PLANNING CHALLENGES FOR NET ZERO...

81
PLANNING CHALLENGES FOR NET ZERO INSTALLATIONS Jerry Zekert, Chief, Master Planning Team, HQUSACE Andrea Kuhn, AICP, LEED Green Associate, Senior Planner, HQ USACE William Goran, Director, Center for the Advancement of Sustainability Innovations (CASI) U.S. Army Corps of Engineers ERDC CERL Cyndi Skinner, AICP, Fort Hunter Liggett Michael Case, PhD, Net Zero Program Manager, USACE ERDC CERL US Army Corps of Engineers BUILDING STRONG ®

Transcript of PLANNING CHALLENGES FOR NET ZERO...

Page 1: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

PLANNING CHALLENGES FOR NET ZERO INSTALLATIONS

Jerry Zekert, Chief, Master Planning Team, HQUSACE

Andrea Kuhn, AICP, LEED Green Associate, Senior Planner, HQ USACE

William Goran, Director, Center for the Advancement of Sustainability Innovations (CASI) U.S. Army Corps of Engineers ERDC CERL

Cyndi Skinner, AICP, Fort Hunter Liggett

Michael Case, PhD, Net Zero Program Manager, USACE ERDC CERL

US Army Corps of Engineers

BUILDING

STRONG®

Page 2: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

APA Session Plan 17 APR

Topic Speaker Time

(AM)

Introduction to Military Bases and Planning at

Military Bases

Jerry Zekert, Chief, Master Planning Team, and Andrea

Kuhn, AICP, LEED Green

Associate, Senior Planner,

HQUSACE, U.S. Army Corps of

Engineers

10:30-10:50

The Army’s Net Zero

Initiative

William Goran, Director, CASI,

U.S. Army Corps of Engineers

10:50-11:00

Progressing Towards Net

Zero - Installation Planning

Perspective

Cyndi Skinner, AICP, Ft.

Hunter-Liggett, CA

11:00-11:20

Net Zero Technology

Capabilities and

Demonstration

Michael Case, USACE-ERDC,

Champaign IL

11:20-11:35

Discussion All 11:35-11:45 APA April 2012

Page 3: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

Moving to Net Zero

The Role of Master Planning

Jerry Zekert, Chief, Master Planning Team, HQUSACE, and

Andrea Kuhn, AICP, LEED Green Associate, Senior Planner, HQUSACE

Policy Alignment

Sustainable Planning in the DOD

The Problem: Energy Inefficient Development

The Costs of Energy Inefficient Development

The Solution: An Enterprise Approach to Energy Efficient

Development

Page 4: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

FEDERAL LEADERSHIP IN ENVIRONMENTAL, ENERGY, AND ECONOMIC

PERFORMANCE (5 Oct 2009)

It is therefore the policy of the United States that Federal agencies shall increase energy efficiency; measure, report, and reduce their

greenhouse gas emissions from direct and indirect activities; conserve

and protect water resources through efficiency, reuse, and stormwater

management; eliminate waste, recycle, and prevent pollution;

leverage agency acquisitions to foster markets for sustainable technologies and environmentally preferable materials, products, and

services; design, construct, maintain, and operate high performance

sustainable buildings in sustainable locations; strengthen the vitality

and livability of the communities in which Federal facilities are

located; and inform Federal employees about and involve them in the achievement of these goals.

Executive Order 13514

4

Ensure “that planning for new Federal facilities or new leases includes

consideration of sites that are pedestrian friendly, near existing

employment centers, and accessible to public transit, and emphasizes

existing central cities and, in rural communities, existing or planned town

centers.”

Page 5: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

Sustainable planning leads to lasting development by meeting

present mission requirements without compromising the ability

of future generations to meet their needs.

The goal of such development is to make the most effective use of

limited resources, reduce fossil fuel use, and increase alternative fuel

use, and to create more compact and sustainable communities

that still meet security and safety requirements.

ACSIM Policy

5

Planners will incorporate the following key principles of sustainable

planning in their Master Plans, area development plans, and other

planning products:

• compact development

• infill development

• transit-oriented development

• horizontal and vertical mixed-uses

• connected transportation networks

• low impact development

• multi-story construction

• narrow buildings

Page 6: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

The Problem:

Energy-Inefficient

Development

6

Page 7: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

Installation Challenge: Inefficient Planning

Auto

Focused

Abundantly

Paved

Widely

Spaced Olympia WA

Haphazardly

Ordered

Clearly

Segregated

JBLM

Preserving

Military

Capabilities

Energy

Inefficient

7

Page 8: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

KEY FINDINGS

1. Interior lighting and

HVAC account for 54%

of total energy

consumption

2. Strategies that can

reduce need for interior

lighting and HVAC will

produce biggest

benefits

- Narrow Wings

- Operable Windows

Bottom Line

To significantly reduce

energy use, planning of

the built environment

must accommodate

narrow wings.

Estimates of Energy Consumption by Building Type and End Use at U.S. Army Installations by Lawrence Berkeley National Laboratory, 1996.

Energy Inefficient

8

Page 9: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

The Costs of

Energy-Inefficient

Development

9

Page 10: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

Driving a car is probably a typical citizen’s most

polluting daily activity.

EPA

Air Pollution

10

Page 11: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

Climate Change, Energy and DoD

“Climate change and energy will

play significant roles in the future

security environment. Climate

change will shape the operating

environment, roles, and missions

that we undertake...[and]... DoD

will need to adjust to the impacts

of climate change on our facilities

and military capabilities. The

Department is developing

policies and plans to manage the

effects of climate change on its

operating environment, missions,

and facilities.”

DoD Quadrennial Defense

Review, 2010

Climate Change

11

Page 12: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

ROADS +25%

UTILITIES +15%

SCHOOLS +5%

Source: Economic and Fiscal Impacts of Alternative

Land Use Patterns, by Robert Burchell, Rutgers University

Development Economics

12

Page 13: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

area for a pedestrian (4sf)

area for a car (1400sf)

Land Consumption

13

Page 14: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

The Solution:

An Enterprise Approach to

Energy-Efficient

Development

14

Page 15: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

All services are now engaged in updating the UFC for master planning Embed key planning strategies DOD-wide Create a common approach to planning through all the services Adopt best business practices for sustainability and energy efficiency Draft Signed June 2012 (expected)

New Guidance

15

Page 16: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

Sustainable Planning

Natural and Cultural Resource

Management

Healthy Community Planning

Defensible Planning

Capacity Planning - Build more compactly

- Focus on infill development

- Use vertical and horizontal mixed use

- Plan for transit-oriented development

- Design with multi-story construction

- Support energy-efficiency with narrow

buildings

Area Development Planning

Network Planning

Form-Based Planning

Facility Standardization

Plan-Based Programming

Master Planning UFC: 10 Planning Strategies

16

Page 17: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

Consistent

Process

and

Products

17

Page 18: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

Establish 3 Tier suite of Master Planning Performance

Tier 1. Product Compliance. Ensuring planning products are

maintained.

Tier 2. Strategy Compliance. Ensuring that all planning and

development initiatives follow the 10 strategies.

Tier 3. Principle Compliance. Ensuring Planning Practices

are followed. (LEED-ND like criteria).

Master Planning Competency. Highly recommends

continuing education to maintain planning competencies.

Master Planning Performance Indicators

18

Page 19: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

19

All installations must have an approved master plan

Consistent Site Approval Process

Following traditional City planning practices

All development will comply with the master plan, to include planning

Code, and site criteria.

Includes all development.

Installation Planning Board

Oversees Master Planning Practices

Requires inter-governmental coordination

Master Planning Practices

Page 20: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

20

ARMY: AR 210-20, Real Property Master Planning is being

Updated to comply with UFC update; issue July 2012

AIR FORCE: Base Comprehensive Planning is also being updated

To comply with UFC update: target publication Summer 2012

Component Implementation

Page 21: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

PROPOSED policy updates require concepts of sustainability, Energy

Efficiency and Net Zero into planning practices.

Using the planning process, we have developed an integrated development strategy

for installations, using all resource streams

Natick Soldier System Center USACE-led master plan lays out development plan to

achieve goals for sustainability, energy and net-zero.

Ft Hood USACE-led master plan process focuses on energy-efficient master

planning – bringing sustainability concepts to Texas

Marine Corps Air Station Miramar incorporates enterprise approach to sustainable

and energy-efficient master planning

Master Planning Sustainability and Energy Factors class teaches planners how to

apply sustainability energy factors to planning, calculate savings, return of

investments using holistic solutions SRM, MILCON and other peoples money.

Integration: Sustainability, Energy and Net-Zero

21

Page 22: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

Energy – Sustainability - Collaboration

Fort Hood: Compact Development Energy Education Mr. Joe Calcara briefing class

participants (San Francisco, March 2012)

Mr. Allan Carroll working with class

participants (Vicenza, March 2012)

Page 23: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

100%

Projected energy requirement for

master plan

21,651,884kWh requirement

64.6%

Energy requirement after sustainable

planning efforts (35.4% reduction)

12,538,491kWh requirement

28.3%

Energy requirement after on-site

renewable energy generation (36.3%

reduction)

7,993,083kWh requirement

28.3%

64.6

%

100%

Energy and Sustainability: Natick

23

Page 24: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

Energy and Sustainability: Natick

Walkable

campus

development

reduces vehicle

miles and

supports district

energy solutions

New on-base

housing reduces

vehicle miles and

supports and

supports 24/7

district energy

solutions

Narrow wing infill

development supports

planned growth in

energy-efficient

buildings that may use

half the energy of

standard buildings.

24

Page 25: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

The Army’s Net Zero Initiative

APA April 2012

William D. Goran

U.S. Army Corps of Engineers

Engineer Research and Development Center

Construction Engineering Research Lab

P.O. Box 9005, Champaign IL 61826

Phone 217-373-6735

[email protected]

Slides from: Assistant Secretary of the

Army, Installations, Energy and Environment

US Army Corps of Engineers

BUILDING STRONG® 25

Page 26: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

26

Net Zero Hierarchy

A Net Zero ENERGY Installation is an

installation that produces as much energy

on site as it uses, over the course of a year.

A Net Zero WATER Installation limits the

consumption of freshwater resources and

returns water back to the same watershed

so not to deplete the groundwater and

surface water resources of that region in

quantity or quality.

A Net Zero WASTE Installation is an

installation that reduces, reuses, and

recovers waste streams, converting them to

resource values with zero solid waste to

landfill.

A Net ZERO INSTALLATION applies an

integrated approach to management of

energy, water, and waste to capture and

commercialize the resource value and/or

enhance the ecological productivity of land,

water, and air.

“The primary goal is a focus toward net zero and when

we talk about net zero, it's not only net zero energy, but

it's net zero energy, water, and waste. When you look at

the term "net zero" or a hierarchy of net zero you must

start with reduction, then progress through repurposing,

recycling, energy recovery, disposal being the last.“

— HON Katherine Hammack, DoD Bloggers

Roundtable, 10 October 2010

Page 27: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

27

Net Zero Pilot Installations

Page 28: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

Net Zero Energy

A Net Zero ENERGY Installation is

an installation that produces as much

energy on site as it uses, over the

course of a year.

28

Goals:

Contribute to the Army Campaign Plan’s objective of energy security for the Army

Address energy efficiency and conservation first

Preference for use of renewable energy for on-site power; enables operation if grid goes down

Must address redundant energy supply sources

Can the installation function for long periods of time during supply disruptions affecting the

electric grid, natural gas pipeline, propane & fuel oil deliveries, etc.

Applies to both electrical and thermal energy

Behavioral change are necessary to change culture

Must be fiscally responsible

APA April 2012

Page 29: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

Energy Roadmaps

Example Installation

Energy Profile Energy Baseline

Energy Efficiency

Assessments

Renewable Energy

Assessments

Energy Security

Assessments

Energy Project List and

Implementation

Recommendations

29

0

50,000

100,000

150,000

200,000

250,000

300,000

350,000

400,000

2011 2012 2013 2014 2015 2016 2017 2018 2019 2020

Sit

e B

tus

Year

Biomass

Wind

Geothermal

PV

Solar HotWater

Propane

ElectricalGrid

APA April 2012

Page 30: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

Net Zero Water Strategy

Goals:

Contribute to the Army Campaign Plan’s water security Major Objective

Reduce freshwater demand through water efficiency and conservation

Access/develop alternate water sources to offset freshwater demand

Develop water-efficient green infrastructure

Implement low-impact development to manage storm water

A Net Zero WATER Installation

limits the consumption of

freshwater resources & returns

water back to the same watershed

so not to deplete the groundwater

and surface water resources of

that region in quantity and quality

over the course of a year

30

Reduction

Re-Purpose

Recycling & Composting

Energy Recovery

Disposal

APA April 2012

Page 31: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

31

Water Supply

Water Use

Losses

Irrigation

Cooling/

Process

Indoor building

Alternate water

On-site ground

On-site surface water

Municipal

Water Balance =

comparison of water

supplied to water used.

Net Zero – Water Balance

0

0.05

0.1

0.15

0.2

0.25

Page 32: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

Waste avoidance via

procurement practices

& other pollution

prevention (P2) efforts

Waste that can’t be re-

used, recycled, or

composted is sent to a

WTE plant (on- or off-

post)

All recyclable or

compostable waste

collected & diverted (to

on- or off-post

facilities)

Installation re-use centers &

efforts to match waste

stream ‘products’ with

potential users (e.g., crushed

drywall used for soil

amendment; construction &

demolition (C&D) debris

reuse)

Waste-to-Energy ash (if

not further diverted) &

any limited special

wastes

Pilot Installations should have a comprehensive

program that starts at the top of the hierarchy

Net Zero Waste Strategy

32

APA April 2012

Page 33: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

Waste Roadmaps

Material flow analysis

Improved procurement

practices

Re-purpose / re-use

strategy

Recycling & composting

strategy

Potentially viable waste-

to-energy technologies

Example Installation

Waste Produced

Profile

To

ns o

f

Waste

Year

33 APA April 2012

Page 34: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

34

Leveraging Private Investments Potential Financing Mechanisms

Energy Savings Performance Contracts (ESPC)

Utilize private capital to make infrastructure improvements on military

installations

Payment is derived from the savings generated by the improvements –

Savings are verified through Measurement & Verification (M&V)

Utility Energy Service Contracts (UESC)

Procurement method using utility expertise & capital to meet Federal

conservation mandates

Utility’s costs repaid directly from installation’s avoided costs resulting from

project implementation

Enhanced Use Lease (EUL)

Funding method for construction on installations by allowing a private

developer to lease underutilized property

Payment usually in the form of power back to the installation

Power Purchase Agreement (PPA)

Allow federal agencies to fund on-site renewable energy projects with no

upfront capital costs incurred

Page 35: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

Master Planning Challenges

at a Net Zero Installation

Cyndi Skinner, AICP

Chief of Master Planning & Real Property

Directorate of Public Works

232 California Avenue

USAG Fort Hunter Liggett, CA 93930

[email protected]

Page 36: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

USAG Fort Hunter Liggett is an Army

Reserve installation in California’s Central

Coast region

36 APA April 2012

Page 37: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

14

Federal Installation Energy & Sustainability Mandates

Mandate Topic Energy & Sustainability Performance Target [Source]

Energy use in Federal buildings • Reduce 3% per year to total by 30% by 2015 (2003 baseline) [EO 13423, EISA 2007]

GHG emission reduction • Identify GHG emission reduction targets to be met by 2020 from 2008 baseline [EO 13514]

• Army target – 34% [SA Memo to OSD]

Energy metering for improved

energy management

• Meter electricity by Oct 2012 [EPACT 2005]

• Meter natural gas and steam by Oct 2016 [EISA 2007]

Electricity use for federal

government from renewable

sources

• At least 3% of total electricity consumption (FY07-09), 5% (Fy10-12), 7.5% (FY13 +) [EPACT

2005, NDAA 2007]

Total consumption from

renewable sources

• At least 50% of required annual renewable energy consumed from “new” renewable sources

[EO 13423]

• 25% by 2025 -”Sense of Congress” [ EISA 2007], NDAA 2007

Hot water in new / renovated

federal buildings from solar

power

• 30% by 2015 if life cycle cost-effective [EISA 2007]

Fossil fuel use in new /

renovated Federal buildings • Reduce 55% by 2010; 100% by 2030 [EISA 2007]

Net zero buildings

• All new buildings entering design in 2020 and after achieve net zero energy by 2030 [EO

13514]

• New federal buildings achieve net zero by 2030 [EISA 2007]

Fleet vehicle petroleum

consumption

• Reduce 20% by 2015 (Base 2005) [EISA 2007]

• Reduce by 2% per year thru FY2020 (Base 2005) [EO 13423, EO 13514]

Fleet vehicle alternative fuel use • Increase 10% by 2015 (Base 2005) [EISA 2007]

• Increase by 10% annually to reach 100% (Base 2005) [EO 13423]

Water consumption • Reduce consumption intensity by 2% annually FY 08-FY 15 (2007 baseline ) [EO 13423]

• Reduce consumption by 2% annually for 26% total by FY 2020 (2007 baseline ) [EO 13514]

Page 38: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

Key to meeting the challenge

‘Master Planning for Net Zero’

• Fort Hunter Liggett’s Commander is engaged

and highly supportive

• Constant collaboration between the energy

manager, environmental manager and the

master planner

• Partnership with your local energy provider

• Support from the Army

38

APA April 2012

Page 39: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

Net Zero Energy –

the approach

• Reduce consumption to the

minimum amount possible –

including changing behavior, retro-

fitting facilities

• Re-purpose facilities – take under

utilized facilities and repurpose them

into more efficient use

• Produce for remaining demand,

preferably utilizing renewable

energy; solar, ground source heat

pumps, geo-thermal, etc.

39

APA April 2012

Page 40: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

APA April 2012

Additional factors:

• Staffing is always a challenge

• Understanding the issues / metrics

• How to get federal mandates into a master plan

• “It wasn’t budgeted”

• Maximizing shrinking real estate

• It’s difficult...

40

Page 41: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

ACSIM policy: ...Create more compact urban

communities that still meet security and safety

factors. Planners will incorporate the following key

principles of sustainable planning in their Master

Plans, area development plans, and other

planning products:

• compact development

• infill development

• transit-oriented development

• horizontal and vertical mixed-uses

• connected transportation networks

• low impact development

• multi-story construction

• narrow buildings

Page 42: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

Blackhawk Hills Area Development Plan –

Barracks, Classroom and Admin Quads

FY14

TASS

FY13

ORTC

Future Admin

& Classroom

Quads

FY13

UPH

Future

ORTC

Future

ORTCs

Future

Barracks

In-fill

Future

Main Gate

Current HQ site

42

APA April 2012

Page 43: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

Blackhawk Hills Buildout Potential = 2.2M SF

Administrative:

444,000 sf minimum

888,000 sf maximum

Barracks:

180,500 sf minimum

361,000 sf maximum

Training/DES:

129,000 sf minimum

258,000 sf maximum

Maintenance:

41,250 sf minimum

82,500 sf maximum

ORTC:

209,000 sf each

627,000 sf total

Minimum: 1,421,750 sf

Maximum: 2,216,500 sf

Parking Required: 1,800 spaces

Parking Provided: 1,900 spaces

43

APA April 2012

Page 44: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

Future Classroom/Admin Quad - 7th ID @ Infantry Rd

91st

Reserve

Center

44

APA April 2012

Page 45: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

Mission Valley ADP Illustrative Plan

FY14

TASS (80th

Schoolhouse) FY13

ORTC

FY11 77,000 SF

ECS Maintenance

FY11 104,000 SF

ECS Warehouse

1MW Solar

arrays, 1 & 2

FY11 Wash Rack

24 bays,

tactical vehicles

Future

ORTC

Training facilities;

USARC funded

Future

ORTC

Future DOL Warehouse to

support garrison & training

Future Motor pool

expansion 20+ ac

45

APA April 2012

Page 46: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

Mission Valley Buildout Potential = 1.5M SF

Mission Support Space: (min building levels) 79,999sf removed

1,145,150sf added

1,065,151sf gained

Mission Support Space: (max building levels) 79,999sf removed

1,599,950sf added

1,519,951sf gained

Parking Car Parks:

863 spaces added

46

APA April 2012

Page 47: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

Mission Valley Training Support Area

Range

Ops

Future

ORTC

5 Units Training Warehouses and Classrooms

FY14

TASS

Future

ORTC

APA April 2012

Page 48: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

Hacienda Heights ADP Illustrative Plan

48

APA April 2012

Page 49: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

Fort Hunter Liggett UPH

Page 50: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

Baseline Data

• Current Electrical Load 12M KwH

• Future Electric Load (MILCON) 6M KwH

• Thermal Load (propane/diesel) 11M KwH

Total 29M KwH

“NZEI Roadmap”

• Energy Conservation Projects (28%) 8M KwH

• Human Factor” Conservation (10%) 3M KwH

• UNICOR renewable projects (24%) 7M KwH

• ECIP Renewable Projects (38%) 11M KwH

Total 29M KwH

Army NZEI Goal is 2020!

Fort Hunter Liggett

50

APA April 2012

Page 51: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

Project Title Energy Production % towards

NZEI

Energy Management

Control System

Reduces energy

use by 15%

15%

PH 3 1MW Solar PV Array

w/initial EMCS

1.8M KwH

produced

6.2%

Ph 4 1MW Solar PV Array

w/initial “smart grid”

1.8M KwH

produced

6.2%

Solar Hot Water

(Barracks/DFAC)

1M KwH

conserved

3.4%

Grid Energy Storage

(Battery)

1.5M KwH stored 5.2%

Ground Source Heat Pumps 3M KwH

conserved

10.3%

*46.3% towards NZEI Goal*

Renewable Energy Projects

Page 52: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer
Page 53: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer
Page 54: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

Net Zero Technology Initiatives

APA April 2012

Dr. Michael Case

Program Manager, Installations

U.S. Army Corps of Engineers

Engineer Research and Development

Center

Construction Engineering Research Lab

P.O. Box 9005, Champaign IL 61826

Phone 217-373-7259

[email protected]

US Army Corps of Engineers

BUILDING STRONG® 54

Page 55: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

55

NZI-E Planning Tool Objectives

• Provide Installation Planners and contractors a capability for integrated analysis and optimization so that they achieve Net Zero Energy status.

• Provide support for Installation Master Plans, Energy Plans, and prioritization for energy upgrades

• Support public/private partnerships by identifying sound projects appropriate for private financing.

• Establish framework for follow-on Water, Waste, and Greenhouse Gas modeling

Page 56: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

Typical Current Approach

• Expert Team

– Optimize Buildings

– Examine District

Heating/Cooling/CHP options

– Renewable Projects

• Recent/Ongoing Projects

– EISA 2007 study

– Fort Irwin

– Fort Carson

– Fort Bliss

– Fort Bragg

• Pros/Cons

– Pro – Draw on valuable experience

– Pro – Access to specialized

knowledge

– Con – expensive

– Con – takes time

– Con – limited resources

– Con – repetitive

261

Barracks

262

Barracks

263

Central

Heating

Plant

264

Barracks

267

Barracks

265

Barracks

271

DFAC

LP

GL

PG

LP

G

DH

W

DH

W

DH

W

DH

W

DH

W

D

H

W

South

Page 57: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

NZI Approach

• Best practices process

• Automated facility load

estimation

• Library of energy models

• Region/Facility type

Energy Efficiency

Measure (EEM) package

optimization

• District/Cluster equipment

package optimization

• Recommended phasing

of NZI projects

Page 58: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

• EW2

Plan

• Projects

Sequenc

e

Schedule

• Costs

• Risk

•DD1391

NZI Planning Cycle

1 Setup

Site

Data

2 Minimize

loads

3 Optimize

and integrate

across Installation

and region

4 Update plans

with Justification

& Documentation

• Building

• Geography

• Utilities

• Cost Data

• Water

• Waste

• Greenhouse Gas

Execute, Track,

Measure

Page 59: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

Cost-Optimizing Zero Energy Systems Integrating EEM’s that are Net Zero Ready

• Debate over whether to conserve energy or

generate it

• Need the lowest cost path

to a building configuration

which uses net-zero energy

• Point 4 is the Crossover

Point: where generating

renewable energy is more

cost-effective than

additional Energy Efficiency

Measures or Net-Zero

Ready. Point 4 is normally

at 60% to 80% savings

depending on building and

location

Page 60: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

Finding your baseline

• NZI Load Estimation

• Metered data best!

• Usually need to estimate using

models

• EnergyPlus, FEDS, DOE2/eQuest,

Water Balance, SWARS,etc.

• Make sure model handles

resolution required (e.g., 8760

hours)

Page 61: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

Inventory/Classify Building Types

Page 62: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

Run baseline to determine loads/flows

Page 63: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

Review/Calibrate Baseline

Page 64: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

Review Load Profiles

Page 65: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

Predictive Model

• Model Measures to

be applied

• Energy, Water,

Waste

• Best Practices,

Technology,

Behavior COF

TEMF

UEPH

Page 66: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

Review Measures to be Modeled

Page 67: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

Simulation Predicts Performance & Cost

Page 68: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

Compare Alternatives - Decision Criteria

Page 69: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

Supporting Graphics

Page 70: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

Supporting Data For Decision Criteria

Page 71: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

Installation Level Optimization

• Best Measures

• Sizes

• Operation Strategies

• Lowest Cost

• Models –

• NZI Optimization Tool, POLIS, REO, FEDS,

MODEST, MSW (Solid Waste), DSS

(Water)

Page 72: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

Electricity Generation & Use in USA

Buildings are ~71% of total

Largest Cause of Greenhouse Gas

Source: US DoE EIA 2008

Buildings

70.6%

Conversion

Losses = 63.4%

of Energy for

Electric Generation Trans & Dist Losses

= 7.4% Net Gen Elec

Page 73: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

Building Cluster Analysis

Barracks

Maintenance

Facility… Office

Buildings

… = …

Other

Facilities

?

74

Page 74: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

Building Cluster Fossil Fuel Optimization Process

Page 75: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

NZI Optimization Tool (NZI-Opt)

• Supply side equipment

• Lowest Life Cycle Cost

• To cluster or not to cluster

• Meet site constraints

Exploration

Space

(“Super-

Structure”)

Reporting &

Implementation

Plan

Plan

Architecture(s)

determined

• Heating • Cooling • Electic • Critical Electric • Water

• Potable

• Grey • Wastewater

• Solid Waste

• COGEN

• Biomass

• Solar PV

• Solar Thermal

• Wind

• Storage

• Fuel Cells, etc

Page 76: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

How it works

NZI-Opt begins with definitions for all possible equipment pieces that could serve the cluster demands. These definitions include region-independent parameters such as efficiency, energy inputs, and energy outputs. Some equipment examples are shown below.

Electric Chiller

Organic Rankine Cycle

Gas Boiler

AC Bus

Fuel Cell

Gas Turbine

Absorption Chiller

Diesel Generator

Wind Turbine

Photovoltaic

Electric Heater

Page 77: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

Selecting a Supply Architecture

The optimization process determines the best suite of equipment by

ensuring that the demands for heat, cooling, electric, etc are

fulfilled at each of the 8760 hours in the year, while satisfying the

additional environmental and legislative requirements.

Page 78: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

Sizing the Supply Equipment

Specific equipment pieces are sized and their interactions with each other

are tracked throughout the year. The result is a complete “supply” solution

that provides the sizing, initial cost, and operating cost of every piece of

equipment in the lowest cost solution.

Cooling

Load

Heat

Load

Critical

Load

Electrical

Load

HX

Electric

Grid

Boiler

Gas Turbine

Diesel Generator

Adsorb.

Chiller Org. Rankine Cycle Elec. Chiller

Wind Turbine Microgrid

AC Bus

AC Grid Bus

Key

Heat

Cooling

Electric

Waste Heat

Nat/Bio Gas

Diesel

31.2

MW

40.6

MW

0.9

MW

56.0

MW

12.0

MW

32.5

MW

3.2

MW

48.0

MW

72.0

MW

51.8

MW

Page 79: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

Orderly Approach

Once the equipment suite and sizing has been determined a post-

process optimization can be run to determine the implementation

schedule for the equipment. This process is meant to account for

annual budget, progressive legislative requirements, and aging

current equipment.

Plan

Page 80: PLANNING CHALLENGES FOR NET ZERO INSTALLATIONSmedia2.planning.org/APA2012/Presentations/S625_Planning... · 2012. 5. 3. · William D. Goran U.S. Army Corps of Engineers Engineer

Reporting

Plan