer Refrigerant from Supervisor to Craftsperson in Inventory Usage

1. Click on the Go To menu Inventory Inventory Usage.

2. Select the “New Inventory Usage” icon from the toolbar. 3. Enter ‘Transfer Refrigerant from Supervisor to Craftsperson’ in the

Description field.

Page 106: PSU Supervisor Training Manual

106   Manager/Supervisor/Lead  Training  Manual  

4. Use the “Select Value” icon next to the “Usage Type” field to select ‘TRANSFER’.

5. Enter ‘REF_BG’ in the “Storeroom” field.

6. Enter ‘craftrain’ (the Person ID of the craftsperson that is being issued the material) in the “Issued To” field in the Default Table Data section.

7. Select “New Row” in the Usage Lines section.

8. Enter ‘216800’ in the “Item” field.

Page 107: PSU Supervisor Training Manual

Manager/Supervisor/Lead  Training  Manual   107  

9. Enter ‘STR01-V’ in the “From Bin” field. (This represents the virgin bin for this item for the ‘supertrain’ user.)

10. Enter ‘5’ as the quantity being transferred in the “Quantity” field. (This is in Lbs.)

11. Enter ‘REF_BG’ in the “To Storeroom” field.

Page 108: PSU Supervisor Training Manual

108   Manager/Supervisor/Lead  Training  Manual  

12. Enter ‘CTR01-V’ in the “To Bin” field. (This represents the virgin bin for this item for the ‘crafttrain’ user.)

Page 109: PSU Supervisor Training Manual

Manager/Supervisor/Lead  Training  Manual   109  

13. Save the record.

The transaction is staged, but has not been executed at this point. If the user is a craftsperson, this is as far as they can go. A Supervisor will need to complete the Inventory Usage record.

3. Select the “Set Inventory Usage record to complete” icon on the toolbar.

4. Select “OK” on the Change Status window.

The transfer transaction is now complete. The “-V” bin for the craftsperson has been increased by the amount transferred and the “-V” bin for the supervisor has been decreased by the same amount.