PLUMESTOP APPLICATION PAVES THE WAY FOR …

16
PLUMESTOP APPLICATION PAVES THE WAY FOR REDEVELOPMENT CASE STUDY: DVT and Predicve Modeling Contribute to Achieving Remediaon Goals

Transcript of PLUMESTOP APPLICATION PAVES THE WAY FOR …

Page 1: PLUMESTOP APPLICATION PAVES THE WAY FOR …

PLUMESTOP APPLICATION PAVES THE WAY FOR REDEVELOPMENTCASE STUDY:DVT and Predictive Modeling Contribute to Achieving Remediation Goals

Page 2: PLUMESTOP APPLICATION PAVES THE WAY FOR …

OverviewAdvanced Site Characterization Methods Help to Achieve Ambitious Site Goals

Advanced design verification testing and predictive modeling methods were used at a contaminanted chlorinated solvent site in northern California to guide a remarkably successful in situ remediation effort. Complete reduction of chlorinated volatile organic compounds (CVOCs) in the treatment areas and remedial objectives achieved allowed redevelopment of the property.

The site is a former industrial facility where chlorinated solvents were spilled during industrial manufacturing processes occurring from 1941 to 1970. In 1972, a retail shopping center was constructed over the site following the removal of the industrial facility’s structures. In anticipation of redevelopment, buildings in the western portion of the shopping center where the former industrial building sat were removed in 2019.

The redevelopment plan includes an apartment complex and commercial buildings. Remediation to address the CVOC contamination was necessary to allow the development to proceed. The primary CVOC chemicals of concern were tetrachloroethene (PCE) and degradation products, trichloroethene (TCE), cis-1,2-dichloroethene (cis-DCE), and vinyl chloride (VC). PES Environmental, Inc., an NV5 Company, (PES) of Novato, California, was selected by the developer as their Environmental Consultant for this project.

Investigations to define the nature, extent, and general structure of the groundwater plume had been ongoing at the site since the 1980s. More recent characterization activities included membrane interface probe (MIP) and cone penetrometer testing (CPT) study, which identified an approximate 1.5-acre plume area requiring remediation.

2 Overview

Page 3: PLUMESTOP APPLICATION PAVES THE WAY FOR …

When PES engaged REGENESIS on the project, the overall plume features were understood. Critical to developing a remediation plan, the following data was needed:

• groundwater velocity,

• location of primary contaminant transport zones, and

• groundwater CVOC concentrations beyond the source and near-source areas.

A better understanding of contaminant flux was needed. By understanding the contaminant flux, a cost-effective remediation plan could be designed, specifically engineered to achieve a project goal. In this case, the goal was to fully remediate the CVOCs in the target treatment areas within two years following application of the treatment approach.

Page 4: PLUMESTOP APPLICATION PAVES THE WAY FOR …

Design Verification TestingDVT is Especially Effective at Pin-Pointing the Specific Dosing and Treatment Unique to a Site

Design verification testing or DVT is a proprietary approach employed by REGENESIS comprising various in-field and laboratory testing methods to verify remedial design assumptions. Each project site is unique and requires different testing methods based on the site conditions and the project’s goals.

A DVT plan was prepared for this site through a collaborative effort between REGENESIS and PES. The DVT plan was devised to gather the information needed to design a remediation approach that could meet the two-year remediation objective with the greatest efficiency and economy, with a primary focus on defining contaminant flux.

Injection testing using clear water was also a key DVT component since it confirmed the volumes needed to achieve the pore-volume filling required. The injection test also established a pumping rate that RRS could sustain without pressure build-up, which allowed a reasonably precise estimate of the time to complete the fieldwork. A list of DVT items conducted, their purpose, and who completed each item is summarized below.

Example of soil cores collected as part of design verification testing procedures. These cores help to verify soil conditions and confirm the presense of remedial amendments within the target treatment interval.

4 Design Verification Testing

Page 5: PLUMESTOP APPLICATION PAVES THE WAY FOR …

DVT ResultsFollowing the DVT, REGENESIS was able to reduce the target treatment volume by approximately 20 percent. The clear water injection test confirmed that RRS could maintain low injection pressures at a moderate injection pumping rate.

DVT Summary

DVT Item Completed by Purpose

Identify transmissive zones through grain size analysis

Track performance and demonstrate progress toward remedial goals

Define contaminant flux to determine product dosing and optimize treatment row placement needed to meet remedial timeframes

Assess optimal product injection radius, and define remediation injection timeframe

Continuous Soil Cores/Soil Settling Tubes

Performance Monitoring Well Installation

Passive Flux Study

Clear Water Injection Test

REGENESIS

PES

PES Field Deployment and Collection

REGENESIS Flux analysis and Predictive Models

REGENESIS and PES

Example of settling tubes used as part of design verification testing

0

5

10

15

20

25

30

35

40

1:12 PM 1:40 PM 2:09 PM 2:38 PM 3:07 PM 3:36 PM 4:08 PM 4:33 PM 5:02 PM 5:31 PM

0

100

200

300

400

500

600

700

800

900

1000

PSI GPMTotal Volume DTW

PSII/

GPM

/DTW

Tota

l Vol

ume

Inje

cted

(Gal

lons

)

Chart showing pumping rate, injection pressures, depth to water and total volume injected.

Design Verification Testing 5

Page 6: PLUMESTOP APPLICATION PAVES THE WAY FOR …

Predictive Modeling and Remedial DesignFlux-Based Predictive Modeling Used to Optimize Remediation to Meet Two-Year Timeline

REGENESIS utilizes a proprietary flux-based modeling program to predict remediation cleanup timeframes. The relative certainty of the predicted timeframes is dependent on the understanding of contaminant flux. To determine flux model inputs, passive flux meters (PFMs) were placed within the plume body to delineate the prominent flux zones and magnitude.

The PFMs indicated that the average groundwater velocity was less than 300 feet per year at the site, roughly four times less than the earliest estimates using traditional hydraulic characterization methods. However, the PFM-confirmed velocity matched closely to a plume-aspect ratio curve-fitting method REGENESIS employs for plume treatments. Thus, the PFM study mostly aligned with REGENESIS product dosing estimates.

6 Application

Page 7: PLUMESTOP APPLICATION PAVES THE WAY FOR …

From this information, REGENESIS confirmed the remediation approach and optimized the remediation design to achieve the two-year remediation goal with the greatest economic efficiency, leading to the submittal of a Response Plan to the Regional Water Quality Control Board (RWQCB). The following components were specified in the Response Plan:

• In situ source area shallow groundwater remediation using 3-D Microemulsion®, S-MicroZVI® and Bio-Dechlor INOCULUM Plus® (BDI) to promote enhanced reductive dechlorination (ERD) via biological and direct chemical reduction.

• Source area excavation and disposal of CVOC-impacted soils.

• In situ groundwater plume remediation via sorption enhanced chemical reduction using PlumeStop® and S-MicroZVI.

• Supplemental ERD injections into lower sand unit beneath the source area utilizing S-MicroZVI and 3-D Microemulsion (including supplemental well installation to monitor performance in source area).

W1-A1 W1-A2 W2-A1 W2-A20.0

0.5

1.0

1.5

Mas

s Fl

ux (m

g/m

2 /da

y)

Mass Flux

2.0

2.5

3.0

PCE 1,2DCETCE

Chart Depicts CVOC Mass Flux at two well pairs, W1 and W2

Results 7

Page 8: PLUMESTOP APPLICATION PAVES THE WAY FOR …

RemediationProject Timeline

The remediation was completed during four separate phases spanning from March 2019 through March 2020.

• March 2019 In situ source area shallow groundwater remediation. Approximately 26,600 gallons of 3-D Microemulsion, S-MicroZVI, and BDI were injected.

• September – October 2019 Source area excavation and disposal of over 4,400 cubic yards of CVOC-impacted soils.

• October – November 2019 In situ groundwater plume remediation. Over 200,000 gallons of diluted PlumeStop and S-MicroZVI mixtures were injected.

• March 2020 Supplemental injections into lower sand unit beneath source area. Approximately 35,000 gallons of diluted S-MicroZVI and 3-D Microemulsion mixtures were injected.

Application Design Summary

Contaminants of Concern

PCE, TCE, cis-DCE, VC

Concentrations <10 µg/L - 200 µg/L

Remedial Application Application Area 68,000 ft2

Treatment Volume 1.36 million ft3

Treatment Interval 10-30 ft bgs. Timespan 28 field days

Products Applied PlumeStop, S-MicroZVI 208,560 gal

8 Remediation

Page 9: PLUMESTOP APPLICATION PAVES THE WAY FOR …

The remedial design included in the Response Plan specified grid-array injections in the source area and a series of transects in the main plume area, optimally spaced to achieve full plume reductions within two years.

REGENESIS Remediation Services (RRS) injected all remedial reagents, completing the project on time and budget with PES’ oversight. As predicted by the clear water injection testing, RRS maintained low injection pressures and moderate flow rates throughout the project.

Remediation 9

Page 10: PLUMESTOP APPLICATION PAVES THE WAY FOR …

Oct 1 Nov 30 Jan 292019 2020

Mar 29 May 28 Jul 27 Sept 25

Conc

entr

ation

(µg/

L)

Date

60

50

40

30

20

10

0

ResultsThe Highly Successful Remediation Paves the Way for Property Redevelopment

Charts Showing Remedial Performance in the A1-Upper Treatment Zone. Chart data provided by PES

PCE TCE cis-1,2-DCE VC Ethane

Oct 1 Nov 30 Jan 292019 2020

Mar 29 May 28 Jul 27 Sept 25

Conc

entr

ation

(µg/

L)

Date

140

120

100

80

60

40

20

0

10 Results

To monitor performance in the main plume area, paired wells were installed downgradient of each transect beyond the injection radius of influence. The wells were screened in defined sections of the treatment interval: A1-Upper and A2-Lower Treatment Zones. In the source area, performance replacement monitoring wells were installed following the excavation and before source injection treatments. Four post-application monitoring events have been completed in the main plume area, and three post-application events have been completed in the source area.

PCE TCE cis-1,2-DCE VC EthaneW4-A1 Downgradient of Barrier 1

W5-A1 Downgradient of Barrier 2

Page 11: PLUMESTOP APPLICATION PAVES THE WAY FOR …

Results 11

The remediation has met the predicted performance expectations. After approximately one year post-injection, greater than 90 percent CVOC reductions have been achieved in the main plume area. Reductions have been most pronounced, 98 percent, in the lower A2 Zone thus far, correlating with the overall higher groundwater velocities observed in this zone during the PFM study. Significant concentrations of ethane, an abiotic degradation byproduct, have been observed in both the A1 and A2 Zones, indicating complete degradation of the CVOCs is occurring with little to no daughter product formation.

W6-A2 Downgradient of Barrier 1

W4-A2 Downgradient of Barrier 2

Charts Showing Remedial Performance in the A2-Lower Treatment Zone. Chart data provided by PES

Well W6-A2Downgradient of Barrier 1

Oct 1 Nov 30 Jan 292019 2020

Mar 29 May 28 Jul 27 Sept 25

Conc

entr

ation

(µg/

L)

Date

250

200

150

100

50

0

Well W4-A2Downgradient of Barrier 1

Oct 1 Nov 30 Jan 292019 2020

Mar 29 May 28 Jul 27 Sept 25

Conc

entr

ation

(µg/

L)

Date

3.0

2.5

2.0

1.5

1.0

0.5

0.0

PCE TCE cis-1,2-DCE VC Ethane

PCE TCE cis-1,2-DCE VC Ethane

Page 12: PLUMESTOP APPLICATION PAVES THE WAY FOR …

12 Results

In the source area, the combined excavation and in situ injection have reduced CVOC concentrations by 98 percent, indicating the virtual elimination of the CVOC source. The source area treatment is anticipated to be effective for several more years. As monitoring progresses, the source-elimination effect will be further reflected in the downgradient plume, which has already demonstrated substantial reductions.

The use of DVT and predictive modeling tools allowed the REGENESIS and PES team to maximize the injected remediation technologies’ functionality to achieve the greatest benefit and attain the remedial objectives within the two-year timeframe. Based on the observed performance after one year, PES has successfully petitioned the RWQCB to end plume monitoring and remove the performance monitoring wells so that the property redevelopment can proceed.

Page 13: PLUMESTOP APPLICATION PAVES THE WAY FOR …

PlumeStop® Liquid Activated Carbon™ is a fast-acting groundwater remediation reagent which captures and biodegrades a range of contaminants, thus accelerating the successful treatment of impacted sites and leading to their permanent closure. As a science-based, in situ treatment technology, REGENESIS’ PlumeStop rapidly removes contaminants from groundwater and stimulates their permanent degradation.

Technologies UsedPlumeStop, S-MicroZVI, and 3-D Microemulsion

S-MicroSul�dated Zero-Valent Iron

S-MicroZVI® is an In Situ Chemical Reduction (ISCR) reagent that promotes the destruction of many organic pollutants and is most commonly used with chlorinated hydrocarbons. It is engineered to provide an optimal source of micro-scale zero valent iron (ZVI) that is both easy to use and delivers enhanced reactivity with the target contaminants via multiple pathways. S-MicroZVI can destroy many chlorinated contaminants through a direct chemical reaction. S-MicroZVI will also stimulate anaerobic biological degradation by rapidly creating a reducing environment that is favorable for reductive dechlorination.

3-D Microemulsion® is an injectable liquid material specifically designed for in situ remediation projects where the anaerobic biodegradation of chlorinated compounds through the enhanced reductive dechlorination (ERD) process is possible. ERD is the primary anaerobic biological process by which problematic chlorinated solvents such as tetrachloroethylene (PCE) and trichloroethene (TCE), dichloroethene (DCE) and vinyl chloride (VC) in groundwater are biologically transformed into less harmful end products such as ethene.

®

Page 14: PLUMESTOP APPLICATION PAVES THE WAY FOR …

About The ConsultantPES Environmental

PES Environmental, Inc., an NV5 Company, (PES), with offices in Novato, California; Seattle, Washington; and Veneta, Oregon, was formed in 1989 in response to the demand for experienced environmental consultants capable of providing high quality services in environmental engineering, hydrogeologic consulting, hazardous waste management, and regulatory compliance. PES is a highly respected, client-oriented company with a reputation for solving environmental problems.

PES provides high quality environmental consulting in the following areas: Site Investigation, Monitoring, and Remediation Services; Multi-PRP/Superfund Services; Underground Storage Tank Management Services; Real Estate Transaction-Related Services; Industrial Hygiene / Lead, Asbestos and Mold Surveys and Abatement Services; Facility Permitting, Compliance, and Closure Services; Third Party (Peer) Review, Litigation Support, and Expert Witness Services; Storm Water Management Services; and Dredging and Dredged Sediment Management Services.

About The Project ManagerWenqian Dou, PhD, PE

Dr. Dou is a Registered Civil Engineer in California specialized in environmental engineering. She has over 13 years of environmental consulting experience, providing technical support, oversight, and project management for various environmental projects throughout the nation. She has acquired extensive experience with Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) and Resource Conservation and Recovery Act (RCRA) regulations.

Dr. Dou has worked on remediation projects with a wide range of chemicals, including volatile organic compounds (VOCs), such as tetrachloroethene (PCE) and trichloroethene (TCE), semivolatile organic compounds (SVOCs), polychlorinated biphenyls (PCBs), total petroleum hydrocarbons (TPH), polycyclic aromatic hydrocarbons (PAHs), and heavy metals. She is experienced in cost estimating, proposal writing, litigation support, negotiating with regulators, and interacting with community members.

14 About PES

Page 15: PLUMESTOP APPLICATION PAVES THE WAY FOR …

We’re Ready to Help You Find the Right Solution For Your Site

Visit www.REGENESIS.com to learn more.

1011 Calle SombraSan Clemente, CA 92673 USAPh: (949) 366-8000Fax: (949) 366-8090

Bath, United KingdomPh: +44 (0) 1225 61 81 61

Dublin, IrelandPh: +353 (0) 1 9059 663

Torino, ItaliaPh: +39 338 8717925

Ieper, BelgiëPh: +32 (0) 57 35 97 28

EuropeGlobal Headquarters

Page 16: PLUMESTOP APPLICATION PAVES THE WAY FOR …

www.REGENESIS.com ©2021 All rights reserved. PlumeStop, S-MicroZVI, 3D Microemulsion and REGENESIS are registered trademarks of REGENESIS Bioremediation Products. All other trademarks are the property of their respective owners.