Progress Status at Pour 5,6 Locations
11
Progress Status at Podium LB 6,7 & UB 5 Locations Status as on 24 th Nov’15
description
Progress Status a
Transcript of Progress Status at Pour 5,6 Locations
![Page 1: Progress Status at Pour 5,6 Locations](https://reader033.fdocuments.net/reader033/viewer/2022050909/5695d2081a28ab9b0298df48/html5/thumbnails/1.jpg)
Progress Status at Podium LB 6,7 & UB 5 Locations
Status as on 24th Nov’15
![Page 2: Progress Status at Pour 5,6 Locations](https://reader033.fdocuments.net/reader033/viewer/2022050909/5695d2081a28ab9b0298df48/html5/thumbnails/2.jpg)
30% staging works yet to be done at pour 5 UB location.
![Page 3: Progress Status at Pour 5,6 Locations](https://reader033.fdocuments.net/reader033/viewer/2022050909/5695d2081a28ab9b0298df48/html5/thumbnails/3.jpg)
Retaining wall (Dependent activity ) not yet casted at pour 5 UB location
![Page 4: Progress Status at Pour 5,6 Locations](https://reader033.fdocuments.net/reader033/viewer/2022050909/5695d2081a28ab9b0298df48/html5/thumbnails/4.jpg)
40% shuttering works yet to be done at pour 5 UB location.
![Page 5: Progress Status at Pour 5,6 Locations](https://reader033.fdocuments.net/reader033/viewer/2022050909/5695d2081a28ab9b0298df48/html5/thumbnails/5.jpg)
Staircase columns not yet casted at pour 5 location.
![Page 6: Progress Status at Pour 5,6 Locations](https://reader033.fdocuments.net/reader033/viewer/2022050909/5695d2081a28ab9b0298df48/html5/thumbnails/6.jpg)
20% shuttering work yet to be done at pour 6 location.
![Page 7: Progress Status at Pour 5,6 Locations](https://reader033.fdocuments.net/reader033/viewer/2022050909/5695d2081a28ab9b0298df48/html5/thumbnails/7.jpg)
No manpower been deployed for reinforcement works at Pour 6 location.
![Page 8: Progress Status at Pour 5,6 Locations](https://reader033.fdocuments.net/reader033/viewer/2022050909/5695d2081a28ab9b0298df48/html5/thumbnails/8.jpg)
Beam B34 bottom not yet initiated at pour 6 location.
![Page 9: Progress Status at Pour 5,6 Locations](https://reader033.fdocuments.net/reader033/viewer/2022050909/5695d2081a28ab9b0298df48/html5/thumbnails/9.jpg)
Rain water tank bottom slab not yet casted at pour 6 location.
![Page 10: Progress Status at Pour 5,6 Locations](https://reader033.fdocuments.net/reader033/viewer/2022050909/5695d2081a28ab9b0298df48/html5/thumbnails/10.jpg)
16 columns yet to be casted at pour 7 location .
![Page 11: Progress Status at Pour 5,6 Locations](https://reader033.fdocuments.net/reader033/viewer/2022050909/5695d2081a28ab9b0298df48/html5/thumbnails/11.jpg)
Casting of starters not been initiated at pour 7 locations