Preparation and ways of utilization of hydroelectric plants in system of ancillary services in...

8
Preparation and ways of utilization Preparation and ways of utilization of hydroelectric plants in system of of hydroelectric plants in system of ancillary services in Electric power ancillary services in Electric power system of Czech Republic system of Czech Republic Ing. Jan Dřímal Control Systems Division OSC, a.s. Czech Republic Hydroforum 2005

Transcript of Preparation and ways of utilization of hydroelectric plants in system of ancillary services in...

Page 1: Preparation and ways of utilization of hydroelectric plants in system of ancillary services in Electric power system of Czech Republic Ing. Jan Dřímal.

Preparation and ways of utilization of Preparation and ways of utilization of hydroelectric plants in system of ancillary hydroelectric plants in system of ancillary services in Electric power system of Czech services in Electric power system of Czech RepublicRepublic

Ing. Jan DřímalControl Systems DivisionOSC, a.s.Czech Republic

Hydroforum 2005

Page 2: Preparation and ways of utilization of hydroelectric plants in system of ancillary services in Electric power system of Czech Republic Ing. Jan Dřímal.

2

Resource control in EPS of Czech RepublicResource control in EPS of Czech Republic

RTISZ

Dispatchcenter

C en tral datab ase of Č EZ resource preparatio n

U nitcon t. system ,

techn ology

Operativecontrol ofoperation

KOTEL

. . .TELE 1

ČEZ dispatch center - trade and technical

ČEZ resources

Trade

Co

ntr

ol s

yste

mD

C Č

EP

S

Info

rmat

ion

sy

stem

to

pre

par

ere

so

urc

e o

per

atio

n

Info

rmat

ion

an

d c

on

tro

l sy

stem

of

ČE

Z r

eal

tim

e re

sou

rce

op

era

tio

n

TELE 2

. . .

Electric power/distribution system

Operationpreparation

TELE n

O ther resources

ČEPS

U nitcon t. system ,

techn ology

U nitcon t. system ,

techn ology

Page 3: Preparation and ways of utilization of hydroelectric plants in system of ancillary services in Electric power system of Czech Republic Ing. Jan Dřímal.

3

Power plant terminal (TELE)Power plant terminal (TELE)

Power plant terminal (TELE) based on OSCART

TELE Operator station Control unit

O ther connected systems

Modems

Technology

Servicestation

LAN

OSCART

Systems connectedby LAN

Page 4: Preparation and ways of utilization of hydroelectric plants in system of ancillary services in Electric power system of Czech Republic Ing. Jan Dřímal.

4

System of ancillary servicesSystem of ancillary services

Primary frequency control

Secondary power control

Tertiary power control

Quick starting reserve (available within 10 minutes)

Operating reserve (available within 90 minutes)

Secondary voltage and reactive power control

Island operation capability

Black start capability

Page 5: Preparation and ways of utilization of hydroelectric plants in system of ancillary services in Electric power system of Czech Republic Ing. Jan Dřímal.

5

Preparation of power plants to provide ancillary servicesPreparation of power plants to provide ancillary services

Assessment of the properties and capacities of the power plant

Submitting an application

Preparation and verification of the capacity of power plant to provide selected ancillary services

Certification measurement

Equipment the power plant with the power generating plant terminal (TELE)

Conclusion the appropriate contracts with the TSO

Page 6: Preparation and ways of utilization of hydroelectric plants in system of ancillary services in Electric power system of Czech Republic Ing. Jan Dřímal.

6

Model utilization in Model utilization in preparationpreparation of TG EDA of TG EDA for black start capabillityfor black start capabillity

Power control

Speed control

TG

EPS

Load

Position regulation

Page 7: Preparation and ways of utilization of hydroelectric plants in system of ancillary services in Electric power system of Czech Republic Ing. Jan Dřímal.

7

Comparison of model with real operationComparison of model with real operation

5 5 6 0 6 5 7 0 7 5 8 0 8 5t [ s ]

1 8

2 0

2 2

2 4

2 6

2 8

3 0

3 2

3 4YR K[% ]

49.0

49.5

50.0

50.5

51.0

51.5

52.0

52.5

53.0F

[Hz]

0.0

2.5

5.0

7.5

10.0

12.5

15.0

17.5

20.0N e

[M W ]

Ne

YRK

F

YRK_model

F_model

Ne_model

Page 8: Preparation and ways of utilization of hydroelectric plants in system of ancillary services in Electric power system of Czech Republic Ing. Jan Dřímal.

Preparation and ways of utilization of hydroelectric Preparation and ways of utilization of hydroelectric plants in system of ancillary services in Electric power plants in system of ancillary services in Electric power

system of Czech Republicsystem of Czech Republic

Thank you for your kind attentionThank you for your kind attention

Ing. Jan DřímalOSC, a.s.

Control Systems Division