Presented by Dorian Conger Conger-Elsea, Inc. 2000 Riveredge Parkway, Suite 740 Atlanta, GA 30328...
-
Upload
janel-tucker -
Category
Documents
-
view
214 -
download
0
Transcript of Presented by Dorian Conger Conger-Elsea, Inc. 2000 Riveredge Parkway, Suite 740 Atlanta, GA 30328...
1
Responding to a PI&R Substantive Crosscutting Area
Presented by Dorian CongerConger-Elsea, Inc.
2000 Riveredge Parkway, Suite 740Atlanta, GA 30328
800-875-8709 phone770-926-8305 fax
2009 Human Performance, Root Cause, and Trending ConferenceDel Ray Beach, FL
Copyright 2014 Conger-Elsea, Inc.
PI&R is the most important program at the plant from a regulatory standpoint. A PI&R Substantive Crosscutting Area results from a failed Problem Identification and Resolution (PI&R) process; most frequently a failing or seriously flawed corrective action program.
Copyright 2014 Conger-Elsea, Inc. 2
HOW DID IT HAPPEN?
3
1. Extent of Condition
2. Extent of Cause
3. Safety Culture
4. Management System and Programmatic Considerations
5. Inadequate cause evaluations (root and apparent)
Copyright 2014 Conger-Elsea, Inc.
FIVE KEY AREAS FOUNDMISSING OR INSUFFICIENT
4
Column 1 – Licensee Response (86)
Column 2 – Regulatory Response (15) - 95001
Column 3 – Degraded Cornerstone (2) - 95002
Column 4 – Multiple/Repetitive Degraded Cornerstone (1) - 95003
Column 5 – Unacceptable Performance
Copyright 2014 Conger-Elsea, Inc.
BASIC INFORMATION ABOUT THE NRC
5
Column 2 - $1 - $2 Million
Column 3 - $10 - $20 Million
Column 4 - $100 - $300 Million
Copyright 2014 Conger-Elsea, Inc.
ESTIMATED COST OF RECOVERY
6
Back to the drawing board – Restructure the Corrective Action Program (CAP)
MAKE THE NECESSARY CHANGES TO THE CORRECTIVE ACTION PROGRAM TO MAKE THE UPGRADED PROCESS REPEATABLE AND SUSTAINABLE.
Detailed evaluation of the existing program Rewrite the governing procedures (near state-of-the-art; final changes to follow) Train the plant staff, as appropriate:
Root Cause Analysts (Team Leaders) Apparent Cause Analysts Management Alignment training – Executives and Managers; Supervisors Familiarize remaining plant staff
Conduct root cause evaluations using the new procedures with expert mentoring (two rounds recommended; may also include team leader skills training)
Train station executives and managers to the elevated standards for root cause analysis and the proper behavioral expectations for Corrective Action Review Board (CARB) members
CARB review and approve the upgraded root cause reports with related corrective actions (CARB observed and mentored/coached as needed)
Implement the new PI&R process with 2-4 months of run time
Copyright 2014 Conger-Elsea, Inc.
HOW DO WE GET OUT OF THIS MESS?
7
MOCK NRC PI&R Inspection – Establish a team of experts to perform a MOCK PI&R Inspection
NRC Team Leader experience NRC Inspector experience Root Cause and Corrective Action Program
expertise Safety Culture expertise
Copyright 2014 Conger-Elsea, Inc.
HOW DO WE GET OUT OF THIS MESS? (Continued)
8
Perform the MOCK PI&R Inspection
Two weeks onsite One week for report preparation (if needed) Deliver the report to the plant management Provide advice and counsel to plant management
regarding NRC PI&R expectations and the need to communicate importance to the entire plant staff
Copyright 2014 Conger-Elsea, Inc.
HOW DO WE GET OUT OF THIS MESS? (Continued)
9
Evaluate current program – 2 weeks involving two or three senior consultants/principals
Rewrite CAP procedures – 4-6 weeks for the drafting and editing 2 weeks for the reviews and approvals
Training – 1 week - Root Cause Analysts (Team Leaders) - fully mentored; 5-day class 1 week - Apparent Cause Analysts – two 2-day class sessions 2 week - Management Alignment training – Executives and Managers (two 2-day
sessions; Supervisors (two 4-hours sessions; plus video) 1 week - Familiarize remaining plant staff (all hands meetings as needed)
Conduct Cause Evaluations per the new standard and procedures – 8-12 weeks for conducting mentored cause evaluations to assure competence
and readiness of the personnel to sustain the process CARB review and approval of reports –
As completed Implement the new process prior to the MOCK PI&R inspection –
Allow 2-4 months run time Conduct MOCK inspection and report –
2 weeks for performing the on-site inspection and writing the report with recommendations
Copyright 2014 Conger-Elsea, Inc.
TIMING THE RELATED ACTIVITIES
10
1. Understanding the magnitude of the problem2. Top management commitment and active
participation3. Resource commitment to properly perform the
upgraded CAP process4. Demonstrate commitment by implementing
corrective actions5. Demonstrate that the new CAP process can be
sustained without intervention6. Ultimately, demonstrate the upgraded processes to
an NRC inspection team to clear the PI&R Substantive Crosscutting Area
Copyright 2014 Conger-Elsea, Inc.
KEYS TO SUCCESS