PAPER_PINTO_INES_H00227102
-
Upload
ines-pinto -
Category
Documents
-
view
106 -
download
0
Transcript of PAPER_PINTO_INES_H00227102
Dual Gradient Drilling Inês Sofia C.V. Pinto, ISPG
March, 2016
Copyright 2016 Society of Petroleum Engineers This paper was prepared in the context of the Individual Project
ABSTRACT
Nowadays, most of the accessible reservoirs are depleted, becoming necessary to find a way to recover the
remaining hydrocarbons reserves. Also, challenging reservoirs that cannot be accessed by using conventional
methods can become producible if other techniques are applied. Managed Pressure Drilling (MPD) can be one
of the solutions.
By using this method, the control of the Bottom Hole Pressure (BHP) is improved, which is crucial in fields with
a narrow drilling window. Thus, problems related with well control are mitigated, reducing the Non-Productive
Time (NPT) and increasing safety.
In this project four variations of MPD are analysed and it is given more emphasis to the DGD technique which is
the main subject of this project. This method refers to offshore drilling operations where the drilling fluid
returns are not done by using the riser. It is applied when a single fluid causes the wellbore pressure to exceed
the formation pressure, resulting in loss of circulation.
One of the main benefits of DGD is the reduction in the number of casing strings which implies a saving in both
material cost and rig time. Moreover, this allows to have higher production tubing diameters.
Regarding the application of DGD methods, two case studies, not related to each other, are analysed. Although,
both cases compare the conventional drilling with DGD, the final objectives are different. No real data about
deep offshore were provided or possible to obtain. Hence, values were assumed to perform these studies.
INTRODUCTION
World energy demand is continuously increasing. However, nowadays, most of the accessible reservoirs are
depleted. For that reason, there is a necessity of improvement in the technology to recover the remaining
hydrocarbons reserves and to explore new and challenging reservoirs. Consequently, it is crucial to find a way
of exploring reservoirs that would not be economically feasible by using conventional drilling methods:
Managed Pressure Drilling (MPD) can be one of the solutions to overcome this problem.
Conventional drilling methods, namely Overbalanced Drilling (OBD) and Underbalanced Drilling (UBD) are
predominantly concerned with the formation fluid influx and well control during the drilling operation.
Therefore, a drilling window between pore pressure and fracture pressure must be defined. A safety margin
and overbalance (static or dynamic) must be considered as well. If the mud gradient used is less than the pore
pressure gradient then an influx of formation fluids can occur leading to a kick and, in the worst case scenario,
a blowout. On the other hand, if the fracture pressure is exceeded, formation fracture may occur leading to
drilling fluid losses and, in the worst case scenario, loss of well control.
When planning a drilling program, it is important to keep in mind that the Bottom Hole Pressure (BHP)
difference increases with the depth. For example, comparing the BHP by using two mud densities, 8 ppg and
9.5 ppg, it is noticeable that the overbalance increases with depth, Figure 1. Moreover, the higher the mud
density is, more significant will be the difference in BHP.
In the example below, the difference of BHP values is about 1400 psi at 18,000 ft. This is very important when
planning the mud program to ensure that the fracture pressure is not exceeded.
2 Inês Sofia C. V. Pinto SPE
Figure 1 - Comparison of BHP by using different mud densities.
The OBD method has been the method of choice for the majority of wells drilled since the early 20th
century
(Elliot, et al., 2008) and it uses a mud gradient higher than the pore pressure gradient but lower than the
formation fracture pressure gradient. This means that when drilling fluid is circulated down the drillstring and
up the annulus, the Equivalent Circulating Density (ECD) is greater than the pore pressure but smaller than the
formation fracture pressure. On the other hand, the UBD method is focused on preventing drilling fluid loss
into the formation. Thus, the hydrostatic head of the drilling fluid is intentionally designed to be lower than the
pore pressure of the formations that are being drilled. The hydrostatic head of the fluid may naturally be less
than the formation pressure or it can be induced by adding different substances to the liquid phase of the
drilling fluid, such as natural gas, nitrogen or air.
The ECD can be interpreted as the density of a fluid, which in static conditions and at a depth of interest
produces the same pressure as a given drilling fluid in dynamic conditions (Kartevoll, 2009).
ECD management is critical to control the well. This is particularly important when drilling through zones with a
narrow Pore Pressure (PP) / Fracture Gradient (FG) window. ECD can be calculated using the following
equation:
ECD = MW + Pd / (0.052 TVD)
Where MW is the mud gradient [ppg], Pd is the annulus frictional pressure drop at a given circulation rate [psi],
TVD is true vertical depth [ft] and 0.052 is a unit conversion factor (Drilling Engineering, HWU, 2014).
Although being the most applied techniques, conventional drilling methods have some drawbacks. In OBD the
most relevant of them is its dependence of multiple casing strings to prevent fluid losses into the formation. In
deep offshore wells, the drilling window can be so small that becomes mandatory to set a big number of casing
strings even before reaching the target formation. As a result, a well with a too small diameter to
accommodate the necessary production tubing can be obtained, invalidating the economic feasibility of the
well (Elliot, et al, 2008). In UBD method, where ECD is maintained below the pore pressure, fluids from exposed
formations are allowed to flow into the wellbore and in the worst case scenario a kick can occurs. Besides,
when drilling long reach wells, pressure associated challenges are encountered, such as wellbore instability and
well control problems.
In order to overcome all of these problems and challenges, MPD was developed. This technique is primarily
used to drill wells that should not be drilled by using conventional techniques, either OBD or UBD, such as in
rigs where it is not possible to use flaring, or while drilling through high-permeability formations.
However, in wells with sufficiently large drilling pressure windows, pressure losses can be controlled by
changing drilling fluid’s properties and their flow rates and rates of penetration (Elliot, et al, 2008).
Figure 2 shows the behaviour of the MPD technique, comparing with OBD and UBD methods.
(1)
3 Inês Sofia C. V. Pinto SPE
Figure 2 - Comparison of OBD, UBD and MPD behavior. Adapted from ADS.
In OBD method, the resultant BHP is above the pore pressure and below the formation fracture pressure,
whilst in UBD method, it is used an ECD below the pore pressure but greater than pressure required to
maintain wellbore stability. The MPD method uses a combination of mud gradient, back pressure and dynamic
circulating pressures to dynamically maintain the bottom hole pressure inside the drilling window. By using this
technology, it is possible to have a precise control of the BHP, keeping it within the drilling pressure window
(Elliot, et al, 2008). In this way, projects that were not possible to develop employing conventional methods,
can be drilled with MPD.
MANAGED PRESSURE DRILLING
MPD uses a combination of techniques to mitigate the risks and costs associated with drilling operation by
managing the open hole pressure profile whilst drilling. These techniques include controlling backpressure,
fluid density, fluid rheology, annular fluid level, circulating friction and hole geometry in any combination
(Hannegan, 2005) to maintain a bottomhole pressure above pore pressure but below fracture pressure.
According to IADC, MPD is an adaptive drilling process to increase the control of the annular pressure profile
throughout the wellbore and if it used as a primarily means of operation, it represents a proactive approach to
the drilling operation.
When using this technique, a mud gradient less than that of pore pressure gradient is used and the additional
pressure to maintain overbalance is provided from the dynamic annular pressure loss (when circulating). A
backpressure is created by closing a surface choke.
As is it possible to observe in Figure 3, the use of backpressure reduces the difference between hydrostatic
pressure and formation fracture pressure, without increasing the mud gradient.
Figure 3 - Pressure vs. Depth graph, highlighting the backpressure. Adapted from Elliot, et al, 2008.
Analysing this graph it is possible to see the difference between hydrostatic pressure and formation fracture
pressure without applying backpressure (interval 1) and applying backpressure (interval 2).
4 Inês Sofia C. V. Pinto SPE
With the rig pumps on, the pressure equation in a closed circulation system is:
BHPDynamic = ΔPStatic + PAFP + PBP(Dynamic)
Where ΔPStatic is the drilling fluid hydrostatic pressure, PAFP is the annulus frictional pressure (AFP) created by
the circulating drilling fluid and PBP is the surface backpressure applied to the annulus by pressure control
equipment connected to the wellhead (Rehm, et al, 2008).
In a closed system, the backpressure term, PBP, is always present during a connection and sometimes, while
drilling. Equation 2 is applied when mud is circulating. Under static conditions, when the rig pumps are off,
PAFP = 0 and this equation becomes:
BHPStatic = ΔPStatic + PBP(Static)
With the purpose of adjusting the annular pressure profile between the pore pressure and the formation
fracture pressure, it is possible to use a mud gradient statically underbalanced. It can be brought back in
balance by applying a surface backpressure, that would then be reduced slightly once circulation begins. While
in conventional drilling the static and dynamic pressures are always different, in MPD techniques, they can be
equal.
In accordance with the MPD subcommittee of IADC, MPD can be separated into two categories: reactive and
proactive. MPD is reactive when the well is firstly designed for conventional drilling, but the equipment is
rigged up to quickly react to unexpected pressure changes. It is an enhanced form of passive well control to
help manage unexpected downhole pressure. Proactive MPD is used to mitigate drilling hazards and to reduce
Non-Productive Time (NPT) such as drilling fluid changes, casing and open hole programs. In this case the
equipment is rigged up to actively alter the annular pressure profile (Rohani, 2011).
MANAGED PRESSURE DRILLING TECHNIQUES
As reported by Arnone (Arnone & Vieira, 2009), there are four recognized variations of MPD:
Constant Bottomhole Pressure (CBHP);
Mud Cap Drilling (MCD);
Return Flow Control Drilling (RFC) or HSE Method;
Dual Gradient Drilling (DGD).
It is possible to combine several variations on the same prospect and it is expected that these combinations
become more frequent in prospects where drilling operations become more difficult to perform (Aadnoy, et al,
2009).
OPERATIONAL CONSIDERATIONS
Before choosing what type of drilling method will be applied, an accurate planning program must be
performed. In the case of MPD being the best technical and economic choice it is necessary to select which
method is the most appropriate for each case. As reported by Nauduri (Nauduri, et al.,2010), even with all the
advances in science and technology as well as the huge availability of equipment and expertise, the industry
still needs a Candidate Identification Mechanism (CIM)/Candidate Selection Model (CSM) exclusively developed
for MPD and its applications, considering the technical and economic aspects of a given project. Therefore, a
MPD CIM created by petroleum industry and the Petroleum Engineering Research Program at Texas A&M
University (TAMU) was described by Nauduri (Nauduri, et al.,2010). It provides a tool that takes into account
the available engineering data and determines if MPD is the best solution for a given project. Besides being an
important and interesting topic, it is not in the scope of this work and it will not be developed.
Similarly to all drilling operation methods, MPD also carries a set of risks. Due to its complexity, a detailed
planning containing the description of all risks at each stage of the MPD operation, plans to mitigate those risks
and contingency action plans, usually starts earlier when comparing with conventional drilling. This planning
should include a review of a number of parameters that will be mentioned below (Rehm, et al, 2008).
(2)
(3)
5 Inês Sofia C. V. Pinto SPE
DUAL GRADIENT DRILLING
Drilling in deep water is a challenging operation and one of the principal issues regarding this procedure is the
typical low fracture gradients and shallow abnormal pressure. It is quite common to find margins between the
fracture gradient and the required mud that are inferior to 1 ppg (Advanced Drilling Techniques, 2006). DGD
method is used when a single fluid causes the wellbore pressure to exceed the formation pressure, resulting in
loss of circulation (Rohani, 2011).
DGD refers to offshore drilling operations where the drilling fluid returns are not done by using the riser. These
returns can be dumped at the seafloor (pump and dump), which is not permitted in all jurisdictions and it is
only advisable for top sections, or returned to the rig through return lines (riserless muds return) (Rehm, et al,
2008).
As its name suggests, Dual Gradient Drilling (DGD), uses a combination of two mud gradients, i.e., the
hydrostatic gradient in the wellbore is composed by two different parts. In the upper portion of the wellbore,
above the fluid interface, a lighter fluid that can be a liquid or a gas fills the annulus from the Rotary Kelly
Bushing (RKB) down to the fluid interface depth. This fluid interface can be placed at the seafloor or above it.
At the lower part, a heavier mud that always lies between pore pressure and fracture pressure is used, Figure
4. By using fluids with different densities it is possible to manage the BHP to obtain a pressure profile that
better fits the drilling window (Sui & Nygaard, 2015).
Figure 4 - Principle of Dual Gradient Drilling. Adapted from Advanced Drilling Techniques, 2006.
In the conventional drilling method, the gradient in the wellbore is always relative to the rig, i.e., the mud
column is hydraulically continuous from the bottomhole to the surface, which corresponds to the blue line in
the figure above.
In DGD method, it is possible to control the BHP in static and dynamic ways, decreasing it, shown by the red
line. On the upper portion of the well, the seafloor pump reduces the imposed pressure, while the higher
density mud below the seafloor achieves the necessary bottomhole pressure (BHPDGD) to control the formation
pore pressure (Rehm, et al, 2008). The pressures can be underbalanced inside the cased hole or riser but in the
open hole, it must always use an overbalanced drilling. This underbalance is possible to achieve by reducing the
mud gradient used in the upper section to a value inferior to the seawater density or adjusting the cut point to
a point below the seafloor (Advanced Drilling Techniques, 2006).
DGD APPROACHES AND SYSTEMS
There are different DGD methods available although their main operating principles are similar. DGD can be
applied to drill top-hole sections before setting the BOP or after BOP installation. Post-BOP techniques can be
performed by pumping drilling fluid back to surface through subsea pumps. The pumps can be located at
seabed (seabed pumping) or suspended above it (mid-riser pumping). Another technique consists in diluting
returns by injecting a lighter fluid usually just above the BOP stack.
6 Inês Sofia C. V. Pinto SPE
In the diagram present in Figure 5, the active DGD systems are presented, in accordance with Cohen (Cohen, et
al., 2011).
Figure 5 - IADC DGD Approaches and Systems. Adapted from Cohen, et al., 2011.
ADVANTAGES OF DGD
By obtaining a pressure profile that better fits the drilling window, Dual Gradient Drilling method presents a set
of benefits. The most relevant of them are explained below.
Reduction of casing strings From an economical perspective, this is one of the main benefits of DGD. A reduction of casing strings implies a
saving in both material cost and rig time. Primary cement capabilities are also improved (Advanced Drilling
Techniques, 2006).
A DGD approach resides in the effective mud gradient at the previous casing shoe being inferior to the effective
mud gradient at the drilling depth. If the casings setting depths are not limited by the mud gradient of the
previous casing shoe, it is possible to eliminate casing points and therefore to reduce casing strings, allowing to
have higher production tubing diameters (Advanced Drilling Techniques, 2006).
By obtaining a pressure profile that fits better inside the drilling window it is possible to reach higher depths
before setting the casing, Figure 6. This is critical, not only from a time and cost perspectives, but also because
it allows using larger production casing and tubing.
Figure 6 - Goal of DGD method. Adapted from Advanced Drilling Techniques, 2006.
By eliminating casing points, the hole size at the end of the section increases which can be crucial in deeper
wells. The production casing must be large enough to run subsea safety valves in the annulus between the
production casing and production tubing. This last must have a sufficient diameter to achieve or even increase
the planned hydrocarbons production, which will increase the early income and hence the profit. Another
important aspect of the increased wellbore diameter is that in some situations it is possible to convert an
exploration well into a production well. By converting exploration wells a high value can be added to a project.
7 Inês Sofia C. V. Pinto SPE
This alteration is a very important subject for oil companies mainly in deep and ultra-deep offshore, where the
well cost is extremely high.
Lower deck space and loads are needed
There is also a major problem associated with conventional riser systems in deep water. The deeper the water
is, more marine riser joints are needed to be loaded onto the vessel, resulting in a reduction of deck space as
well as bigger concerns about loading capacity limitations. Besides that, to fill up these risers, a huge quantity
of drilling fluid is necessary. For example, to fill 10,000 ft of 19 ½’’ I.D. riser, about 3700 bbl of mud is required.
This is not only highly costly but the volume of mud can be excessive for the storage capacity of the rig (Rehm,
B. et al, 2008).
Easier to manage pressure control
When using conventional drilling, the hydrostatic pressure at the bottomhole can only be safely modified by
changing the mud density. To achieve this, it is necessary to circulate out all the mud volume that is in the
annulus and prepare a new mud. When drilling a well at 16,500 ft this operation takes a minimum of 3 hours.
Mud density increasing is a common procedure in conventional drilling to adjust the changes in formation
pressure. By using DGD, the BHP can be modified by varying the fluid interface depth. Thus, it is faster to
change the BHP allowing a more accurate pressure control, since the fluid interface in the riser can be
continuously adjusted making it possible to eliminate the friction pressure loss. Consequently, it is possible to
keep the BHP constant which make it easier to drill in a narrow mud window (Gaup T., 2012).
Improved kick and loss detection
The fluid level in the riser is continuously monitored. Unexpected modifications in the fluid interface depth and
the consequent changing in subsea pump rates gives indication of drilling fluid losses or influx of formation
fluids. Thus, by using DGD, it is faster to detect these problems allowing to take safety measures quickly.
ROP increasing
DGD can compensate the friction pressure by reducing the mud density level inside the riser. By maintaining
the BHP constant, the ECD can be kept below fracture pressure. Therefore, the ROP can be increased, reducing
the drilling time and therefore the costs.
CHALLENGES OF DGD
In compliance with Gaup (Gaup, 2012) and Saptharishi (Saptharishi & Deendayal, 2012), some of the limitations
of DGD includes:
Equipment
New equipment and technology might need to be developed before fully taking advantage of the DGD system.
Most of equipment applied in this method is placed in the subsea, making it more complicated to repair or
even to do the maintenance. A set of control lines are used to control the subsea equipment and they can
become tangled due to sea currents. This can create problems affecting the equipment functionality (Gaup T.,
2012).
Risk of Riser Collapse
When using nitrogen to decrease the mud density above the fluid interface, it is necessary to determine the
collapse loads of the riser. The outside hydrostatic pressure created by the seawater must not exceed the
collapse resistance of the riser considering that it is full of gas (Gaup T., 2012).
Conservative Industry
The oil and gas industry, and particularly the drilling industry, is often considered to be conservative. Although
new ideas arise frequently, it is difficult to implement new technologies in this well stablished market. Safety
and productivity are the most important factors in this industry and usually the risk of applying new
technologies is too high to compensate for the possible profit (Gaup, T., 2012).
8 Inês Sofia C. V. Pinto SPE
In agreement with Gaup (Gaup, 2012), despite of its higher CAPEX requirements when comparing to
conventional drilling more companies are starting to use this method. Following this trend, more equipment is
expected to be ordered, making production costs decline for higher produced hydrocarbons volumes. This can
motivate other companies to start using the DGD method. In addition, some tax systems give incentives for
CAPEX expenditure which can act as a motivation factor as well.
As stated by Redden (Redden, 2010), one reason that explains why DGD technology has not been applied as a
common practice in the early 2000s was the contracts period. At that time, rig contracts had a time span of 12
to 18 months which allowed to drill two or three wells, taking into account the slower daily rates employed at
that time comparing to what is common practice today. Nowadays, rig contracts have a longer duration, 4 to 5
years, allowing a higher investment in technology and making DGD more attractive. Obviously, the current
uncertainty in oil price contributes for the delayed implementation of this technology.
Well Control Procedures for Dual-Gradient Drilling
As reported by Rehm (Rehm. et al, 2008), the industry has expressed concern about DGD well control due to its
complexity, stating that it will be more difficult to implement and therefore is less safe than conventional deep
water well control. However, as stated by Rehm (Rehm. et al, 2008), this is not true. They claim that it is
different but with the controls installed into the DGD equipment, the well control is improved in several ways.
In DGD well control all the primary kick indicators of conventional drilling such as the increasing of flow rate
and pit volume, flowing well with pumps shut off and improper hole fill up during trips are applicable.
However, some of them are enhanced. For example, the seafloor pump is used as a positive displacement
meter and is much more accurate than a “Flo-Show”. When a kick occurs, the seafloor pump rate increases to
keep a constant inlet pressure. The increasing of frictional pressure in the return line is detected by the seafloor
pump outlet pressure gauge. If the pump is set to operate at a constant rate, the inlet pressure will increase
when a kick occurs (Rehm, B. et al, 2008).
Another advantage in DGD well control is the relatively small volume in the return line compared to the marine
riser. As the quantity of mud to be displaced is inferior, the bottoms up time decreases making the cuttings and
gas come up faster and pore pressure indicators are detected earlier (Rehm, B. et al, 2008). In the same
manner than conventional drilling methods, these are kick indicators and to verify that a kick is actually
occurring, a flow check must be performed.
CASE STUDIES
Two case studies, not related to each other, are presented. Both compare the conventional drilling method
with DGD technique but with different objectives. The first case demonstrates how much the maximum
horizontal drilling length can be increased when applying DGD. The second case shows the possibility of casing
strings reduction comparing to conventional drilling.
Case Study 1 – Increasing of Horizontal Drilling Length
The aim of this practical case is to determine the difference of the maximum horizontal length that a well with
the same characteristics and layout can reach by using conventional drilling method and DGD technique with
gas injection.
For the sake of clarity, the well was considered to be vertical until reach 10,000 ft and horizontal from this
point on, not considering the Kick-Off Point (KOP) and the Buildup Rate (BUR). Nevertheless, in the schematic
illustration of this case study a demonstrative curvature is represented.
Data description
Although no data was provided, it was possible to obtain values to perform this case study. Despite not being
able to release the information source, this data represents a typical real situation. In the table below are
shown all the values assumed during this exercise.
9 Inês Sofia C. V. Pinto SPE
Table 1 - Data summary.
Depth of seafloor 3,500 ft
Planned depth of the horizontal section of the well 10,000 ft
Mud density 9.5 ppg
Pore pressure gradient 0.48 psi/ft
Fracture pressure gradient 0.52 psi/ft
Friction pipe loss 0.089 psi/ft
Friction annular loss 0.024 psi/ft
Pressure at seafloor after gas injection 1,300 psi
Data limitation
Since no values regarding the economical perspective were possible to obtain, the discussion and economic
impact evaluation cannot be performed from a quantitative point of view. However, it is important to mention
that this would be a very interesting analysis that could be done as future work.
Data limitation Since no values regarding the economical perspective were possible to obtain, the discussion and economic
impact evaluation cannot be performed from a quantitative point of view. However, it is important to mention
that this would be a very interesting analysis that could be done as future work.
Methods
Before calculate the maximum horizontal distances for both cases, a table of pressures determination is
presented below, considering the following expression:
Hydrostatic Pressure = ρ x Constant x Depth
To determine the maximum horizontal distance that is possible to reach when applying the DGD technique, it is
assumed that gas is injected at the seafloor and the pressure above the fluid interface drops to 1,300 psi.
Results
Determination of the maximum horizontal distance by using conventional drilling
Knowing that the hydrostatic pressure at bottomhole is 4,940 psi and the frictional annular loss is 240 psi, the
total pressure at bottomhole is calculated at 5,180 psi.
Thus, the difference between the fracture pressure and the bottomhole pressure is 20 psi.
Assuming that the friction annular loss is constant (0.024 psi/ft), it is possible to obtain the horizontal distance
that can be drilled until reach the fracture pressure. By applying a simple relation, a distance of 833 ft is
obtained.
Determination of the maximum horizontal distance by using DGD
Assuming that gas is being injected at the seafloor and the hydrostatic pressure ate seabed after the gas
injection drops from 1,729 psi to 1,300 psi, how far is it possible to drill horizontally?
In order to reply to this question, it is necessary to calculate the frictional annular loss between the drill bit and
the seafloor formations:
Hydrostatic pressure between the TD TVD and the seafloor + ΔPannulus + Pgas = FP ↔
↔ 9.5 x 0.052 x (10,000 – 3,500) + ΔPannulus + 1,300= 5,200 ↔
↔ ΔPannulus = 689 psi
Assuming that the friction annular loss is constant (0.024 psi/ft) and applying the same relation as before it is
possible to determine the total length that is possible to drill: 28,708 ft.
To determine the maximum horizontal distance, it is necessary to subtract the vertical length between the TD
TVD and the seafloor (6,500 ft), and therefore, it is possible to drill 22,208 ft.
Figure 7 shows a comparison of the maximum horizontal length drilled by using conventional drilling (orange)
and DGD – gas injection (green).
(4)
(5)
10 Inês Sofia C. V. Pinto SPE
Figure 7 - Schematic representation of the well trajectory and maximum horizontal length drilled by Conventional Methods and DGD – gas injection.
Discussion and Economic Impact
By changing the drilling method from conventional to DGD it is possible to increase the maximum horizontal
length from 833ft to 22,208ft. This has a huge impact in extended reach wells. Since it is possible to drill longer
wells, the necessity of drilling more wells reduces or even disappear. Besides the cost of a single well increases
due to its extension, the total cost of the prospect development and production decreases considerably.
Case Study 2 – Reduction of Casing Strings
This study has the objective of investigating the effect of DGD on the operational costs. According to this
purpose, a well casing program is planned by using conventional drilling. The results are then compared with
the casing program of a well located exactly at the same position, simulated by using DGD method.
Data description
As mention before, in the scope of this work, no real data about deep offshore was provided. Thus, all the
values used in this case study are hypothetical. PP and FG curves had to be manually built point by point to
define the drilling window, Figure 8. The curves behaviour is based on the practical case presented in Peker,
2012. However, the reasoning is valid for any set of real data.
Figure 8 - Drilling window definition.
Data limitation Since there is not actual data it is not possible to make an exhaustive comparison between conventional drilling
and DGD technique, essentially in the economic point of view.
Methods
To compare the number of casing strings applied in both drilling techniques, a water depth of 6,200 ft is
assumed. It is considered that the Top Of Reservoir (TOR) is located at 12,100 ft and the Oil Water Contact
(OWC) at 15,000 ft.
Also, mud densities used to drill each hole section are defined, except for conductor casing that is driven. Since
the drilling window is very narrow near the seafloor a mud of 8.8 ppg is defined to drill the first section. In the
next sections, the mud density is increased ensuring that fracture pressure is not exceeded.
To determine the number of casing strings a straight line corresponding to a determined mud gradient is drawn
from the surface until it intercepts the fracture pressure gradient line. At this point, a casing shoe is set. This
procedure is repeated with higher mud densities until reach the TD TVD.
11 Inês Sofia C. V. Pinto SPE
The criteria to define these values were:
6,200 ft water depth: it is generally accepted that DGD is applicable in water depths greater than 5,000 ft;
Mud density: use a mud density which allows to run a casing string as longer as possible, ensuring an
overbalance of 200 psi and not exceeding the fracture pressure according with what was already discussed
regarding drilling window limits.
Results
Conventional Drilling
By applying these methods, in conventional drilling, the well would have 8 casing strings, Figure 9.
Figure 9 - Casing setting depths using Conventional Drilling.
Table 2 presents the casing program and the mud density used to drill each hole section.
Table 2 - Casing Program for Conventional Drilling.
Bit size [in] Casing O.D. [in] Casing Section Casing Type Shoe Depth [ft] Mud Density [ppg]
Driven 36 Conductor Casing 6,300 Sea water ≈ 8.7 ppg
30 24 Surface Casing 6,888 8.8
22 20 Intermediate Casing 7,216 9.0
17 1/2 16 Intermediate Casing 7,872 9.2
14 3/4 13 3/8 Intermediate Casing 8,528 9.5
12 1/4 10 3/4 Intermediate Liner 9,512 10.5
9 1/2 7 5/8 Intermediate Liner 10,824 11.8
6 1/2 5 1/2 Production Liner 14,432 12.5
DGD method
In order to design the casing program applying DGD method, it was used seawater as drilling fluid to drill the
upper portion of the wellbore. Regarding the lower part, it was assumed the same criteria used in conventional
drilling. As shown in Figure 10, in this case the lines corresponding to mud gradients are designed from the
seabed until the TD TVD.
Figure 10 - Casing setting depths using DGD.
12 Inês Sofia C. V. Pinto SPE
Table 3 presents the casing program and the mud density used to drill each hole section.
Table 3 - Casing Program for DGD.
Bit size [in]
Casing O.D. [in]
Casing Section Casing Type Shoe Depth
[ft] Mud Density
[ppg]
Driven 30 Conductor Casing 6,300 Sea water ≈ 8.7 ppg
26 20 Surface Casing 7,225 8.8
17 1/2 14 Intermediate Casing 8,528 10.2
12 1/4 9 7/8 Intermediate Liner 9,512 12.7
8 1/2 7 Production Liner 13,120 14.3
Discussion and Economic Impact
By comparing Figures 9 and 10, it is evident the reduction of casing strings in DGD method. While in the first
case, 8 casing strings are necessary to ensure the well stability, in the second approach, only 5 casing strings
are required. Moreover, the Outside Diameter (O.D.) of the conductor casing is larger in conventional drilling
(36´´) which implies a higher cost. Besides that, the final diameter is larger in DGD method. In conventional
drilling, the final O.D. is 5 1/2 ´´, while in DGD method is 7´´. Assuming the same casing grade for both cases, 26
lb/ft, the Inside Diameter (I.D.) is respectively 4.548´´ and 6.276´´. This represents a huge difference when
choosing the production tubing size. The economic feasibility of the well can be affected, if the diameter of the
production tubing is too small.
Therefore, by applying DGD method it is expected a cost saving not only because less material is needed but
also due to drilling time decreasing. As stated in Advanced Drilling Techniques, 2006, DGD has the potential to
reduce costs over 50% and for each casing point that is eliminated, 4 to 6 days of rig are saved plus the cost of
hole evaluation, casing and logging. Considering that a day work has a cost of $18,500 (PSAC, 2015), by applying
DGD method it is possible to have a reduction up to $330,000 (37.5%) just taking into account the daily rig cost.
RISKS AND MITIGATIONS
The drilling operation involves a higher cost and a significant percentage is attributed to losses of drilling
equipment and drilling fluids. Despite being unlikely to perform a drilling operation without finding any
problem, by managing drilling risks it is possible to identify and control incidents that may arise. The risk index
is given by the multiplication of the impact by the likelihood as it is shown in table below.
Table 4 - Risk Index. Adapted from personal notes.
During the field development planning phase, all risks and hazards should be addressed. Risks must be
identified and the appropriate mitigation measures need to be in place.
Also, compliance to all company and regulatory HSE should be ensured. Preferably, the selected systems
should be passive, low maintenance and inherently safe as far as practicable (Chaudhury and Whooley, 2014).
CONCLUSIONS
The DGD is an unconventional drilling technique which allows to control the BHP in static and dynamic ways.
The hydrostatic gradient in the wellbore is composed by two different parts: in the upper section a lighter fluid
fills the annulus from the RKB down to the fluid interface depth and at the lower part a heavier mud is used. By
applying fluids with different densities it is possible to manage the BHP obtaining a pressure profile that better
fits the drilling window.
13 Inês Sofia C. V. Pinto SPE
Regarding the economic aspect, despite this method requires a higher CAPEX, if applied in the right situations it
can bring significant cost savings. This economic success is achieved not only due to time-dependent causes but
also by other factors such as casing strings reduction, drilling fluid savings and enhanced HSE.
Concerning the application of DGD methods, although no real data are applied, the benefits of using DGD
technique in wells with a considerable water column are noticeable. In case study 1, the increasing of the
maximum horizontal distance is very significant. While using conventional drilling it is only possible to drill 833
ft, by applying DGD with gas injection this length increases to 22,208 ft. Regarding the case study 2, where the
objective is the number of casing strings reduction by the of application of DGD method, it is possible to
eliminate 3 casing strings with the benefit of increasing the final diameter. Even though, this study is based in
hypothetic values, it is important to mention that in case of analysing real data, a Leak Off Test (LOT) must be
conducted below each casing shoe to determine the fracture pressure of the formation.
SUGGESTIONS FOR FURTHER WORK
DGD techniques are still being developed and it is becoming increasingly important for the future of drilling
engineering. It is of the utmost importance to optimise its application and for this reason as future work, it is
proposed to perform a detailed study of the operation timeline when applying DGD, considering all the
procedures and equipment involved and the necessary hardware.
It is suggested to analyse a set of wells drilled with DGD technique and create a database to define a model to
be used in the industry. This will allow the optimisation of drilling operations as well as the possibility of
integration of this technology with other techniques. This could be performed in the context of a PhD program.
ACKNOWLEDGMENTS
This project was developed in the context of the Master of Science in Petroleum Engineering from Heriot-Watt
University, provided by ISPG and Galp. The author would like to express her acknowledgement to Galp all the
staff involved, for the opportunity to take part on this Master’s Program.
NOMENCLATURE
BHP Bottom Hole Pressure
BUR Buildup Rate
CAPEX Capital Expenditure
CBHP Constant Bottom Hole Pressure DGD Dual Gradient Drilling
ECD Equivalent Circulating Density
FG Fracture Gradient IADC
International Association of Drilling Contractors KOP Kick-Off Point
MPD Managed Pressure Drilling MCD Mud Cap Drilling NPT Non-Productive Time OBD Overbalanced Drilling
PP Pore Pressure
RFC Return Flow Control
TAMU Texas A&M University UBD Underbalanced Drilling
14 Inês Sofia C. V. Pinto SPE
REFERENCES
Aadnoy, B., Cooper, I., Misca S., Mitchell, F. & Payne, L. (2009). Advanced Drilling and Well Technology, SPE.
Aberdeen Drilling School (ADS). Current Drilling Challenges.
Advanced Drilling Techniques (2006). Master of Petroleum Engineering, Curtin University of Technology,
Department of Petroleum Engineering.
Chaudhury, G. and Whooley, A., Wood Group Kenny. (2014). Art, Science, and Engineering of Managing Offshore
Field Development Economics and Risks. Paper OTC-25344-MS. Presented at the Offshore Technology Conference,
Houston, Texas, USA, 5– 8 May 2014.
Cohen, J. et al. (2010). Gulf of Mexico's First Application of Riserless Mud Recovery for Top-hole Drilling - A Case
Study. Paper OTC 20939. Presented at 2010 Offshore Technology Conference, Houston, Texas, USA, 3 – 6 May
2010.
Drilling Engineering (2014). Institute of Petroleum Engineering, Heriot-Watt University.
Elliot, D., Montilva, J., Francis, P., Shelton, J., Reitsma, D. & Vincent, R. (2011). Managed Pressure Drilling Erases
the Lines. Oilfield Review Spring:23 no. 1. Schlumberger.
Gaup, T. (2012). Simulations of Dual Gradient Drilling. Earth Sciences and Petroleum Engineering, Norwegian
University of Science and Technology, Norway.
Hannegan, D. (2005). Managed Pressure Drilling in Marine Environment- Case Studies. Weatherford International.
Paper SPE 92600 presented at the 2005 SPE/IADC Drilling Conference, Amsterdam, The Netherlands, 23- 25
February 2005.
Kartevoll, M. (2009). Drilling Problems in Depleted Reservoirs. Master’s Dissertation, Faculty of Science and
Technology, University of Stavanger.
Nauduri, S., Medley, G., Corp, S. E. & Schubert, J. (2010). MPD Candidate Identification: To MPD or Not To MPD.
Paper SPE/IADC 130330 presented at the 2010 SPE/IADC Managed Pressure Drilling and Underbalanced
Operations Conference and Exhibition, Kuala Lumpur, Malaysia, 24–25 February 2010.
Peker, M. (2012). Economical Impact of Dual Gradient Drilling System. Master’s Dissertation, Graduate School of
Natural and Applied Sciences Middle East Technical University.
PSAC – Petroleum Services Association of Canada. (2015). 2015 Well Cost Study.
Redden, J. (2010). Dual-gradient drilling promises to change the face of deepwater. Offshore. 5, Vol. 70, 50.
Rehm, B., Schubert, J., Haghshenas, A., Paknejad, A. & Hughes, J. (2008). Managed Pressure Drilling. Gulf Drilling
Series, Gulf Publishing Company, Houston, Texas.
Rohani, M. (2011). Managed-Pressure Drilling: Techniques and Options for Improving Operational Safety and
Efficiency. Petroleum and Coal, Sharif University of Technology, Tehran, Iran.
Saptharishi, P. & Deendayal, P. (2012). Optimization of Well Performance by Dual Gradient Drilling - A Literature
Analysis.9th Biennial International Conference & Exposition on Petroleum Geophysics.
Sui, D. & Nygaard, O. (2015). Automated Dual Gradient Drilling and its Parametric Analysis during Connection.
Petroleum Engineering Department, University of Stavanger and the Statoil Akademia program. Science Direct.